APPENDIX 2 - Piers & Harbours - Capital Projects Tracker
Estimated overall
project cost Spend to date Remaining budget
FY 24/25 Forecast FY 25/26
Craignure Pier - Feasibility Study
Ground investigation has completed on site. Awaiting final
interpretation report to allow completion of OBC.
SMILG meeting being organised. Marine *53,000 1,063 1,300 *2,000 Thi OBC element is on track
Tayinloan & Gigha - Feasibility & Ground Investigation
Consultants progressing Environmental Impact Assessments and design
options ongoing and in process. Infrastructure Design *12,400 42 624 0
Budget estimate to be revised,
awaiting further details
Oban Municipal Port Project HRO progressing Marine 14 7 7 0
On track and 'in process' with
Transport Scotland
Campbeltown Old Quay - Wall A Active on site, work progressing Infrastructure Design 6,000 172 5,000 *1,000 On track
Oban North Pier - Structural Assessment - PB Site works complete - awaiting final report Marine 9 2 7 0 On track
Campbeltown New Quay - HPU Control panel and cylinder O/H Works on major commponents of the vital infrastructure Marine 100 0 100 0 On track
Craignure - New PAS Design and Build
Consultant supporting preparation on tender for new structure. Aiming
to tender for new PAS in Q3 FY24/25. Result of this will inform on
precise costs for a new PAS structure Marine *1,000 0 *1,000 0 On track
Cuan Ferry Piers  - OBC Development of outline business case for Cuan future infrastructure Marine *2,000 0 0 *2,000
Cost and delivery timescales currently
estimated. To be updated
Easdale Pier - OBC
Development of outline business case for Easdale Pier future
infrastructure Marine *1,000 0 0 *1,000
Cost and delivery timescales currently
estimated. To be updated
Ellenabeich Pier - OBC
Development of outline business case for Ellenabeich Pier future
infrastructure Marine *1,000 0 0 *1,000
Cost and delivery timescales currently
estimated. To be updated
Fionnphort - New Aligning Structure - Construction
Small budget for FY24/25 reflects procurement of EIA study and
subsequent application of neccessary licenses. Budget extending in
future years to support construction of assets Infrastructure Design *25,500 50 500 *20,000
On track for delivery following Iona
breakwater
Iona Ferry Slip - Breakwater Construction
Preferred Tenderer identified. Awaiting resolution with Marine
Directorate before award of contract Marine & Infrastructure Design 15,000 3 10,000 5,000
Marine Directorate issue needs
resolved. Contract not awarded, risk of
losing preferred bidder.
Rothesay - Berthing Face Stab Works
Phase 2 live. Direct award prepared for Phase 3 Roundhead
replacement Marine 4,500 196 3,500 *1,000 On track
Port Askaig - New Islay Vessel Enabling Works
Team is progressing a solution to enhance existing facilities. Under
discusson with CFL and Transport Scotland. Marine *2,000 33 1,912 0 Costs depend on options progressed
Dunoon Harbour - Essential Upgrade Works
Scope of project greatly reduced. Budget to be reduced and minor
works completed Marine *350 0 50 *300
Redefine scope and reduce budget
accordingly. Timetable for new scope
to be determined by Scottish
Goverment decisions.
Feolin
Installation of a passenger only access at Feolin for periods when the
vehicular vessel is not available. Marine TBC 0 to be updated 0
Not started, minor delay for design /
fabrication completion
Jura Ferry - Staff Housing
Subject to Islands Programme funding application - will require
immediate action if succesful Marine 80 0 80
Awaiting outcome of application likely
Q3
Jura Ferry - New Vessel Concept Design
Subject to Islands Programme funding application - will require
immediate action if succesful Marine 300 0 300
Awaiting outcome of application likely
Q3
* Beside a figure indicates an estimate - parts of the project not fully costed or confirmed at this stage Cost RAG rating
Less that 10% overspend
Between 10% and 50% overspend
over 50% overspend
Delivery RAG rating
On time/target
Not started/minor delay
Unexpected issues
Potential Projects - awaiting funding
ResponsibleDetailsProject Name RAG Comment at August 2024Cost RAG Delivery
RAG
Costs (,000)