Page 1

Argyll and Bute Council 
Comhairle Earra-Ghàidheal Agus Bhòid 
Executive Director:  Douglas Hendry 
Kilmory, Lochgilphead, PA31 8RT
Tel:  01546 602127  Fax:  01546 604435
DX 599700 LOCHGILPHEAD
24 January 2024 
NOTICE OF MEETING 
A meeting of the ARGYLL AND BUTE HARBOUR BOARD will be held BY MICROSOFT TEAMS
on WEDNESDAY, 31 JANUARY 2024 at 3:00 PM, which you are requested to attend. 
Douglas Hendry
Executive Director 
BUSINESS 
1. APOLOGIES FOR ABSENCE 
2. DECLARATIONS OF INTEREST (IF ANY) 
3. OBAN HARBOUR REVISION ORDER UPDATE (Pages 3 - 6)  
Report by Executive Director with responsibility for Roads and Infrastructure Services
* 4. PIERS AND HARBOURS - OBAN HARBOUR - COSTS AND CONSERVANCY
(Pages 7 - 14)  
Report by Executive Director with responsibility for Roads and Infrastructure Services
* 5. PIERS AND HARBOURS - MARINE ASSET MANAGEMENT PLAN FEES AND
CHARGES 2024/2025 (Pages 15 - 22)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
Items marked with an “asterisk” are items, on the basis of information available at the time this
Agenda is published, on which the Committee may not have delegated powers to act, and which
may therefore require to be referred to the Council or another Committee, and that referral may
depend on the decision reached at the meeting. 
Argyll and Bute Harbour Board 
Councillor Fiona Howard Councillor John Armour
Councillor Garret Corner Councillor Amanda Hampsey
Councillor Andrew Kain (Chair) Councillor Jim Lynch
Councillor Ross Moreland (Vice-Chair) Councillor Andrew Vennard   
Contact: Hazel MacInnes Tel: 01546 604269
Public Document Pack

Page 2

This page is intentionally left blank

Page 3

ARGYLL AND BUTE COUNCIL  HARBOUR BOARD 
ROADS AND INFRASTRUCTURE
SERVICES 
31 JANUARY 2024 
OBAN HARBOUR REVISION ORDER UPDATE 
1.0 INTRODUCTION 
1.1 This report is provided to update Members on the status of plans to establish the
Municipal Oban Harbour and the progress of the Oban Harbour Revision Order
(HRO). 
1.2 It also details the process for the formal consultation process to make the Order. 
2.0  RECOMMENDATIONS 
It is recommended that the Harbour Board: 
2.1 Note and consider the update provided in this report. 
3.0 DETAIL   
Harbour Revision Order (HRO) 
3.1.1 The Council’s Harbour Board met on 31st August 2023 and approved a draft of
the HRO for the formal application, assuming there were no material changes
requested by Transport Scotland in the meantime. The report clearly set out the
key steps, including the 6 week consultation period consequential to that
decision. 
3.1.2 Table 1 below shows the steps in the formal process. 
Table 1
Step Description Actioned by
1 Formal application requested by Transport Scotland
and submitted by Argyll & Bute Council.
Accompanied by fee & supporting documentation.
Transport Scotland &
Council Officers.
2 Public Notice – 42 days (6 weeks) of public
consultation. May result in representations being
received from members of the public, community
groups or statutory consultees. 
Objection handling by
Transport Scotland by
written representation,
hearing or inquiry.
Negotiation / modifications
by Argyll & Bute Council.
Page 3 Agenda Item 3

Page 4

3 Consultation with statutory consultees is also open
for 42 days but may not exactly match the same
commencement day as the public consultation
period. (see 3.2.6)
Managed by Transport
Scotland, then passed to
Argyll & Bute Council.
4 Scottish Ministers consideration of application and
decision.
Scottish Government.
5 Decision letter issued & decision published. Transport Scotland.
6 Order Made. Argyll & Bute Council assume control of
new harbour area.
Scottish Government. 
3.1.3 Following the successful conclusion of informal discussions and confirmation
that no material changes were made to the draft HRO, the formal application
has now been submitted to Transport Scotland along with the associated
documentation and fee. 
3.2 The Consultation Phase 
3.2.1 The arrangements for the consultation are governed by the Harbours Act 1964,
and this does not provide leeway or discretion on the part of the Council for the
42 day period (6 weeks) to be extended or altered. 
The 6 week period of public consultation began with the publication of an
advertisement in a local newspaper and ran from 30th November 2023 until the
10th January 2024. 
3.2.2 The Council, in looking at the timing of the 6 week consultation period has been
sensitive to balancing the need to progress the Harbour Order with the need to
make sure that the 6 week consultation period did not begin or end during either
of the Christmas or New Year holidays. 
3.2.3 Scottish Ministers directed that the draft was also served on specified bodies or
persons and this has been done to coincide as closely as possible with the
public consultation period. The Statutory Consultees are:
• Scottish Environment Protection Agency
• NatureScot
• Northern Lighthouse Board
• The Royal Yachting Association Scotland
• Planning and Building Standards – Argyll and Bute Council 
• UK Chamber of Shipping
• Maritime and Coastguard Agency 
3.2.4 We have also published the submission on the Council’s website for public
viewing and promoted that via social media, our ‘Keep in the Loop’ service and
by any other appropriate means identified in liaison with the Council’s
Communications Team. This is an established consultative process from the
informal consultation already carried out for the Oban HRO. 
3.2.5 The process requires 42 days for representations to be made and during this
Page 4

