ARGYLL AND BUTE COUNCIL  ARGYLL & BUTE HARBOUR BOARD
ROADS AND INFRASTRUCTURE SERVICES       20 MARCH 2025 
MARINE ASSET MANAGEMENT PLAN – CRAIGNURE FERRY TERMINAL 
1.0 INTRODUCTION 
1.1 This report provides Harbour Board Members with the latest update on the
proposed ferry terminal project at Craignure, Isle of Mull, and seeks
authorisation to proceed from the Outline Business Case (OBC) and progress to
the next phase, which includes Environmental Impact Assessment (EIA),
planning and licencing. 
1.2 Previously reported costs through the Marine Asset Management Plan are £3M
over the next two years, to reach the construction stage, which includes
completion of business cases, Environmental Impact Assessments, design and
tendering. 
1.3 The next stage will also develop more accurate construction costing estimates
as the design and methodology become more informed. The initial construction
projection cost of £50 million is now estimated at c.£96 million based on
inflationary increases to the original 2020 estimates. 
2.0 RECOMMENDATIONS 
2.1 Members are asked to:
2.1.1 Consider and discuss this update on the new ferry terminal project at Craignure
in conjunction with the Project Forecast (appendix 1).
2.1.2 Note that c.£96 million is the high-level construction projection estimate at present
based on inflationary increases to the 2020 estimates.
2.1.3 Approve the continuation of the project to the next phase of the project with the
option referred to as option ‘D1’ (image 1) as the preferred option.

Page 2

2.1.4 Approve the advisory and consultation structure at 3.5 and described in the terms
of reference for the Working Group (appendix 2), consisting of Working Group
and Reference Group to advise Council Officers and Elected Members. 
3.0 DETAIL 
3.1 Background to the Craignure Pier Development Project
3.1.1 Scottish Government and Transport Scotland strategic planning, as part of the
Islands Connectivity Plan requires Argyll and Bute Council to upgrade the ferry
terminal at Craignure to facilitate planned deployments of new and existing
vessels. 
The existing pier and passenger access are not fit for those plans and so new
infrastructure is required.
3.1.2 Project Scope & Objectives
The Project Scope is defined in the Employer’s Requirements document (a
working document at OBC stage), which defines the infrastructure scope and
performance and capacity requirements. 
The Project Objectives include:
• Replace the existing terminal infrastructure, parts of which are in poor
condition, deteriorating or have limited structural capacity.
• Increase berth capacity at the new ferry terminal to allow the full range of
design vessels to be safely accommodated.
• Ensure vessels can reliably berth year-round at the new ferry terminal,
including in challenging weather conditions and overnight, to reduce
weather-related cancellations and improve the winter timetable.
• Increase resilience of the new ferry terminal operations.
• Allow safe and efficient embarkation and disembarkation for both vehicles
and foot passengers, including those with impaired mobility and wheelchair
users.
• Increase capacity of the new vehicle marshalling area in line with industry
standards, addressing congestion on the A849.
• Provide a new terminal building with modern facilities, meeting staff and
passenger requirements.
• Provide access for RNLI lifeboat, which is used for medical evacuations
from Mull to mainland.
• Avoid and minimise disruption to the ferry service as far as practicable
during the construction works.

Page 3

3.1.3 In order to progress this project, a preferred option should be confirmed so that
detailed designs, cost estimates and construction methods can be developed.
Several different locations have been the subject of extensive discussions and
consultations since the original STAG report was presented in 2019. 
3.1.4 Over this time, a general acceptance was readily apparent that the existing pier
is in the optimal location for the ferry service. Factors such as safe water depth,
recognising residential and commercial areas and prevailing weather direction
all underline the position that the preferred option should be as close to the
existing infrastructure as possible, without intolerable disruption to the existing
ferry service.
3.1.5 A major factor in confirming the location was provided by the Ground
Investigations (GI) carried out last year. 
The GI encompassed an area covering two of the most suitable location options
closest to the existing pier, giving the best information on technical construction
issues like pile size in relation to water depth and the condition of the rock base
of the seabed. It also gave an indication on how close proximity working may
affect the ferry service and mitigations to consider during the construction
phase.
3.1.6 As service continuity during the construction phase is a major concern for all
stakeholders, specific discussions were held with the ferry service provider CFL
/CalMac and vessel Masters. The experience gained from working together
during the GI works and feedback from the Masters of the large vessels
reassured the team that no significant gain would result from a relatively small
increase in the distance of the construction from the existing pier.
3.1.7 The data and information gathered during this period has resulted in the option
that is closer to the existing pier, referred to as D1 (image 1), as the optimal site
for the new infrastructure and is recommended as the preferred option to take
forward.

