Democracy Spraffa

Marine Asset Management Plan - Works Update

Argyll and Bute Council · 11 September 2025
Back to Argyll and Bute Harbour Board — 11 September 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL     ARGYLL AND BUTE HARBOUR BOARD
ROADS AND INFRASTRUCTURE SERVICES                          11 SEPTEMBER 2025 
MARINE ASSET MANAGEMENT PLAN – WORKS UPDATE 
1.0 EXECUTIVE SUMMARY  
1.1 The purpose of this report is to update Members on the programmed Capital
works being carried out to develop and upgrade the Council’s marine
infrastructure. 
It includes significant programmes currently planned as well as those underway
which cover ten of our Ports and Harbours and represents a potential
investment of almost £22.5m over the current year. 
Estimates which are included where the project runs beyond the already
approved costs are subject to change depending on design, construction
methods and market issues. The most detailed estimates are naturally focused
on the next 5 years. The plan is adaptable and can change to suit emerging
priorities and circumstances. 
1.2 Members are asked to:
Consider the update on the major programmes currently being addressed within
the Argyll and Bute Council’s MAMP (appendix 1).

Page 2

ARGYLL AND BUTE COUNCIL     ARGYLL AND BUTE HARBOUR BOARD
ROADS AND INFRASTRUCTURE SERVICES                          11 SEPTEMBER 2025 
MARINE ASSET MANAGEMENT PLAN – WORKS UPDATE 
2.0 INTRODUCTION 
2.1 This report provides Harbour Board Members with a review of the marine
infrastructure works contained within the Marine Asset Management Plan
(MAMP). It includes significant and major programmes currently planned as well
as those underway.   
3.0 RECOMMENDATIONS 
3.1 Members are asked to:
3.1.1 Consider the update on the major programmes currently being addressed within
the Argyll and Bute Council’s MAMP (appendix 1) 
4.0 DETAIL 
4.1 The MAMP lists the programmed Capital works being carried out to develop and
upgrade the Council’s marine infrastructure. Estimates are included where the
project runs beyond the already approved costs, and these are subject to
change depending on design, construction methods and market issues. More
detailed estimates are focused on the next 5 years. The plan is adaptable and
can change to suit emerging priorities and circumstances.
4.1.1 The plan contains projects located throughout the Argyll and Bute Council
area, many of which include work to adapt existing, or renew, infrastructure to
support the CalMac Ferry Limited (CFL) services in advance of new vessels
being delivered.
4.1.2 Funding for these Capital projects is mainly delivered by Prudential Borrowing,
paid back through fees and charges collected at our major ports. However,

Page 3

other funding and grant opportunities from other sources are actively explored,
for example Crown Estates Scotland and Transport Scotland.
4.1.3 Projects are competitively tendered to ensure a wide range of quotations,
delivering value for money across a range of suppliers to deliver works to a high
quality and on time. Projects are monitored and re-forecast regularly to manage
risks and adjust budgets where required and in good time. 
4.2 Alongside our maintenance, servicing and conservancy works, there are
presently several long and shorter-term projects across Argyll & Bute which are
listed here.
• Craignure – New Ferry Terminal (including Passenger Access System
refurbishment).
• Iona breakwater – protection of ferry berthing slip.
• Fionnphort overnight berthing facility.
• Port Askaig – Enabling works for new CalMac vessel.
• Campbeltown Harbour – Wall A renewal.
• Rothesay Harbour – phased strengthening works. 
• Feolin – Jura passenger only service access.
• Gigha / Tayinloan – SVRP upgrades including overnight / charging at Gigha. 
4.2.1 Craignure Terminal 
The Council’s Harbour Board Members met on 20 March and approved the
completion of the Outline Business Case (OBC) and a continuation of the
project to the Final Business Case (FBC) pre-construction stage costing
c.£3million. 
The Project Objectives include:
• Replace the existing terminal infrastructure, parts of which are in poor
condition, deteriorating or have limited structural capacity.
• Increase berth capacity at the new ferry terminal to allow the full range of
design vessels to be safely accommodated.
• Ensure vessels can reliably berth year-round at the new ferry terminal,
including in challenging weather conditions and overnight, to reduce
weather-related cancellations and improve the winter timetable.
• Increase resilience of the new ferry terminal operations.