Page 5

period Transport Scotland will conduct their own consultations with the statutory
consultees served with the draft HRO. Each consultee will have 42 days to
respond so this may not run concurrently with our public consultation period. 
3.2.6 All objectors must state the grounds of the objection.  Their representations
have been forwarded on to us from Transport Scotland and in addition, as we
have had consultations on this subject before, representations sent directly to us
have been shared with Transport Scotland. 
3.2.7 There is no fixed timescale for handling any representations received.   Now the
42 day period has ended Transport Scotland and Argyll and Bute Council are
liaising to agree a timeframe to review the remaining representations. The
timeframe may be extended if required and objections can be withdrawn at any
time by writing to Ministers but at the end of the timeframe Transport Scotland
will contact all outstanding objectors to confirm the status of the objection. 
3.2.8 Ministers will make the decision on the appropriate route to deal with any
objections which are not withdrawn which can include further written
representation or in extreme or complex cases a hearing or public inquiry on
similar lines to planning inquiries. 
3.2.9 The Minister will then consider the material provided and reach a decision,
which may involve modifications to the Order to meet objections or provide
mitigation measures. 
3.2.10 Ministers will then consider the draft and issue a formal decision letter to the
Council, copied to consultees and objectors and published on the Transport
Scotland website. 
3.2.11 In the event the decision is positive the Order will be made and we must publish
notice of this in the Edinburgh Gazette and a local paper (again most likely the
Oban Times) and serve copies on the same people identified and notified of the
original application.   
4.0 CONCLUSION 
4.1 This report provides an update to Members on the status of plans to establish
the Municipal Oban Harbour and the progress of the Oban Harbour Revision
Order (HRO). 
5.0 IMPLICATIONS 
5.1 Policy – The Harbour Board agreed in December 2021 that the Council should
proceed to make the arrangements to formally manage the unmanaged
section of Oban Bay.   
5.2 Financial – No financial implications at this stage, all costs have been met
Page 5

Page 6

through existing budgets and the Municipal Harbour will have fees and
charges through conservancy charges etc. which will cover the operating
costs. 
5.3 Legal – the HRO process is a formal legal process set out in the 1964
Harbours Act. 
5.4 HR – HR implications will be identified as the proposal progresses.   
5.5  Fairer Scotland Duty: 
5.5.1   Equalities – None known. 
5.5.2   Socio-economic Duty – None known.
5.5.3 Islands – consultation will be carried out with the island communities as a
continuation and expansion of the Options Appraisal Process reported to the
December harbour Board.
5.6 Climate Change – due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise.  
5.7 Risk - The Council progressing to become a Municipal Port Authority for the
unmanaged areas of Oban Bay increases the safety within Oban Bay.  There
is a risk that there could be a number of objections and representations during
the process which could impact on timescale and these will be considered as
and when they arise.  
5.8  Customer Service – Improved and safer environment for all users. 
Kirsty Flanagan, Executive Director with responsibility for Roads and Infrastructure 
Policy Lead for Roads and Transport, Councillor Andrew Kain 
January 2024                                            
For further information contact: Jim Smith, Head of Roads and Infrastructure, or
Scott Reid, Marine Operations Manager 
Page 6

