ARGYLL  AND BUTE COUNCIL  COUNCIL  
FINANCIAL SERVICES 30 JUNE 2022 
CAPITAL BUDGET MONITORING REPORT – 31 MARCH 2022 
1.0 EXECUTIVE SUMMARY 
1.1 This report provides an update on the position of the capital budget as at 31
March 2022. The report provides information on the financial position in respect
of the capital plan and also the performance in terms of delivery of capital plan
projects. 
1.2  Financial Position: 
• Outturn for 2021-22 – actual net expenditure for the full financial year is
£24,831k compared to an annual budget of £31,012k giving rise to an
underspend for the year of £6,181k (19.9%).  
• Total Capital Plan – forecast total net project costs on the total capital
plan are £194,796k compared to a total budget for all projects of
£194,701k giving rise to a forecast overspend for the overall capital plan
of £95k (0.05%). 
1.3 Project Delivery: 
• Asset Sustainability – Out of 112 projects there are 63 projects (56%) on
track, 49 projects (44%) off track but recoverable and 0 projects off track
(0%).
• Service Development - Out of 42 projects there are 23 projects (55%) on
track, 19 projects (45%) off track but recoverable and 0 projects (0%) off
track.
• Strategic Change – Out of 26 projects there are 8 projects (31%) on track,
18 projects (69%) off track but recoverable and 0 projects (0%) off track.   
1.4 
1.5
The Capital Programme is funded by various income streams as detailed in
Appendix 4. Additional funding allocated since the last report relates to Cycling,
Walking, Safer Routes, Town Centre Fund and Campbeltown Flood Scheme. 
Due to the Covid-19 outbreak there has been a reduction in anticipated capital
receipts in 2021-22 however this appears to be a delay rather than a permanent
reduction and over the life of the entire capital programme there is no overall
impact. The position will continue to be monitored on an ongoing basis.

Page 2

ARGYLL  AND BUTE COUNCIL COUNCIL
FINANCIAL SERVICES 30 JUNE 2022
CAPITAL BUDGET MONITORING REPORT – 31 MARCH 2022
2.0 INTRODUCTION
2.1
2.2
2.3
2.4
This report provides an update on the position of the capital budget as at 31 March
2022. The report provides information on the financial position in respect of the
capital plan and also the performance in terms of delivery of capital plan projects. 
Following the decision at Policy and Resources Committee on 9 December 2021,
the Rothesay Pavilion project is on pause whilst potential funding options are being
considered. The financial information included within this report therefore now
excludes amounts relating to Rothesay Pavilion however for your information
actual expenditure during the year was £718k.   
A £1m cost pressure was identified during the year in relation to repairs to the
A884 Ardbeg Sea Wall, where severe storm damage resulted in failure of the sea
wall on Bute. Emergency works were carried out and a permanent solution is
currently being developed. Additional funding of £1m was allocated for this
purpose at the Council meeting on 24 February 2022 however there remains a risk
that costs will exceed this. It was agreed at Environment, Development and
Infrastructure Committee on 2 June 2022 that the Chair would approach the
Scottish Government with a view to securing additional resources to support the
scheme.
Project Managers were asked to identify specific Covid-19 impacts on the capital
programme. At the budget meeting on 25 February 2021, the Council agreed to
provide £2.5m of funding and following agreement at the Policy and Resources
Committee on 14 October 2021, this, plus a further £0.146m, was added to the
capital programme.
Furthermore, at the budget meeting on 24 February 2022, an additional £3.9m was
set aside for future capital contract increases. This includes up to £1.2m for
Campbeltown Flood Scheme, the final costs of which are estimated to be
£15.215m. The Scottish Government will fund 80% of scheme costs with the
Council expected to contribute an estimated £3.043m.
It should be noted that there are likely to be other significant financial impacts, as
follows: 
• Rothesay Pavilion – project currently paused due to increased costs as a
result of the main contractor being placed into administration in March 2020.
• Harbour Investment Programme – likely to be contractual cost increases in
future years (expected to be funded from additional borrowing, the cost of
which could be met from increased fees and charges).
• Helensburgh Waterfront Development – commercial negotiations are
ongoing with the main contractor to determine financial impact.
• Universal Free School Meals – delayed roll out to P6 and P7 and uncertain
capital funding levels available from Scottish Government. No mention of
the roll out is included within the Resource Spending Review.
• Other general construction inflationary increases.

Page 3

3.0 
3.1 
3.2             
RECOMMENDATIONS 
Note the contents of this report and the financial summaries as detailed 
at Appendix 6. 
Approve the proposed virements at Appendix 3 and the roll forward of any 
over or underspends in relation to expenditure and income as part of the 
year end process. 
4.0 OUTTURN FINANCIAL POSITION 2021-22 
4.1  Overall Position 
Actual net expenditure for the full financial year is £24,831k compared to an annual
budget of £31,012k giving rise to an underspend for the year of £6,181k (19.9%).  
4.2 Project/Department Position 
The table below shows the forecast expenditure and budget for the year by project
type and service. 
Project Type:
Annual
Budget            
£'000
Forecast
Outturn        
£'000 
Forecast
Variance 
COVID-
19
Related       
£'000
Forecast
Variance 
Non
COVID-
19
Related       
£'000
Forecast
Variance         
£'000
Asset Sustainability 19,679 16,855 463 2,361 2,824
Service Development 4,798 4,754 0 44 44
Strategic Change 6,535 3,222 0 3,313 3,313
Total  31,012 24,831 463 5,718 6,181
Service:          
ICT 1,238 1,132 0 106 106
Education 7,666 6,774 463 429 892
Live Argyll 406 272 0 134 134
Health & Social Care
Partnership 268 20 0 248 248
Shared Offices 2,119 804 0 1,315 1,315
Roads & Infrastructure 13,066 10,084 0 2,982 2,982
Development &
Economic Growth 732 504 0 228 228
CHORD 5,517 5,240 0 277 277
Total 31,012 24,831 463 5,718 6,181 
Material variances are explained in Appendix 1 and there are a number of smaller
variances contributing to the underspend.

Page 4

5.0 TOTAL PROJECT COSTS 
5.1 Overall Position 
Forecast total net project costs on the total capital plan are £194,796k compared to
a total budget for all projects of £194,701k giving rise to a forecast overspend for
the overall capital plan of £95k (0.05%). 
As described at section 2.4 above, the total project costs include £2,646k of Covid-
19 related expenditure as agreed at Policy and Resources Committee on 14
October 2021. The total project costs also include £1,133k of the £3,900k agreed
at Council on 24 February 2022 which has been allocated to Campbeltown Flood
Scheme. The remainder has not yet been allocated to the capital plan. 
5.2  Project/Department Position 
The table below shows the forecast expenditure and budget for the total capital
plan by project type and service. 
Project Type:
Capital
Plan
Budget           
£'000
Forecast
Project
Costs        
£'000 
Capital
Plan
Variance 
COVID-19
Related       
£'000
Capital
Plan
Variance 
Non
COVID-
19
Related       
£'000
Total
Capital
Plan
Variance         
£'000
Asset Sustainability 69,038 69,049 0 (11) (11)
Service Development 18,078 18,161 0 (83) (83)
Strategic Change 107,585 107,586 0 (1) (1)
Total  194,701 194,796 0 (95) (95)
Service:          
ICT 5,764 5,764 0 0 0
Education 45,544 45,549 0 (5) (5)
Live Argyll 3,600 3,629 0 (29) (29)
Health & Social Care
Partnership 4,242 4,244 0 (2) (2)
Shared Offices 22,291 22,291 0 (0) (0)
Roads &
Infrastructure 64,949 64,962 0 (13) (13)
Development &
Economic Growth 4,473 4,518 0 (45) (45)
CHORD 43,838 43,838 0 (0) (0)
Total 194,701 194,796 0 (95) (95) 
Material variances are explained in Appendix 2 and there are a number of
smaller variances leading to the forecast overspend.

