MINUTES of SPECIAL MEETING of ARGYLL AND BUTE HARBOUR BOARD held BY
MICROSOFT TEAMS 
on WEDNESDAY, 31 JANUARY 2024 
Present: Councillor Andrew Kain (Chair) 
Councillor Fiona Howard
Councillor John Armour
Councillor Garret Corner 
Councillor Jim Lynch
Councillor Ross Moreland
Councillor Andrew Vennard 
Attending: Kirsty Flanagan, Executive Director
Douglas Hendry, Executive Director
Jim Smith, Head of Roads and Infrastructure Services
Scott Reid, Marine Operations Manager
Stuart McLean, Committee Manager 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillor Amanda Hampsey. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interest. 
3. OBAN HARBOUR REVISION ORDER UPDATE 
The Harbour Board gave consideration to a report providing an update on the status of
plans to establish the Municipal Oban Harbour and the progress of the Oban Harbour
Revision Order (HRO).  The report also detailed the formal consultation process to make
the Order. 
Decision 
The Argyll and Bute Harbour Board noted the update provided in the submitted report. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated January 2024, submitted) 
* 4. PIERS AND HARBOURS - OBAN HARBOUR - COSTS AND CONSERVANCY 
The Harbour Board gave consideration to a report that outlined the costs and associated
reasonable charges (conservancy charge) for the running and maintenance of an
expanded Oban Harbour, as defined in the Harbour Revision Order (HRO), which was
currently under process with Transport Scotland. 
Decision 
The Argyll and Bute Harbour Board agreed to recommend to Council in the event that the
Harbour Revision Order (HRO) is made -

Page 2

1. that when setting the fees and charges for 2024 / 2025 it approves, for vessels with
a Gross Registered Tonnage (GRT) over 50 registered tonnage, a baseline
Conservancy Charge of 7p / GRT to generate sufficient income to run, maintain
and develop Oban Harbour and the Council’s marine infrastructure; 
2. to agree that CalMac ferries have a reduced rate of 2p / GRT due to the reasons
detailed in the submitted report; 
3. to note that this represents a figure for the first year only and that it should be
assessed for effectiveness each year and adjusted accordingly; 
4. to agree that the adjusted conservancy charge is to be assessed, reported and
approved annually in line with the Marine Fees and Charges and is to be included
in that report for the Harbour Board for recommendation to Council; and 
5. to agree that the vessel types listed in the report at paragraph 4.3 should be
exempt from transit or ‘Conservancy’ charges. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
Services dated January 2024, submitted) 
* 5. PIERS AND HARBOURS - MARINE ASSET MANAGEMENT PLAN FEES AND
CHARGES 2024/2025 
The Harbour Board gave consideration to a report proposing the necessary increase in
fees and charges for the forthcoming financial year 2024/25 in order to meet the
requirements for the Argyll and Bute Council Asset Management Plan referenced in the
report considered by the Harbour Board in August 2023. 
Decision 
The Argyll and Bute Harbour Board – 
1. agreed to recommend to the Council, when setting the fees and charges for 2024 / 2025
that it approves an increase to piers and harbours fees and charges of 3% to generate
sufficient income to develop the Council’s marine infrastructure; 
2. noted that this presents a stepped “proposed increase to allow smoothing” over a 10 year
period for meeting both the sustainability costs and future improvement costs associated
with the marine infrastructure which Argyll and Bute Council has responsibility for; and   
3. agreed that the asset management plan would continue to be updated on a rolling 10 year
basis. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated January 2024, submitted) 
6. OBAN HARBOUR REVISION ORDER - CLARIFICATION FOR NOTING 
A report clarifying comments made in an earlier report of 31 August 2023 to the Harbour
Board was before the Board for noting. 
Decision

Page 3

The Argyll and Bute Harbour Board noted the update provided in the submitted report. 
(Reference:  Report by Executive Director with responsibility for Roads and Infrastructure
dated January 2024, submitted)