Page 7

ARGYLL AND BUTE COUNCIL     ARGYLL AND BUTE HARBOUR BOARD
ROADS AND INFRASTRUCTURE SERVICES                   31 JANUARY 2024 
PIERS & HARBOURS - OBAN HARBOUR – COSTS AND CONSERVANCY 
1.0 INTRODUCTION 
1.1 There are three separate Harbour Orders in place for Oban: the North Pier,
Railway Pier and South Pier. The approaches and waters through the bay are
not covered by an Order. The responsibility for these waters defaults to the
Maritime and Coastguard Agency (MCA). Having one or more Statutory
Harbour Authority controlling the entirety of the bay would remove any
ambiguity and would likely result in benefits to users of the bay. 
1.2 For a number of years the Council with CMAL, CalMac, the Northern
Lighthouse Board and various stakeholders have worked to progress a
solution which would result in all of the bay, including the approaches, being
covered by provisions which would enable the bay to be fully managed. In
particular, the Oban Bay Management Group (OBMG) has been providing a
joint approach to improving navigational safety at Oban since 2007. The
group consists of Caledonian Maritime Assets Ltd (CMAL), Argyll and Bute
Council (ABC), Northern Lighthouse Board (NLB), CalMac Ferries Ltd (CFL),
Oban Bay Stakeholder Group (OBSG), Oban Community Harbour
Development Association (OCHDA) and Oban Community Council (OCC).
The Council’s plans for a Municipal Harbour have the support of the OBMG. 
1.3 This report follows on from the decision of the Council’s Harbour Board at its
meeting on 31 August where the Harbour Board agreed the final draft HRO for
submission to Transport Scotland to commence the statutory consultation
process. That report clearly set out the key steps, including the 6 week
consultation period consequential to that decision. It was for Council officers to
then progress with these steps, including the commencement and timing of the
consultation period to ensure that the HRO was in a position to be operational
as soon as practicably possible. 
1.4 This report also allows Members to consider the costs and associated reasonable
charges (Conservancy Charge) for the running and maintenance of an expanded
Oban Harbour, as defined in the Harbour Revision Order (HRO) currently under
process with Transport Scotland.
Page 7 Agenda Item 4

Page 8

2.0 RECOMMENDATIONS 
2.1 Members are asked to recommend to Council in the event the HRO is made:
2.1.1 When setting the fees and charges for 2024 / 2025 that it approves, for
vessels with a Gross Registered Tonnage (GRT) over 50 registered
tonnage, a baseline Conservancy Charge of 7p / GRT to generate sufficient
income to run, maintain and develop Oban Harbour and the Council’s
marine infrastructure;
2.1.2 Agree that CalMac ferries have a reduced rate of 2p / GRT due to the
reasons detailed in the report;
2.1.3 Note that this represents a figure for the first year only and that it should be
assessed for effectiveness each year and adjusted accordingly;
2.1.4 Agree that the adjusted conservancy charge is to be assessed, reported and
approved annually in line with the Marine Fees and Charges and is to be
included in that report for the Harbour Board for recommendation to Council;
and
2.1.5 Agree that the vessel types listed in the report at 4.3 should be exempt from
transit or ‘Conservancy’ charges. 
3.0 BACKGROUND 
3.1 In August 2023 the Harbour Board agreed a final draft of the HRO for submission
to Transport Scotland which expands the current SHA area around Oban North
Pier to include a larger portion of Oban Bay and the Kerrera Sound.
3.2 Figure 1: Chart of new harbour limits included with the HRO. The harbour limits
shown shaded blue below: 
Page 8

Page 9

3.3 On 10th November 2023 following a period of informal review with Transport
Scotland, the formal application for the HRO was made by the Council. The
statutory consultation period of 42 days commenced on 30th November 2023 with
the publication of an advert in the Oban Times newspaper and expired on 11th
January 2024. 
3.4 If made, the draft Order will become law and Oban Harbour will come into
existence by extending the Council’s current jurisdiction out to the limits shown in
Figure 1. This will come with added responsibility for maintaining the harbour for
shipping and the powers to raise funds to do so. These charges are usually
referred to as ‘Conservancy’ charges but can be equally combined in the day to
day ‘harbour dues’ or berthing fees.
3.5 In determining the level at which charges are set, a number of assumptions have
to be made which will be monitored over the year, so that the Harbour Authority
can be confident when recommending the fees and charges each year that they
are effective and reasonable. Some of those assumptions and notes are listed
here:
a. CalMac Ferries timetables – an assumption has been made around the
number of sailings for the year. At present service disruption and weather
have some impact on the expected income.
b. CalMac vessel allocation – an assumption has been made around tonnage
and vessels deployed on the routes although these may change. A figure
of 15M GRT has been used from generally accepted historical data for
GRT with available recent updates e.g. Loch Frisa deployment has a
significant reduction on GRT on the Craignure route.
c. Large vessel movements – an assumption has been made around the
level and size of non-ferry traffic.
d. Small vessels less than 50 GRT and ‘pleasure craft’ will be exempted from
conservancy charges.
e. Economy of scale savings and recharging within Council departments for
services may not be reflective of the costs which another Harbour Authority
would incur for the same services e.g. training, resilience and insurance.
f. Recognition that as public bodies utilising public funds CFL already pay
CMAL harbour dues for the CMAL Harbour Authority area as detailed in
their own schedule of charges. Every effort will be made to simplify the
charging process between Argyll and Bute Council and CFL as the current
ferry operators.
3.6 Discussions between Argyll and Bute Council and CFL are ongoing regarding an
agreement for the payments and charges made each year. It is anticipated that a
simplified charging structure, beneficial to both bodies can be agreed during 2024
/ 2025. 
Page 9