Page 4

• Allow safe and efficient embarkation and disembarkation for both vehicles
and foot passengers, including those with impaired mobility and wheelchair
users.
• Increase capacity of the new vehicle marshalling area in line with industry
standards, addressing congestion on the A849.
• Provide a new terminal building with modern facilities, meeting staff and
passenger requirements.
• Provide access for RNLI lifeboat, which is used for medical evacuations
from Mull to mainland.
• Avoid and minimise disruption to the ferry service as far as practicable
during the construction works. 
This next stage will develop more accurate construction costing estimates as
the design and methodology become more informed. The initial construction
phase projection cost of £50 million is now estimated at c.£96 million based on
inflationary increases to the original 2020 estimates. 
Officers are currently progressing with the tender to appoint the management
consultants who will progress the project to Final Business Case (FBC). The
tender is anticipated to be live by November 2025 with an appointment
expected in January 2026. 
Spend to date: £1,481k 
2025 / 2026: £1,500k 
2026 / 2027: £1,500k 
Current planning figure: £50m 
Longterm Estimate: £100m
4.2.2 Craignure Passenger Access System (PAS) 
The design and build tenders were returned with costs significantly higher than
originally estimated and timescales significantly longer than expected. Officers
have since discussed options with representatives from CMAL and Calmac and
agreed that operationally an inspection and refurbishment of the existing facility
should take place to extend the safe working life of the existing PAS until the
new pier is completed. This is anticipated to include some structural elements,
electrical wiring, painting etc. CMAL and Argyll and Bute Council will work
together to progress this. 
4.2.3 Iona breakwater 
The contractor, Foyle & Marine Dredging Ltd is now fully mobilised to site
following the Marine Directorate license issues, which have now been resolved
resulting in the authorisation to commence laying the breakwater structure. This

Page 5

has resulted in an increase to the cost of the project of around 7%, but officers
are hopeful that this can be mitigated due to the preparation work already
completed. 
Rock material from Northern Ireland and Norway will be used to manage supply
issues with rock from Glensanda Quarry. Works to the existing slipway and new
toilet block, which had continued during the delay, are nearing completion. 
Spend to date: £2,500k 
2025 / 2026: £13,000k 
2026 / 2027: £0 
Current planning figure: £15m 
4.2.4 Fionnphort
Fionnphort overnight berthing facility is progressing to follow on from the Iona
works, for approximately 18 months construction.
Preparation is progressing with Fionnphort to ensure: 
• Overnight berth 
• Safe access for crew 
• Sheltered berthing 
• Charging and supply facilities 
• Traffic survey to enhance the passenger road user interface at the terminal
area. 
An Environmental Impact Assessment (EIA) is in process including the socio-
economic assessment. Design colleagues are continuing to deal with details
with CalMac Marine regarding swept paths and approaches. When Marine
Scotland approve the EIA we will submit construction, dredging and planning
parallel to this Design colleagues will assemble the tender. Public
engagement dates to follow. 
It is reasonable to expect that the seagrass problems on the Iona side will be
the same for Fionnphort, therefore every effort is being made to resolve the
fundamental issue with Transport Scotland and the Marine Directorate. 
Spend to date: £273k 
2025 / 2026: £527k 
2026 / 2027: £20,000k 
Current planning figure: £25.8m

Page 6

4.2.5 Port Askaig
We are progressing with Council works to enhance existing facilities,
consisting of relining, signage, parking allocation, CCTV and traffic access
control installation.
Lining and roundabout and CCTV power have been completed. Signage and
traffic control gates will be installed imminently. We are also discussing details
with CalMac on traffic management measures; information signs and other
facilities staff will require at the port.
Accounts remain for the extra land / overspill area. 
Spend to date: £77k 
2025 / 2026: £1,923k 
2026 / 2027: £0 
Current planning figure: £2m 
4.2.6 Campbeltown
Campbeltown Harbour continues to be very busy commercially. 
Overhauled linkspan cylinders will be reinstated in the coming weeks when
logistics allow and will be followed by the remainder of the linkspan overhaul
and life extension works.
Other business opportunities include using Campbeltown as a strategic
supply hub for the planned offshore wind projects are being explored and this
represents a real opportunity, to develop the Port and secure long-term work
in and from Campbeltown harbour. 
Replacement of ‘Wall A’ at the Old Quay is well underway and due for
completion in October 2025. Concrete and quayside marine fittings have been
completed. 
Spend to date: £3,833k 
2025 / 2026: £3,017k 
2026 / 2027: £0 
Current planning figure: £6m 
4.2.7 Rothesay Quay
Preparations continue for Phase 3 of the overall works, which will see a
strengthening of the east roundhead and will include fender renewals. Stage 1
of this project requires an existing bollard to be relocated off the roundhead.
This work is currently at the design stage and is planned for tender around

