1.0 EXECUTIVE SUMMARY 
1.1 This report details the proposed annual Strategic Housing Investment Plan which
will cover the period 2023/24 - 2027/28. The document is required to be submitted
to the Scottish Government by October 2022. This paper summarises the
proposals for the revised SHIP, in line with statutory requirements and the latest
guidance. 
In July 2021 The Scottish Government allocated Resource Planning
Assumptions (RPAs) to local authorities for the five years to the end of March
2026. The Scottish Government have confirmed that the figures for 2027 and
2028 can be based on the allocations from previous years although they are not
formal definitive allocations: 
Year 2023/24 2024/25 2025/26 2026/27 2027/28 Total
RPA £18.264m £18.328m £18.632m £18.632m £18.632m £92.488m 
1.2 In 2021/22, the SHIP delivered 143 new affordable homes. This SHIP identifies
potential for around 247 units to be completed in 2022/23 and over 750 additional
homes to be completed or approved in subsequent years. 
1.3 As well as addressing unmet local need and contributing to national targets, the
proposed programme will generate additional investment in the local economy,
supporting additional jobs including new apprenticeships in the construction
sector and associated labour market; it will stimulate community regeneration and
sustainability; it will help to attract and retain residents and employees for local
businesses; it will encourage movement within, and more effective operation of,
the local housing system; it will also contribute to improving general health and
well-being; and more pragmatically the new homes will also generate additional
Council tax revenue. 
RECOMMENDATIONS   
It is recommended that the Council:  
a) Approve the SHIP proposals summarised in this report, which will then be
submitted to the Scottish Government in October 2022. 
ARGYLL AND BUTE COUNCIL  COUNCIL
DEVELOPMENT AND 
ECONOMIC GROWTH 
29 SEPTEMBER 2022 
STRATEGIC HOUSING INVESTMENT PLAN (SHIP) 2023/24 - 2027/28

Page 2

ARGYLL AND BUTE COUNCIL                                                              COUNCIL 
DEVELOPMENT AND ECONOMIC 
GROWTH                29 SEPTEMBER 2022 
STRATEGIC HOUSING INVESTMENT PLAN (SHIP) 2023/24 - 2027/28 
2.0 INTRODUCTION 
2.1 This paper seeks council approval of the revised Strategic Housing Investment
Plan (SHIP) 2023/24 – 2027/28 which will then be submitted to the Scottish
Government in October 2022. The core purpose of the SHIP is to set out strategic
investment priorities for affordable housing over a five year period to achieve the
outcomes set out in the Local Housing Strategy. 
2.2 The SHIP remains a continuous, iterative process: individual projects are subject
to a variety of factors which can lead to slippage or revision; and the overall
programme requires constant monitoring.   Formal updates are now required on
an annual basis. 
2.3 The revised SHIP has potential for delivery of around 247 units this year, and over
750 new affordable homes in subsequent years. 
3.0      RECOMMENDATIONS 
3.1  It is recommended that the Council: 
a) Approve the SHIP proposals summarised in this report which will then be
submitted to the Scottish Government in October 2022. 
4.0 DETAIL 
4.1 From 2017, the Scottish Government and COSLA/Association of Local
Authority Chief Housing Officers (ALACHO) agreed that SHIPs would revert to
being submitted on an annual basis. In June 2022 revised guidance was issued
to assist local authorities prepare their SHIPs, which require to be submitted to
the Scottish Government by October 2022, and will cover the period 2023/24–
2027/28. 
4.2 The Local Housing Strategy (LHS) sets out the strategic policy approach of the
council and its partners to delivering high quality housing and related services
across all tenures to meet identified need in the area. SHIPs are directly
informed by the LHS and its policies and are developed in consultation with key
stakeholders. Therefore, the SHIP is operational in nature and not considered
as a policy document.

Page 3

4.3 The core purpose of the SHIP remains to set out strategic investment priorities
for affordable housing over a five year period to achieve the outcomes
contained in the LHS. The plan reinforces the council as the strategic housing
authority; the importance of the outcomes and targets set out in the LHS; and
informs Scottish Government investment decisions. 
4.4 The SHIP should therefore:- 
 Set out investment priorities for affordable housing; 
 Demonstrate how these will be delivered; 
 Identify the resources required to deliver these priorities; and 
 Enable the involvement of key partners.   
The SHIP should contain a succinct narrative in PDF form, submitted as a
supporting document to the SHIP in the Housing and Regeneration
Programme (HARP) system, which explains the context to the SHIP including: 
 A statement on alignment with the LHS demonstrating that priorities
identified in the SHIP are consistent with what the local authority
outlined in its LHS (and any subsequent updates) and how the SHIP
priorities will contribute to delivery of LHS Outcomes;  
 A summary of the methodology used to prioritise projects; 
 Details of how the local authority has responded to and resolved
development constraints on projects prior to the site start date; 
 Details on how the local authority’s own resources and other funding
are supporting the delivery of affordable housing in its area;  
 Details of progress towards the delivery of its Affordable Housing
Supply Programme across all tenures by completions;  
 Details of affordable housing projects for Gypsy/Travellers;  
 Details of Housing Infrastructure Fund projects where these are linked
to affordable housing delivery;  
 Details of local plans to support the delivery of wheelchair accessible
housing within its area;   
 A statement that strategic housing priorities are aligned and are
consistent with Rapid Rehousing Transition Plan priorities;   
 Details of affordable housing projects that are aligned with the local
authority’s Child Poverty Action Report;   
 Details that duties under the Islands (Scotland) Act have been followed
by the local authority if appropriate;  
 Details of any empty homes services and actions to bring homes back
into use;  
 Details of how Council Tax on Second and Empty Homes has been
used to assist affordable housing;   
 Details of how Developer Contributions have been used to assist
affordable housing; and   
 The type and level of consultation undertaken with RSLs, communities,
developers and other stakeholders in developing the SHIP and how
this has helped with the development of strategic investment priorities.

Page 4

4.5  Key Aspects of the SHIP Guidance Issued in June 2022 
Building on previous guidance, the Scottish Government’s most recent
guidance includes an enhanced emphasis on ensuring that the SHIP is
aligned with the local Child Poverty Action report. The delivery of affordable
housing is key to efforts to alleviate poverty in general. 
The guidance also requires details on how the SHIP supports and enables the
local authority to deliver duties required under the Islands Act. 
The guidance continues to include an enhanced emphasis on the delivery of
wheelchair accessible housing in support of action 62 of the Fairer Scotland
for Disabled People Action Plan. 
The latest guidance also emphasises and includes specific linkages between
the SHIP process and the duty on local authorities to produce Rapid Rehousing
Transition Plans, essentially ensuring that the delivery of the SHIP will have
direct impact on homelessness in the local authority area. 
4.6 Resource Planning Assumptions (RPAs). 
In July 2021 The Scottish Government allocated Resource Planning
Assumptions (RPAs) to local authorities for the five years to the end of March
2026. The Scottish Government have confirmed that the figures for 2027 and
2028 can be based on the allocations from previous years although they are not
formal definitive allocations: 
Year 2023/24 2024/25 2025/26 2026/27 2027/28 Total
RPA £18.264m £18.328m £18.632m £18.632m £18.632m £92.488m 
It should be noted that this is potential investment for Argyll and Bute, dependent
on actual need and deliverability of suitable projects. While obviously very
welcome, this level of funding will also present real challenges for the Council and
its partners. This would be subject to sufficient complementary funding being
available from the Council and RSLs themselves to support the programme; and
the capacity of the constrained local construction industry to gear up to such an
enhanced level of productivity. 
4.7 Additional funding is required to complement the Scottish Government
investment, and in Argyll and Bute this includes a significant contribution from the
Council’s Strategic Housing Fund (SHF) as well as Housing Association
investment drawn from private sector borrowing. The council’s SHF is primarily
based on the revenue raised from reduced tax discounts on holiday and second
homes. The SHIP sets out plans to fully utilise the SHF over 5 years to support
the affordable housing development programme, including empty homes grants
and loans. The projected income to the SHF over the next 3 years is
approximately £2m per annum. An indicative estimate of around £2.29m would
be required to support in full the Scottish Government investment outlined in the

Page 5

2023/24 RPA above based on the Scottish Government’s updated baseline
benchmark of £95 500 per unit. 
4.8 Consultation and Collaboration 
The preparation of the SHIP is intended to be viewed as a corporate activity
with close working relationships fostered across housing, planning, economic
development and other internal services. It is also crucial that the SHIP process
is based on collaboration between the Council, RSLs, communities,
developers, the Scottish Government and other stakeholders such as the
Health and Social Care Partnership; and that the SHIP document should
provide a detailed narrative about how consultation and collaboration has been
undertaken with all stakeholders. In Argyll and Bute, while the Council remains
the strategic authority with overall responsibility for the plan, local RSLs and
developers are engaged formally and informally throughout the process, and
do lead on delivering most of the individual projects. Regular review meetings
are held with SHIP officers from the Council, RSLs, and the Scottish
Government, and all proposals and decisions are considered by the
overarching, multi-agency Strategic Housing Forum. Updates are also being
tabled at local area community planning groups; and at the level of specific
projects, sites and settlements, a range of community representatives and
individual residents are routinely engaged and consulted. In recent years, a
number of local community councils and development trusts have pro-actively
engaged in the SHIP process, undertaking localised Housing Need and
Demand Assessments (HNDAs), with Council support, to feed into the process
and contributing to discussions on the project proposals. Additional
engagement has been promoted across the local business sector and a
network of employers and other interested parties has been established for
future consultation. 
4.9 A primary focus for the new SHIP has been engagement with the Health and
Social Care Partnership (HSCP) to ensure adequate specialist provision is
included in the new build programme. The HSCP’s new 3 year strategic plan
was launched in 2022 and incorporates a Housing Contribution Statement
(HCS) outlining the essential role housing plays in supporting and maintaining
independence, health and well-being of residents. The new LHS consolidates
the partnership working with the HSCP and sets out a high level outcome which
is: 
“To enable people with particular needs to live independently in their
own homes and to remain in their communities” 
The post of dedicated Housing Occupational Therapist which was established
in October 2018 to co-ordinate and promote these needs through the SHIP
group, was made permanent in 2021. 
4.10 Housing Infrastructure Fund (HIF) 
The Scottish Government introduced a Housing Infrastructure Fund in 2016 to
support housing development through dedicated loans and grants. The HIF will