Page 5

6.0  TOTAL PROJECT PERFORMANCE 
6.1 Overall Position 
There are 180 projects within the Capital Plan, 94 are Complete or On Target, 86
are Off Target and Recoverable and 0 are Off Track. 
6.2  Project Position 
The table below shows the Performance Status of the Projects in the Capital Plan. 
Project Type:
Complete
/ On
Target
Off Target/
Recoverable
Off Target/
Problem Total    
COVID
-19
Related
Non-
COVID
-19
Related
COVID
-19
Related
Non-
COVID
-19
Related 
Asset
Sustainability 63 1 48 0 0 112
Service
Development 23 0 19 0 0 42
Strategic
Change 8 0 18 0 0 26
Total 94 1 85 0 0 180
Service:            
ICT 4 0 3 0 0 7
Education 18 1 14 0 0 33
Live Argyll 19 0 9 0 0 28
Health &
Social Care
Partnership 15 0 2 0 0 17
Shared
Offices 8 0 23 0 0 31
Roads &
Infrastructure 20 0 23 0 0 43
Development
& Economic
Growth 9 0 7 0 0 16
CHORD 1 0 4 0 0 5
Total 94 1 85 0 0 180

Page 6

6.3  Chart of Performance Status 
The graph provides a view of the Performance Status of the Projects included  in
the Capital Plan: 
7.0 OFF TRACK PROJECTS 
7.1  There are no Off Track projects for this report. 
0
20
40
60
80
100
120
Asset Sustainability Service Development Strategic Change
Number
Off Target/
Problem
Off Target/
Recoverable
Complete/ On
Target

Page 7

8.0
8.1
9.0
9.1
STRATEGIC CHANGE PROJECTS
Appendix 5 gives detailed information in respect of the Strategic Change
Projects within the Capital Plan, including details of the forecast cost of the
project against the approved budget, the start and anticipated completion date of
the project and an assessment of the risks of the project and if these are not
green gives an explanation of the problem.
CHANGES TO THE CAPITAL PLAN
The table below shows previous changes to expenditure budgets within the
Capital Plan at summary level, including slippages and accelerations offset by
any budget adjustments. There are no proposed changes in terms of slippages
or accelerations in the current month as any over or under spends are rolled
forward into future years as part of the year end process. The total slippage in
the capital programme throughout 2021-22 was £28.217m.   As reported in Audit
Scotland’s Financial Overview 2020-21, capital expenditure across Scotland’s
councils reduced by more than 20% as a result of Covid-19, impacting both
costs and delivery plans.
There are a number of proposed virements within Shared Offices, largely in
relation to the Our Modern Workspace Project, the detail of which can be found
at Appendix 3. 
The updated capital plan incorporating the proposed virements and roll forward
of over or under spends can be found in Appendix 7. Income budgets will also
be aligned accordingly as part of this process.
Department
Prev.
Agreed
Changes 
2021-22
£’000
Asset Sustainability (1,037)
Service Development (362)
Strategic Change (11,772)
Total (13,171)
Service:
ICT (39)
Education (967)
Live Argyll (134)
Health & Social Care Partnership (494)
Shared Offices (354)
Roads & Infrastructure (11,298)
Development & Economic Growth 307
Major Projects (192)
Total (13,171)
This is something that has continued in 2021-22.

Page 8

10.0            FUNDING 
10.1 
10.2 
11.0 
11.1 
11.2 
11.3 
11.4 
11.5 
11.6 
11.7 
11.8
The Capital Programme is funded by various income streams as detailed in
Appendix 4. Additional funding allocated since the last report relates to Cycling,
Walking, Safer Routes, Town Centre Fund and Campbeltown Flood Scheme. 
Due to the Covid-19 outbreak there has been a reduction in anticipated capital
receipts in 2021-22 however this appears to be a delay rather than a permanent
reduction and over the life of the entire capital programme there is no overall
impact. The position will continue to be monitored on an ongoing basis. 
IMPLICATIONS 
Policy – Monitors progress against the capital plan. 
Financial – Monitors funding and commitments of the capital plan. 
Legal – Available funding may not address all Statutory and Regulatory
requirements in relation to Health and Safety. 
HR – Available funding may have an impact on the sustainability of the Property
Design Team and Infrastructure Design Team. 
Fairer Scotland Duty – None. 
12.5.1     Equalities – protected characteristics – None. 
12.5.2     Socio-economic Duty – None. 
12.5.3     Islands – None. 
Climate Change – The Council is committed to addressing climate change via
projects within the capital plan. 
Risk – There are risks around increasing capital contract costs and the level and
timing of capital receipts. 
Customer Service – None. 
Kirsty Flanagan 
Executive Director/Section 95 Officer 
6 June 2022                                                  
Policy Lead for Finance and Commercial Services – Councillor Gary 
Mulvaney 
For further information contact: Anne Blue, Interim Head of Financial Services 
APPENDICES 
- Appendix 1 – Financial Outturn variance explanations
- Appendix 2 – Total Project finance variance explanations
- Appendix 3 – Changes to Capital Plan and Financial Impact
- Appendix 4 – Capital Funding
- Appendix 5 - Cumulative spend, completion dates and risks relating                         
to significant capital projects. 
- Appendix 6 - Financial Summary – Overall
- Financial Summary – Executive Director Kirsty Flanagan
- Financial Summary – Executive Director Douglas Hendry
- Appendix 7 - Updated/Revised Capital Plan

Page 9

APPENDIX 1 – Outturn Variance Explanations
Listed below are the projects where the current year variance is +/- £50k. 
Project 
Annual
Budget
£’000
Outturn
£’000 
(Over)/
Under
Forecast
Variance
COVID-19
Related         
£’000
(Over)/
Under
Forecast
Variance
Non COVID-
19 Related         
£’000
Total
(Over)/
Under
Forecast
Variance         
£’000
Explanation
Secondary Schools  762 299  463 0 463 Works re-scheduled to summer 22-23; budget slipped
to reflect disruptive influence of COVID and
associated material and labour supply issues. 
Dunclutha Children’s Home 54 0  0 54 54 Continued issues with roads and infrastructure costs;
retention monies still held to offset defects cost. 
ICT Applications Project 848 766  0 82 82 Budget to be reprofiled. 
Legionella Control Works  271 56  0 215 215 Developmental budget for 22-23 associated legionella
costs. 
Asbestos Property Works  57 0  0 57 57 Developmental budget for 22-23 associated asbestos
costs. 
Carbon Management Business
Cases
60 0  0 60 60 Developmental budget for 22-23 associated Carbon
Management costs and future business cases. 
NPDO Schools Solar PV Panel
Installations 
100 0  0 100 100 Developmental budget for 22-23 and residual work
associated with remedial Capital Works. 
Non-NPDO Schools PV Panel
Installations 
88 0  0 88 88 Developmental budget for 22-23 and residual work
associated with remedial Capital Works. 
Roads Reconstruction 11,250 10,775  0 475 475 Balance of Covid funding to be carried forward. 
Public Convenience Upgrades  82 0  0 82 82 No expenditure in 21-22, budget to be reprofiled.