Page 10

4.0 DETAIL
The Oban Harbour Statutory Harbour Authority (SHA) will have an obligation
to ensure open and safe use of the Harbour and to make reasonable charges
for the running and maintenance of the Harbour. 
4.1 The authority to charge “ship, passenger and goods dues” as considered “fit” is
vested in Argyll and Bute Council by the Harbours Act 1964 section 26(2) and
applicable at all locations where Argyll and Bute Council is the statutory harbour
authority and exercise its statutory harbour powers in accordance with its
governing legislation. 
The monies raised from levying harbour dues are primarily used to maintain the
harbours and to provide for their long-term viability and encompasses, 'ship,
passenger and goods dues', namely those charges associated with:
a. Ships entering, using or leaving the harbour;
b. Passengers embarking or disembarking at the harbour;
c. Goods brought into, taken out of, or carried through the harbour by ship;
4.2 Definitions given below are not exhaustive but are significant in the context of this
report and Oban Harbour. A more detailed schedule of charges will be required
to cover the full range of Ports and services carried out by Argyll and Bute Council
as Harbour Authority at other locations and the legal distinctions between the
different types of vessel or craft.
4.2.1 ‘Pleasure vessels’ are vessels used for sport or recreational purposes and do not
operate for financial gain. A more extensive legal definition is provided by the
Merchant Shipping (Vessels in Commercial Use for Sport or Pleasure) 1998 (SI
1998/2771) as amended. 
If more than 12 passengers are carried, irrespective of whether payment is made,
the vessel is a “passenger ship” under UK Merchant Shipping regulations and
needs to be appropriately surveyed and certificated.
4.2.2 ‘Fishing Vessel’ means a vessel for the time being used (or, in the context of an
application for registration, intended to be used) for, or in connection with fishing
for sea fish other than a vessel used (or intended to be used) for fishing otherwise
than for profit; and for the purposes of this definition “sea fish” includes shellfish,
salmon and migratory trout (as defined by section 44 of the Fisheries Act 1981). 
A vessel for the time being used (or intended to be used) wholly for the purpose
of conveying persons wishing to fish for pleasure is not a fishing vessel.
4.2.3 ‘Ferry’ means a sea going passenger vessel designed or adapted to carry more
than 12 passengers and may also have the ability to convey vehicles and goods,
especially over a relatively short distance and on a regular service. Which refers
to a series of ro-ro ferry or passenger craft crossings, operated so as to serve
traffic between the same two or more ports, or a series of voyages from and to
the same port without intermediate calls, either:
Page 10

Page 11

a. According to a published timetable; or
b. With crossings so regular or frequent that they constitute a recognisable
systematic series.
4.2.4 Charges will be referred to the Gross Registered Tonnage (GRT) of a vessel and
normally per day, although future rates may incorporate other durations of stay if
required for flexibility and convenience e.g. 4 day cruise call or short stay call
4.3  Exemptions
4.3.1 The following categories of craft shall be exempt from payment of ‘conservancy’
charges but may still be liable for berthing or combined charges at berths within
Oban Harbour Authority area, being vessels not covered by the other defined
categories and which are not exempt (in law) from paying pier and harbour
charges:
a. No charges will apply to vessels which are involved in an ongoing
emergency.
b. Commercial and pleasure vessels under 50 GRT.
c. Fishing vessels.
d. Tenders used to access another vessel in the vicinity of harbour or facility.
e. Canoes / kayaks.
f. Personal watercraft (Jet Ski etc.).
g. Sail / paddle boards.
4.4 Present Costs Estimates
4.4.1 The table 1 below lists a summary of running costs for Oban Harbour 
Table 1 - Summary of costs 
4.5 Vessel Traffic
4.5.1 In 2022 the Harbour area saw c.15,500 transits of the North entrance to the
Harbour area by vessels with Automatic Identification System (AIS) fitted. 54% of
these were attributed to passenger vessels, of which the vast majority are CalMac
ferry transits to and from the CMAL Harbour Authority area.
Category Description (examples) Annual Cost
Equipment Service
Agreements
Workboat engine / service contracts £5,000
Building & Admin PMSC / ISPS / CCTV £6,000
Survey & Dredging Bathymetry 3 & 10 years / Dredging
6 to 10 years
£13,000
Maintenance & Repair Infrastructure / Dive inspections /
fender repairs
£50,000
Staff Staff employment on current shift
pattern
£225,000
Training IOSH / PFSO / Powerboat £5,000
Total annual estimate  £300,000
Page 11