Page 6

prioritise sites which are of strategic importance and cannot proceed or have
stalled due to exceptional infrastructure works. The Council secured a £2.1
million HIF grant to address the costs of upgrade works at Kirk Road/Lorn Road. 
This work is now complete and has enabled delivery of the ongoing 300 unit
affordable housing development at Dunbeg, which remains a high strategic
priority for the council and its partners. The SHIP annual update contains
proposals for 3 further HIF projects in Argyll. 
4.11 Other Affordable Housing Provided Without AHSP Assistance 
SHIPs should contain details of all proposed affordable housing projects within
the local authority area including those which will be provided without AHSP
support. This could include off the shelf purchases, buybacks of ex-council/RSL
stock, projects where councils have exclusively used their own resources,
pension funds or other sources of funding, including Scottish Government non-
AHSP funds to develop housing. 
The Council will continue to explore these and all other appropriate options to
increase the supply of affordable housing. The Council agreed an Open Market
Purchase Statement with the Scottish Government in January 2022. 
SHF has contributed to 1 Rural and Islands Housing Fund projects in Argyll
during 2022 – the refurbishment of 6 properties for affordable rent on Ulva
through the North West Mull Community Woodland Company (NWMCWC). In
addition a Community Housing Network Group has been established by the
Council to support community groups to take forward housing projects which
meet identified need. 
The potential impact of the proposed Rural Growth Deal (RGD) for Argyll and
Bute will be significant, and the SHIP and the housing sector in general can
contribute to this strategic agenda. 
4.12 Current Progress: Outputs 2021/2022 
Table 1 details the affordable housing delivered by the SHIP in 2021/22. 
TABLE 1:  SHIP New Build Homes by HMA & Project, 2021/22
Housing Market
Area
Projects Completions % of total
Cowal Cairndow (FYNE HOMES) 6 4%
Lorn Kirk Road (Dunbeg) (WHHA) 4 3%
Dunbeg Phase 3 (LINK) 115 80%
Helensburgh and
Lomond
Garelochhead (ACHA) 10
7%
Islay, Jura and
Colonsay
Imeraval Phase 3 (WHHA) 8
6%
TOTAL 143 100%

Page 7

4.13 The Revised SHIP Programme 
The current year, 2022/23, is covered by a Strategic Local Programme
Agreement while the new SHIP is intended to commence from 2023/24. The
following tables summarise all proposals at the time of writing, including those
projects which were completed in the first quarters of this year and for which
funding has already been drawn down. It should be noted that the status of
many future projects, particularly in the later years, remains provisional and
purely indicative at this stage; some may not proceed within the timescale.
However there is also scope for additional proposals to be brought forward or
included in earlier years. 
TABLE  2: SHIP Projects Completions/Anticipated Completions in 2022/23
Project address Developer Units Anticipated
Completion Date
Inveraray Phase 2 ACHA 10 Completed June
2022
Tarbert  ACHA 4 Nov 2022
Millknowe Campbeltown ACHA 2 Nov 2022
Tom-A-Mhoid Road Dunoon FYNE HOMES 1 March 2023
Dunbeg Phase 3 (remaining
units) LINK 185 March 2023
Sawmillfield Helensburgh WHEATLEY GROUP 36 March 2023
Jura  WHHA 10
Completed July
2022
Argyll & Bute 2022/23 Total Completions (est.) 248 March 2023 
TABLE 3: SHIP Core Programme - Potential Completions by March 2028
Project address Developer Units Anticipated
Completion1
Bowmore Phase 4 ACHA 18 Year 1 (23/24)
Eton Avenue Dunoon  ACHA 4 Year 1 (23/24)
North Connel - Phase 2 ACHA 2 Year 2 (24/25)
Tighcargaman Port Ellen   ACHA 20 Year 2 (24/25)
Dalintober  ACHA 25 Year 2 (24/25)
Coll  ACHA  10 Year 2 (24/25)
Tarbert ACHA 15 Year 2 (24/25)
Tarbert ACHA 15 Year 3 (25/26)
Keills  ACHA 4 Year 4 (26/27)
Jeanie Deans Helensburgh DUNBRITTON HA 12 Year 1(23/24)
Helensburgh Golf Club DUNBRITTON HA 62 Year 1 (23/24)
18th Tee, Helensburgh DUNBRITTON HA 16 Year 1 (23/24)
Cardross DUNBRITTON HA 37 Year 3 (25/26)
Succoth Phase 2, Arrochar DUNBRITTON HA 12 Year 4 (26/27)
Lochgilphead Riverside Drive
Baddens FYNE HOMES 6 Year 1 (23/24)
Inveraray Phase 1 FYNE HOMES 16 Year 1 (23/24)
Ballochgoy Rothesay FYNE HOMES 10 Year 1 (23/24)

Page 8

Rothesay Academy Phase 1 FYNE HOMES 30 Year 2 (24/25)
Inveraray Phase 2 FYNE HOMES 10 Year 2 (24/25)
Rothesay Academy Phase 2 FYNE HOMES  20 Year 4 (24/25)
Cairndow Phase 2 FYNE HOMES 4 Year 5 (27/28)
Tighnabruaich Phase 2 FYNE HOMES 10 Year 5 (27/28)
Dunbeg Phase 4 LINK 90 Year 2 (24/25)
Rosneath LINK 49 Year 3 (25/26)
Hospital Field site Oban LINK 50 Year 3 (25/26)
Lonan Drive Oban  LINK 44 Year 3 (25/26)
Glencruitten LINK 100 Year 4 (26/27)
Dunbeg Phase 5 LINK 75 Year 4 (26/27)
Dunbeg Phase 6 LINK 75 Year 5 (27/28)
Port Charlotte Phase 1 WHHA 14 Year 1 (23/24)
Imeraval Phase 4 Islay WHHA 20 Year 1 (23/24)
Tobermory Phase 3  WHHA 12 Year 2 (24/25)
Port Appin Phase 1 WHHA 6 Year 2 (24/25)
Craignure  WHHA 22 Year 2 (24/25)
Colonsay WHHA 5 Year 2 (24/25)
Salen WHHA 8 Year 3 (25/26)
Port Appin Phase 2 WHHA 24 Year 5 (27/28)
Bunessan Phase 2 WHHA 4 Year 5 (27/28) 
Argyll and Bute Total  956 2023-2028 
1 NB. Timescales are indicative and subject to change; and will be monitored on a
regular basis. Some projects could also revise their final number of units. 
4.14 Alternative sites are also being considered either to replace or enhance some
of the sites listed in above tables. The Council also continues to provide support
for communities considering the use of the Government’s Rural and Island
Housing Funds and other resources to deliver affordable housing out with the
core AHSP development programme. The table below provides details of these
projects. 
TABLE 4 : Community Housing Projects
HMA PROJECT/COMMU
NITY
UNITS
Mull & Iona Ulva (Refurb) 6
Mull & Iona Glengorm (Refurb) 5
Islay, Jura &
Colonsay
Port Askaig, Islay 2
Islay, Jura &
Colonsay
Scalasaig, Colonsay
Phase  1
12 units in total made up of
3 Self build plots, 
3 Private Rented units (Mowi) 
6 affordable housing units of which 4 are social
rent and 2 are shared equity 
Argyll and Bute Total 25

Page 9

4.15 Impact Assessments 
In preparing the SHIP, as in all aspects of housing policy and planning, the
Council has taken account of the housing needs of all the communities we
serve, and continues to address equalities issues and adhere to principles of
diversity and inclusion. In addition to the robust baseline evidence of specialist
accommodation and support needs across the range of equalities client groups
contained in the HNDA, the Council is proactively pursuing engagement with
the Health and Social Care Partnership to inform the SHIP programme. An
overarching equality impact assessment will be completed for the LHS and this
will inform our assessment of the impact of the SHIP, and how the strategic
aims are embodied in the housing priorities of the programme. Housing
Services will also consider requirements for Health Inequalities Impact
Assessments, Child Rights and Wellbeing Impact Assessments or other
potential policy implications. However, as the responsible authority for the
purposes of the relevant 2005 Act, the Council has determined that a Strategic
Environmental Assessment (SEA) is not required for the LHS or SHIP. 
5.0 CONCLUSION 
5.1 The Scottish Government will review the SHIP in line with the process agreed
jointly with COSLA. Their appraisal will therefore take account of the following: 
the extent to which the SHIP delivers LHS Outcomes; the extent to which it is
feasible to deliver; the local authority’s contribution to the delivery of the
programme, both in terms of its facilitation role and in terms of maximisation of
resources; evidence that the Council is supporting the efficient delivery of the
SHIP; evidence of stakeholders’ involvement in developing the SHIP and in the
implementation of proposals; and the extent to which it takes account of equality
issues. In March 2021, the Scottish Government provided positive feedback on
the previous SHIP, submitted last year, and their comments have also continued
to inform this latest version of the SHIP moving forward. 
5.2 It is recognised that an adequate supply of suitable housing is becoming an
increasing pressure within Argyll and Bute. The Council is fully committed to, and
actively exploring, all opportunities to enable housing delivery which meets the
identified need and demand across the local authority area. 
6.0 IMPLICATIONS   
6.1  Policy - Proposals are consistent with current Council policy, including the
revised policy in respect of the use of Strategic Housing Fund monies. The
SHIP supports the Local Housing Strategy vision and outcomes which are
directly aligned with the overarching objectives of the Outcome Improvement
Plan, in particular Outcome 2 – we have infrastructure that supports
sustainable growth.

Page 10

6.2  Financial - The proposals are based on the Resource Planning Assumptions
provided by the Scottish Government; the Strategic Housing Fund and RSL
private finance. There will be an ongoing requirement to retain and target SHF
resources to support the proposed programme. 
6.3  Legal - The submission of the SHIP will meet our statutory duties, and following
its approval, Strategic Local Programme Agreements will be concluded
between the Council and Scottish Government. 
6.4  HR – None.   
6.5   Fairer Scotland Duty - The proposals are consistent with aims and objectives
set out in the local housing strategy, which is subject to an EQIA.   
6.5.1  Equalities Protected characteristics - There are targets set within the SHIP to
deliver housing which meet the needs of specialist groups.   
6.5.2  Socio-economic Duty – The delivery of affordable housing across Argyll and
Bute facilitates socio-economic opportunities for all. The SHIP links with the
Child Poverty Strategy. 
6.5.3  Islands – The Housing Needs and Demand Assessment process takes full
account of housing need on the islands. New build developments on the islands
are included in each of the SHIP tables. 
6.6  Climate Change – All new build properties delivered through the SHIP are built
to a Greener Standard. 
6.7  Risks – Risk assessment is an integral part of each development and will be
considered as the programme moves forward. The SHIP is required to show
how risk will be managed. Failure to deliver a robust SHIP could result in loss
of substantial government investment for the local authority area. Alternatively,
however, failure to forward plan judiciously and to programme development in
line with identified needs could result in over supply; generating imbalances in
the local housing market, and creating risks for RSLs and the management of
their existing stock, with consequent adverse effects on local neighbourhoods
and communities. 
6.8  Customer Service - The proposals will deliver increased access to a range of
suitable, affordable housing options. 
Kirsty Flanagan, Executive Director with responsibility for Development and
Economic Growth 
Councillor Robin Currie, Policy Lead for Economy and Rural Growth   
September 2022 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth   
Fergus.Murray@argyll-bute.gov.uk