Page 10

Electric Vehicle Chargers 97 4  0 93 93 Procurement ongoing, agreed with Transport
Scotland to carry forward funding. 
Campbeltown Flood Scheme 525 294  0 231 231 Tender for works due to be awarded end of May
2022. 
Harbour Investment Programme 3,676 1,192  0 2,484 2,484 Projects delayed for various reasons including Marine
Scotland licencing delays, contractor and contractual
issues.
Helensburgh Waterfront
Development 
11,065 10,827  0 238 238 External funding for additional works to take place in
22-23. 
Clean Energy (NDEEF) 1,100 636  0 464 464 Works scheduled to complete in June 22-23 - budget
to be reprofiled accordingly in line with timescales for
second valuation due to contractor and retention
payment. 
Glengorm Capping 82 0  0 82 82 New application to Business Stream made and
expenditure expected to take place in 22-23. 
Nature Restoration Fund 108 0  0 108 108 Distribution of funding/projects still to be agreed. 
Other Variances under £50k                   805 805 Total value of non-material variances less than +/-
£50k
Total  463 5,718 6,181

Page 11

APPENDIX 2 – Total Project Finance Variances
Listed below are the projects where the total project variance is +/- £50k. 
Project 
Capital
Plan
Budget
£’000
Forecast
Project
Costs
£’000 
(Over)/
Under
Forecast
Variance
COVID-19
Related         
£’000
(Over)/
Under
Forecast
Variance
Non COVID-
19 Related         
£’000
Total
(Over)/
Under
Forecast
Variance         
£’000
Explanation       
No variances +/-£50k for this report.
Other Variances under £50k             0 (95) (95) Total value of non-material variances less than +/-
£50k. Project Managers are working to reduce these
small individual overspends by identifying
underspends elsewhere within the capital plan.
Total  0 (95) (95)

Page 12

APPENDIX 3 – Changes to Capital Plan and Financial Impact
OVERALL COST CHANGES
Project 2021-22
£’000
2022-23
£’000
2023-24
£’000
Future
Years
£’000
Total
Capital
Plan
£’000
Recommendation Explanation
Our Modern Workspace
(OMW) Project  549 87  30 666 Vire budget from multiple
projects listed below. 
Our Modern Workspace (OMW) project is
progressing, supporting flexible return to offices.
Budget identified from existing office
rationalisation/upgrade projects no longer required
below as a result. 
Castle House, Dunoon  (10)   (10) Vire budget to OMW. Residual budget no longer required. 
Dunoon Office
Rationalisation  (220) (7)  (227) Vire budget to OMW. Budget no longer required as a result of OMW
Project.  
Joint Valuation Board  (39)   (39) Vire budget to OMW. Budget no longer required. 
Lorn House, Oban  (22)   (22) Vire budget to OMW. Residual budget no longer required.
Manse Brae District
Office, Lochgilphead  (120)   (120) Vire budget to OMW. Budget no longer required as a result of OMW
Project.  
Oban Municipal Buildings  (16)   (16) Vire budget to OMW. Residual budget no longer required.
Old Quay Offices,
Campbeltown  (15)   (15) Vire budget to OMW. Residual budget no longer required.  
Tobermory Area Office  (42)   (42) Vire budget to OMW. Residual budget no longer required.  
Whitegates Office,
Lochgilphead  (25)   (25) Vire budget to OMW. Budget no longer required as a result of OMW
Project.  
Rothesay Office
Rationalisation  (40)   (40) Vire budget to OMW. Budget no longer required as a result of OMW
Project.  
Shared Offices Block
Allocation   (80)  (30) (110) Vire budget to OMW.
Budgets relating to Agile Working Project and
Union Street, Rothesay now longer required as a
result of OMW Project.  
Argyll House, Dunoon   12   12 Vire budget from projects
below.
Additional budget required for outstanding final
payments. 
Fire Risk Assessments  (6)   (6) Vire budget to Argyll
House, Dunoon.  Rolling budget utilised as and when required. 
Asbestos Capital Property
Works   (6)   (6) Vire budget to Argyll
House, Dunoon. Rolling budget utilised as and when required.
Total Cost Changes 0 0 0 0 0

Page 13

SLIPPAGES AND ACCELERATIONS 
Project 2021-22
£'000
2022-
23
£'000
2023-
24
£'000
Future
Years 
£’000
Total
Capital
Plan
£’000
2021-22
COVID-
19
Slippage
£'000
2021-22
Non
COVID-19
Slippage
£'000
Recommendation Explanation
None for this report.            
Total Slippages &
Accelerations 0 0 0 0 0 0 0     
There are no proposed changes in the current month regarding slippages or accelerations as any over or underspends are rolled forward into future years as part of the
year end process. Income budgets will also be aligned accordingly as part of this process.

Page 14

CAPITAL PROGRAMME FUNDING Appendix 4
Approved
Capital
Funding
Carry
Forwards
from 20-21
Slippage /
Acceleration
Additional
Funding
Updated
Capital
Funding
Available
Estimated
Capital
Funding
Carry
Forwards
from 20-21
Slippage /
Acceleration
Additional
Funding
Updated
Capital
Funding
Available
Estimated
Capital
Funding
Carry
Forwards from
20-21
Slippage /
Acceleration
Additional
Funding
Updated
Capital
Funding
Available
General Capital Grant 9,596 0 0 0 9,596 9,569 0 0 0 9,569 9,569 0 0 0 9,569
Transfer to Revenue for Private Sector Housing Grant (PSHG) -1,033 0 0 0 -1,033 -1,033 0 0 0 -1,033 -1,033 0 0 0 -1,033
Capital Receipts 806 0 0 0 806 1,387 0 0 0 1,387 1,095 0 0 0 1,095
Flooding Allocation 155 0 0 0 155 155 0 0 0 155 155 0 0 0 155
Ring Fenced Capital Grant 2,005 0 -77 175 2,103 4,656 0 77 2,645 7,378 0 0 0 5,728 5,728
Restricted Funding 8,311 -21 -186 803 8,907 1,486 0 186 358 2,030 1,150 0 0 0 1,150
Funded by Reserves 14,163 2 -3,372 0 10,793 3,145 0 3,200 1,133 7,478 36 0 172 0 208
Additional Funding from Revenue 135 0 0 600 735 0 0 0 18 18 0 0 0 0 0
Insurance 1,681 0 0 0 1,681 0 0 0 0 0 0 0 0 0 0
Harbour Investment Programme 3,676 0 -2,484 0 1,192 31,180 0 2,484 0 33,664 16,900 0 0 0 16,900
Prudential Borrowing 648 0 1,090 0 1,738 15,528 0 312 3,244 19,084 5,006 0 -1,429 0 3,577
Loans Fund Review 5,393 0 -2,619 0 2,774 0 0 2,619 1,406 4,025 0 0 0 0 0
COVID Funding 4,171 0 -2,167 0 2,004 1,640 0 2,167 0 3,807 0 0 0 0 0
49,707 -19 -9,815 1,578 41,451 67,713 0 11,045 8,804 87,562 32,878 0 -1,257 5,728 37,349
BREAKDOWN OF ADDITIONAL FUNDING
Additional Funding 2021-22 2022-23 2023-24 Month Reported
Gibraltar Street Public Realm Improvements 250 Jan-22
CO2 Monitoring in Schools 77 Jan-22
Helensburgh Cycleways 95 Grant Funding Jan-22
Kilmory Business Park 30 120 Grant Funding Feb-22
Helensburgh Waterfront Development 331 Live Argyll Feb-22
Hermitage Park 8 Third Party Contribution Feb-22
Roads Reconstruction 50 Grant Funding Feb-22
Play Park Refurbishment 79 Scottish Government Feb-22
Coastal Change Adaptation 159 Scottish Government Feb-22
Cycling Walking Safer Routes 98 173 Scottish Government Mar-22
Victoria Halls 15 Live Argyll Mar-22
Capital Funded from Revenue 600 18 Revenue Funding Mar-22
Town Centre Fund 24 Scottish Government Mar-22
Campbeltown Flood Scheme 5,716 5,728 Scottish Government Mar-22
Campbeltown Flood Scheme 2,539 Reserves Mar-22
Total 1,578 8,804 5,728
2023-24
Source
Grant Funding
Scottish Government
Current Year (2021-22) 2022-23

