Argyll and Bute Council
Comhairle Earra-Ghàidheal Agus Bhòid 
Executive Director:  Douglas Hendry 
Kilmory, Lochgilphead, PA31 8RT
Tel:  01546 602127  Fax:  01546 604435
DX 599700 LOCHGILPHEAD 
24 June 2022 
SUPPLEMENTARY PACK 1 
ARGYLL AND BUTE COUNCIL - BY MS TEAMS on THURSDAY, 30 JUNE 2022 at 10:30 AM 
I enclose herewith item 10 (Levelling Up Fund) which was marked to follow on the Agenda for
the above meeting. 
Douglas Hendry
Executive Director 
ITEM TO FOLLOW 
10. LEVELLING UP FUND - BUSINESS CASE AND BID SUBMISSION UPDATE 
Report by Executive Director with responsibility for Development and Economic
Growth  (Pages 3 - 14) 
Argyll and Bute Council 
Contact: Sandra Campbell  Tel: 01546 604401
Public Document Pack

Page 2

This page is intentionally left blank

Page 3

ARGYLL AND BUTE COUNCIL COUNCIL
DEVELOPMENT AND
INFRASTRUCTURE 
30 JUNE 2022 
UK LEVELLING UP FUND – BUSINESS CASE AND BID SUBMISSION UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 The purpose of this report is to inform members of the Council on the final
position and key principles concerning the Levelling Up Business Cases for
both of the council’s levelling up bids.  The report confirms the different
elements of each of the bids  being submitted to the UK Government and looks
for council agreement regarding the principle of match funding in the event that
one or both of the bids being successful.   
1.2 The bids have been prepared across a range of council services, working with
partners, and consultants.  Public consultation has been taken forward through
stakeholder groups and further refinement of the projects will be necessary if
either of the bids are successful through the finalisation of designs and
regulatory processes. 
1.3 The council has chosen to prepare packaged bids to better reflect the
economic, population and geographic challenges of Argyll and Bute as a
predominately rural region.   It is considered that these bids could be
potentially transformational for our economy, as a place to live, invest and visit. 
The bids take account of strict delivery deadlines of the fund spending profile
and the need to reach net zero.  The fund is highly competitive with no
guarantee of success however all of the work to date has helped to develop
the different project elements of each bid package to a shovel ready status. 
1.4 There is a need to indicate where a minimum of 10% of match funding will
come from and this is detailed in Table 1 of the report.  Individual elements of
the projects have been identified in Tables A to D. Due to the dependency on
attracting external funding elements for the regeneration bid, a phased
approach may need to be taken. 
1.5 The deadline for submission of the respective business cases is 6th July 2022. 
One bid will be for an area regeneration town centre project, maximum £20m
and the second a Transport Bid, up to £50m. 
RECOMMENDATIONS 
It is recommended that the Council: 
a) Consider and approve the individual elements of the bids being
submitted.
Page 3 Agenda Item 10

Page 4

b) Consider and approve in principle the identified match funding for each
bid.
c) Agree that the final approval of the business case and submission of the
Council’s LUF application be delegated to the two Executive Directors in
consultation with the Leader and Depute Leader of the Council and the
Leader of the largest Opposition Group by the deadline of 6th July 2022.  
Page 4

Page 5

ARGYLL AND BUTE COUNCIL COUNCIL
DEVELOPMENT AND
INFRASTRUCTURE 
30 JUNE 2022 
UK LEVELLING UP FUND – BUSINESS CASE AND BID SUBMISSION UPDATE 
2.0 INTRODUCTION 
2.1 This report provides an update on the Levelling Up Bids respective Business
Cases and following approval their proposed submission of two bids, one
concerned with regeneration and one concerned with transport, to the UK
Government. 
2.2 The UK Government’s Levelling-Up Fund was announced by the Chancellor at
the 2020 Spending Review. It is a fund jointly managed by HM Treasury, the
Department for Levelling Up, Housing and Communities and the Department
for Transport. It is worth £4.8 billion and is intended to support capital
investment projects in town centre and high street regeneration, local transport
projects, and cultural and heritage assets which must be bid for via a
competition. 
2.3 The fund focuses investment on regeneration projects that require up to £20m
of funding. There is however no minimum bid level. For higher value transport
schemes, there is also scope in securing investment in larger projects up to
£50m by exception, but these will be subject to more detailed business case
processes and will need to score highly overall across the bidding criteria.
There are additional compliance requirements for the Public Sector Equality
Duty and State Aid rules. This is therefore a highly competitive process with no
guarantee of success. 
2.4 All bids need to have the approval of the Council responsible for delivering
them and the relevant Transport Authority (in our case the Council and Trunk
Roads).  There needs to be consultation with a range of local stakeholders,
evidence of which has to be submitted as part of the application. Constituency
MPs must also be consulted, although support from the local MP is not a
necessary condition for a successful bid. The deadline for submission is 6th
July 2022. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that the Council: 
a) Consider and approve the individual elements of the bids being
submitted.
b) Consider and approve in principle the identified match funding for each
bid.
Page 5