Page 11

Douglas Whyte, Team Lead – Housing Strategy
Douglas.Whyte@argyll-bute.gov.uk 
Appendix 1 – Argyll and Bute Strategic Housing Investment Plan 2023/24 – 2027/28 
APPENDIX 1 – ARGYLL AND BUTE STRATEGIC HOUSING INVESTMENT PLAN
2023/24 – 2027/28

Page 12

ARGYLL and BUTE
STRATEGIC HOUSING INVESTMENT PLAN
2023/24 - 2027/28

Page 13

CONTENTS 
SECTION PAGE      
INTRODUCTION 
1) The Strategic Framework 
2) Stakeholder Consultation 
3) Prioritising the Programme 
4) Delivering the Programme: Mitigating Risks and Resolving
Development Constraints 
5) Resourcing the Programme and the Council’s Contribution 
6) Empty Homes 
7) Child Poverty and Fuel Poverty 
8) Specialist Provision including Wheelchair Habitable Housing 
9) Gypsy/Traveller Sites 
10) Homelessness/ Rapid Rehousing Transition Plans 
11) Buybacks, Second-Hand Acquisitions and Off-Shelf 
12) Update from the Previous Ship 
13) The Revised Programme 
14) Monitoring and Review and Impact Assessments 
CONCLUSION 
Appendices

Page 14

Helensburgh
& Lomond 
Bute &
Cowal 
Mid-Argyll,
Kintyre & Islay
Oban, Lorn &
the Isles 
MULL
Tobermory
Oban
Campbeltown
Bowmore
Rothesay 
Helensburgh Lochgilphead 
COLL
TIREE 
COLONSAY
GIGHA
IONA
BUTE
ISLAY
JURA 
The focus of the Strategic Housing Investment Plan (SHIP) is affordable housing
provision via new build, replacement, rehabilitation or re-modelling. 
“Affordable housing” in this context refers to accommodation made available
at a cost below full market value to meet an identified need and includes: 
 Social rented housing. 
 Subsidised low-cost housing for sale (discounted, shared ownership or
shared equity);
 Low-cost housing without subsidy (entry level housing for sale); and
 Mid-market rental housing provided by social landlords.” 
Guidance on the Preparation of Strategic Housing Investment Plans,   
Scottish Government, July 2016 
AFFORDABILITY – as a basic rule of thumb, an affordable house price is reckoned to
be no more than 3.5 times the annual income of the household; and in terms of renting a
property, the affordable benchmark is often considered to be around 25% of the
household’s income.

Page 15

Argyll and Bute Council remains committed to working closely with the Scottish
Government, local housing associations, and other key partners to increase the
effective supply of affordable homes across the local authority area so that
everyone can access a good quality affordable home that meets their needs. 
The Strategic Housing Investment Plan (SHIP) is a key local authority
document which identifies priority housing projects to support the delivery of
local and national strategic housing targets, as well as helping to increase the
supply of housing across other tenures as appropriate. 
The Local Housing Strategy (LHS) sets out the strategic policy approach of the
council and its partners to deliver high-quality services across all tenures and
meet identified needs in the area. The strategy and its associated policies
directly inform the SHIP.   
This plan is an operational document, setting out how it will deliver the LHS
priorities and outcomes through a five-year strategic investment programme. It
reinforces the council’s role as the strategic housing authority; and informs
Scottish Government housing investment decisions. It also underpins the
preparation of Strategic Local Programme Agreements (SLPAs). 
Specifically, the SHIP is the key document for identifying: 
 proposed strategic housing projects which require funding from the
Scottish Government’s Affordable Housing Supply Programme;
 proposed affordable housing projects which can be provided without
Scottish Government funding support; and
 projects across all tenures requiring grant and loan funding from the
Scottish Government’s Housing Infrastructure Fund. 
This SHIP builds on the previous SHIP published in 2021 and has been
developed in consultation with key stakeholders. The outline draft plan was also
approved by the SHIP Officers’ Group and the Strategic Housing Forum in
2022, and the finalised SHIP was approved on **** 2022 by the full council for
submission to the Scottish Government.    
INTRODUCTION     
This SHIP covers the five years from 2023/24 to 2027/28.

Page 16

The SHIP narrative provides a context to the SHIP and includes the following: 
 A statement outlining the role the SHIP investment priorities plays in
delivering LHS outcomes.
 Details of stakeholder consultation undertaken in developing the SHIP.
 A summary of the project prioritisation framework, including:
 Prioritisation by unit size;
 Prioritisation by how the project addresses duties placed on the council by
the Islands (Scotland) Act; and 
 The council’s investment priorities for housing in town centres
 A list of the risks and key issues constraining the delivery of the programme
and identifying the actions that are required to mitigate against these
constraints. For example, using different construction methods to deliver
SHIP projects.
 Resourcing the programme, including : 
 Details of how the council’s own resources, such as Council Tax on
Second and Empty Homes, support affordable housing delivery;
 Details of other funds that are supporting the delivery of affordable
housing;
 Details of Developer Contributions that have been used to assist
affordable housing delivery; and 
 The role of the Housing Infrastructure Fund in delivering new
affordable housing.
 A summary of the empty homes services and actions being taken by the
council to bring homes back into use.
 Aligning the SHIP programme with the requirement specified in the Argyll
and Bute’s Child Poverty Action Report.
 Details of specialist housing provision delivered over the SHIP period,
including wheelchair-accessible housing. 
 An outline of capital works undertaken on Gypsy/Traveller sites and if the
Gypsy/Traveller Accommodation Fund may fund future works.
 Outlining how the strategic housing priorities are aligned with Rapid
Rehousing Transition Plan priorities.
 A statement on the council’s approach to buybacks, second-hand
acquisitions and off-the-shelf purchases. 
 A review of the previous SHIP (published in 2021)
 A summary of the projects in this SHIP. Full details of these projects can be
seen in the Scottish Government’s electronic system HARP (Housing And
Regeneration Programme)
 Details of how the SHIP will be monitored and reviewed including how the
SHIP programme impacts upon:
 Equalities and Socio-Economic Impact Assessment 
 Child Rights and Wellbeing Impact Assessment
 Health Impact Assessment 
 Islands and Communities Impact Assessment 
 Strategic Environmental Assessment

Page 17

 Argyll & Bute Outcome Improvement Plan (ABOIP) 
Six long-term outcomes underpin this objective: - 
While the housing sector has a role to play in achieving all of these outcomes, the
provision of affordable new build housing, particularly the delivery of the SHIP,
primarily focuses on Outcome 2 (infrastructure supporting sustainable growth). 
1) THE STRATEGIC FRAMEWORK 
The Argyll and Bute Outcome Improvement Plan 2013-
2023 sets out the Community Planning Partnership’s
(CPP) vision for achieving long term outcomes for
communities in Argyll and Bute. As the overarching
strategic document for local partners, including the council,
it provides the high-level context for a wide range of
strategies, plans and policies, including both the Local
Housing Strategy and the SHIP. 
The council and its partners are soon to commence their
review of the current Outcome Improvement Plan and aim
to publish the refreshed document in 2023. Future SHIPs
will align with the new Local Outcome Improvement Plan. 
The overall objective of the plan for the 10 years to 2023 is – 
Argyll and Bute’s economic success is built on a growing population.
In Argyll and Bute:
1. The economy is diverse and thriving.
2. We have infrastructure that supports sustainable growth.
3. Education, skills and training maximises opportunities for all.
4. Children and young people have the best possible start.
5. People live active, healthier and independent lives.
6. People live in safer and stronger communities

Page 18

 Local Housing Strategy (LHS) 2022/23-2026/27 
Underpinning this vision are four high-level outcomes: 
The SHIP continues to play a key role in promoting the overall LHS vision and
delivering on LHS, particularly outcome 1 (Supply and Place Making).   The
council developed a new HNDA in 2021, which the Scottish Government
subsequently approved. The council’s LHS housing supply target of providing
1075 affordable homes from 2022/23 to 2026.27 (215 homes per year) which is 
significantly higher than the baseline HNDA estimate to take account of local and
national strategic aspirations for repopulation, economic recovery, and overall
growth throughout the authority area. 
 Housing supply target 2022/23 to 2026/2027 is 1,450 units across
all tenures (290 per annum). 
 Affordable housing supply target 2022/23 to 2026/27 is 1,075  (215
per annum) 
“Everyone in Argyll & Bute has access to a suitable, high-
quality home which is affordable and located within a
vibrant, sustainable and connected community.” 
1) Housing Supply and Place Making
2) House Condition, Energy Efficiency and Poverty
3) Specialist Provision and Independent Living
4) Housing Options, Information and Support
The Council continues to ensure that the investment
programme and priorities set out in the SHIP are
consistent with the vision, aims and objectives of the
LHS; and that these build on the latest Housing Need
and Demand Assessment (HNDA). Existing strategic
priorities and outcomes continue to be ratified and
supported by partners and stakeholders via the Argyll
and Bute Strategic Housing Forum. Earlier in 2022
the council published it’s new LHS which covers a
five-year planning period from 2022/23 to 2026/27.
The LHS sets out an updated core vision: 
In summary, the SHIP will aim to deliver sufficient suitable and
affordable new homes to attract and retain young people and families,
to support a sustainable and thriving business sector, and to meet the
needs of the elderly/ageing population, and those with particular
needs.
 Potentially, up to 10% of the five-year provision could be for
alternative tenures such as shared equity; and
 10% should comprise some form of “specialist provision”
including 5% which should be fully wheelchair habitable.