Page 12

4.5.2 Most of the traffic entering, transiting or departing the Harbour area will have had
some interface with a facility in the harbour, either the North Pier, Northern
Lighthouse Board quay, CMAL Harbour Authority area or one of the anchorages.
When this is the case berthing dues etc. will be charged by the facility owner and
in the case of the North Pier as this is owned by the Harbour Authority these
charges can be adapted to include a combined fee inclusive of conservancy.
4.5.3 In determining a base rate for the ‘transit only’ or ‘conservancy’ charge it is
recognised that it should not overburden customers and businesses using Oban
Harbour who pay ‘berthing dues’ elsewhere already.
4.6 Conservancy income
4.6.1 The table 2, below shows a summary of estimated income for a base rate of 7p
per GRT for liable vessels and a reduced rate of 2p per GRT for CFL services. 
4.6.2 The total estimated income incorporates an initial c.15% to cover some of the
start-up costs and the commencement of a business case for the North Pier
extension, which will look at the future development of Oban Harbour.
4.6.3 The estimates below should be refined over the first year, reassessed and
reported with recommendations on changes for year 2 onwards. Changes will
take account of:
a. Any ‘fixed sum’ simplified agreement with CFL, taking into account new
tonnage and scheduled timetables.
b. Reduction of the determined ‘start-up’ costs over an agreed period.
c. Actual vessel traffic movements and GRT over the year. 
Table 2 - Summary of estimated income for Year 1
Facility Description Value
North Pier c.200,000 GRT / year @ 7p £14,000
Cruise
anchored
c.265,000 GRT / year @ 7p £18,550
Other liable
commercial
transits 
c.200,000 GRT year @ 7p £14,000
CalMac c.15,000,000 GRT / year @ 2p £300,000
Total  £346,550 
5.0 CONCLUSION
5.1 This report follows on from the decision of the Council’s Harbour Board at its
meeting on 31 August where the Harbour Board agreed the final draft HRO for
submission to Transport Scotland to commence the statutory consultation
process. This report also allows Members to consider the costs and associated
reasonable charges (Conservancy Charge) for the running and maintenance of
an expanded Oban Harbour, as defined in the Harbour Revision Order (HRO)
Page 12

Page 13

currently under process with Transport Scotland. The Conservancy Charges will
form part of the fees and charges report which will be considered by Council as
part of the 2024/25 budget process. 
6.0 IMPLICATIONS
6.1 Policy - None directly arising from this report however this position to be
revisited in the event that the HRO is adopted.   
6.2 Financial - The proposed increase of fees and charges will ensure that future
income is sufficient to maintain and develop marine assets. Costs incurred to
date have been met through existing budgets.
6.3  Legal - Considered to be none directly arising from this report.
6.4  HR - Additional staff required to operate the extended SHA have been recruited
and are currently deployed assisting the Harbour Master in preparing for the
introduction of the SHA together with training and general marine duties.
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics An EqSEIA is being developed for the
Oban SHA.
6.5.2   Socio-economic Duty - None directly arising from this report.
6.5.3 Islands - Development of the harbour will enhance safety, service reliability
and community connectivity between the mainland and islands and provide
additional resilience and support for vessels utilising Oban Bay.
6.6 Climate Change - there are no direct impacts in regard to climate change from
this report, due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise.  
6.7 Risk - Applied charges will help ensure the repair and maintenance on existing
infrastructure.
Above charges may have a detrimental economic impact on businesses using
the facilities for example:
• bulk importers
• timber exporters
• wind farm developers
• Cruise companies. 
Significant increases may also reduce usage and customers while making
attracting new business more difficult. 
External influences may come to bear on ferry usage patterns which may, in
turn, impact on income from ferry fees and charges i.e. Vessel breakdowns
Page 13

Page 14

and redeployments, Environmental issues (car use) and potential changes in
RET. 
6.8  Customer Service - Customers and key stakeholders will be informed of fees
and charges when set. An overall improvement in travel experience and
reliability should result with improved and maintained infrastructure. 
Executive Director with responsibility for Roads and Infrastructure,
Kirsty Flanagan
Policy Lead for Roads and Transport, Councillor Andrew Kain 
January 2024                                                  
For further information contact:
Scott Reid, Marine Operations Manager 
Jim Smith, Head of Roads and Infrastructure Services 
Page 14

