ARGYLL AND BUTE COUNCIL  COUNCIL 
DEVELOPMENT AND ECONOMIC
GROWTH  
30 JUNE 2022 
STRATEGIC HOUSING FUND APPLICATION – ISLAND OF ULVA 
1.0 EXECUTIVE SUMMARY
1.1 The main purpose of this report is to update members on progress in relation
to the refurbishment of 6 properties on the island of Ulva by the North West
Mull Community Woodland Company (NWMCWC) and to request an
additional Strategic Housing Fund payment to enable the delivery of the 6
affordable houses on the island of Ulva. 
RECOMMENDATIONS
Members are asked to approve the sum of £90,663 from the Strategic
Housing Fund. This is in addition to the £12,000 per unit (£72,000 in total)
Officer mandate grant already approved from the Strategic Housing Fund for
this project.

Page 2

ARGYLL AND BUTE COUNCIL  COUNCIL 
DEVELOPMENT AND ECONOMIC
GROWTH  
30 JUNE 2022 
STRATEGIC HOUSING FUND APPLICATION – ISLAND OF ULVA 
2.0 INTRODUCTION
2.1 The North West Mull Community Woodland Company (NWMCWC) purchased
the island of Ulva in 21st June 2018 via the Community Right to Buy process.
The purchase price was £4.65 million with £4.25 million funding from the
Scottish Land Fund. The remainder of the funding came from other sources
such as private donations, local and internet based fund raising. One of the key
actions of the NWMCW was to refurbish the 6 properties of the island of Ulva
to assist with the repopulation of the island.   
2.2  The Council has previously approved significant Strategic Housing Fund
contributions to enable the delivery of affordable housing in areas of high
housing need in the local authority.  In November 2021, the Council approved
£168,999 from the Strategic Housing Fund to enable the development of 5
affordable houses at Port Mor on Colonsay.   
3.0 RECOMMENDATIONS
3.1 Members are asked to approve the sum of £90,663 from the Strategic
Housing Fund. This is in addition to the £12,000 per unit (£72,000 in total)
Officer mandate grant already approved from the Strategic Housing Fund for
this project. 
4.0 BACKGROUND
4.1 In June 2018, the North West Mull Community Woodland Company
(NWMCWC) purchased the island of Ulva via the Community Right to Buy
process. The purchase price was £4.65 million with £4.25 million funding from
the Scottish Land Fund. The remainder of funding came other sources such as
private donations, local and internet based fund raising. Funding was put in
place for a Development Manager, a part time Administrator, a Land Use
survey, a Bio Diversity Action plan survey and initial design work for the housing
refurbishment. 
4.2 One of the key aims of the NWMCWC for Ulva is to repopulate the island from 5
residents to 20 residents in the first 10 years initially through renovating the

Page 3

existing properties on the island. Work is also ongoing with ACHA to look at
building 5 new affordable houses on the island by 2024. Bringing new people to
Ulva will be both critical to developing a thriving and sustainable community and
ensuring there are a range of skills to help deliver the projects proposed for the
island. This fits well with the council’s priority to increase our population. 
4.3 In conjunction with the housing provision there are plans to restore and repurpose
the listed buildings of Telford Church and Ulva House in due course and as funds
permit. 
4.4 Plans to return abandoned and neglected agricultural land to productive use have
been implemented as part of a 5 year ACES programme (Agri Climate
Environment Scheme). 34 Highland cattle were purchased in 2019, new stock
fencing has been installed and some bracken control measures carried out. A new
stockman is due to start work at the beginning of June 2022. An overall Land
Management Plan has been developed and a full ecological survey of the island
undertaken. An upgrade to the pier at Ulva Ferry is underway which will make it
safer for the fishermen (there are 7 boats based there) and users of the Ulva Ferry. 
5.0 DETAIL 
5.1 NWMCWC is currently part way through the refurbishment of the 6 existing
properties, at an estimated cost of £1.8M. All were deemed to be below the
Tolerable Standard so required extensive work to turn them into modern and
affordable housing stock. Essentially each property is being stripped back
internally to the bare walls and rebuilt (including new roofs where necessary).
All houses will be fully insulated, double glazed and new air source heat
pumps are being installed to ensure they are as energy efficient as possible. 
5.2 During the course of renovations it has become apparent that the existing
septic tanks serving the properties have not been emptied for years and as a
result are now broken beyond repair and not functioning. They all require to
be replaced. This is outside the original scope of the works agreed for the
refurbishments but critical to NWMCWC’s ability to let the renovated
properties. 
5.3 Two new treatment plants, repairs and improvements to the existing sewerage
system are required at a cost of £72,530.  Due to Ulva’s geology rock
breaking equipment is required to prepare sites at both Fisherman’s Cottage
and Bracadale. The contractor has stated clearly that the costs are indicative,
in so far as they cannot tell precisely how long it is going to take to remove the
rock. The other issue that have raised concerns about is with regards the
state of the present access tracks and their ability to get machinery of the
required size and nature out to each location, in order to actually do the work.
No provision has been made for any costs that would be associated with the
repair/improvement/upgrade of these existing tracks. 
5.4 These costs are inclusive of transportation of the units and appropriate site
preparation equipment to the island. However, given that the extent of the
excavations required and the ease with which it can be done, is at the time of