Page 19

Scottish Government Priorities and COHI.
One of the Scottish Government’s priorities is to ‘support a more balanced
population across Scotland.’ To achieve this aim, the Scottish Government has
developed a strategy called- ‘A Scotland for the future: Opportunities and
Challenges of Scotland’s Changing population’ to ensure all areas have a more
balanced population “so all our communities can flourish”. 
The Scottish Government’s National Islands Plan aims to address population decline
and ensures a healthy, balanced population profile. In particular, the National Islands
Plan commits to supporting the repopulation of rural and island communities. 
Housing to 2040 aims to deliver the vision for everyone in Scotland, including island
communities, by understanding and identifying what positive measures need to be
taken forward to address, promote and ultimately reduce inequality in housing
outcomes across all housing tenures by 2040 and build strong sustainable
communities. 
The Convention of the Highlands and Islands (CoHI) aims to address the Scottish
Government’s priorities outlined above by establishing a population working group
which recommended that pilot projects were established to tackle depopulation. The
council is a member of CoHI and is participating in the pilot projects. The council has
identified the following areas as repopulation zones: 
•          Rosneath Peninsula 
•          Kintyre (Tarbert to Southend)
•          Tiree and Coll 
•          Bute 
A settlement officer has been employed on a one-year contract to examine the
availability and quality of housing across Argyll and Bute and factors such as cost,
land supply, and infrastructure barriers. The findings from this project will inform
housing investment decisions and future SHIPs. 
As outlined in previous SHIPs, the preparation of this plan, as well as the planning
and delivery of individual projects, remains a continuous, iterative corporate activity.
Since 2019, close working relationships have been further enhanced and streamlined
as the council’s service restructuring brought Housing and Planning Services together
with Economic Development and Regeneration in a single department of
Development and Infrastructure under one Head of Service. In addition, the internal
joint working will include ad hoc involvement of other departments such as Roads,
Property Development/ Estates when appropriate. The SHIP process reflects a strong
collaborative approach with Registered Social Landlords (RSLs, or housing
associations), the Scottish Government, communities, developers and other
stakeholders. 
2) STAKEHOLDER CONSULTATION

Page 20

Key partners include: 
 The Scottish Government: More Homes Scotland Division
 Argyll & Bute Council
 Argyll & Bute Health & Social Care Partnership
 Argyll Community Housing Association
 Fyne Homes Housing Association
 Dunbritton Housing Association
 West Highland Housing Association
 Link Group Ltd
 Wheatley Group
 Loretto Housing Association 
 Bield Housing Association
 Trust Housing Association
 HMNB Clyde/ MOD 
 Loch Lomond & Trossachs National Park
 Rural Housing Scotland 
 Communities Housing Scotland.
 Highlands & Islands Enterprise
 Veterans Housing Scotland
 Scottish Water
 Home Energy Scotland
 ALIenergy 
At the very local level, on a site-by-site basis, RSLs and Council officials continue to
liaise closely with private developers, local landowners, local community groups and
development trusts, and a range of other stakeholders to negotiate, facilitate, enable
and deliver viable projects within the context of the LHS and the framework of the
SHIP. Updates are also being tabled at local area community planning groups.
Community representatives and residents are routinely consulted regarding specific
projects, sites and settlements. 
The Argyll & Bute Strategic Housing Forum, comprising a wide range of key
partners from the Community Planning Partnership, constitutes the overarching
Housing Market Partnership with ultimate responsibility for overseeing the
implementation and monitoring of the LHS and the SHIP; and is chaired by the Council
Leader. The Strategic Housing Forum is also responsible for making appropriate
recommendations to Council Members and lobbying the Scottish Government
regarding housing issues in Argyll and Bute. The Terms of Reference for the Forum,
as the formally constituted local housing market partnership within Argyll and Bute,
were reviewed and agreed upon in September 2020 and are available on request to
the council.
The SHIP Officers Development Group - In addition to regular programming
meetings between the council, the Scottish Government and individual RSLs, a
dedicated SHIP Officers Group continues to bring practitioners from all these parties
together on a quarterly basis to address and progress operational development
matters which are then reported to the overarching Strategic Housing Forum. In
2018/19, a secondary SHIP Partners Group was convened involving other partners

Page 21

such as infrastructure services (Roads and Amenities) and agencies such as Scottish
Water to consider specific project-based issues. This proved successful in addressing
specific constraints and has now been incorporated, as appropriate, within the SHIP
Officers Group and the Strategic Housing Forum.
Community Housing Network Group- Argyll and Bute Council, as the strategic
housing authority, recognises the importance of community groups and their role in
delivering affordable housing. The Community Housing Network Group (CHNG) was
established to improve communication and partnership working. The group exists to
fulfil the following aims: 
 Provide a forum for community groups interested in developing affordable
housing to come together and discuss important aspects of their work to
deliver housing solutions in their communities;
 Provide guidance to the community groups on relevant areas of policy and
practice; 
 Facilitate external speakers on areas of subject expertise relevant to the
group members; and
 Encourage sharing complex issues between members, understanding that no
one organisation has all answers.
Various community groups within the network have successfully attracted funding
from the Rural and Islands Housing Fund or the Scottish Land Fund to provide
affordable housing. More details are outlined in Section 5. 
Rural Growth Deal (RGD) Housing Sub-group- The Rural Growth Deal housing
sub-group aims to provide affordable housing for workers to enable businesses to be
sustainable or grow. The proposal is to 
 construct housing for sale at an affordable price;
 place rural burdens and planning conditions on homes financed by the Rural
Growth Deal to ensure they are used as principal housing for residents and
workers; and
 develop proposals relating to portable worker accommodation and support
employers to furnish properties for staff. 
Argyll and Bute Child Poverty Action Group- The Argyll and Bute Child Poverty
Action Group recognises that it is vital that the council, Health Board, the third sector
and communities work together to tackle child poverty. Housing is an essential
component in tackling child poverty; hence, the service has been represented in the
group since its inception. However, in 2021/22, the Housing Policy and Strategy Team
joined the group to ensure that housing investment and key policies prioritised tackling
child poverty. The SHIP will deliver housing investment, enabling some families to be
allocated affordable, energy-efficient homes.

Page 22

Health and Social Care Partners 
To realise this vision, people need access to appropriate housing models and care
staff to enable them to live at home or in a homely setting. The balance between care
in residential and community settings has already shifted considerably towards looking
after people at home. This is evidenced by 53% of those aged 65+ who require 10+
hours of home care per week being looked after at home1. However, expanding care
at home is restricted by staff numbers and the Health Board claims that a lack of
affordable housing is a barrier to enabling it to attract health and social care staff. The
SHIP and Rural Growth Deal will provide affordable homes which could attract health
and social care staff to the area. In addition, the delivery of suitable specialist provision
via the SHIP programme will be critical to enabling people with needs to live
independently in their own home. 
A dedicated Housing Occupational Therapist (OT) post was created to take this
agenda forward and cement the close partnership between the council, RSLs and the
HSCP. This includes reviewing the circumstances and requirements of families with
particular needs, developing a better understanding of the accommodation and
support needs of wheelchair users, and facilitating early interventions, particularly
concerning adaptations and property layouts and design. One innovative outcome of
this joint work was delivering a cross-sectoral training programme for partners. This
will also help inform the SHIP process and promote greater engagement across the
board. 
The Housing OT and relevant HSCP officers will continue participating in the SHIP
Operational Group and the Strategic Housing Forum. In 2021, the council approved
the recommendation that this post should become permanent, funded by Housing
Services. The Housing OT and the LHS strategy team worked together to conduct
research and consultation with wheelchair users across Argyll and Bute. This research
helped identify specific new build targets for wheelchair accommodation, which have
been incorporated into this plan and take immediate effect in respect of the SHIP                                                                 
1 Health and Social Care Joint Strategic Plan 2022-25
As a priority, the Council continues to foster
closer engagement with the Health & Social
Care Partnership (HSCP) at all levels (from
senior management group to locality planning
groups). The HSCP’s current three-year
Strategic Plan was launched in 2022,
incorporating a revised and updated Housing
Contribution Statement (HCS) which outlines
the essential role that housing plays in
supporting and maintaining independent
living and the health and wellbeing of
residents. The SHIP has a direct and
significant contribution to make to this
outcome.
“People in Argyll and Bute will live longer healthier
independent lives”

Page 23

programme. In 2021, Council Housing Services appointed a dedicated Mental
Health/Addictions Housing Practitioner focused on supporting the delivery of the
Rapid Re-housing Transition Plan, further enhancing the strategic and operational
links between housing, health and social care. 
Wider Stakeholders, Local Business, and Economic Development - Other
stakeholders and strategic partners will be engaged on an ad hoc basis as
appropriate. Increasingly, given the overarching strategic imperatives, economic
development and regeneration partners are also emerging as key associates in the
SHIP and LHS process. This has led, for instance, to an ad hoc working group
(facilitated by Housing, Economic Development and HIE) co-ordinating dedicated
events in August 2018 and September 2019, for local employers and representatives
of the business sector to engage with housing providers and explore innovative
delivery mechanisms and opportunities such as the Rural Growth Deal. The events
also provided networking opportunities for local community representatives as well as
RSLs (which of course constitute local, community-based and focused organisations
and charitable associations in their own right). In total, over 50 organisations,
agencies, services and individuals attended the events, and the intention is to retain
this network as one thematic interest group for future consultation and engagement
when developing the next Local Housing Strategy. This consultation exercise informed
the Rural Growth Deal. The council commissioned research in Mull, and this further
engaged the business sector. 
Community Engagement - In addition to the above, the council has recently
reviewed and updated its approach to localised housing need and demand
assessment, building on a number of years’ experience with community councils,
development trusts, local study groups, green belt groups, tenants and residents’
associations, and various other local bodies across mainland Argyll and throughout
the islands. The result is a detailed resource for local communities and third-party
support agencies to carry out surveys, stakeholder engagement, and data analysis,
with the support of council staff, in order to assemble the crucial, “high quality, fit for
purpose” evidence base required to secure public funding and help to deliver practical
housing solutions[1]. The council has engaged with local representatives on Mull, and
community councils in North Lorn, for instance, to implement the new toolkit; and this
is now available. 
HMNB Clyde / MOD engagement-As reported in previous SHIPs, the Strategic
Delivery and Development Framework (SDDF) was established between the Council
and HMNB Clyde to achieve maximum benefit for the base the wider community as a
consequence of the proposals for increasing the naval presence at Faslane. This
dedicated working group continues to explore the potential accommodation needs
arising from the development of the naval base as the Royal Navy’s UK Submarine
Centre of Specialisation and the consequent economic impact this is likely to have in
the local area. The SHIP is therefore required to take full account of the associated
emerging accommodation needs in the Helensburgh and Lomond area. To this end,
a comprehensive housing market study of the area was completed in 2018, which
involved further extensive consultation and stakeholder engagement. Additionally, the
council is conducting a wider economic study in partnership with the MOD.                                                                 
[1] The Argyll and Bute Community Housing Assessment Toolkit (CHAT) is available on demand from Council
Housing Services. See contact details on the final page of this Plan.