Page 15

Strategic Change Projects - Cumulative Spend, Start/Finish Dates and Project Risks APPENDIX 5
Strategic Change Projects
Prior Years
Spend
£'000
Current Year
Forecast
£'000
Total Project
Forecast
£'000
Total Project
Budget
£'000
Project Start
Date
Original
Estimated
Completion
Date
Project
Risks
Identified Explanation
Dunoon Primary 7,170 19 10,869 10,869 18/12/2014 30/04/2020 Amber Physically complete - negotiations with contractor delaying payment of final sums outstanding.
Kirn Primary School 9,878 114 10,119 10,119 24/04/2014 31/10/2017 Amber Physically complete - negotiations with contractor delaying payment of final sums outstanding.
Replacement of Oban High 2,496 2 3,250 3,250 24/04/2014 31/01/2019 Amber Physically complete - negotiations with contractor delaying payment of final sums outstanding.
CHORD Oban 7,129 4 7,905 7,905 27/10/2016 31/03/2022 Amber Issues with contract close out impacting on timescales.
Street Lighting LED Replacement 2,700 16 3,900 3,900 01/08/2016 30/03/2022 Amber Tender for final package of works still to be awarded - budget to be reprofiled.
Helensburgh Office Rationalisation 11,500 20 11,838 11,838 25/04/2013 31/03/2022 Amber Project subject to legal dispute.
CHORD Dunoon 12,238 32 12,522 12,522 03/02/2012 09/03/2018 Amber
Main contract complete and retentions paid. Landscaping and remediation works ongoing but
issues with water ingress may require works in 22-23.
Helensburgh Waterfront Development 1,387 10,827 22,557 22,557 01/04/2017 31/03/2024 Amber Additional funding awarded resulting in increased budget. Budget to be reprofiled.
Kilmory Business Park Phase 2AA 0 9 150 150 01/02/2022 01/09/2023 Amber Development Agreement still to be concluded.
Harbour Investment Programme 1,802 1,192 91,292 91,292 01/04/2017 31/03/2028 Amber
Works expected to commence towards the end of the year and awaiting information for vessel
designs.
Carbon Management Business Cases 201 0 261 261 01/02/2014 31/03/2022 Amber Budget to be reprofiled pending development of new projects.
Campbeltown Flood Scheme 181 294 1,232 1,232 01/08/2016 31/03/2023 Amber Contracts not yet awarded for Kilcreggan or Ettrickdale projects.
Carbon Management - Group Heating Conversion Project 1,938 0 1,948 1,948 01/02/2016 31/03/2022 Amber Complete.
Carbon Management - Non Education 14 0 50 50 01/04/2015 31/03/2022 Amber Projects being determined.
NPDO Schools Solar PV Panel Installations 761 0 944 944 26/06/2014 31/03/2022 Amber Budget to be reprofiled pending development of new projects.
Non NPDO Schools Solar PV Panel Installations 400 0 488 488 20/03/2014 31/03/2022 Amber Budget to be reprofiled pending development of new projects.
Carbon Management Capital Property Works 2016/17 19 0 39 39 01/02/2016 31/03/2022 Amber Budget to be reprofiled pending development of new projects.
Oil to Gas Heating Conversions 182 0 187 187 01/02/2012 31/03/2022 Amber Budget to be reprofiled pending development of new projects.
TIF - Halfway House Roundabout 0 43 640 640 tbc tbc Green Scope of project still to be determined - budget to be reprofiled.
TIF - Oban Airport Business Park 447 6 590 590 22/01/2015 31/03/2022 Green
Campbeltown Schools Redevelopment 1,649 0 2,130 2,130 16/02/2012 30/11/2018 Green Physically complete - negotiations with contractor delaying payment of financial sums outstanding.
CHORD - Helensburgh 6,483 2 6,557 6,557 29/09/2011 30/04/2015 Green Main contract complete. Art project originally proposed for 21-22 now slipped into 22-23.
TIF - North Pier Extension 214 0 214 214 06/12/2017 06/12/2021 Green Complete.
TIF - Lorn/Kirk Road 1,959 0 2,170 2,170 22/01/2015 31/03/2021 Green Complete.
Carbon Management Fuel Conversions 107 0 107 107 01/02/2014 31/03/2019 Green Complete.
Kilmory Biomass  Carbon Management 956 0 956 956 20/09/2012 31/03/2019 Green Complete.
Strategic Change Total 75,250 12,580 196,365 196,365
Project Risk Classifications:
Green - Risks can be managed and are viewed as stable or reducing.
Amber - Risks are increasing but are still manageable.
Red - Risks are increasing or have increased to such an extent they may affect delivery of the project.
Capital Expenditure Dates Risks

Page 16

ARGYLL AND BUTE COUNCIL - CAPITAL PLAN MONITORING REPORT - OVERALL COUNCIL
FINANCIAL SUMMARY - NET EXPENDITURE
Budget Forecast
(Over)/Under
Variance Budget Forecast
(Over)/Under
Variance
£000s £000s £000s £000s £000s £000s
EXPENDITURE
Asset Sustainability Projects
Executive Director Douglas Hendry 6,773 4,553 2,220 24,757 24,775 (18)
Executive Director Kirsty Flanagan 14,707 14,013 694 46,857 46,857 0
Asset Sustainability Total 21,480 18,566 2,914 71,614 71,632 (18)
Service Development Projects
Executive Director Douglas Hendry 3,454 3,397 57 15,144 15,169 (25)
Executive Director Kirsty Flanagan 7,264 7,004 260 31,616 31,675 (59)
Service Development Total 10,718 10,401 317 46,760 46,844 (84)
Strategic Change Projects
Campbeltown Schools Redevelopment 0 0 0 2,130 2,130 0
Dunoon Primary 3 19 (16) 10,869 10,869 0
Replacement of Oban High 2 2 0 3,250 3,250 0
Kirn Primary School 110 114 (4) 10,119 10,119 0
Carbon Management - Non Education 21 0 21 50 50 0
Carbon Management Business Cases 60 0 60 261 261 0
NPDO Schools Solar PV Panel Installations 100 0 100 944 944 0
Non NPDO Schools Solar PV Panel Installations 88 0 88 488 488 0
Carbon Management Fuel Conversions 0 0 0 107 107 0
Carbon Management Capital Property Works 2016/17 20 0 20 39 39 0
Carbon Management - Group Heating Conversion Project 10 0 10 1,948 1,948 0
Kilmory Biomass  Carbon Management 0 0 0 956 956 0
Oil to Gas Heating Conversions 5 0 5 187 187 0
Campbeltown Office Rationalisation 1 0 1 596 596 0
Helensburgh Office Rationalisation 30 20 10 11,838 11,838 (0)
Rothesay Office Rationalisation 10 0 10 10 10 0
Campbeltown Flood Scheme 525 294 231 15,215 15,215 0
Street Lighting LED Replacement 34 16 18 3,900 3,900 0
Harbour Investment Programme 3,676 1,192 2,484 91,292 91,292 0
TIF - Lorn/Kirk Road 1 0 1 2,170 2,170 0
TIF - North Pier Extension 0 0 0 214 214 0
TIF - Oban Airport Business Park 7 6 1 590 590 0
TIF - Halfway House Roundabout 40 43 (3) 640 640 0
CHORD - Helensburgh 2 2 0 6,557 6,557 0
CHORD Dunoon 41 32 9 12,522 12,522 0
CHORD Oban 0 4 (4) 7,905 7,905 0
Helensburgh Waterfront Development 11,065 10,827 238 22,557 22,557 0
HWD - FFE (Funded by LA) 19 6 13 350 350 0
Kilmory Business Park Phase 2AA 30 9 21 150 150 0
Dunoon Pier OBC 0 0 0 2,844 2,844 0
Strategic Change Total 15,900 12,586 3,314 210,698 210,698 (0)
Total Expenditure 48,098 41,553 6,545 329,072 329,174 (102)
INCOME
Asset Sustainability
Executive Director Douglas Hendry (55) (62) 7 (55) (62) 7
Executive Director Kirsty Flanagan (1,746) (1,649) (97) (2,521) (2,521) 0
Asset Sustainability Total (1,801) (1,711) (90) (2,576) (2,583) 7
Service Development Projects
Executive Director Douglas Hendry (173) (173) 0 (7,475) (7,475) 0
Executive Director Kirsty Flanagan (5,747) (5,474) (273) (21,207) (21,208) 1
Service Development Total (5,920) (5,647) (273) (28,682) (28,683) 1
Strategic Change Projects
Helensburgh Office Rationalisation 0 0 0 (349) (349) 0
Dunoon Primary 0 0 0 (137) (137) 0
Campbeltown Flood 0 0 0 (270) (270) 0
Harbour PB (3,676) (3,676) 0 (91,292) (91,292) 0
01 TIF - Lorn/Kirk Road (49) (49) 0 (2,018) (2,018) 0
H'burgh CHORD Public Realm Imprv 0 0 0 (570) (570) 0
Helensburgh Waterfront Development (5,290) (5,290) (0) (6,493) (6,493) (0)
HWD - FFE (Funded by LA) (350) (350) 0 (350) (350) 0
CHORD - Dunoon Waterfront 0 0 0 (10) (10) 0
CHORD - Oban 0 0 0 (1,624) (1,624) 0
Strategic Change Total (9,365) (9,365) (0) (103,113) (103,113) (0)
Total Income (17,086) (16,723) (363) (134,371) (134,379) 8
Net Total 31,012 24,831 6,181 194,701 194,796 (95)
Appendix 6
Full Year This Financial Year Total Project Costs
31 March 2022