Page 15

ARGYLL AND BUTE COUNCIL     ARGYLL AND BUTE HARBOUR BOARD
ROADS AND INFRASTRUCTURE SERVICES                   31 JANUARY 2024 
PIERS & HARBOURS - MARINE ASSET MANAGEMENT PLAN FEES & CHARGES
2024 / 2025 
1.0 INTRODUCTION 
1.1 This report allows Members to consider the necessary increase in fees and
charges for the forthcoming financial year 2024 / 2025, in order to meet the
requirements for the Argyll and Bute Council Asset Management Plan referenced
in the August 2023 Harbour Board report. 
2.0 RECOMMENDATIONS 
2.1 Members are asked to:
2.1.1 Recommend to the Council, when setting the fees and charges for 2024 /
2025 that it approves an increase to piers and harbours fees and charges of
3% to generate sufficient income to develop the Council’s marine
infrastructure.
2.1.2 Note that this presents a stepped “proposed increase to allow smoothing”
over a 10 year period for meeting both the sustainability costs and future
improvement costs associated with the marine infrastructure which Argyll
and Bute Council has responsibility for.
2.1.3 Agree that the asset management plan will continue to be updated on a
rolling 10 year basis.   
3.0 BACKGROUND 
3.1 It was agreed at the December 2022 Harbour Board meeting that any fees and
charges; “…increase will be in-step with the motion passed at the Harbour Board
meeting in January 2018 that agreed to set charges that meet both the asset
Page 15 Agenda Item 5

Page 16

sustainability costs and future improvement costs associated with the piers and
harbours which the Council has a responsibility for.” 
4.0 DETAIL
In order to fund the various works identified in the Marine Asset Management
Plan it is necessary to increase fees and charges on a year-on-year basis.
Annual increases in future years are expected to be in the order of between
3% and 5%, depending upon confirmed works identified for that particular
year (plus any discretionary inflationary increase). 
4.1 Current Works 
Marine Services are presently engaged in a number of long and shorter term
projects and works across Argyll and Bute which include:
4.1.1 Iona breakwater – protection of ferry berthing slip 
The breakwater planning application has been uploaded and is on schedule to
tender this year. Contractor award should be in the summer of 2024 and
completion by summer 2025 which will now include the adjacent slipway repairs
as well as the replacement toilet block. The present forecast of 1 year construction
may be subject to the contractor work scope and supply chains, particularly rock
armour.
4.1.2 Fionnphort overnight berthing facility 
Preparation is progressing with Fionnphort to ensure: 
• Overnight berth 
• Safe access for crew 
• Sheltered berthing 
• Charging and supply facilities 
• Traffic survey to enhance the passenger road user interface at the terminal area. 
An Environmental Impact Assessment (EIA) is in process including the socio-
economic assessment. Design colleagues have addressed all potential issues
with CalMac Marine regarding swept paths and approaches. When Marine
Scotland approve the EIA we will continue with the marine licences, public
engagement and other preparations with a view to tender in the summer of 2024. 
Public engagement visits with drop in day and presentation at Fionnphort and
Iona took place in April last year and were well attended.
4.1.3 Port Askaig – Marshalling area development for new CalMac vessels 
Port Askaig will be upgraded to accommodate the larger capacity CalMac ferries
with the first vessel expected to be delivered in October this year and
subsequently entering service following sea trials and crew familiarisation. The
Page 16

Page 17

second vessel will follow in early 2025. Consultants SYSTRA were commissioned
to carry out a study to determine options for the existing marshalling area when
initial attempts to purchase land for additional space were unsuccessful. 
The concept design will provide nominal marshalling space of 129% of the new
vessel PCU capacity and in occasional or extreme circumstances can be
increased to 186% of the vessel PCU capacity while still incorporating extra safety
features. 
Additional off site space of c.50 PCU will also be progressed.  
4.1.4 CAT 5 Water Supply Protection 
In line with The Water Supply (Water Fittings) (Scotland) Byelaws 2014, Scottish
Water require a number of piers under A&BC ownership to be upgraded to ensure
private and local public water supplies are protected from backflow contamination
and that harbours/terminals/pontoons etc. are adequately protected to fluid
category 5. 
Argyll and Bute Council were notified of an initial four sites requiring immediate
upgrade works in relation to private water supplies, in order to provide backflow
protection, and for the prevention of contamination back into the local mains
supply network:
• Campbeltown Old Quay
• Oban North Pier
• Carradale
• West Loch Tarbert 
We can report that these works are being completed and post works site
inspections by Scottish Water, where works have been completed have been very
positive. A planned programme to cover our other facilities is being developed.
4.1.5 Shore Side Electrical Supply
New ferries and infrastructure upgrades today require an electrical supply for
rapid and / or overnight battery charging which outstrips the existing network.
Argyll and Bute Council have been working closely with CMAL and SSEN to
programme these upgrades, some of which have equipment lead times of up to
4 years. This work is to ascertain the feasibility of providing a shore supply to the
vessels and to confirm and outline the electrical and civil engineering
requirements for providing such a supply, ensuring that the port developments
are fit for the introduction of the new vessels. Initial meeting with SSEN was
positive and they do not foresee any major problems in meeting the capacity
required within the timescales.
The works to date include:
Page 17

