MINUTES of MEETING of ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE
COMMITTEE held in the COUNCIL CHAMBER, KILMORY, LOCHGILPHEAD AND ON A HYBRID
MEETING BASIS BY MS TEAMS ATTENDANCE 
on THURSDAY, 2 JUNE 2022 
Present: Councillor Robin Currie (Chair) 
Councillor John Armour
Councillor Jan Brown
Councillor Garret Corner
Councillor Mark Irvine
Councillor Andrew Kain
Councillor Jim Lynch
Councillor Tommy MacPherson 
Councillor Ian  MacQuire
Councillor Luna Martin
Councillor Ross Moreland
Councillor William Sinclair
Councillor Andrew Vennard
Councillor Peter Wallace 
Attending: Kirsty Flanagan, Executive Director
Fergus Murray, Head of Development and Economic Growth
Jim Smith, Head of Roads and Infrastructure Services
Stuart McLean, Committee Manager
Nathan Gallogley, Staycation Officer 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillors John McAlpine and Donald Kelly. 
2. DECLARATIONS OF INTEREST 
Councillor Jim Lynch declared a non-financial interest in item 10 (Update on Staycation
Proposals) as he was a member of the GRAB Trust.  Having noted the updated Standards
Commission Guidance in relation to declarations (issued on 7 December 2021) with
specific reference to section 5.4(c) he did not consider that he had a relevant connection
and as such would remain the meeting and speak and vote on this report. 
3. MINUTES 
The Minute of the Environment, Development and Infrastructure Committee held on 3
March 2022 was approved as a correct record. 
4. KEY PERFORMANCE INDICATORS FQ4 - 2021/22 - DEVELOPMENT AND
ECONOMIC GROWTH & ROADS AND INFRASTRUCTURE SERVICES 
A paper presenting the Environment, Development and Infrastructure Committee with the
FQ4 2021/22 Key Performance Indicators (KPIs) for Development and Economic Growth
and Roads and Infrastructure Services was considered. 
Decision 
The Committee reviewed and scrutinised the FQ4 2021/22 KPI Report as presented. 
(Reference: Report by Executive Director with responsibility for Customer Support
Services dated 25 April 2022, submitted)

Page 2

5. ROADS CAPITAL RECONSTRUCTION PROGRAMME 2022/23 UPDATE 
At the Environment, Development and Infrastructure Committee held on 3 March 2022 a
programme of roads reconstruction works was endorsed.  Since the programme was set,
there have been significant international occurrences which have affected the prices of
both fuel and bitumen. 
A report providing an update on the roads reconstruction programme for 2022/23 was
before the Committee for consideration. 
Decision 
The Committee:- 
1. Endorsed the approach taken to deliver the programme within budget given the price
increases; and 
2. Noted that the 2022/23 footway programme would be reported to the September
Environment, Development and Infrastructure Committee. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated 20 May 2022, submitted) 
6. ROADS AND INFRASTRUCTURE PROJECTS - COUNCIL FUNDED 
A report providing Members with information on the Council funded projects and schemes
being taken forward by the Roads and Infrastructure Service was considered. 
Decision 
The Committee:- 
1. Endorsed the overall programme of council funded projects being taken forward by
Roads and Instructure Services; 
2. Noted that a programme of street lighting column replacements will be brought to the
Environment, Development and Infrastructure Committee in September 2022 and 
3. Agreed to the Chair of the Environment, Development and Infrastructure approaching
the Scottish Government with a view to securing additional resources to support the
scheme to repair the damaged Bute sea wall. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated 24 May 2022, submitted) 
7. ROADS AND INFRASTRUCTURE PROJECTS - EXTERNALLY FUNDED 
A report providing Members with information on the wide ranging programme of works
which are externally funded considered.

Page 3

Decision 
The Committee:- 
1. Endorsed the overall programme of major externally funded projects being taken
forward by Roads and Instructure Services; 
2. Endorsed the programme of bridge works set out at Appendix 1 of the report; 
3. Endorsed the programme of playpark works identified as High Priority set out at
Appendix 2 of the report; and 
4. Instructed Officers to undertake a more robust consultation process with communities
for future rounds of funding in respect of playpark works. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated May 2022, submitted) 
8. DIGITAL EXCLUSION FUND - UPDATE 
The Council established a £250,000 Digital Exclusion Fund at its budget meeting on 25
February 2021.  The Fund was created to support communities and in some cases
individuals that are missing out on national programmes due to logistics and economies of
scale. 
A report bringing forward two proposals for funding from the Digital Exclusion Fund was
considered. 
Decision 
The Committee approved:- 
1. The provision of capital funding to Kerrera Digital Infrastructure project to a maximum
of £40,000; and 
2. The provision of revenue funding to a maximum of £10,000, should the Islands
Infrastructure Find bid be successful, in order to provide connectivity charges for
identified island community halls for a period of 24 months. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 19 May 2022, submitted) 
9. ECONOMIC STRATEGY AND RECOVERY PLAN UPDATE 
Members approved a new Economic Strategy for Argyll and Bute in March 2019 and a
high level economic recovery plan in June 2020 for the Argyll and Bute region in response
to the Covid 19 pandemic.  In August 2020, a further report to the Business Continuity
Committee identified key objectives and actions that needed to be taken forward to assist
with economic recovery. 
A report providing Members with a brief economic overview and an update on progress on
both the actions agreed in the original economic strategy approved in June 2019 and the
subsequent recovery plan approved in 2020, was considered.

Page 4

Decision 
The Committee:- 
1. Considered the contents of this report and noted the updated Argyll and Bute
Economic Strategy Actions contained in Appendix 1 of the report and also noted the
progress of the Economic Recovery Plan Actions identified in Appendix 2 of the report;
and 
2. Considered and noted the intention to look at future economic priorities given the
rapidly changing economy. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated May 2022, submitted) 
10. UPDATE ON STAYCATION PROPOSALS 
The Council allocated two funding pots to support staycations in Argyll and Bute. 
£500,000 was allocated from the 2021/22 budget and supplemented by a further £100,000
from the 2022/23 budget to support the delivery of a range of facilities across Argyll and
Bute necessary to support camping and motorhome staycations. 
Consideration was given to a report providing an update on the staycation facilities
approved in December 2021 by the Committee for 2022, which were now set up and
operational. 
Decision 
The Committee:- 
1. Noted and considered the content of the paper; and 
2. Noted that Staycation was an evolving process with key milestones identified
throughout the year and beyond. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 7 June 2022, submitted) 
11. TRANSPORT FOR STRATHCLYDE: A NEW PUBLIC TRANSPORT NETWORK 
Consideration was given to a report advising of correspondence received from the Chair
of Strathclyde Partnership for Transport (SPT) which sought support from local authorities
for the vision and direction detailed within “Transport for Strathclyde: A New Public
Transport Network”. 
Decision 
The Committee:- 
1. Noted the letter from Councillor Dr Martin Bartos, Chair of SPT; and 
2. Supported the vision and direction detailed in the letter.

Page 5

(Reference: Report by Executive Director with responsibility for Development and
Economic Growth/Roads and Infrastructure Services dated April 2022, submitted) 
12. ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
WORK PLAN 2022/23 
The Environment, Development and Infrastructure Committee work plan was before the
Committee for information. 
Decision 
The Committee noted the contents of the work plan. 
(Reference: Environment, Development and Infrastructure Committee Work 2022/23,
submitted)