Page 17

MONITORING REPORT
Budget
Year End
Forecast
(Over)/Under
Variance Budget Forecast
(Over)/Under
Variance
£000s £000s £000s £000s £000s £000s
EXPENDITURE
Asset Sustainability Projects
Flood Prevention 216 136 80 1,220 1,220 0
Coastal Protection 0 0 0 200 200 0
Coastal Change Adaptation 0 0 0 159 159 0
Bute Sea Wall Repairs 250 250 0 1,000 1,000 0
Helensburgh Flood Mitigation 15 16 (1) 448 448 0
Bridge Strengthening 350 357 (7) 2,406 2,406 0
Local Bridge Maintenance Fund 2 3 (1) 5,450 5,450 0
Roads Reconstruction 11,250 10,775 475 26,111 26,111 0
Roads Reconstruction - Helensburgh CHORD 114 67 47 114 114 0
Roads Reconstruction - Oban CHORD 0 49 (49) 52 52 0
Helensburgh CHORD - Signage etc 0 0 0 10 10 0
Lighting 70 74 (4) 1,114 1,114 0
Environmental Projects 40 79 (39) 1,013 1,013 0
Play Park Refurbishment 0 0 0 155 155 0
Public Convenience Upgrades 82 0 82 82 82 0
Footway Improvements 600 641 (41) 910 910 0
Glengorm - Capping 82 0 82 82 82 0
Glengorm - Cell and Transfer Station (PB) 330 375 (45) 935 935 0
EV Quick Chargers 97 4 93 97 97 0
Tobermory Car Park 47 49 (2) 1,000 1,000 0
Active Travel 0 0 0 500 500 0
Bin Replacement Programme 0 0 0 100 100 0
Glen Loin Car Park - CFCR 160 160 0 160 160 0
Plant and Equipment - CFCR 64 64 0 64 64 0
Islay Jura Ferry Engine - CFCR 60 60 0 60 60 0
Roads Recon - A816 - CFCR 97 97 0 97 97 0
Server Sustainability 81 81 0 186 186 0
PC Replacement 522 508 14 560 560 0
Telecomms Network 178 168 10 178 178 0
Block Allocation - ICT 0 0 0 2,394 2,394 0
Asset Sustainability Total 14,707 14,013 694 46,857 46,857 0
Service Development Projects
Preliminary design for  Regional Transport projects 0 0 0 221 221 0
Campbeltown Old Quay 0 0 0 1,424 1,424 0
Fleet Management - Prudential Borrowing 1,171 1,213 (42) 4,861 4,861 0
Fleet Management 1,595 1,595 0 2,859 2,859 0
Lismore Ferry 463 461 2 655 655 0
Millpark Depot Demolition 0 0 0 126 126 0
Oban Depot Development Project 35 35 0 2,100 2,100 0
Lochgilphead Depot Rationalisation 0 10 (10) 19 29 (10)
Jackson's Quarry Refurbishment 283 285 (2) 283 285 (2)
Witchburn Road Demolition (1) 0 (1) 157 158 (1)
Safe Streets, Walking and Cycling (CWSS) 382 385 (3) 2,878 2,881 (3)
SPT - bus infrastructure 0 0 0 1,405 1,405 0
Cycleways - H&L (FSPT) 197 197 0 2,972 2,972 0
Helensburgh Public Realm - Arts Strategy Fund 1 2 (1) 53 53 0
Town Centre Funds 2,048 2,035 13 3,561 3,604 (43)
Dunoon Cycle Bothy 16 13 3 279 279 0
Dunoon STEM Hub 49 5 44 608 608 0
Ardrishaig North Active Travel 0 0 0 600 600 0
Nature Restoration Fund 108 0 108 108 108 0
Gibraltar Street Public Realm Improvements 0 2 (2) 250 250 0
Hermitage Park 69 0 69 3,314 3,314 0
Applications Projects 848 766 82 2,883 2,883 0
Service Development Total 7,264 7,004 260 31,616 31,675 (59)
Strategic Change Projects
Campbeltown Flood Scheme 525 294 231 15,215 15,215 0
Street Lighting LED Replacement 34 16 18 3,900 3,900 0
Harbour Investment Programme 3,676 1,192 2,484 91,292 91,292 0
TIF - Lorn/Kirk Road 1 0 1 2,170 2,170 0
TIF - North Pier Extension 0 0 0 214 214 0
TIF - Oban Airport Business Park 7 6 1 590 590 0
TIF - Halfway House Roundabout 40 43 (3) 640 640 0
Strategic Change Total 4,283 1,551 2,732 114,021 114,021 0
Total Expenditure 26,254 22,568 3,686 192,494 192,553 (59)
INCOME
Asset Sustainability
EV Quick Chargers (97) 0 (97) (97) (97) 0
Roads Reconstruction (1,299) (1,299) 0 (1,299) (1,299) 0
Environmental Projects (20) (20) 0 (20) (20) 0
Glengorm Capping/New Cell - Prudential Borrowing (330) (330) 0 (330) (330) 0
Tobermory Car Park 0 0 0 (775) (775) 0
Asset Sustainability Total (1,746) (1,649) (97) (2,521) (2,521) 0
Service Development Projects
Applications Projects (391) (391) 0 (437) (437) 0
Safe Streets, Walking and Cycling (388) (385) (3) (2,483) (2,483) 0
SPfT 0 0 0 (1,243) (1,243) 0
Cycleways - H&L (FSPT) (197) (197) 0 (3,072) (3,072) 0
Town Centre Funds (499) (499) 0 (1,972) (1,972) 0
Dunoon STEM Hub (507) (508) 1 (607) (608) 1
Dunoon Cycle Bothy (70) (70) 0 (279) (279) 0
Gibraltar Street Public Realm Improvements (250) (250) 0 (250) (250) 0
Hermitage Park (226) (226) 0 (3,245) (3,245) 0
Fleet Management - PB (1,171) (1,171) 0 (4,861) (4,861) 0
Fleet Management (96) (96) 0 (96) (96) 0
Lochgilphead Depot Rationalisation (1) 0 (1) (1) (1) 0
Millpark Depot Demolition Insurance 0 0 0 (53) (53) 0
Oban Depot - Mill Park Insurance Claim (1,681) (1,681) 0 (1,681) (1,681) 0
Oban Depot - Appin Depot Sale (150) 0 (150) (150) (150) 0
Lismore Ferry (120) 0 (120) (620) (620) 0
Witchburn Road Demolition 0 0 0 (157) (157) 0
Service Development Total (5,747) (5,474) (273) (21,207) (21,208) 1
Strategic Change Projects
Campbeltown Flood 0 0 0 (270) (270) 0
Harbour PB (3,676) (3,676) 0 (91,292) (91,292) 0
01 TIF - Lorn/Kirk Road (49) (49) 0 (2,018) (2,018) 0
Strategic Change Total (3,725) (3,725) 0 (93,580) (93,580) 0
Total Income (11,218) (10,848) (370) (117,308) (117,309) 1
Net Departmental Total 15,036 11,720 3,316 75,186 75,244 (58)
31 March 2022
Full Year This Financial Year Total Project Costs
FINANCIAL SUMMARY NET EXPENDITURE - EXECUTIVE DIRECTOR KIRSTY FLANAGAN
Appendix 6