Page 24

A key issue in relation to housing and potential requirements for the SHIP is the
implementation of the Future Accommodation Model (FAM), which the MOD is piloting.
The 2015 Strategic Defence and Security Review (SDSR) committed the Ministry of
Defence to make a new accommodation offer to help more service personnel live in
private accommodation and meet their aspirations for home ownership. The way
people live, and work is changing, and the FAM reflects this, giving more choice to
more Service personnel and their families over where, how and with whom they
live.  The pilot is a chance for the MOD to test the policy and how it is delivered before
deciding whether to roll it out across the UK. If this is confirmed, the majority of bases
will gradually transition to the FAM over the next decade or two. The FAM pilot was
launched in September 2019 for the Faslane site, and this will have a direct impact on
the Helensburgh & Lomond housing market area and beyond. Ensuring sufficient and
suitable capacity within the local housing system to address the anticipated increased
demand will be a priority for the SHIP over the next 5 – 10 years. 
In addition, the council has carried out a dedicated in-house study of the particular
needs of veterans and serving military personnel more widely, i.e., beyond those
based at or leaving Faslane; the results informed the new HNDA in 2021 and LHS in
2022. This has involved engagement with local and national organisations such as
Veterans Housing Scotland and Poppy Scotland, among others.
hnda_technical_paper_09_-_veterans_and_armed_services.pdf (argyll-bute.gov.uk) 
The SHIP has a clear and transparent framework for prioritising projects to be
delivered. Investment is targeted at Housing Market Area’s (HMA), communities and
settlements where communities experience the greatest affordable housing
pressures. These priorities recognise the importance of investing in smaller, fragile
rural communities as well as larger urban areas. The communities have been
identified by consideration of: 
 the relative and absolute pressure on the existing affordable housing; 
 the ability to meet the need in the wider housing market area;  
 recent investment patterns;   
 deliverability (site ownership, infrastructure or planning constraints, etc.);
 the potential contribution to population and economic growth. 
3) PRIORITISING THE PROGRAMME

Page 25

Given that localised “hotspots” or pressured areas may still be masked within the wider
geographic HMAs, a further refinement of the evaluation process is also required at
the localised settlement (or letting area) level to reflect the complex rural and island
geography of Argyll and Bute. Therefore, the council continues to employ the following
key indicators: - 
Prioritisation by Housing Need – 
Dunbeg remains the immediate development priority for the council, although the
SHIP has several other projects in and around Oban. 
Strategically, Helensburgh & Lomond is also a high priority in terms of need and
potential growth opportunities. Critically, the impact of the increased MOD presence
at the Faslane naval base and the consequential impact from families and
dependents, as well as enhanced supply-chain requirements servicing the base, will
inevitably result in additional accommodation pressures within this catchment area. 
The LHS concluded that Mid Argyll could benefit from further developments, albeit
this continues to be closely monitored to avoid creating imbalances in the existing
system. Cowal is currently most at risk of severe depopulation. However, it could be
regenerated with judicious development, operating in tandem with improvements in
employment opportunities and transport infrastructure. There are particular needs in
this HMA for a few larger families who require specialist provision. 
Small-scale developments could also significantly and positively impact the Atlantic
Islands, which is also the case throughout the rural mainland. Bute and Kintyre
appear to be relatively well balanced in terms of current supply and demand (with
annual RSL lets sufficient to address waiting list demand and ongoing evidence of
Criteria Indicator/Evidence
Identified need  HNDA & local updates – total shortfall in affordable housing.
Pressure ratios  CHR - waiting list applicants per available let on annual basis.
Homeless
Pressure  
HL1 statistics - applicants & time to close cases; temporary
accommodation; % of RSL lets to homeless cases.
Social stock
levels
Proportion of existing RSL stock to total number of dwellings on
Council Tax Register.
Wider 
Strategic 
Fit
Synergies with LDPs; economic development plans or
regeneration initiatives; the local improvement plan; and the
primary objective of reversing population decline.
Specialist
Provision 
HNDA/CHR/Health & Social Work caseload – total shortfall for
special needs accommodation & evidence from waiting lists or
bespoke research.
Risk/
Deliverability
Satisfies key development criteria (site ownership; planning
consent; resourced; infrastructure constraints; contractor
capacity). Early liaison with planning remains critical.
Affordability (of
proposed rent)
Compared to Scottish Govt. benchmarks and other RSL rents;
as % of LHA; and as % of local household incomes.

Page 26

long-term voids in these areas, despite recent strategic stock rationalisation
programmes). Nevertheless, emerging analysis suggests these local housing
markets have also been experiencing significant shifts in demand, and potential
needs may be evolving and growing, particularly as a consequence of the Covid
pandemic. 
The recently published Mid-year population estimates by the National Records for
Scotland identified Argyll and Bute as the 6th fastest growing local authority, with the
population growing by 0.9% from 2020-21, exceeding the ambitious LHS growth
target of 0.5%. This increase in population will further fuel housing demand in the
HMAs which have seen the greatest population growth. However, future housing
demand may be damped by the predicted recession in 2023; in such turbulent times,
the council will continue to monitor need and demand in HMAs and modify
investment priorities accordingly. 
Prioritisation by Tenure – The majority of the SHIP programme should be for social
rent; however, alternative affordable tenures such as shared equity, other low-cost
home ownership options or below-market rent will be considered on a site-by-site
basis in line with local market conditions and needs, and actively encouraged where
appropriate, subject to a robust business case being made. 
Prioritisation by Size – The HNDA and the HOMEArgyll common housing register
identify that the most significant demand is for one and two-bedroom properties;
hence, the SHIP will continue to promote the delivery of smaller properties. The
number of applicants waiting for a one or two-bedroom property rose by 10% from
2021. As of July 2022, 83% of the active waiting list applicants required 1- or 2-
bedroom accommodation, while 12% required three beds and 5% required four or
more bedded properties. The number of applicants wanting a four-plus bedroom
property fell from 15% in 2021 to only 5% in 2022. 
Although waiting list demand for larger properties has fallen, the HNDA process
identified demand for larger, family-sized accommodation. “Bright Start, Bright
Future” by the Scottish Government identified larger families as one of the vulnerable
family types which are more likely to experience child poverty. The council is
committed to addressing child poverty, and hence the SHIP partners will consider
economically viable options, to deliver larger homes where there is a specific need,
including private acquisitions and off-the-shelf properties. (See section 11). 
Prioritisation by Particular Needs – Specialist housing provision is often required
for:
 those who have impairments such as cognitive, physical, sensory
developmental or a combination of impairments. 
 older people with mobility or other health care needs
 those with mental health conditions. 
To provide suitable accommodation for those with disabilities/ impairment and the
ageing population, the LHS specifies a target of 10% of new build should be
purpose designed as specialist provision to suit households with medium to high-
level particular needs.

Page 27

As far as possible, all general needs new builds are designed to the minimum
lifetime, Housing for Varying Needs Standards, to maximise the accessibility for
residents whose circumstances and needs will change over time.
In addition, the extent and nature of the future ageing population, for instance, will
necessitate strategic investment in developing and delivering housing-based care,
support and aids, and adaptations. To this end, the council has developed a more
cohesive partnership with the Integrated Health & Social Care body to ensure that
the SHIP process is fully aligned with the health and social care integration agenda
and other relevant plans such as the “Keys to Life” strategy for persons with learning
disabilities, the Integrated Children’s Services Plan, the refreshed national housing
strategy for Older Persons published in August 2018, “Age, Home and Community:
the next phase”; and the Fairer Scotland for Disabled People strategy published by
the Scottish Government in 2016; among others. Further refinement of the
wheelchair housing targets in line with the Scottish Minister’s directive is set out in
Section 8 of this plan. 
The finer detail of the programme will be arrived at through specification of suitable
type and size of accommodation for individual developments, taking into account the
needs of actual households on the waiting list and, where appropriate and as far as
possible, in consultation with local community stakeholders. 
Prioritising projects which align with the council’s overarching vision to grow
the population 
The Argyll and Bute Rural Growth deal aims to facilitate the delivery of a range of
housing tenures to accommodate local workers and support business growth in the
initial pilot areas of Tobermory and Bowmore. The Islay and Mull SHIP projects will
complement the RGD housing proposals. 
Prioritising projects which improve town centres 
In addition, to supporting remote rural and island communities, the SHIP programme
also supports projects which improve town centres. Historically RSLs in previous
SHIPs have delivered new build affordable housing in:
 Albany Street- Oban (6 units completed in 2019), 
 St Cuthberts, Dunoon (17 units completed in 2017), 
 The Rothesay CourtHouse- Rothesay (25 units for Shared Equity – last property
sold in 2022).
This SHIP has the following town centre projects 
 Jeanie Deans Helensburgh
 Eton Avenue Dunoon
SHIP projects should provide Rural and Island Proofing2 – the Council’s
Housing Service will continue to apply a policy of rural-proofing housing plans and
strategies to ensure the more remote and isolated areas, or those designated as
“fragile”, are not disadvantaged or adversely affected by investment and                                                                 
2 Rurality is defined in the Scottish Government Urban Rural Classification, see: 
http://www.gov.scot/Topics/Statistics/About/Methodology/UrbanRuralClassification. In addition, one
definition of fragility is outlined in the report: Review of Fragile Areas and Employment Action Areas in
the Highlands and Islands, HIE, November 2014.

Page 28

development decisions. Critical to this aim is joint working with local planners to
support the development and sustainability of designated key rural settlements
across Argyll and Bute, as well as supporting the aims of the Loch Lomond &
Trossachs National Park. 
Key factors influencing the prioritisation of rural developments include: 
 the ratio of waiting list applicants to lets; 
 the ratio of social housing to second homes; 
 proportionate historic losses through Right to Buy; 
 the percentage of social housing to total dwelling stock; and 
 the ratio of local earnings to average or lower quartile house prices and
private rents. 
While existing, evidenced need remains the primary concern, consideration will also
be given to rural areas of potential economic development and/or population growth
in liaison with Economic Development colleagues and the local business sector. 
The rural/urban housing differential is acknowledged nationally in the structure of
the Scottish Government’s benchmark framework for grant funding, whereby Argyll
and Bute receives a rural uplift to address the additional costs involved in remote
rural and island development. The council previously commissioned dedicated
studies of island housing markets, specifically for Mull and Islay3, which provided
evidence of the disproportionate uplift development costs for these areas and
highlighted specific issues and barriers to development in these contexts. 
This SHIP has also been developed within the context of the Islands (Scotland) Act
2018, which introduced measures to support and help the unique needs of
Scotland’s islands now and in the future. The Act also seeks to help create the right
environment for sustainable growth and empowering communities. With around 23
inhabited islands in this local authority area (more than any other Scottish authority),
Argyll and Bute is committed to supporting and sustaining population and economic
growth in these communities and will always ensure to engage directly with the
islands when new policies and strategies are being developed that may impact on
them. The SHIP aims to support the priorities of the island communities, and our
consultation reflects this commitment. In addition to the aforesaid island studies, we
ensure that our overarching HNDA process allows for a significant, representative
sample of local households on individual islands to participate and register their
housing needs and voice their general views on local housing. A formal Islands
Impact Assessment has been developed as part of the LHS process, and this
document also covers the SHIP. See Section 14 for details. 
Consultation with Argyll and Bute’s island communities found that only 20% of Argyll
islanders believe there is sufficient affordable housing available locally, and only
22% agree that there is a variety of housing types, sizes and tenure to meet local
people’s needs. 92% of Argyll islanders believe there is insufficient housing to meet
local demand. In addition, high levels of fuel poverty are recorded on the islands,
and very high rates of ineffective stock (mainly second/holiday homes). The rapid
expansion of short-term-lets in recent years has also contributed to the high rates                                                                 
3 “Islay Strategic Housing Overview”, Community Housing Scotland (2019); “Isle of Mull Strategic Housing
Review”, Rural Housing Scotland (2019).

