ARGYLL AND BUTE COUNCIL  ARGYLL & BUTE HARBOUR BOARD
ROADS AND INFRASTRUCTURE SERVICES       MARCH 21 2024 
MARINE ASSET MANAGEMENT PLAN 
1.0 INTRODUCTION 
1.1 This report provides Harbour Board Members with a review of the marine
infrastructure works Asset Management Plan. It includes an update on
significant and major programmes currently planned and underway within Argyll
and Bute Council’s Marine Asset Management Plan. 
2.0 RECOMMENDATIONS 
2.1 Members are asked to:
2.1.1 Consider the update on the major programmes currently being addressed within
the Argyll and Bute Council’s Marine Asset Management Plan.
2.1.2 Note that £28.75 million worth of capital works are underway or about to
commence in the financial year 2024 / 2025.
2.1.3 Note that there is a potential spend of c. £129 million over the next 5 years, the
majority of which will support the new CMAL & CFL / CalMac fleet renewal.
2.1.4 Approve the award of the £15 million works for Iona breakwater project. 
3.0 DETAIL 
3.1.1 Funding for Piers & Harbours is mainly provided by Prudential borrowing paid
back through fees and charges, however external funding can also be sourced

Page 2

through capital grants, shared cost agreements and funds made available for
specific projects. 
The Marine Asset Management Plan is an adaptable plan fed into by changing
priorities and circumstances. It also relies on steady and predictable income from
those ferry services utilising Argyll & Bute Council infrastructure to repay loan
charges. 
Costs will be best estimated and closely watched for best value. Rising prices and
availability of resources are risks which will need to be monitored in each of the
projects and forecasts adjusted accordingly. 
3.2 Marine Services are presently engaged in a number of long and shorter term
projects and works across Argyll & Bute which include:
3.2.1 Craignure – New Ferry Terminal 
Following advice from the Scottish Government’s Marine Directorate we have
unfortunately had to stand down our ground investigation (GI) contractor until the
spring. 
The GI works have been awarded to DUNHELM Geotechnical & Environmental
Ltd with an initial plan to start on site 24th August last year for around 4 weeks.
We do not anticipate that our works proposals will change through this extra
process. 
Our priority remains getting through the licence process as quickly and efficiently
as possible and having everything in place for these important works to go ahead. 
A timeline is being developed around some assumptions on the scale of
construction for each option and location. Following extended local consultation
and input, the potential issue of consensus between Craignure Community, CFL
and the wider Mull and Iona views on scale will require a resolution when the GI
works are completed 
Costs are estimated at £3M over the next two years, to reach construction which
includes Ground Investigation, Licencing, completion of business cases,
Environmental Impact Assessments, design and tendering. 
3.2.2 Iona breakwater – protection of ferry berthing slip
The breakwater works were tendered recently with returns received at the end of
January 2024. Contractor commencement is planned to begin in the summer of
2024 with completion estimated by summer 2025. These works will include the
adjacent slipway repairs as well as the replacement of the toilet block. 
Tender return is for £15M and approval is sought for this award.
3.2.3 Fionnphort overnight berthing facility

Page 3

Fionnphort overnight berthing facility 
Preparation is progressing with Fionnphort to ensure: 
• Overnight berth 
• Safe access for crew 
• Sheltered berthing 
• Charging and supply facilities 
• Traffic survey to enhance the passenger road user interface at the terminal area. 
An Environmental Impact Assessment (EIA) is in process including the socio-
economic assessment. Design colleagues have addressed all potential issues
with CalMac Marine regarding swept paths and approaches. When Marine
Scotland approve the EIA we will continue with the marine licences, public
engagement and other preparations with a view to tender in the summer of 2024.
Costs are estimated at £500k for 2024 / 2025 and thereafter an estimated £25M
for construction works. 
3.2.4 Port Askaig – Marshalling area development for new CalMac vessels
Port Askaig will be upgraded this year to accommodate the new, larger capacity
CalMac ferries. The first vessel is expected to be delivered in October and
entering service after sea trials and crew familiarisation.
The concept design provides for a nominal marshalling space of 129% of the new
vessel PCU capacity and in occasional or extreme circumstances can be
increased to 186% of the vessel PCU capacity while still incorporating extra safety
features. 
Additional off site space of c.50 PCU is also be progressed
Costs are estimated at £2M for the new vessel enabling works including the off-
site car park.
3.2.5 Campbeltown Harbour
Tenders were returned for the replacement of ‘Wall A’ at the Old Quay and is
ready now for award.
Tender return is for £6M to complete the replacement of the quay wall over the
next two year period.
3.2.6 Rothesay Harbour
Stability works to the main berthing face were tendered over the winter and are
due to be awarded very shortly. These works will be undertaken overnight to
minimise disruption of the ferry service.

Page 4

Once the tender is awarded, coordination discussions will take continue with
Calmac to ensure minimal disruption to services and to protect any especially
busy times. These works are planned to commence in spring 2024 and expected
to extend into early 2025.
Costs are expected to be £4.5M over the two year period.
3.2.7 Dunoon Harbour
Although the combined programme of works for Gourock, Dunoon and Kilcreggan
has been paused while Transport Scotland completes its work on the vessel
funding, areas where improvements are required have been identified irrespective
of the outcome of the larger project.
The intention is that these improvements will form ‘Phase 1’ of the larger works if
they go ahead, however that decision is not required to justify these particular
improvements to the facilities and utilities connections.
Interim plans are in development with costs expected to be in the region of £350k
which include a waiting room / Harbour Office building and a connection to
amenities. 
4.0 CONCLUSION 
4.1 This report provides Harbour Board Members with a review of the marine
infrastructure works Asset Management Plan. It includes an update on significant
and major programmes currently planned and underway within Argyll and Bute
Council’s Marine Asset Management Plan. 
5.0 IMPLICATIONS
5.1 Policy 
None directly arising from this report.
5.2 Financial 
The increases to fees and charges proposed at the December Harbour Board
will ensure that future income is sufficient to maintain and develop Argyll
& Bute Council marine assets for the coming year. Further increases or
alternative funding routes will be required to sustain the proposed
projects in future years.
5.3  Legal

Page 5

Considered to be none directly arising from this report.
5.4  HR 
None.
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics   
None directly arising from this report. 
5.5.2   Socio-economic Duty   
None directly arising from this report. 
5.5.3  Islands 
Completed works and projects will enhance service reliability and
community connectivity
5.6 Climate Change 
There are no direct impacts in regard to climate change from this report, due
regard will be given to climate change with a view to minimising any
climate change impact and these will be considered as and when they
arise. 
5.7 Risk 
Completed works will reduce the repair and maintenance on existing
infrastructure 
External influences may come to bear on ferry usage patterns which may, in
turn, impact on income from ferry fees and charges i.e. Vessel
breakdowns and redeployments, Environmental issues (car use), Brexit,
Covid 19 and potential changes in RET. This will pose a potential risk to
income.
5.8  Customer Service 
An overall improvement in travel experience and reliability should result with
improved and maintained infrastructure.
5.9 The Rights of the Child (UNCRC) 
None directly arising from this report 
Kirsty Flanagan
Executive Director with responsibility for Roads and Infrastructure Services
Policy Lead Councillor Andrew Kane

Page 6

FEBRUARY 2024                                                  
For further information contact:
Scott Reid, Marine Operations Manager Tel: 01546 604 696
Jim Smith, Head of Roads and Infrastructure Services Tel: 01546 604 324 