Page 18

MONITORING REPORT
Budget Forecast Variance Budget Forecast Variance
£000s £000s £000s £000s £000s £000s
EXPENDITURE
Asset Sustainability
Education 4,311 3,422 889 14,176 14,176 0
Live Argyll 453 327 126 2,373 2,389 (16)
Health and Social Care Partnership 214 20 194 2,942 2,944 (2)
Shared Offices 1,795 784 1,011 5,266 5,266 0
Asset Sustainability Total 6,773 4,553 2,220 24,757 24,775 (18)
Service Development Projects
Ardrishaig Primary Pre 5 Unit 0 0 0 2 2 0
Bowmore Primary School - Pre 5 Unit 0 0 0 149 149 0
Clyde Cottage - 600 hour provision 25 2 23 579 579 0
Craignish Primary School - Pre 5 Extension 0 0 0 400 400 0
Iona Primary School - Pre 5 Unit 0 0 0 490 490 0
Islay High and Rosneath Primary School Pitches 14 26 (12) 707 719 (12)
Lochgoilhead Primary School - Pre 5 Unit 0 0 0 391 391 0
Park Primary Extension/Pre Fives Unit 0 0 0 341 341 0
Sandbank Gaelic Pre Five Unit 0 0 0 491 491 0
Bunessan Primary School - Gaelic Medium Improvements 0 0 0 120 120 0
Early Learning and Childcare 0 0 0 850 850 0
Early Learning and Childcare - 1140 Hours 3,200 3,182 18 7,751 7,751 0
CO2 Monitoring - Covid Mitigation in Schools 63 76 (13) 192 192 0
Early Learning and Childcare - 1140 Hours - CFCR 111 111 0 111 111 0
Bowmore Primary School - Gaelic Medium Grant 0 0 0 38 38 0
Riverside Leisure Centre Refurbishment (13) 0 (13) 1,232 1,245 (13)
Dunclutha Childrens Home 54 0 54 1,300 1,300 0
Service Development Total 3,454 3,397 57 15,144 15,169 (25)
Strategic Change Projects
Campbeltown Schools Redevelopment 0 0 0 2,130 2,130 0
Dunoon Primary 3 19 (16) 10,869 10,869 0
Replacement of Oban High 2 2 0 3,250 3,250 0
Kirn Primary School 110 114 (4) 10,119 10,119 0
Carbon Management - Non Education 21 0 21 50 50 0
Carbon Management Business Cases 60 0 60 261 261 0
NPDO Schools Solar PV Panel Installations 100 0 100 944 944 0
Non NPDO Schools Solar PV Panel Installations 88 0 88 488 488 0
Carbon Management Fuel Conversions 0 0 0 107 107 0
Carbon Management Capital Property Works 2016/17 20 0 20 39 39 0
Carbon Management - Group Heating Conversion Project 10 0 10 1,948 1,948 0
Kilmory Biomass  Carbon Management 0 0 0 956 956 0
Oil to Gas Heating Conversions 5 0 5 187 187 0
Campbeltown Office Rationalisation 1 0 1 596 596 0
Helensburgh Office Rationalisation 30 20 10 11,838 11,838 (0)
Rothesay Office Rationalisation 10 0 10 10 10 0
CHORD Oban 0 4 (4) 7,905 7,905 0
CHORD - Helensburgh 2 2 0 6,557 6,557 0
CHORD Dunoon 41 32 9 12,522 12,522 0
Helensburgh Waterfront Deveopment 11,065 10,827 238 22,557 22,557 0
HWD - FFE (Funded by LA) 19 6 13 350 350 0
Kilmory Business Park Phase 2AA 30 9 21 150 150 0
Dunoon Pier OBC 0 0 0 2,844 2,844 0
Strategic Change Total 11,617 11,035 582 96,677 96,677 (0)
Total Expenditure 21,844 18,985 2,859 136,578 136,621 (43)
INCOME
Asset Sustainability
Education 0 (7) 7 0 (7) 7
Live Argyll (55) (55) 0 (55) (55) 0
Asset Sustainability Total (55) (62) 7 (55) (62) 7
Service Development Projects
Sandbank Gaelic Pre Five Unit 0 0 0 (478) (478) 0
Bunessan Primary School - Gaelic Medium Improvements 0 0 0 (30) (30) 0
Early Learning and Childcare (135) (135) 0 (629) (629) 0
Early Years 1140 Hours 0 0 0 (6,300) (6,300) 0
Bowmore Primary School - Gaelic Medium Grant (38) (38) 0 (38) (38) 0
Service Development Total (173) (173) 0 (7,475) (7,475) 0
Strategic Change
Helensburgh Office Rationalisation 0 0 0 (349) (349) 0
Dunoon Primary School 0 0 0 (137) (137) 0
H'burgh CHORD Public Realm Imprv 0 0 0 (570) (570) 0
Helensburgh Waterfront Development (5,290) (5,290) (0) (6,493) (6,493) (0)
HWD - FFE (Funded by LA) (350) (350) 0 (350) (350) 0
CHORD - Dunoon Waterfront 0 0 0 (10) (10) 0
CHORD - Oban 0 0 0 (1,624) (1,624) 0
Strategic Change Total (5,640) (5,640) (0) (9,533) (9,533) (0)
Total Income (5,868) (5,875) 7 (17,063) (17,070) 7
Net Departmental Total 15,976 13,111 2,865 119,515 119,552 (37)
31 March 2022
Total Project CostsFull Year This Financial Year
Appendix 6
FINANCIAL SUMMARY NET EXPENDITURE - EXECUTIVE DIRECTOR DOUGLAS HENDRY

Page 19

CAPITAL PLAN 2021-22 APPENDIX 7
Overall Summary
Service
Previous Years
£000's
2021-22        
£000s
2022-23
£000s
2023-24              
£000s
2024-25
£000s
2025-26       
£000s
Total
£000s
Education 33,043 6,942 6,102 4,843 2,226 0 53,156
Shared Offices 16,667 804 4,097 644 428 0 22,640
ICT 1,360 1,523 1,564 983 771 0 6,201
RIS 16,027 18,344 64,279 29,542 36,037 2,422 166,651
DEG 12,747 2,642 4,073 180 0 0 19,642
HSCP 1,246 18 2,109 441 428 0 4,242
Live Argyll 1,274 298 1,224 431 428 0 3,655
CHORD 37,606 10,880 4,114 285 0 0 52,885
Overall Total 119,970 41,451 87,562 37,349 40,318 2,422 329,072