Page 4

3.2 Preferred option 
Image 1: Preferred option ‘D1’  
3.2.1 Layouts included on the diagram above are largely for information at this point as
those items and details are picked up and refined at the next stage. The footprint
size is based on the maximum area that may be required for operations and may
see some reduction when refined. The EIA and planning are best approached
with this maximum area as a starting point because it is a simpler process to
reduce the scale rather than find during detailed design that the site requires more
space and must therefore reapply for further licences and permissions.
3.2.2 The preferred option location is based on several connected factors and has been
the subject of extensive consultation over a significant period. These discussions
also included the ferry Captains and their professional opinions for future service
needs.
3.2.3 The reasoning is based on:
• Rebuild to north of existing pier.
o The established location is the optimal site for safe water depth and to
have as much of the new infrastructure away from residential areas. 
• As far south as possible with sufficient distance away from the existing pier for
maximum service continuity during construction.

Page 5

o Again, this keeps the building as close to the already established area
of ferry marshalling operations.
o Maximises the northern approach area for the ferry in marginal weather
conditions.
• New pier to be parallel with the existing pier.
o For optimal weather protection.
o The pier heading was confirmed by the ferry Masters as optimal.
• Re-orientate marshalling area to increase efficiency and to reduce ribbon
effect.
o Keeping the infrastructure from spreading along the coast in a thin strip
increasingly remote from the pier.
o Operational area is concentrated around the terminal building and
linkspan. 
3.3 Proposed construction programme
3.3.1 The following is also attached as a PDF in Appendix 1 for ease of reading. 
Image 2: Proposed construction programme 
Notes on programme:
• ** start date is dependent on outcome of EIA determination. If unexpected
surveys are required to confirm information which will impact procurement
& construction methodology, the start date may be postponed until the
survey data can be provided.
• a tender process is expected to be required for the task "Surveys & EIA". 
• the task "Surveys & EIA" is shown as starting in-line with "EIA scoping
opinion review" based on officers and the consulting team having
confidence in the understanding of the survey requirements once the EIA
scoping is complete, rather than waiting for a response before beginning
the works. This is beneficial particularly in relation to seasonal surveys.

Page 6

3.3.2 Anticipated Survey and Technical Requirements
As an indication of the work required in the next phase, the following table is a
summary of the surveys anticipated to be included in the EIA. 
Table 1: Anticipated Survey Requirements
Survey Type Method Brief Explanation
Air Quality monitoring Diffusion tube set-up for
a defined period
Nearest council diffusion tubes are in Oban
https://www.scottishairquality.scot/latest/diffusion-
sites-info/87542
Air Quality data likely needed to inform ES with
regards to impacts of traffic flows on local
environment during construction and operation,
as well as emissions from vessels.
Noise and Vibration
(above ground)
monitoring
Survey equipment in
place for 1 week plus
surveyors taking
measurements on site
Baseline noise data is needed to allow an
assessment of potential effects on sensitive
receptors, notably residential properties in the
vicinity of the ferry terminal. Representative
baseline levels are used to model potential
construction and operational noise levels at these
locations.
Guidance is to avoid summer periods as these
are typically quieter/not normal patterns – we
may recommend a survey that spans both to get
representative ‘commuter’ traffic and
representative ‘tourist’ traffic – TBC by a noise
specialist.
Traffic surveys Surveyor counts on/in
vicinity of site
To inform transport assessment of traffic flows
associated with construction and operation and
to inform air quality/noise assessments – this
data is used to derive forecast flows in the future
to support Air quality and noise assessments.
A clear understanding of current traffic
volumes/congestion will be used to develop the
design requirements of the marshalling yard
redesign.
Underwater noise
monitoring
Static hydrophone Up to date ambient underwater noise levels
during a representative period will be important to
shape the potential effects to sensitive marine
receptors, notably harbour porpoise for which the
adjacent SAC is designated for.
The site is not pristine/undisturbed due to
established ferry routes and therefore the
availability of accurate data will allow a