Page 6

c) Agree that the final approval of the business case and submission of the
Council’s LUF application be delegated to the two Executive Directors in
consultation with the Leader and Depute Leader of the Council and the
Leader of the largest Opposition Group by the deadline of 6th July 2022. 
4.0 DETAIL 
4.1 Officers of the council, working across a number of services, have been
collaborating with our partners, together with our consultants, to prepare two
separate bids to the UK Levelling Up Fund. 
4.2 Members have been regularly informed with progress concerning the bids
following the initial member workshops that identified the Council’s priority
projects, with the most recent update provided at the May 2022 meeting of the
Council and subsequent briefing updates.  Given the extensive geography of
Argyll and Bute, the council decided to submit two package bids involving a
number of distinct geographical areas and not to focus on a single project for
each bid.  This approach reflects the specific challenges, and also the
opportunities of a large rural Local Authority such as Argyll and Bute. 
4.3 The Levelling Up Bids need to take account of the UK Government Business
Case guidance which was only issued on 13th April 2022.  This has been a
very challenging process for the council to undertake.  Each bid requires a
considerable amount of supporting information and this has informed and
substantially altered the content of our final proposals in order to make the best
business case possible for this transformational capital funding.  It should be
noted that inflation has substantially reduced the scale of the bids and what
can be achieved.  Each bid has to take into account inflationary pressures for
the next 3 years including specific island cost pressures. 
4.4 It should be noted by members that each bid will require a minimum of 10%
match funding and where possible we have utilised external funding sources
from partners and existing council commitments.  However, in respect of the
regeneration bid, due to the dependency on attracting external funding
elements, a phased approach may need to be taken. In some cases the bid
seeks to add value to a complementary infrastructure investment. Table 1
identifies proposed match funding sources.  It should be noted that some of the
figures presented in the tables are estimates and could be subject to change. 
The use of this identified match funding will depend on whether the bids are
successful, or not. Individual elements of the Bids are included in Tables A to
D. It is expected that the UK Government will make a decision on the bids in
the Autumn albeit this may be subject to delays given the high number of bids
anticipated.   
4.5  You will see from Table 1 that the regeneration bid proposes to include a
greater amount than the minimum 10% match funding required.  The reason
for this is due to the amount of works required to meet project objectives,
adhere to bid criteria combined with exceptional inflationary pressures at this
time, which require to be factored in to our bid, and in particular the costs
associated with restoring the former Royal Hotel and Dunoon Pier.  In regard
to Dunoon, a lot of the match funding relates to works and investment that the
Page 6

Page 7

Council would be undertaking.  It is hoped that the UK Government will see the
overall objective and the significant return that they will gain from this
investment. The council will look to attract additional external funding wherever
possible to meet this match requirement.   
Table 1 
Transportation Bid - Connected Argyll and Bute
Projects Total £m LUF £m Match
£m Source Match % 
Port Askaig marshalling*  2.2 2.2   
Jura ferry replacement
incl infrastructure
upgrades at Feolin to
accommodate ferry 
9.0 9.0   
B8016 Port Askaig - Port
Ellen LGV 12.0 12.0   
A846 Port Askaig - Port
Ellen Active travel
Included in above    
Bowmore-Bridgend
Active travel 5.8 5.2 0.6
Transport
Scotland
Places (to be
secured)  
Dunbeg housing and
commercial area - road
and active travel
infrastructure
14.3 11.4 2.9 TIF 
Regeneration Bid – Rothesay & Dunoon Marine Gateways 
Projects  Total £m  LUF £m  Match
£m 
Potential
Source 
Match % 
Rothesay  11.4  8.0  3.4
RGD / RCGF* /
Cycling Walking
Safer Streets /
IIF* / Existing
project / HES* /
NLHF* 
Dunoon  18.1  12.0  6.1 
Existing project
/ Prudential
Borrowing /
RGD / HES* /
Crown Estates 
Totals  29.5 20.0 9.5  32.2% 
*subject to successful applications to external funders 
Page 7