Page 20

CAPITAL PLAN 2021-22 APPENDIX 7
Education
Category Service Project
Previous
Years
£000's
2021-22
£000s
2022-23
£000s
2023-24
£000s
Future
Years
£000s
Total
£000s
Asset Sustainability Education Asbestos Control/Removal Works 0 0 7 0 0 7
Block Allocation - Education 0 0 3,216 4,231 2,226 9,673
Digital Inclusion 20-21 0 0 9 0 0 9
Free School Meals 0 0 14 0 0 14
Homeless Houses - Housing Quality Standard 0 0 1 0 0 1
Internal Refurbishment Budget 0 0 7 0 0 7
Lochgilphead Primary School Demolition - CFCR 0 20 0 0 0 20
Pre-5's/Nurseries 0 0 1 0 0 1
Pre-5s/Nurseries - CFCR 0 34 0 0 0 34
Primary School - CFCR 0 17 0 0 0 17
Primary Schools 0 2,891 530 23 0 3,444
School Houses - Housing Quality Standard 0 159 26 0 0 185
Secondary Schools 0 299 463 0 0 762
Asset Sustainability Total 0 3,422 4,274 4,254 2,226 14,176
Service Development Education Ardrishaig Primar School - Pre Five Extension 2 0 0 0 0 2
Bowmore Primary School - Gaelic Medium Grant 0 0 38 0 0 38
Bowmore Primary School - Pre Five Unit 149 0 0 0 0 149
Bunessan Primary School - Gaelic Medium Improvements 120 0 0 0 0 120
Clyde Cottage - 600 hours provision 554 2 23 0 0 579
CO2 Monitoring - Covid Mitigation in Schools 0 76 116 0 0 192
Craignish Primary School - Pre Five Extension (600 hours funding) 400 0 0 0 0 400
Early Learning and Childcare 850 0 0 0 0 850
Early Learning and Childcare - 1140 Hours 3,514 3,182 1,036 19 0 7,751
Early Learning and Childcare - 1140 Hours - CFCR 0 111 0 0 0 111
Iona Primary School - Pre Five Unit (600 hours funding) 490 0 0 0 0 490
Islay High & Rosneath PS Pitches 693 14 0 0 0 707
Lochgoilhead Primary School - Pre Five Unit (600 hours funding) 391 0 0 0 0 391
Park Primary Extension and Pre Fives Unit 341 0 0 0 0 341
Sandbank Gaelic Pre Five Unit 491 0 0 0 0 491
Service Development Total 7,995 3,385 1,213 19 0 12,612
Strategic Change Education Campbeltown Schools Redevelopment 2,054 0 76 0 0 2,130
Dunoon Primary School 10,346 19 304 200 0 10,869
Kirn Primary School 9,906 114 99 0 0 10,119
Replacement of Oban High School 2,742 2 136 370 0 3,250
Strategic Change Total 25,048 135 615 570 0 26,368
Overall Total 33,043 6,942 6,102 4,843 2,226 53,156

Page 21

CAPITAL PLAN 2021-22 APPENDIX 7
Shared Office
Category Service Project
Previous
Years
£000's
2021-22
£000s
2022-23
£000s
2023-24
£000s
Future
Years
£000s
Total
£000s
Asset Sustainability Shared Offices Argyll House, Dunoon 0 7 12 0 0 19
Asbestos Capital Property Works 0 0 51 0 0 51
Block Allocation 0 0 0 336 398 734
Bowmore Area Office 0 0 76 0 0 76
Burnett Building 0 1 110 0 0 111
Capital Property Works 0 0 28 0 0 28
Cleaner Energy 0 636 961 178 0 1,775
Concerto Licence 0 45 0 0 0 45
Fire Risk Assessment Works 0 0 14 0 0 14
Hill Street Dunoon Rewire 0 0 33 0 0 33
Kilmory Castle 0 13 1,368 43 0 1,424
Legionella Control Works 0 56 215 0 0 271
Manse Brae District Office 0 26 1 0 0 27
Manse Brae Roads Office 0 0 2 0 0 2
Our Modern Workspace 0 0 549 87 30 666
Asset Sustainability Total 0 784 3,420 644 428 5,276
Strategic Change Shared Offices Campbeltown Office Rationalisation 595 0 1 0 0 596
Carbon Management - Group Heating Conversion Project (Prudential Borrowing)1,938 0 10 0 0 1,948
Carbon Management Business Cases (FPB) 201 0 60 0 0 261
Carbon Management Capital Property Works 16/17 19 0 20 0 0 39
Carbon Management Fuel Conversions (FPB) 107 0 0 0 0 107
Helensburgh Office Rationalisation  (FPB,REC) 11,508 20 310 0 0 11,838
Kilmory Biomass Project OBC (FPB,REV) 956 0 0 0 0 956
Non-NPDO Schools PV Panel Installations 400 0 88 0 0 488
NPDO Schools Solar PV Panel Installations 761 0 183 0 0 944
Oil to Gas Heating Conversions (FPB) 182 0 5 0 0 187
Strategic Change Total 16,667 20 677 0 0 17,364
Overall Total 16,667 804 4,097 644 428 22,640

Page 22

CAPITAL PLAN 2021-22 APPENDIX 7
Major Projects
Category Service Project
Previous
Years
£000's
2021-22
£000s
2022-23
£000s
2023-24
£000s
Future
Years
£000s
Total
£000s
Strategic Change CHORD CHORD - Dunoon 12,435 32 55 0 0 12,522
CHORD - Helensburgh -Public Realm Imprv 6,527 2 28 0 0 6,557
CHORD - Oban 7,250 4 651 0 0 7,905
Helensburgh Waterfront Development 8,550 10,827 2,895 285 0 22,557
HWD - FFE 0 6 344 0 0 350
Kilmory Business Park Phase 2AA 0 9 141 0 0 150
OBC for Dunoon Pier 2,844 0 0 0 0 2,844
Strategic Change Total 37,606 10,880 4,114 285 0 52,885
Overall Total 37,606 10,880 4,114 285 0 52,885

Page 23

CAPITAL PLAN 2021-22 APPENDIX 7
ICT
Category Service Project
Previous
Years
£000's
2021-22
£000s
2022-23
£000s
2023-24
£000s
Future
Years
£000s
Total
£000s
Asset Sustainability ICT Block Allocation - ICT 0 0 704 919 771 2,394
PC Replacement 0 508 52 0 0 560
Server Sustainability 0 81 41 64 0 186
Telecomms Network 0 168 10 0 0 178
Asset Sustainability Total 0 757 807 983 771 3,318
Service Development ICT Applications Projects 1,360 766 757 0 0 2,883
Service Development Total 1,360 766 757 0 0 2,883
Overall Total 1,360 1,523 1,564 983 771 6,201