Page 7

proportionate assessment of underwater noise
generation and propagation.
Bird surveys Surveys of the site over
seasonal period
Glas Eileanan SPA – common tern breeding
Cnuic Agac Cladach Mhuile – golden eagle
breeding
May be required to inform Habitats Regulations
Appraisal of the construction/operation of the
replacement ferry terminal (do not envisage
operational effects but we do need the data on
local bird activity to inform conclusions).
Consultation with Nature Scot recommended
prior to finalising the scope of these surveys.
Marine mammal
surveys
Surveys of the site over
seasonal period
To obtain accurate data on harbour porpoise and
other marine mammal presence within Craignure
Bay and study area to inform marine ecology
effects during construction and operation.
Surveys depends on the target species but
recommend spring/summer to capture most
sensitive period. This will inform any mitigation
required and/or conditions to subsequent
licences.
Consultation with Nature Scot recommended
prior to finalising the scope of these surveys.
Baseline Photography
surveys and ZTV
preparation
Landscape specialists
on site to take
photographs
To inform landscape, seascape and visual
assessments of the proposed development.
Lynn of Lorn National Scenic Area opposite side
of Sound of Mull
ZTV = zone of theoretical visibility to inform need
for assessments
Coastal Modelling Static model equipment Dependent on availability of data and calibrated
models for the area, if not available then Data
used to inform wave action and the detailed
design of the replacement terminal and
reclamation to ensure no significant effects on
wave action and ferry operations. Similarly, the
coastal processes modelling may also be used to
inform the nature of sediment plumes formed
during dredging and where these may travel to
afterwards to deposit which may inform dredge
methods. Sediment budget within the bay.
Sediment and water
sampling –
contaminants
Vibrocore and surface
water sampling to
required dredge depth
and in dredge area
Required to inform dredge licensing to ensure
that contaminants are known within the seabed
sediment and to gather information on water
quality to inform assessments.
Note that this will require its own marine licence
from MD-LOT

Page 8

Sediment/core
sampling – marine
archaeology and
palaeoarchaeology
Vibrocore sampling (as
part of same campaign)
May be required to inform archaeological
assessments of the palaeo-landscape below
seabed level – many parts of the UK were
affected by previous ice age cycles and these
features are present on the seabed.
The need for this activity will be determined by a
suitable archaeological specialist as part of the
EIA Scoping activity
Note that this will require its own marine licence
from MD-LOT (part of the activity above – only
one licence required to cover both)
Site Walkover
(contaminated land)
Up to 2 no. surveyors To inform a contaminated land desk study
required for planning/EIA to inform terrestrial
impacts, due to the requirement to excavate the
site to redevelop.
Scope to be confirmed but considered likely to be
required.
UK Habitat survey Up to 2 no. surveyors To inform BNG requirements as part of planning
and to provide information on ecological impacts
and protected species that may be in the site
boundary.
Statutory requirement of 10% not mandatory in
Scotland but always nice to show possibility of
landscaping and site improvements for local
community – e.g. as part of new terminal
building.
Benthic Ecology
surveys
Vessel grabs and port
structure survey
Could be done as part of sediment vibrocore
campaign to inform assessment of marine
ecology and dredge impacts to any notable
species along with any invasive species present
on port structures to be aware of.
Seasonal – summer survey window (April-Sept).
Scope to be consulted with NatureScot
Revised otter surveys Up to 2 no surveyors To ensure updated survey information is
available at the time of writing the EIA (not for
scoping stage)
Can be done at any time.
Economic Impact Study External An economic impact study may be required to
inform the socioeconomics assessment – this will
look at the potential effects during construction
(on local economy and job opportunities) and
operation (on the local economy and job
opportunities/tourism).
These studies are useful to demonstrate any
forecast demand in ferry access (PAX/Frequency

Page 9

of trips) in line with tourism, local economy and
ferry upgrades. 
3.4 Updated project construction estimate
3.4.1 Previously reported costs are estimated at £3M over the next two years, to reach
construction stage, which includes completion of business cases, Environmental
Impact Assessments, design and tendering.
3.4.2 As reported above, the high-level estimate at present is c.£96 million. This cost
has been developed by taking the total forecast construction project cost in
2020 for option D1 and updating this cost with inflation.
3.4.3 This figure has not been updated since August 2024. When the OBC is
completed an update cost forecast can be provided for further approval by
Members at the next ‘gateway stage’, which will be this time next year before
completion of the FBC.
Inflation has been taken at the mid-point of the construction stage.  This point
in time is January 2028.  The cost has been rounded to the nearest £1000.
3.4.4 The total forecast for the construction phase of the project is c£96 million.
This forecast does not include.
• OBC stage works.
• Works between OBC and construction stage.
• Other associated works out-with the construction stage.
• Costs of any land acquisition. 
3.5 Governance and consultation
The project will follow a recognised route through the approval, procurement and
consultation landscape.
3.5.1 Approval procedure
Craignure port is an Argyll and Bute Council asset, and the governance clearly
sits with Council Members.
The project is one of those being overviewed by senior officials on the Marine
Asset Management Board with approval by Members required at each key
milestone or ‘Gateway’ review. These are points where a review of all the relevant
aspects of the project thus far can be weighed, and a decision made on
proceeding with the next step of the project.
Key milestones are indicated on the project forecast and may be described as
follows:

Page 10

• 2025 March Harbour Board. Completion of the OBC. Selection of a
preferred option and permission to proceed to FBC for more accurate cost
estimates, licencing and surveys.
• 2026 March Harbour Board. Pre-completion of the FBC but in any case,
the procurement and tender updates, cost estimates, EIA and licencing
updates.
• 2026 September Harbour Board. Pre-construction contract award.
Although Craignure port is a Council asset, responsibility for decisions around
the ferry service supported by the terminal is determined ultimately by Transport
Scotland.
For the new infrastructure to be fit for purpose as well as a sound investment
for the future, as clear an understanding as possible of the service needs is
required at an early stage and throughout the process.
Therefore, a technical ‘Working Group’ has been formed from those public
organisations with responsibility and accountability for the service, namely
Argyll and Bute Council (infrastructure), Transport Scotland (strategy), CMAL
(new vessels) and CFL / CalMac (service provider).
The Working Group is referred to as the Craignure Pier Development Working
Group (CPDWG) and have Terms of Reference, which are attached as
appendix B. The Working Group will assist officers on coordination, information
on any changes to vessel or service programmes, make recommendations as
appropriate, act as a check on requirements and provide feedback on
consultation questions and points.
It will be for officers to then advise and recommend to Members based on the
best and most up to date information.
3.5.2 Procurement strategy
The Craignure ferry terminal project is a very large-scale marine construction
project with specific logistical issues associated with island-based works and
specialised construction companies who can provide those works. Marine and
procurement officers are working closely with consultants on an appropriate
procurement strategy that will best provide for a reliable delivery of the project
with a high degree of confidence regarding cost and construction time.
3.5.3 Consultation  
Alongside the ‘Working Group’ the long established Craignure Marine
Infrastructure Liaison Group (CMILG) will continue to be the point of contact
with the Community Councils, ferry groups, residents, businesses and Local
Elected Members. It is an important platform ensuring every voice is heard and
opinion noted and is Chaired by Councillor Armour who is Policy Lead for
Roads, Transport and Amenity Services and sits on the Council’s Harbour
Board. All substantive points raised at the CMILG meetings will be addressed

Page 11

and responded to through the Working Group thus ensuring a qualified reply is
recorded. 
4.0 CONCLUSION 
4.1 This report provides Harbour Board Members with the latest update on the
proposed ferry terminal project at Craignure, Isle of Mull, and seeks authorisation
to proceed from the Outline Business Case (OBC) and progress to the next
phase, which includes Environmental Impact Assessment (EIA), planning and
licencing. 
5.0 IMPLICATIONS
5.1 Policy - None directly arising from this report.
5.2 Financial – Estimated costs for the next phase of the project will be added to
the Marine Asset Management Plan, allowing for the financial implications and
loan planning to be smoothed over an appropriate period.
5.3  Legal - Considered to be none directly arising from this report.
5.4  HR -  None.
5.5  Fairer Scotland Duty:
5.5.1   Equalities - protected characteristics - None directly arising from this
report.
5.5.2   Socio-economic Duty - None directly arising from this report. 
5.5.3  Islands - Completed works and projects will enhance service reliability
and community connectivity.
5.6 Climate Change - There are no direct impacts regarding climate change from
this report, due regard will be given to climate change with a view to minimising
any climate change impact and these will be considered in the Environmental
Impact Assessment for the works. 
5.7 Risk -  A comprehensive Risk Register is maintained for this project. 
Costs may change over time and a realistic risk factor is included in the
estimates.
External influences may come to bear on ferry usage patterns which may, in
turn, impact on income from ferry fees and charges i.e. Vessel breakdowns and
redeployments, Environmental issues (car use), Brexit and potential changes
in RET. This will pose a potential risk to income.

Page 12

5.8  Customer Service - An overall improvement in travel experience and reliability
should result with improved infrastructure.
5.9 The Rights of the Child (UNCRC) - None directly arising from this report. 
Kirsty Flanagan, Executive Director with responsibility for Roads and
Infrastructure Services 
Policy Lead for Roads, Transport and Amenity Services: Councillor John
Armour 
February 2025                                                  
For further information contact:
Scott Reid, Marine Operations Manager Tel: 01546 604 696
Stephen Hall, Interim Head of Roads and Infrastructure Services Tel: 01546 604 324 
APPENDICES
Appendix 1 - Proposed construction programme 
Appendix 2 - Craignure Pier Development Working Group Terms of Reference