Page 8

Commercial area
platform (regeneration –
must be less than 10%
value
Included in above 
UAV airside hanger; Non-
airside tent or building
(TBD); LED lights and
solar panels
6.5 5.8 0.7 RGD 
Hydroban (garage
adaptations; storage
tanks; hydrogen
dispensers; buses)
4.0 2.8 1.25 Private 
Totals 53.8 48.4 5.45  10.0% 
4.6 The Bids are included in two separate programmes:- 
 The Regeneration Bid up to £20m – Argyll and Bute Western
Seaboard Marine Gateways Initiative – Rothesay and Dunoon.  
 The Transport Bid up to £50m – Connected Argyll and Bute –
Whisky Islands; and North Lorn Economic Growth Zone. 
4.7 The Regeneration Bid – Argyll and Bute Western Seaboard Marine
Gateways Initiative – Rothesay and Dunoon.   
This bid focusses on Rothesay and Dunoon linked by the Clyde and their
history as seaside holiday destinations.  Both these communities have higher
than average claimant counts and areas of deprivation that have proved
difficult to address over a number of decades.  There is a clear demonstrable
need for investment in these communities building upon what the council and
our partners have already taken forward in terms of place based investment.   
4.8 In Rothesay, the focus of the bid is the restoration of the former Royal Hotel
that dominates the main ferry entrance to the Island of Bute. The bid aims to
establish key worker housing on the upper floors of the building creating 12
units for rent and a commercial space on the ground floor likely targeted at
public/voluntary sectors given the central location of the building in the heart of
the town centre. The remaining works relate to the upgrading of the adjacent
Guildford Square and surrounding public realm areas with active travel routes. 
Unfortunately, the estimated costs of these works which have had to factor in
inflation and other locational costs to minimise risk to the council.  This
approach has limited what we can do with the money available including
possible match funding.  Consequently, the submitted masterplan will have to
take a phased approach to delivery with the Levelling Up Fund as the critical
starting point.   
Page 8

Page 9

Table A 
Projects Total £m LUF £m Match
£m Source
Royal Hotel  5.3  
4.0(tbc
as
subject to
state
subsidy
control)
1.3 
RCGF* /
Existing
Project /
HES* /
NLHF*
Public realm enhancements, including:
active travel and interventions to
Guildford Square, Harbour Area,
Esplanade, Royal Hotel Area, Winter
Gardens and Victoria and Argyle
Streets
6.1  4.0  2.0 
RGD /
Cycling
Walking
Safer
Streets /
IIF*
Totals 11.4 8.0 3.4 
*subject to successful applications to external funders 
4.9 In Dunoon, the focus of the bid is the waterfront area and the iconic wooden
pier.  The bid includes the retention of the grade A listed Signal Tower
structure and a partial restoration of the pier timber structure.  In addition, the
bid aims to upgrade the adjacent marshalling area and carpark areas including
a further upgrade of the Argyll Gardens as a multi-purpose events space. The
aim here is to create a flexible events/festival area but at the same time keep
the functionality of the area to enable people to easily access the ferry, the
Queens Hall and town centre. A key aim is to improve the wellbeing of people,
creating a place where people feel safe with the ability to undertake a range of
activities using the space created.  The proposal also includes better active
travel links and small areas of green space helping to reach net zero. Again, a
phased approach to our overall ambition will have to be taken with Levelling
Up Funding a critical first step. 
Table B 
Projects Total £m LUF £m Match
£m Source
Public realm enhancements, including:
active travel, and interventions to
Argyll Gardens, Coal Pier Car Park,
Terminal Area 
8.6  6.0  2.6 
RGD /
Crown
Estates /
Existing
Project /
Cycle
Walking
Safer
Streets
Restored Dunoon Wooden Pier
(Option 2)
8.4 (tbc) 6.0 2.4
RGD /
HES*/
NLHF*
Page 9