Page 24

CAPITAL PLAN 2021-22 APPENDIX 7
Roads and Infrastructure Services
Category Service Project
Previous
Years
£000's
2021-22
£000s
2022-23
£000s
2023-24
£000s
Future Years
£000s
Total
£000s
Asset Sustainability RIS Acquisition of Glen Loin Car Park, Arrochar - CFCR 0 160 0 0 0 160
Bin Replacement Programme 0 0 100 0 0 100
Bridge Strengthening 0 357 1,349 350 350 2,406
Bute Sea Wall Repairs 0 250 750 0 0 1,000
Coastal Change Adaptation 0 0 159 0 0 159
Coastal Protection 0 0 20 80 100 200
Eilean Dhuira Ferry Engine - CFCR 21-22 0 60 0 0 0 60
Environmental Projects 0 79 734 100 100 1,013
EV Quick Chargers 0 4 93 0 0 97
Flood Prevention 0 136 474 305 305 1,220
Footway Improvements 0 641 269 0 0 910
Glengorm - Capping 0 0 82 0 0 82
Glengorm - Cell and Transfer Station (PB) 0 375 560 0 0 935
Helensburgh CHORD - Signage etc 0 0 10 0 0 10
Helensburgh Flood Mitigation 0 16 432 0 0 448
Investment in Active Travel 0 0 500 0 0 500
Lighting 0 74 740 150 150 1,114
Local Bridge Maintenance Fund 0 3 1,237 4,210 0 5,450
Play Park Renewal 0 0 155 0 0 155
Public Convenience Upgrades 0 0 82 0 0 82
RIS - Roads Plant and Equipment - CFCR 0 64 0 0 0 64
Roads Recon - A816 - CFCR 0 97 0 0 0 97
Roads Reconstruction 0 10,775 8,475 3,449 3,412 26,111
Roads Reconstruction - Helensburgh CHORD 0 67 47 0 0 114
Roads Reconstruction - Oban CHORD 0 49 3 0 0 52
Tobermory Car Park 0 49 951 0 0 1,000
Asset Sustainability Total 0 13,256 17,222 8,644 4,417 43,539
Service Development RIS Campbeltown Old Quay 1,381 0 43 0 0 1,424
Fleet Management 1,264 1,595 0 0 0 2,859
Fleet Management - Prudential Borrowing 1,461 1,213 2,187 0 0 4,861
Jackson's Quarry Refurbishment 0 283 0 0 0 283
Lismore Ferry Replacement 157 461 2 15 20 655
Lochgilphead Depot Rationalisation 19 0 0 0 0 19
Mill Park Depot Demolition 126 0 0 0 0 126
Oban Depot Development 2,065 35 0 0 0 2,100
Preliminary design for  Regional Transport projects (tif) 205 0 16 0 0 221
Witchburn Road Demolition 158 -1 0 0 0 157
Service Development Total 6,836 3,586 2,248 15 20 12,705
Strategic Change RIS Campbeltown Flood Scheme 584 294 10,354 3,983 0 15,215
Harbour Investment Programme PB 5,514 1,192 33,664 16,900 34,022 91,292
Street Lighting LED Replacement 3,093 16 791 0 0 3,900
Strategic Change Total 9,191 1,502 44,809 20,883 34,022 110,407
Overall Total 16,027 18,344 64,279 29,542 38,459 166,651

Page 25

CAPITAL PLAN 2021-22 APPENDIX 7
Development and Economic Growth
Category Service Project
Previous
Years
£000's
2021-22
£000s
2022-23
£000s
2023-24
£000s
Future
Years
£000s
Total
£000s
Service Development DEG Ardrishaig North Active Travel 0 0 600 0 0 600
Cycleways - H&L (FSPT) 2,525 197 100 150 0 2,972
Dunoon Cycle Bothy 0 13 266 0 0 279
Dunoon STEM Hub 0 5 603 0 0 608
Gibraltar Street Public Realm Improvements 0 2 248 0 0 250
Helensburgh Public Realm - Arts Strategy Fund 0 2 51 0 0 53
Hermitage Park 3,245 0 69 0 0 3,314
Nature Restoration Fund 0 0 108 0 0 108
Safe Streets, Walking and Cycling (CWSS) 1,949 382 547 0 0 2,878
SPT - bus infrastructure 1,405 0 0 0 0 1,405
Town Centre Funds 757 1,992 782 30 0 3,561
Service Development Total 9,881 2,593 3,374 180 0 16,028
Strategic Change DEG 01 TIF - Lorn/Kirk Road 2,169 0 1 0 0 2,170
05 TIF - North Pier Extension 214 0 0 0 0 214
09 TIF - Oban Airport Business Park 483 6 101 0 0 590
TIF - Halfway House Roundabout 0 43 597 0 0 640
Strategic Change Total 2,866 49 699 0 0 3,614
Overall Total 12,747 2,642 4,073 180 0 19,642

Page 26

CAPITAL PLAN 2021-22 APPENDIX 7
Health & Social Care Partnership
Category Service Project
Previous
Years
£000's
2021-22
£000s
2022-23
£000s
2023-24
£000s
Future
Years
£000s
Total
£000s
Asset Sustainability HSCP Ardfenaig 0 0 125 0 0 125
Block Allocation 0 0 390 431 428 1,249
Capital Property Works 0 0 139 0 0 139
Digitalising telecare 0 0 100 0 0 100
Eadar Glinn 0 0 196 0 0 196
Glencruitten Hostel 0 2 36 0 0 38
Gortonvogie 0 0 80 0 0 80
Greenwood/Woodlands 0 0 224 0 0 224
Lochgilphead Resource Centre 0 0 16 0 0 16
Lorn Resource Centre 0 16 0 0 0 16
Struan Lodge Boiler 0 0 252 0 0 252
Thomson Home Rothesay 0 0 125 0 0 125
Tigh An Rudha HFE 0 0 372 10 0 382
Asset Sustainability Total 0 18 2,055 441 428 2,942
Service Development HSCP Dunclutha Childrens Home 1,246 0 54 0 0 1,300
Service Development Total 1,246 0 54 0 0 1,300
Overall Total 1,246 18 2,109 441 428 4,242

Page 27

CAPITAL PLAN 2021-22 APPENDIX 7
Live Argyll
Category Service Project
Previous
Years
£000's
2021-22
£000s
2022-23
£000s
2023-24
£000s
Future
Years
£000s
Total
£000s
Asset Sustainability Live Argyll Aqualibrium 0 0 28 0 0 28
Campbeltown Community Centre - Fire Alarm and Door Upgrade 0 16 0 0 0 16
Campbeltown Museum - Burnet Bldg 0 12 0 0 0 12
Capital Property Works 0 0 1,031 431 428 1,890
Corran Halls - Emergency Heating Works 0 15 0 0 0 15
Helensburgh Swimming Pool - Roofing 0 23 0 0 0 23
Inveraray CARS 0 0 21 0 0 21
LA - Indoor Cycles 0 37 0 0 0 37
LA - Victoria Halls - Modular Stage 0 15 0 0 0 15
Lochgilphead Community Ed Centre 0 8 0 0 0 8
Lochgilphead Library Relocation 0 5 20 0 0 25
Queen's Hall - Partition Wall 0 6 0 0 0 6
Riverside Leisure Centre - Cladding Upgrade 0 1 46 0 0 47
Riverside Leisure Centre - Spa Pool Upgrade 0 0 20 0 0 20
Rothesay Swimming Pool 0 28 27 0 0 55
The Moat Centre - Gym Store 0 3 0 0 0 3
The Moat Centre - Heating Upgrade 0 53 0 0 0 53
The Moat Centre - Window Upgrade 0 8 0 0 0 8
Victoria Hall, Campbeltown 0 30 0 0 0 30
Victoria Halls, Helensburgh 0 51 10 0 0 61
Asset Sustainability Total 0 311 1,203 431 428 2,373
Service Development Live Argyll Riverside Leisure Centre Refurbishment 1,245 -13 0 0 0 1,232
Service Development Total 1,245 -13 0 0 0 1,232
Strategic Change Live Argyll Carbon Management 29 0 21 0 0 50
Strategic Change Total 29 0 21 0 0 50
Overall Total 1,274 298 1,224 431 428 3,655