ARGYLL AND BUTE COUNCIL     ARGYLL AND BUTE HARBOUR BOARD 
ROADS AND INFRASTRUCTURE SERVICES                         11 SEPTEMBER 2025 
MARINE ASSET MANAGEMENT PLAN – FUNDING 
1.0 EXECUTIVE SUMMARY  
The purpose of this report is to inform Members of discussions and measures
being undertaken by officers to determine options for how the Marine Asset
Management Plan (MAMP) is to be implemented and funded. 
Currently funding for Piers & Harbours is mainly provided by Prudential borrowing
paid back through fees and charges, however external funding can also be
sourced through capital grants, shared cost agreements and funds made
available for specific projects. 
The Marine Asset Management Plan is an adaptable plan fed into by changing
priorities and circumstances. It also relies on steady and predictable income from
those ferry services utilising Argyll & Bute Council infrastructure to repay loan
charges. 
1.1 RECOMMENDATIONS 
The Harbour Board endorse that officers continue to engage with Transport
Scotland on future funding options for the Marine Asset Management Plan,
which could include potential ownership transfer, grant funding and fixed
income model with a future update provided to the Harbour Board.

Page 2

ARGYLL AND BUTE COUNCIL     ARGYLL AND BUTE HARBOUR BOARD 
ROADS AND INFRASTRUCTURE SERVICES    11 SEPTEMBER 2025 
MARINE ASSET MANAGEMENT PLAN – FUNDING 
2.0 INTRODUCTION 
2.1 This report provides Harbour Board Members with an update on the status of
discussions and measures to be explored for funding options for the MAMP.
2.2 It was agreed at the December 2022 Harbour Board meeting that any fees and
charges; “…increase will be in-step with the motion passed at the Harbour
Board meeting in January 2018 that agreed to set charges that meet both the
asset sustainability costs and future improvement costs associated with the
piers and harbours which the Council has a responsibility for.”
2.3 The MAMP was started with a value in the region of £50m spread over a 10-
year interval. It now has a potential value of c.£175m, not including the increase
from the Craignure Ferry Terminal project which has the potential to add a
further £50m to the total.
2.4 As a result of these increases, officers have been engaging with Transport
Scotland and initial discussions have taken place, both in general terms and
within the scope of specific projects or for the Harbour Access agreement with
CalMac.   
3.0 RECOMMENDATIONS 
3.1 The Harbour Board endorse that officers continue to engage with Transport
Scotland on future funding options for the Marine Asset Management Plan,
which could include potential ownership transfer, grant funding and fixed income
model with a future update provided to the Harbour Board.

Page 3

4.0 DETAIL 
4.1 Today funding for Capital works at our Ports and Harbours continues to be mainly
provided by Prudential borrowing paid back through fees and charges, however
external funding can also be sourced through capital grants, shared cost
agreements and funds made available for specific projects.
4.1.1 The Marine Asset Management Plan is an adaptable plan fed into by changing
priorities and circumstances. It also relies on steady and predictable income from
those ferry services utilising Argyll & Bute Council Harbours and infrastructure to
repay loan charges.
4.1.2 Most of the works are to prepare existing port infrastructure in advance of new
vessels being delivered for CalMac ferry services.
4.1.3 Overall, the cost of delivering the programme has risen significantly and the
increase is more than could be expected when the plan was initiated. There are
reasons for that which will be well known to Members, with world events and
other issues taking a toll that must now be recognised in our planning for the
future.
4.1.4 The issues facing the MAMP can be summarised as follows:
i. Guarantees of income over long periods.
To pay off loans and interest that the Council is already committed to and
are needed soon to match vessel delivery times. 
ii. Risk is all with Argyll and Bute Council.
Without an agreement like a Harbour Access Agreement (HAA) with the
operator and / or Transport Scotland the ability to service loans is at risk of
falling income from altered ferry services. An example is the Craignure
route having reduced tonnage resulting in a shortfall in anticipated income. 
iii. Construction time and resources stretched across the network.
With so much work ongoing with Councils and CMAL for the CHIFS
upgrades, consultants are becoming harder and more expensive to
engage, pushing costs even higher. This work also has associated vessel
delivery deadlines, so the ability to spread work and costs are limited. 
iv. Fees and charges becoming high and the need to justify.
The operators and Transport Scotland are increasingly looking to justify
the fees and charges they incur, and high berthing fees may have an
adverse effect on Argyll and Bute Ports and Harbours business.