Page 7

early Autumn 2025 with works to relocate the bollard occurring over late
Autumn / Winter 2025. 
Spend to date: £1994k 
2025 / 2026: £500k 
2026 / 2027: £2,000k 
Current planning figure: £2.5m 
4.2.8 Feolin
We will be installing a passenger only access at Feolin, for those periods
when the vehicular vessel is not available and the service would otherwise be
cancelled. Although these occasions are relatively rare, we recognised the
need for a replacement to the ladder access used at present. 
A plan for concrete steps between the existing dolphins following a more
traditional design has been drawn up and approvals received. Officers are
hopeful work will be underway in the coming weeks.
(Other funding £100k total) 
4.2.9 Gigha and Tayinloan
These plans include and overnight berthing and charging facility upgrade at
Gigha, able to accommodate the new SVRP vessels being constructed by
CMAL. There are also accommodating upgrades required at Tayinloan that
along with the new vessels should see an improved service to and from
Gigha.
Further public consultation was carried out by Officers on 27th / 28th August.
Ground Investigation work has now been completed at the locations, and this
will help with refining the construction plans and methodology. Officers are
now progressing licenses for dredging and construction and preparing to
submit documents for Planning Permission. 
Spend to date: £242k 
2025 / 2026: £1,000k 
2026 / 2027: £500K 
Current planning figure: £12.4m

Page 8

5.0 CONCLUSION
5.1 This report provides Harbour Board Members with a review of the marine
infrastructure works contained within the Marine Asset Management Plan
(MAMP). It includes significant and major programmes currently planned as well
as those underway. 
6.0 IMPLICATIONS
6.1 Policy 
None directly arising from this report.
6.2 Financial 
Increases to fees and charges are required to ensure future income is sufficient
to maintain and develop Argyll & Bute Council’s marine assets for future years.
Alternative funding routes will also be explored to support future projects.
6.3  Legal 
Considered to be none directly arising from this report.
6.4  HR 
None.
6.5 Customer Service 
An overall improvement in travel experience and reliability should result with
improved and maintained infrastructure. 
6.6 Risk 
Completed works will reduce the repair and maintenance on existing
infrastructure 
Above inflation increases may have a detrimental economic impact on
businesses using the facilities for example: 
• Fishermen.
• bulk importers.
• timber exporters.
• wind farm developers.
• Cruise companies. 
Significant increases may also reduce usage and customers while making
attracting new business more difficult. 
External influences may come to bear on ferry usage patterns which may, in
turn, impact on income from ferry fees and charges i.e. Vessel breakdowns and

Page 9

redeployments, Environmental issues (car use), Brexit and potential changes in
RET. This will pose a potential risk to income.
6.7 Climate Change 
There are no direct impacts regarding climate change from this report, due
regard will be given to climate change with a view to minimising any climate
change impact and these will be considered as and when they arise.
6.8  Fairer Scotland Duty
None directly arising from this report.
6.9 Equalities - protected characteristics
None directly arising from this report.
6.10 Consumer Duty
None directly arising from this report.
6.11 Island Communities 
Completed works and projects will enhance service reliability and community
connectivity.
6.12 Children’s Rights and Wellbeing 
None directly arising from this report. 
Kirsty Flanagan
Executive Director with responsibility for Roads and Infrastructure Services
Harbour Board Chair: Councillor Ross Moreland
Policy Lead for Transport: Councillor John Armour
August 2025                                                  
For further information contact: Scott Reid, Marine Operations Manager 
APPENDICES
Appendix 1 Marine Asset Management Plan