Page 18

• Craignure - completed 
• Fionnphort – planning (up to 3 years lead time) 
• Gigha – feasibility planning (up to 4 years lead time) 
4.2 Variations to Asset Management Plan 
Unfortunately some of the programme’s planned works have been delayed. The
significant items slipping to future periods are detailed below: 
4.2.1 Kilcreggan 
The Gourock, Dunoon and Kilcreggan combined works plans remain paused
while Transport Scotland completes its work on the vessel funding. 
Ground Investigations preparations for both Kilcreggan and Dunoon remain ready
to tender when confirmation is received that the funding for the vessels has been
secured.
4.2.2 Dunoon 
Although the combined programme of works for Gourock, Dunoon and Kilcreggan
has been paused while Transport Scotland completes its work on the vessel
funding, areas where improvements are required have been identified
irrespective of the outcome of the larger project. 
The intention is that these improvements will form ‘Phase 1’ of the larger works if
they go ahead, however that decision is not required to justify these particular
improvements to the facilities and utilities connections. Interim plans are in
development and will be reported in due course for approval. 
Dunoon link span remains subject to sporadic and intermittent issues with one of
the hydraulic arms. Work is progressing behind the scenes to procure spare and
replacement parts and fit these with minimal disruption to the service. The staff
on site however are safely managing the issues with the assistance of our
framework engineers.
4.2.3 Craignure Terminal 
Following recent advice from the Scottish Government’s Marine Directorate we
have unfortunately had to stand down our ground investigation (GI) contractor. 
Ground Investigation (GI) works have been awarded to DUNELM Geotechnical
and Environmental Ltd with an initial plan to start on site 24th August 2023 for
around 4 weeks. We were not made aware that a licence would be required,
having previously been advised that the exploratory works would be an exempted
activity being outside the protected area. 
Notification was received from NatureScot regarding a ‘Likely Significant Effect’
(LSE) regarding Harbour Porpoises ‘near’ the protected area, however
subsequent communications with NatureScot were concluded positively and the
LSE decision revoked.
Page 18

Page 19

The Marine Directorate have since advised us that they will now require us to
apply for a Marine Licence for the GI works. The licence period is at least 14
weeks – this would have taken us into the worst of the weather over the New
Year, so we are now looking at these works starting in the spring. 
We do not anticipate our works proposals will change through the process. 
This will have cost implications for the project which will be in the region of an
extra £500k and a slippage of the works into next financial year, however our
immediate priority is now getting through the licence process as quickly and
efficiently as possible and having everything in place for these important works to
go ahead in the spring 2024.
4.2.4 Craignure PAS 
The current Passenger Access System (PAS) is beyond the working life of the
equipment which is being maintained for safe operations by CMAL. Revision of
design options based on CFL / CalMac operational requirements has been
completed and the design and build tender will be issued shortly to allow costs to
be assessed. The most cost effective solution will see as much of the new PAS
used in the new terminal design.
4.3 Previous Expenditure 
Since 2017/18 the council has increased Fees and Charges for Piers and
Harbours above inflation to fund prudential borrowing which in turn is financing
the Asset Management Plan. The table below shows the expenditure and
financing costs since 2017/18 with any residue being placed in earmarked
reserves to fund future expenditure. There is currently £2,789,311 held in
earmarked reserves to fund prudential borrowing for Piers and Harbours. 
Table 2: Previous expenditure since 2017/2018 
2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 Total
Actual 319,873 1,485,304 2,759,589 788,161 1,191,927 690,904 7,235,758
Loans
Charges
6,797 48,330 167,337 265,299 317,932 359,117 1,164,813
Additional
Income 
generated
by uplift
113,590 177,012 515,873 560,657 987,525 1,505,617 3,860,274
Surplus
income
added 
to
earmarked
reserves
107,041 133,050 367,750 362,384 672,586 1,146,500 2,789,311 
4.4 As shown in Table 3 below, the increase proposed for 2024 / 2025 is 3%.
Page 19