Page 4

4.3 Future options
4.3.1 Alongside the funding options it is important to note that a Harbour Access
Agreement with CalMac / CFL remains a priority so that the Council and
CalMac / Transport Scotland can plan finances over an agreed period.
4.3.2 Such an agreement would ideally see a single payment per year for berthing
and conservancy fees based on a planned timetable and vessels visiting our
ports, thus protecting the Council’s interests and income should there be
changes to the service, like smaller vessels to replace breakdowns, COVID
timetable cuts etc.
4.3.3 It is now a part of the new Port Marine Safety Code (PMSC) to have these
types of formal agreements in place so more rapid progress on this should be
evident in the coming weeks. 
4.4 Transport Scotland have also floated the idea of a transfer of ownership of
CHIFS Network Ports and mentioned doing this with a package, this is not
necessarily something that either party favour but may be worth exploring. 
4.5 If authorised, it is officer’s intention to progress discussions with Transport
Scotland to determine what feasible choices, costs and savings are
associated with each option.
4.5.1 The discussions will necessarily need to be wide ranged and cover a range of
options. Some examples of topic matter are noted in the following paragraphs. 
4.6 The status quo would see the Council continue with funding projects using the
current Prudential borrowing model. Alongside any reserves, this model has
an ability to smooth out project costs overtime. Expensive projects can use up
reserves very quickly and if they are depleted, the result will be that the more
expensive projects require steeper increases.
4.6.1 A continued ‘partnership’ working alongside CMAL with some shared
contractor framework options, has worked well on shared projects like Port
Askaig and could form a basis for future CHIFS network upgrades. 
4.7 The strategic nature of the infrastructure and how it fits with CHIFS network
upgrades should be recognised and financial assistance could be provided, if
possible, from Transport Scotland to support their network upgrades.
4.7.1 Part grants of up to 60% from Transport Scotland may be available for some
projects, so we would like to understand what projects can receive these
grants, what that process is and any restraints or conditions that would be
imposed.

Page 5

4.7.2 Grant funding discussions may include the Small Vessel Replacement
Programme (SVRP), which involves Fionnphort in phase 1and Gigha
overnight berths, as well as the new Craignure Ferry Terminal.
4.7.3 It is reasonable to expect and explore what positive effect any grant funding
would have on fees and charges for CalMac vessels and how much influence
would provision of grant funds give Transport Scotland over design detail and
costs. Argyll and Bute Council is answerable on a more local level to users
and residents, and the Council must remain wary of that aspect. 
5.0 CONCLUSION 
5.1 This report provides Harbour Board Members with an update on the status of
discussions and measures to be explored for funding options for the MAMP. 
6.0 IMPLICATIONS
6.1 Policy 
None directly arising from this report.
6.2 Financial 
Increases to fees and charges are required to ensure future income is sufficient
to maintain and develop Argyll & Bute Council’s marine assets for future years.
Alternative funding routes will also be explored to support future projects.
6.3  Legal 
Considered to be none directly arising from this report.
6.4  HR 
None.
6.5 Customer Service 
An overall improvement in travel experience and reliability should result with
improved and maintained infrastructure. 
6.6 Risk 
Completed works will reduce the repair and maintenance on existing
infrastructure 
Above inflation increases may have a detrimental economic impact on
businesses using the facilities for example: 
• Fishermen.

Page 6

• bulk importers.
• timber exporters.
• wind farm developers.
• Cruise companies. 
Significant increases may also reduce usage and customers while making
attracting new business more difficult. 
External influences may come to bear on ferry usage patterns which may, in
turn, impact on income from ferry fees and charges i.e. Vessel breakdowns and
redeployments, Environmental issues (car use), Brexit and potential changes in
RET. This will pose a potential risk to income.
6.7 Climate Change 
There are no direct impacts regarding climate change from this report, due
regard will be given to climate change with a view to minimising any climate
change impact and these will be considered as and when they arise.
6.8  Fairer Scotland Duty
None directly arising from this report.
6.9 Equalities - protected characteristics
None directly arising from this report.
6.10 Consumer Duty
None directly arising from this report.
6.11 Island Communities 
Completed works and projects will enhance service reliability and community
connectivity.
6.12 Children’s Rights and Wellbeing 
None directly arising from this report. 
Kirsty Flanagan
Executive Director with responsibility for Roads and Infrastructure Services
Harbour Board Chair: Councillor Ross Moreland
Policy Lead for Transport: Councillor John Armour
August 2025                                                  
For further information contact: Scott Reid, Marine Operations Manager