Page 29

of ineffective stock. This is demonstrated by the council identifying 4000 properties
in 2022 in the entire council area that fall into the short-term lets definition4. The
number of ineffective properties may reduce with the introductions of the Scottish
Governments short-term-let regulations which requires properties being used in this
way to have a short term let license. The council is also contemplating if it will
establish short-term-let zones in areas with particular pressures. Properties used
for short term lets in identified zones will require Planning Permission in addition to
the short-term-let license. The council will continue to monitor the levels of
ineffective stock in tourist hotspots such as islands. 
To tackle the lack of sufficient affordable housing in island communities the SHIP in
the last 5 years (2017- 2022) has delivered 70 units on the islands, equating to 15%
of all units provided within Argyll and Bute. The islands received SHIP investment
of over £16.25 million to deliver these new homes. Of the 12 SHIP projects on-site
or completed during 2021/22, three (25%) were located on the islands, and four
(33%) were in rural locations out with larger towns. A further three projects (25%)
were located in the main towns of Helensburgh, Dunoon and Campbeltown, while
two projects (17%) were in Dunbeg. This reflects a suitably spread of new
developments across the local authority area. 
Future prioritisation process  
The implementation of National Planning Framework 4 (NPF4) requires councils to
support communities undertaking Local Place Plans. This will place greater
pressure on councils to address the needs identified by community plans. In the
future, the council will revise its prioritisation process to include a robust scoring
system to ensure transparency in the decision-making process.                                                                     
4 2820 of the identified Short-Term Lets are known through Council Tax and NDR 1180 additional properties
are estimates.

Page 30

It is important to identify, assess and respond to any risks or potential constraints that
might impact the overall programme or individual projects; and that effective measures
are taken to mitigate these as far and as early as possible. The SHIP aims to assure
that, if funding is secured, any other constraints will be resolved by the time of the
estimated site start of the relevant project. The main risks or constraints that tend to
apply to the SHIP programme include: 
 Increased construction costs which are being impacted by supply chain issues,
unprecedented fuel costs and inflation.
 The constrained capacity of the local construction sector and tight labour
market.    
 Development and Infrastructure constraints.
 Effective land supply and legal procedural constraints.
 Planning issues. 
 Financial assumptions. 
Mitigating Constraints
The council and its partners are working continuously to minimise these risks and
mitigate constraints as far as possible 
a) Increased construction costs and a tight labour market 
The Helensburgh area benefits from wider competition from out with the local
authority boundaries however, this is not the case for the remainder of Argyll and
Bute which is more reliant on the local construction sector. The constrained
capacity of the local construction sector has a huge impact on delivering new
homes. Local contractors rely on tradespeople the central belt to fill in gaps in
provisions. Brexit and Covid 19 have reduced the number of people in the labour
market. Therefore, employees are able to be more selective in the jobs they
undertake. A shortage of labour combined with the exorbitant fuel costs have
placed additional hurdles in the way of recruiting construction workers who are
prepared to travel to Argyll and Bute to undertake construction work. 
The Scottish Government issued revised benchmark costs in October 2021 to
reflect the increased construction costs. However, the cost of labour and materials
appear to have increased more sharply in remote rural and island communities. In
addition, RSLs and contractors continue to highlight concerns in balancing cost
and quality considerations, especially given the ongoing cost of securing private
finance in a high-interest financial environment. These factors will make delivering
new homes within the revised benchmark extremely challenging.   
To mitigate against higher construction costs and shortages of labour the council
and its partner have explored innovative construction solutions. For example, in
Dunbeg, the main contractor MacLeod’s had the experience of developing floor
and roof panels and larger prefabricated wall panels in off-site factories. For
Dunbeg, MacLeod’s installed temporary factories to effectively allow off-site
4) DELIVERING THE PROGRAMME: MITIGATING RISKS AND
RESOLVING DEVELOPMENT CONTSRAINTS

Page 31

manufacturing to take place close to the development site. This allowed for ‘just-
in-time production of floors, roofs and other key components speeding up the
project and ensuring greater quality control and consistency. Other benefits were
having buildings made wind and watertight extremely quickly, reducing waste, and
reducing costs by going to and from sites. 
In addition, the council part funded four modular homes built by the Wee House
Company in Ulva Ferry. Each house is made of between four and six modules,
depending on the size of the finished home, and 90% of construction was
completed under factory conditions, meaning site preparations could be completed
in tandem. It only took a matter of weeks from the modules being delivered to
residents moving into the properties. 
The council and its partners will continue exploring and utilising technological
solutions and modular construction methods if appropriate for the development. 
b) Rapidly changing economic landscape
The HNDA published in 2021 included a range of scenarios such as: 
 the worst-case scenario of severe demographic and economic decline in the
short term; 
 less severe and stabilising scenarios; 
 to more optimistic growth scenarios; 
While the years following lockdown have resulted in increased population and
higher house prices in Argyll and Bute the economic landscape is extremely
volatile and uncertain. High energy costs, high inflation and higher interest rates
could result in economic decline, and financial constraints leading to widespread
unemployment and hardship with resultant loss of homes or tenancies. In this
scenario, there would be a requirement for the safety net of affordable social
rented properties to increase. However, on the other hand, if the behavioural shift
in terms of more home-working and in-migration to remoter, rural and island
havens continues, then that would also entail a requirement for increased
affordable housing supply.   
What certain is the prioritisation framework underpinning the SHIP will need to
respond to these changes. 
c) Development Constraints (such as infrastructure issues: roads, utilities, ground
condition problems/ abnormal costs) - The core SHIP programme has always

Page 32

aimed to focus on sites that are not subject to significant development constraints,
such as contaminated brownfield sites, designated greenbelt areas, or sites with
restricted infrastructure capacity in terms of access roads or water supply.
However, in certain instances within some highly pressured areas where a
substantial shortfall in affordable housing is evidenced or in areas of wider strategic
importance, it may be necessary to consider such sites in the absence of more
practicable or easily progressed sites. Apart from the site constraint, there may be
costs associated with carrying out remedial works, preliminary feasibility studies,
or mitigating the potential impact on areas of archaeological significance or historic
buildings, which further constrain on-site development. Mitigation may be aided by
ensuring site investigation is carried out at early stages and seeking to ensure land
values reflect any remediation costs. Regarding infrastructure constraints, such as
Scottish Water connections/ capacity/ access, early discussions with the Utility
companies will be initiated to address potential issues and achieve possible
synergies in investment programmes. Where possible, abnormal costs should be
deducted from the land purchase price, and unforeseen costs may be met from
alternative sources such as the council’s Strategic Housing Fund, developer
contributions, or other funding sources. 
The Housing Infrastructure Fund (HIF), in particular, has already proven to be a
significant factor in supporting housing development in this authority through grants
for sites which are of strategic importance and cannot proceed or have stalled due
to exceptional infrastructure works (out with the curtilage of the development); and
can help facilitate the unlocking of these sites for the delivery of housing. The
council successfully prioritised the further development of Dunbeg, for instance, as
a key site for delivery of housing utilising this fund and was awarded £2.1m in total,
in line with the eligibility criteria and guidance set out by the Scottish Government. 
d) Effective Land Supply - The RSL land bank and available council-owned sites
have now been depleted, and it may be that in the future land assembly will prove
a significant challenge. A notable feature of a rural and island authority such as
Argyll and Bute is the dominance of large estates in terms of land ownership in
many areas exhibiting housing need. This can present additional challenges in
respect of accessing and assembling suitable sites for development. Nevertheless,
through collaborative efforts with planning colleagues, the council and National
Park are confident that a “generous” supply of land for affordable housing
continues to be sustained, as seen in the table below.

Page 33

TABLE 1: Land Supply within the Local Authority by Housing Administrative Area 2021-2026 
Source: Housing Land Audit 2022. 
Occasionally, proposed projects are subject to complex or protracted negotiations
with private owners and their agents, which can impact on the timing and ultimately
on their deliverability. Therefore, effective liaison with the Scottish Government to
prioritise projects and progress site acquisitions to enable projects to be pulled
forward if required is essential. 
In addition, the impact of both the Council and National Park Affordable Housing
Policies continues to prove valuable; there is an obvious need to sustain practical
negotiations with landowners, Estates, private developers and others. Some RSL
partners have, however, raised concerns that in the current climate, the application
of the Council’s Affordable Housing Policy will make site development less
attractive, and sites are only likely to be developed where there is pressure to
secure a return in the short term. In the medium to long term, the private ownership
of many sites in Argyll and Bute means that the Affordable Housing Policy will
continue to have a definite role in securing a sufficient supply of affordable housing
through developer contributions. Strategic engagement with local communities and
agencies such as Highlands & Islands Enterprise to assess the potential use of
Strategic Land Fund, where appropriate. 
Partners continue to carefully consider the timing and possible phasing of
developments to make realistic assumptions on when affordable housing will
proceed. We aim to ensure that a sufficient supply of sites has been identified to
accommodate unforeseen project slippage and to ensure the spending of allocated
funding. 
In situations where projects cannot be taken forward due to land supply issues, the
council will consider a Compulsory Purchase Order (CPO) approach where there
are compelling benefits to the public interest.

Page 34

e) Planning issues - Early discussions will continue to be prioritised with planning
services (both Council & National Park) regarding road layouts/ car parking
requirements, flood risk assessments, school catchment areas, and other possible
issues. The provision of adequate footpaths adjacent to new developments, for
instance, has been a particularly prominent issue in a number of recent SHIP
projects. All of the development sites included in the SHIP programme should be
effective given that they will, in most cases, require to be already allocated for
housing development in the relevant local development plans. Many of the sites
identified in the SHIP are of relatively small capacity. The costs associated with
progressing smaller sites in the more remote rural areas are likely to be higher if
developed as standalone projects. However, it is envisaged that where SHIP sites
form part of a larger allocation identified in the LDP/ LDP2, through partnership
working with private developers on adjacent sites, the risk of such sites not being
developed on cost grounds will be reduced. 
RSLs in Argyll and Bute have recently made significant progress in delivering
alternative tenures such as shared equity units. The future provision for tenures
other than social rent will require detailed business plans and must reflect a robust
and credible assessment of local needs before approval. The council intends to
evaluate the impact of these projects to inform the future programme. The council
is keen to encourage and support alternative, intermediate tenures when
appropriate, to enhance the housing mix and to increase the range of potential
housing options. 
The three primary funding sources for the SHIP remain as follows: 
a) Scottish Government Grant (the Affordable Housing Supply Programme –
AHSP)
b) Council grant or long-term loan (the Argyll & Bute Strategic Housing Fund – SHF;
which may be supplemented from Council central reserves)
c) Registered Social Landlord (RSL) Private Finance Borrowing     
The majority of developments will require a complex package of funding from at least
all of these sources (additional investment from other sources may also be required –
some of these are outlined below). 
a) Scottish Government Resource Planning Assumptions (RPAs)
In July 2021, the Scottish Government confirmed local authorities’ RPAs up to 2025/26
however the current SHIP runs until 2027/28. The Scottish Government have not yet
agreed the RPA for years four (2026/27) and five (2027/28) of the SHIP programme. To
address this the council has agreed to an assumed RPA for these later years however it
is important to note that the figures for 2026/27 and 2027/2028 are not a formal definitive
allocation. 
5) RESOURCING THE PROGRAMME & THE COUNCIL’S
CONTRIBUTION