Page 10

New harbourmasters and waiting room
building  1.1  0.0  1.1  Prudential
Borrowing
Totals 18.1 12.0 6.1 
*subject to successful applications to external funders 
4.10 In terms of match funding there will be a need to call on future place making
and Crown Estate external funding streams together with possible Rural
Growth Deal Funding under the theme of tourism and place for both locations. 
In Rothesay the Royal Hotel may also require funding associated with the
Rural Growth Deal funding in relation to the housing theme and the council’s
Strategic Housing Fund.  The Royal Hotel is likely to be a joint venture with the
private sector owner and may be subject to state subsidy issues depending on
the final ownership of the building. 
4.11  The Transport Bid - £50m – Connected Argyll and Bute – Whisky Islands;
and Lorn Economic Growth Zone. 
This bid concerns a package of proposals that initially covered three areas of
Argyll and Bute.  Work on preparing the feasibility of individual elements of the
bid unfortunately led to the Helensburgh and Lomond elements having to be
removed and this was reported to Elected Members outwith the committee
process.  As further costings have been determined, it has been apparent that
the bid needs to be scaled back further and the North Islay Active Travel Route
and the Craignure to Salen road improvement has been removed from the bid.
The reason for this is due to the costs associated with each of these elements
and our lack of potential match funding to ensure delivery within the specified
timeframe.   The council will continue to seek external funding to progress
these different elements, which still remain as council priorities subject to the
availability of funding.   
4.12 The remaining elements are focussed in two distinct areas of Argyll and Bute. 
The islands of Islay and Jura (whisky islands) and the North Lorn
Economic Growth Zone.  Both areas are linked by their significant economic
and population growth potential which is held back by a lack of modern
transport infrastructure.   
4.13 In terms of Islay and Jura, the whisky (spirits) industry continues to expand
with a doubling of production levels of existing distilleries and new distilleries
coming forward on a regular basis through the planning process including two
distilleries currently being constructed at Port Ellen.  This expansion also
supports the parallel growth of the tourism industry and has placed a
significant strain on the islands economic infrastructure.  Taking account of
previous research and recent consultation with key stakeholders, the focus on
the bid is around the capacity of the Jura Ferry and its replacement with a
larger capacity but lower carbon vessel together with improved port side
facilities.  Improvements to Port Askaig (council owned asset) will also assist
with the need to have greater capacity at Islay’s ports to cope with larger
ferries commissioned by the Scottish Government.  
Page 10

Page 11

4.14 This demonstrable increase in business activity and the need for increased
port capacity has also influenced the need to improve the key arterial road
routes of Islay that connect both ferry terminals. The key aspects of the bid
include making strategic improvements to the B8016 as a dedicated freight use
for HGVs and improved active travel routes adjacent to the A846 which will be
prioritised for resident and visitor traffic.   
4.15 It is intended to package this bid with the CMAL investment at the Port Ellen
ferry port.   
Table C 
Projects Total £m LUF £m Match
£m Source
Port Askaig marshalling* 2.2 2.2    
Jura ferry replacement incl
infrastructure upgrades at Feolin to
accommodate ferry
9.0 9.0  
B8016 Port Askaig - Port Ellen LGV  12.0  12.0  
A846 Port Askaig - Port Ellen Active
travel Included in above  
Bowmore-Bridgend Active travel 5.8 5.2 0.6
Transport
Scotland
Places
(to be
secured)
Totals 29.0 28.4 0.6 
4.16 North Lorn Economic Growth Zone. This element of the Transport bid
focuses on North Lorn and Mull.  This is an area of Argyll and Bute with real
growth potential in terms of population and economic growth in the fields of
innovation, education and tourism.  In common with Islay/Jura this growth
potential is held back by a lack of critical transport infrastructure which this bid
intends to help address.  Elements of the bid include a contribution to the
development of the Dunbeg Corridor with the construction of the half way
roundabout and associated link road to a proposed commercial area that has
been identified in the Local Development Plan.  This will help enable the
construction of a new link road to create a secondary access to Dunbeg to help
enable a further phase of housing intended to be mixed tenure. It is estimated
at this stage that in excess of 400 additional houses could be created here in
Dunbeg providing much needed housing choice.   
4.17 In addition, 2 hydrogen buses to serve local communities together with a green
hydrogen fuelling station will be built in Oban working in partnership with Green
Power.  This will help Argyll and Bute reach net zero and a further element
involves the development of a UAV Hub at Oban Airport expanding on what is
already envisaged at Oban Airport.   
Page 11