Page 4

writing this report unknown (as articulated above), a 20% contingency sum of
£18,133 has been added to the sum requested – this will only be issued to
NWMCWC if required.  In the event of the full amount not being required, the
remaining funds will be returned to the Strategic Housing Fund. 
6.0  FUTURE PLANS 
6.1 It is important to acknowledge the new housing is not being taken forward in
isolation and conforms to an approved masterplan. NWMCWC are putting in
place plans to maintain and upgrade critical infrastructure on the island. A
new UV water treatment unit is due to be installed by the end of June. This
will provide sufficient capacity to cover projected increases in population
levels and visitor numbers. Longer term, it has been recommended that the
primary source for the water on Ulva be changed from the current spring
source back to the original reservoir source, again so there is sufficient
storage capacity to deal with increasing demand as the island population and
the island economy grows. This will require NWMCWC to source additional
funding at some point to cover the costs of repairing the existing reservoir and
installing new pipe work and a settling tank. 
6.2 Proposals for a new ferry with capacity to goods as well as passengers have
been drawn up with assistance from a naval architect and it is hoped that this
can go forward to an Islands Infrastructure Fund in the future. Having a new,
fit for purpose boat will make the logistics of maintenance and development
activities much easier as well as having a positive impact on the costs of
undertaking such work in the future. 
6.3 Any new housing built on the island in addition to the work that is already
underway, will require to have its own sewage treatment system. 
7.0 CONCLUSION
7.1 This report provides the detail of the additional works required to enable the
delivery of 6 affordable homes on Ulva. This costs of this additional work are
clearly set out in the report.  The Ulva community have an ambition to grow their
population and their economy following the purchase of the island. The provision
of affordable housing in remote rural and island areas of Argyll is essential to the
economic and population growth objectives of both the Ulva community and the
Council. 
8.0 IMPLICATIONS 
8.1 Policy - Complies with the objectives of the Local Housing Strategy. 
8.2 Financial - £90,663 will be required from the Strategic Housing Fund. 
8.3  Legal - we have a statutory duty to deliver statutory housing functions

Page 5

8.4  HR – none. 
8.5  Fairer Scotland Duty: positive in terms of delivering affordable housing.  
8.5.1 Equalities - protected characteristics - none  
8.5.2 Socio-economic Duty - positive in terms of delivering affordable
housing.  
8.5.3 Islands – positive in terms of delivering affordable housing on
the islands 
8.6 Climate Change – the upgrading of housing will have a positive impact for
energy efficiency and climate change. 
8.7 Risk – none. 
8.8  Customer Service – none. 
Kirsty Flanagan, Executive Director with the responsibility for Development and
Economic Growth 
Policy Lead for Economy and Rural Growth: Councillor Robin Currie
Policy Lead for Islands and Business Development: Councillor Liz McCabe 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth 
Fergus.Murray@argyll-bute.gov.uk 
Douglas Whyte, Team Lead – Housing Strategy
douglas.whyte@argyll-bute.gov.uk