Page 35

TABLE 2:  RESOURCE PLANNING ASSUMPTIONS (RPA) 2023- 2028 (£m)
Argyll & Bute 2023/24 2024/25 2025/26 2026/27 2027/28     Total
Minimum RPA £18.264 £18.328 £18.632 £18.632*5 18.632*5 £92.488                 
Source: Scottish Government Letter to Councils – AHSP RPA 2021-26,
July 2021 
The actual AHSP spend in 2021/22 was lower than the original RPA for that year, due in
part to the impact of Covid 19 on the delivery of the programme and the difficulties of
obtaining labour and materials, however spend for the previous year exceeded the
nominal RPA, and over a five year planning period we would expect spend to balance
out. The council will continue encouraging RSLs/developers to maximise funding
opportunities and utilise the available RPA as much as possible. This might include
increasing off-the-shelf / buy-back acquisitions, land banking in areas of identified need
or designated future economic growth spots. 
b) The Council’s Contribution – The Strategic Housing Fund (SHF) 
Resourcing the SHIP programme also requires a significant contribution from the
council’s Strategic Housing Fund (SHF). This fund is primarily based on the revenue
raised from reduced tax discounts on empty and second homes. Where local authorities
have used discretionary powers and reduced the empty and second homes tax
discounts, the additional revenue must be used to support affordable housing delivery
in their areas. In addition, since 2013, local authorities have had the flexibility to remove
the discount and apply a levy of up to 100% on long-term empty properties. These
revenues are not ring-fenced, although their use to bring long-term empty properties
back into use, or to support affordable housing provision, is encouraged by the Scottish
Government. 
Since 2007, the SHF in Argyll and Bute has been used for the following eligible
expenditure:
 Expenditure incurred in relation to assets formally held on the Housing Revenue
Account;
 Expenditure relating to the acquisition of sites for the landbank;
 Expenditure related to the delivery of the Empty Homes Initiative;
 Payments to enhance infrastructure where this is restricting the development of
affordable housing;
 Payments to registered social landlords (RSLs) to partially fund proposed projects
to deliver homes in accordance with the local housing strategy. Since April 2016,
the council has provided grant funding of £12k per unit to supplement the Scottish
Government grant;
 Following the council’s annual policy review of the Strategic Housing Fund in
2018, a potential grant payment of £12k per unit and in some cases more than
this is able to be awarded to community bodies, which have been awarded
Scottish Government support from the Rural or Island Housing funds, to deliver
affordable homes. Awards greater than £12K may be awarded in certain
instances to ensure the deliverability of projects with particular challenges
however this will be decided on a case by case basis 
5 * These figures are based on previous years’ allocation, and they are not formal definitive allocations.

Page 36

In 2021/22 the income generated for the Strategic Housing Fund amounted to £2.143m
and total expenditure that year was £2.672m on the following projects: 
£48,000  – Kirk Rd, Dunbeg
£1,827,197  – Dunbeg Phase 3
£120,000  – Craighouse, Isle of Jura
£72,000  – North West Mull Community Woodland Co 
The balance of this fund as of 31st March 2022 was £9.470m, of which £1.173m was
already committed, and £8.297m was available to fund the SHIP programme.
It is anticipated that the SHF will continue to accrue annual revenue in the order of £2m
over the SHIP planning period. 
TABLE 3: Argyll & Bute Council Strategic Housing Fund, balance as of March 2022
Income
2021/22
Expenditure
2021/22
Balance   March
2022
Committed
Spend
Available to
support SHIP
£2.142m £2.672m £9.470m £1.173m £8.297m 
An indicative minimum estimate of circa £12.4 m would be required to support the core
projects outlined in this SHIP (£12k x 1036 units), 
In addition, the council has also used its financial reserves on occasion to advance
long-term loans to support RSL projects, and this commitment is subject to ongoing
review. 
The council reviewed the Strategic Housing Fund policy in 2018/19. A further
comprehensive audit was carried out in 2019/20 to ensure that this resource continues
to complement Scottish Government priorities for Housing Beyond 2021. 
The findings from the internal audit reported in 2021and are as follows:
 the SHF is being spent appropriately in compliance with legislation and national
guidance and is having a positive impact on the delivery of housing across Argyll
and Bute. 
 the council is achieving value for money from the SHF with a strong partnership
working in a place with RSLs and the Scottish Government. 
 there is benefit in extending the SHF to community groups; however, this requires
proper due diligence to safeguard against the enhanced risk of projects not being
delivered. 
The above demonstrates that the appraisal of the process and policies underpinning the
SHF was positive. 
c) RSL’s Private Finance Borrowing
Banks and other lenders in the private sector also remain vitally important partners in
the delivery of affordable housing. RSLs are required to demonstrate that sufficient
borrowing capacity or reserves exist to ensure the delivery of the proposed
development programme. Following a period of restrictive lending, with greater
scrutiny of projects, higher lending rates and the requirement for additional security
from existing stock, which often resulted in RSLs being forced to use their own
reserves rather than borrow under such conditions; last year RSLs were reporting
positive improvements in their potential to access private finance, and at a national

Page 37

level the sector continues to explore innovative funding models. The impact of rising
interest rates on RSLs’ ability to borrow will have to be kept under review. 
Figure 1 depicts SHIP investment for completed projects. It is important to note that
Dunbeg is not included in the figures as the project is not completed; however, 115
units were completed as of 31st March 2022. Proportionately this would equate to £24
million of investment. 
Private finance was used to support the following completed SHIP projects in 2021/22:
 Kirk Road Dunbeg £80,681
 Cairndow £364,500
 Garelochhead £649,714
 Imereval Phase 3 £270,000
Private finance equated to £1.36 million or 31% of the total investment for these
projects. 
The revenue from the New Supply Shared Equity (NSSE) schemes provided additional
investment to support the SHIP programme. Total investment from all sources for all
SHIP projects completed in 2021/22 amounted to £4.338m. An additional £24 million
of investment was allocated to Dunbeg equating to £28.338 million of investment in
2021/22 
FIGURE 1: Completed SHIP projects 2021/22 by funding source                                           
Source: Council/RSL Records 2021/22
Housing Infrastructure Fund (HIF)
The Housing Infrastructure Fund supports housing development through grants and
loans, with priority given to sites of strategic importance that cannot proceed or have
stalled due to infrastructure requirements. Grant is available to local authorities and
RSLs for works which are out with the curtilage of the affordable housing site and/or
of scale and will open up larger sites for housing development. Loans are available for
viable non-public sector-led sites to support infrastructure delivery. 
The council’s main priority for HIF funding is the Dunbeg development in the Lorn
HMA. As reported in previous SHIPs, the Scottish Government awarded a Housing
Infrastructure Fund grant amounting to £2,129,247 for upgrade works to Kirk Road to
enable the development of 300 new affordable homes to commence. This remains a
significant priority for the council, Link and West Highland Housing Association are
working in partnership to deliver the project. While the infrastructure issues have
been addressed, the impact of Covid-19 in 2020/21 and 2021/22 meant that the
£2,468,000
£336,000
£1,360,000
£174,000
Scottish Government AHSP Council SHF RSL/Developer Other

Page 38

completion of all 300 units has been delayed and consequently, the final units may
not be fully delivered until 2023.                         
While the Scottish Government has confirmed that the HIF will be extended post-
2021, there is no guarantee that Argyll and Bute will receive further awards from this
source; nevertheless, the council and RSL partners will continue to propose potential
projects within the SHIP that could benefit from HIF investment. In August 2022, we
will have 3 HIF projects in Argyll at an estimated cost of £ 5 million. These could
include the following: - 
TABLE 4: SHIP Projects with potential HIF requirements, as of August 2022
Project RSL Total Units Estimated HIF Requirement
Glencruitten, Oban LINK 100 (tbc) £0.72m
Hospital Field, Oban LINK 50 £2.0m
Dunbeg Phases 4-6 LINK 150 £2.5m 
Rural and Islands Housing Funds (R&IHF)
The Scottish Government established a £25 million Rural Housing Fund and a £5
million Islands Housing Fund, which ran to 2021. Both funds aimed to increase the
supply of affordable housing of all tenures in rural Scotland and contribute to the
national affordable homes targets. 
In 2020, Mull & Iona Community Trust was awarded £777,855 from the Rural
Housing Fund. The project was completed in 2021 and provided four new homes in
Ulva Ferry on Mull. 
In 2021 three communities in Argyll and Bute received funding from the Rural/
Islands Housing Fund. 
 North West Mull Community Woodland gained approval for six homes on the
Isle of Ulva
 The Glengorm Farming Partnership obtained approval for five homes in
Tobermory
 The Colonsay Community Development Company secured funding to provide
six homes in Scalasaig on the Isle of Colonsay. 
The Scottish Land Fund 
The Scottish Land Fund (SLF) provided support to housing projects in:
 Colonsay Community Development Company, with a grant award of £390k to
meet site acquisition costs for a mixed-tenure affordable housing project on the
island. Additional funding contributions have been secured from the Council’s
Strategic Housing Fund and Highlands & Islands Enterprise.
 Ulva community-acquired ownership of the island with an award of £2m, and
the community obtained approval in 2021 from the Islands Housing Fund to
finance six homes on Ulva.
 Pennyghael, which entailed carrying out extensive renovations to an existing
property. The council also contributed financially to this project which was
completed in 2021.

Page 39

Rural Growth Deal 
The RGD equates to £50m of investment. Two projects are being taken forward, one
in Bowmore on Islay and one in Tobermory on the Isle of Mull. These projects will
provide housing for key workers. 
Developer Contributions
Argyll and Bute falls within the purview of two planning authorities: while the council
covers most of the mainland and islands, Loch Lomond & Trossachs National Park is
the planning authority for parts of Cowal and Lomond. Both authorities have set out
formal Affordable Housing Policies in their respective Local Development Plans.
These policies outline mechanisms and options to secure developer contributions
where there is a demonstrated need for affordable housing.   
The council’s current policy was adopted in supplementary guidance to the LDP in
March 2016. It required that out with specified housing allocations and Potential
Development Areas (PDAs), new private developments proposing eight or more
homes should deliver a minimum of 25% affordable housing units. Given the revised
and reinforced strategic vision of growth and repopulation for the whole of Argyll and
Bute, it is likely that the affordable housing policy will be applied presumptively across
all HMAs. 
Developer contributions can be delivered by a variety of means, including social rented
housing, mid-market rented housing, payment of commuted sums and also the
building of houses/apartments designed to meet the needs of first-time buyers
(provided these are available at affordable levels as defined by the council’s HNDA
and with reference to the relevant local housing market).   
The sequential mechanisms for securing Affordable Housing via the policy are applied
in the following order: 
 on-site provision; 
 off-site provision; 
 commuted payment; 
 discounted low-cost sale; 
 affordability by design without subsidy.
To date, no commuted sums have been received, and the preferred approach has
been to engage with an RSL to deliver the affordable quota on site. 
The National Park policy follows a similar approach, with a requirement for 25%, 33%
or 50% affordable provision on sites of 4 or more units depending on the location. Sites
of up to 3 units in accessible rural areas may also have a policy requirement under
certain circumstances. A formal policy for calculating commuted sums has been
established but again, little or no payments have been received. 
The delivery of unsubsidised affordable housing for purchase via the Affordable
Housing Policy, but without Scottish Government funding, will normally target a
different client group and requires close working between Housing Services and
Planning colleagues to ensure these models are in fact affordable in accordance with
the LHS and SHIP priorities.