Page 20

Proposed increases are smoothed over future years to avoid large spikes in the
increases which would be required to fund the asset management plan in the
years where large expenditure is planned. 
Table 3: Smoothing of Asset Management Plan Fees and Charges 
4.5 The proposed increases will cover Argyll and Bute Council’s present Marine
Infrastructure Asset Management Plan, involving upgrades to Council
infrastructure which are required for CFL / CalMac (CFL) ferry service
improvements. We continue to have close liaison with Transport Scotland, CMAL
and CFL to ensure lifeline services are prioritised, co-ordinated and resources are
targeted accordingly. The work carried out to support ferry traffic is generally
financed through these fees and charges which are used to service loans charges
for capital borrowing.
4.6 Future income 
The Asset Management Plan is an adaptable plan that is required to have
flexibility to cope with changing priorities and circumstances. It also relies on
steady and predictable income from those ferry services utilising Argyll and Bute
Council infrastructure. 
A close watch on fees and charges income and its effect on future projects is
maintained to ensure the statutory and priority works are delivered. 
The following table shows the anticipated income which will be generated by the
increased fees and charges and the effect it will have on the earmarked balance. 
2023-
24
2024-
25
2025-
26
2026-
27
2027-
28
2028-
29
2029-
30
2030-
31
2031-
32
Planned 
expenditure 
£’000
3,200 28,000 50,000 2,695 0 0 0 0 0
Anticipated 
Annual 
Loans 
Charges 
£’000
389 561 2,065 4,750 4,895 4,895 4,895 4,895 4,895
Additional 
funding 
required to 
pay loans 
charges 
£’000
19 172 1,504 2,686 145 0 0 0 0
Increase 
required if 
fully funded 
in year
0.24% 1.92% 16.34% 28.34% 1.48% 5.00% 5.00% 5.00% 2.50%
Proposed 
increase to 
allow 
smoothing
5.00% 3.00% 3.00% 3.00% 3.00% 5.00% 5.00% 5.00% 2.50%
Page 20

Page 21

Table 4: Profile of income and borrowing costs on Asset Management Plan   
2023-
24
2024-
25
2025-
26
2026-
27
2027-
28
2028-
29
2029-
30
2030-
31
2031-
32
Planned 
expenditure 
£’000
3,200 28,000 50,000 2,695 0 0 0 0 0
Anticipated 
Annual 
Loans 
Charges 
£’000
389 561 2,065 4,750 4,895 4,895 4,895 4,895 4,895
Anticipated 
additional 
income 
generated
£’000
1,908 2,176 2,452 2,737 3,029 3,532 4,060 4,630 4,938
Surplus 
transferred 
to / from 
earmarked 
reserves 
£’000
1,519 1,616 388 -2,014 -1,866 -1,363 -835 -265 43
Cumulative 
balance on 
earmarked 
reserves 
£’000
4,309 5,924 6,312 4,298 2,432 1,069 234 -31 12 
5.0 CONCLUSION
5.1 The proposed fees and charges increase is required to fund future asset
sustainability and improvement costs for the Council’s present plans for piers and
harbours. 
6.0 IMPLICATIONS
6.1 Policy - None directly arising from this report. 
6.2 Financial - The proposed increase of fees and charges will ensure that future
income is sufficient to maintain and develop the Council’s marine assets.   
6.3  Legal - Considered to be none directly arising from this report. 
6.4  HR - None.
6.5  Fairer Scotland Duty:  
6.5.1   Equalities - protected characteristics - None directly arising from this report.
6.5.2   Socio-economic Duty - None directly arising from this report.
6.5.3 Islands - Completed works and projects will enhance service reliability and
community connectivity.
Page 21

Page 22

6.6 Climate Change - there are no direct impacts in regard to climate change from
this report, due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise.  
6.7 Risk - Completed works will reduce the repair and maintenance on existing
infrastructure.
Above inflation increases may have a detrimental economic impact on
businesses using the facilities for example: 
• fishermen
• bulk importers
• timber exporters
• wind farm developers
• Cruise companies. 
Significant increases may also reduce usage and customers while making
attracting new business more difficult. 
External influences may come to bear on ferry usage patterns which may, in
turn, impact on income from ferry fees and charges i.e. Vessel breakdowns
and redeployments, Environmental issues (car use), Brexit, Covid 19 and
potential changes in RET. 
6.8  Customer Service - Customers and key stakeholders will be informed of fees
and charges when set. An overall improvement in travel experience and
reliability should result with improved and maintained infrastructure. 
Executive Director with responsibility for Roads and Infrastructure:
Kirsty Flanagan 
Policy Lead for Roads and Transport: Councillor Andrew Kain 
January 2024                     
For further information contact:
Scott Reid, Marine Operations Manager 
Jim Smith, Head of Roads and Infrastructure Services 
Page 22