Page 12

Table D 
Projects Total £m LUF £m Match
£m Source
Dunbeg housing and commercial area -
road and active travel infrastructure
14.3 11.4 2.9 TIF 
Commercial area platform (regeneration –
must be less than 10% value Included in above 
UAV airside hanger; Non-airside tent or
building (TBD); LED lights and solar
panels
6.5 5.8 0.7 RGD
Hydroban (garage adaptations; storage
tanks; hydrogen dispensers; buses)
4.0  2.8  1.25  Private 
Totals 24.8 20.0 4.85 
4.18 This is a highly ambitious bid containing potentially transformational investment
for Islay/Jura and North Lorn Economic Zone.  Match funding is intended to come
from the Lorn Arc TIF funding, Rural Growth Deal funding in relation to the UAV
hub, active travel funding and Green Power private sector funding.  (See Table 1
of this report).  A bid of £50m is considered exceptional by the UK Government
but the council considers that this scale of investment is critical to the future
success of both these areas and indeed wider Argyll and Bute. 
5.0 CONCLUSION 
5.1 Two bids for the UK Levelling Up Fund, one in relation to Regeneration
activity and one relating to Transport have been prepared by council officers
working across council services and also with partners and consultants.  This
has been a substantial area of work requiring a considerable amount of
justification.  The business case application forms are attached to this report as
appendices and the main elements of each bid have been included in this
report (See Tables A to D) and summarised in a number of tables embedded
in this report. 
5.2 Table 1 of this report identifies potential match funding that is a requirement of
the bid and members are asked to consider this as part of the decision making
process. This will be taken from a range of sources including elements of
capital funding spread over 2/3 years from roads, active travel and ports and
harbours.  Projects may also be supported through additional external funding
sources such as place making and crown estate funding together with the
Rural Growth Deal.   
5.3 It is considered that these bids are potentially transformational for a number of
our Argyll and Bute communities helping to deliver population and economic
growth whilst at the same time helping to reduce our overall carbon footprint.
The UK Levelling Up Fund is a highly competitive fund and there is no
Page 12

Page 13

guarantee for success.  That said, the work done to help prepare these bids
helps support our call for increased capital investment across Argyll and Bute
to address our challenges and opportunities. Following consideration by
members and approval, the bids will be submitted to meet the deadline of the
Round 2 of the UK Levelling Up Fund on 6th July 2022. If the bids are
successful work will then commence to develop the bids further guiding them
through the regulatory process and further engagement with local
communities. 
5.4 The decision on both the bids from the UK Government is expected in the
Autumn, however given the high number of bids expected there could
potentially be a delay in any announcement. 
6.0  IMPLICATIONS 
6.1 Policy – The projects selected all comply with Council established policy. 
6.2 Financial – The £125,000 received from UK Government to develop the bids is
and the February approval of a further £150,000 from the recovery and
renewal fund is sufficient at this time to make the bids.  The report identifies
the need for possible match funding and has identified possible sources in
Table 1 of this report. 
6.3 Legal – None arising from this report however legal agreements may have to
be entered into with relevant partners. The question of state subsidy has been
raised and this is currently being investigated further. 
6.4 HR – none arising from this report but in the event of being successful
additional staff may be required to implement the project.  Management costs
have been built into the bid 
6.5 Fairer Scotland Duty:
6.5.1 Equalities – None identified at this stage. 
6.5.2 Socio-economic Duty – the projects are designed to offer improve socio-
economic opportunities for local communities.
6.5.3 Islands – A number of the projects have positive implications for island
communities. 
6.6 Climate Change – The projects are aiming to help Argyll and Bute reach net
zero through active travel, repurposing town centre buildings, low carbon
buses and ferries. 
6.7 Risk – The main risk remains in not having sufficient time, to deliver the bid if
successful.  This will need to be mitigated through good governance, project
management and having sufficient resources in place to do the work. 
6.8 Customer Service – nothing arising from this report 
Page 13

Page 14

Kirsty Flanagan, with responsibility for Development and Economic
Growth/Roads and Infrastructure Services 
Fergus Murray, Head of Development and Economic Growth 
Jim Smith, Head of Roads and Infrastructure 
24 June 2022 
For further information, please contact:  
Fergus Murray, Head of Development and Economic Growth 
Fergus.Murray@argyll-bute.gov.uk 
Page 14