Page 40

Other Initiatives
The council will also continue to explore and, where appropriate, promote non-AHSP
financing models such as Build-to-Rent, Low-cost Initiative for First Time Buyers
(LIFT), and Open Market Shared Equity (OMSE), which may fall out with the remit of
the SHIP. 
Supporting empty homeowners to take action to bring properties back into use remains
a priority for the council as this will help to maximise the use of existing resources to
meet housing need; contribute to number of the council’s wider strategic objectives;
and provide cross-service benefits both within the council and with external partners.
The council funds an Empty Homes Officer post and the officer can support owners
with a range of practical options to assist them make informed choices about the best
outcome for them and their property. 
During 2021/22 the Empty Homes Officers assisted in bringing 38 empty homes back
into use which was 27% above target. Over the last 5 years, the council’s approach
has enabled owners to bring a total of 217 vacant properties back into use against a
baseline target of 125. 
The length of time that properties had remained empty prior to being brought back into
use varies, the average is between 2-5 years, with the longest empty from 2003. 
TABLE 5: Length of time a property had been empty before being brought back into use in
2021/22
Duration as Empty No of Empty Homes
less than a year 7
between 1-2 years 8
between 2-5 years 14
between 5-10 years 8
longer than 10 years 1
Total 38 
Over the last five years, according to the Council Tax Register,  the number of long-
term empty properties has increased by 5% while the number of second/holiday
homes declined by almost 10%, and the total dwelling stock increased overall by 2.6%. 
6) Empty Homes

Page 41

TABLE 6: Estimated Ineffective Stock Argyll and Bute 2017-2022 
Council Tax Register  2018 2019 2020 2021 2022 % change 2018-
2022
All properties 48,014 48,906 48,285 48,166 48,570 1%
2nd /holiday homes 2,998 2,939 2,881 2,689 2,821 -6%
Long-term empty 1,218 1,479 1,363 1,230 1,135 -7%
No of long term empty
subject to double charge
(200% levy)
762 586 644 644 640 -16%
Long-term empty homes
as % of total
2.54% 3.02% 2.82% 2.55% 2.33% 
Empty + 2nd /holiday
homes as % of total 
8.78% 9.03% 8.79% 8.14% 8.14% 
Source: Council Tax Register 
Compulsory Purchase Orders (CPOs)
The use of Compulsory Purchase Orders legislative powers allow councils to acquire
empty homes under certain circumstances and subject to specific conditions. The
Scottish Government refreshed the guidance in 2018, which has refined the legal
process and made it less complex and time-consuming for local authorities to submit
an application to Ministers for consideration. Whilst the CPO has historically been
considered a last resort and has not been standard practice, it is the council’s view
that these powers do have a strategic role to play and could be used more effectively
where there are no other practical solutions to address the issues of the most
problematic buildings in the area. This has been reinforced by feedback to the LHS
early engagement consultation: when local residents and community groups were
asked to rank the top housing challenges currently facing Argyll & Bute, 38% of
respondents highlighted the impact of empty properties and second/holiday homes,
making it the third highest issue among the local population. CPO powers were
successfully utilised in 2019, to acquire an empty property that had no legal owner.
The council then facilitated back-to-back sale to enable the property to be brought
back into use. Without legal intervention the property would have remained empty
indefinitely having a detrimental and financial impact on the other owners in the
tenement. A CPO policy and process will be incorporated into our empty homes policy
as an action for this LHS, targeting resources to the most difficult cases where there
are no alternative options to bring them back into use. 
In line with the Child Poverty (Scotland) Act 2017, the council, together with the
Health Board, produces on an annual basis the Argyll & Bute Local Child Poverty
Action Report (LCPAR). This report sets out progress against the four statutory,
income-based targets, to be achieved by 2030. These targets are:
 Less than 10% of children are in relative poverty 
 Less than 5% of children are in absolute poverty 
 Less than 5% of children are in combined low income and material deprivation 
 Less than 5% of children are in persistent poverty 
7) CHILD POVERTY AND FUEL POVERTY

Page 42

The Scottish Government’s Delivery Plan for tackling child poverty ‘Bright Start, Bright
Futures’ places the tackling of child poverty at the heart of the Affordable Housing
Supply Programme. Bright Start Bright Futures states: “Housing has a vital role to play
in tackling child poverty; it forms not only the foundation for family life – as a safe place
for children to grow and learn, and for families to come together – but it also one of the
most significant costs which families must continue to meet on an ongoing basis. If
families lose their home, the effects can be devastating – and cause lasting damage to
children’s lives.” In the future the SHIP and LHS monitoring arrangements will more
robustly collate and analyse data on outputs in relation to impacts for children and
families 
Research suggests that living in temporary or insecure housing negatively impacts
children’s development and education, locking them into a cycle of poverty.
Therefore it is vitally important to provide homeless families with children permanent
accommodation. The council and its partners have substantially reduced the number
of homeless families with children in temporary housing. Table 7 shows that both the
number of households and the numbers of children in temporary accommodation fell
last year, and both measures are substantially lower last year than in 2018.

Page 43

TABLE 7: Number of homeless households and the number of children in
temporary accommodation
HOMELESS STATISTICS
21/22 2018 2019 2020 2021 2022
Change 
2021 to
2022 
Number
Change 
2021 to
2022 
%
Households with children or a
pregnant woman in temporary 
accommodation  35 30 25 30 25 -5 -17%
Number of children
in temporary accommodation  85 65 55 60 45 -15 -25%
Source: “Homelessness in Scotland: 2021-22” August 2022 
Although the numbers of homeless children or children threatened with
homelessness within Argyll and Bute increased slightly between 2020/21 to 2021/22,
the general trend has reduced from 267 children in 2017/18 to 166 in 2021/22.
However, the Cost of Living Crisis could reverse this trend as wages are not keeping
track with inflation resulting in families paying exorbitant amounts for food and
energy. This, coupled with higher interest rates, will mean, for some, higher
mortgage payments or private landlords passing on increased mortgage costs to
their tenants. The consequences of energy, food, accommodation as well as many
other products all costing substantially more will mean many families will be unable
to finance the necessities and for some this may result in them becoming homeless.
Therefore, having an adequate supply of affordable housing is more important than
ever.   
TABLE 8: Number of children associated with applications assessed as homeless or 
threatened with homelessness
Local
Authority
2017-
18
2018-
19
2019-
20
2020-
21
2021-
22
Change Change    
20-21 to
21-22
20-21 to
21-22    
Number %    
Argyll & Bute 267 164 153 161 166 5 3%    
Source: “Homelessness in Scotland: 2021-22” August 2022 
In 2021/22, the HOMEArgyll RSLs rehoused 289 households who had at least one
household member under16 years of age. This equated to 467 children housed in
2021/22 which was 39% of the total lets that year. Although housing 467 children last
year was a considerable achievement, as of August 2022, there were 945 applicants
around a third (30%) of the waiting list, with a household members under 16 waiting
to be housed. This equates to 1,807 children currently on the housing waiting list.
Some of these households (121) have been awarded the maximum 200 points and
are deemed to be in extreme housing need and hence will be a priority for rehousing.
However, not all families with children will receive priority assistance for rehousing,
with 201 applicants with children not being awarded any housing points under the
allocations policy. 
The Child Rights and Wellbeing Impact Assessment (see section 14) undertaken as
part of the LHS process highlighted the negative impact on educational attainment of

Page 44

children living in overcrowded accommodation. As of August 2022, 459 households
with children under 16  years of age are overcrowded. Bright Starts Bright Futures
identified families with more than three children are one of the six family types at
greatest risk of poverty. There were 139 applicants with children equating to 14.7%
of HomeArgyll waiting list who required a larger family home (4 or more bedrooms).
The SHIP housing planning process will place additional focus on housing those with
a need for a particular size of property in a specific location. This approach will
ensure that larger family homes are delivered where they are required. This may
including RSLs purchasing appropriate ‘off the shelf’ properties’ (see section 11). 
TABLE 9: Minimum number of bedrooms required by families on the
HomeArgyll waiting list 2022
HOMEARGYLL WAITING
LIST AUG. 2022
1
bed*6  2
beds 3beds
4
beds
5 +
beds TOTAL
Number of Applicants                                   
(with members under 16) 2 477 327 99 40 945
as % of total 0.2% 50.5% 34.6% 10.5% 4.2% 100.0%
Source: HomeArgyll waiting list August 2022. 
There is a need for the SHIP programme to prioritise delivering family housing as the
average time for families with children to be housed is 92 weeks (compared to 100
weeks for households without children). 
In most families housing and energy costs are the largest financial outgoing. The SHIP
not only provides access to affordable homes for families living on low incomes but it
also provides energy efficient homes. In the current economic climate, energy costs
are unprecedentedly high, making it more important than ever to reduce the amount
of energy needed to keep a home warm. Therefore, the council will ensure that 100%
of the SHIP programme will meet the green standards. 
Promoting energy efficiency and tackling fuel poverty remain strategic priorities for
the LHS and key commitments for the council; and maximising opportunities for
sustainability in development remains a key principle underpinning the SHIP. As with
all public bodies, this council is also required to meet its statutory duties arising from
the Climate Change (Scotland) Act 2009, and the LHS and SHIP have been
developed to ensure that the provision of new affordable housing complies with the
Act; and that all housing activities and outputs should contribute to the overarching
net zero targets and principles. One example of a project which embraced the net
zero ambitions was the Passivhaus scheme completed in 2021/22 in Garelochhead. 
6 * These figures are based on minimum bedroom sizes required.

Page 45

The SHIP aims to address the housing needs of all the communities we serve and
continues to reflect a positive approach to equalities issues in line with the policies of
the council and its partners, and the principles of diversity and inclusion in accordance
with the Equality Act 2010. The HNDA (2021) provides robust evidence of
accommodation and support needs across the range of protected equalities
characteristics, and these have been translated into the SHIP priorities. The joint Argyll
and Bute Health, Care & Housing Needs Assessment, completed in 2018, provided
supporting evidence of the requirements for wheelchair accommodation, supported
housing, and other forms of specialist provision. In 2019/20, the council undertook
further specific studies on the need and demand for specialist provision for wheelchair
users, gypsy/travellers, military personnel and veterans, and persons who are autistic
or have learning disabilities. The findings have informed the 2021 HNDA and the
revised LHS which was published in 2022. 
An equalities impact assessment (eqseia) was undertaken during the development of
the LHS, and this will inform the SHIP. 
All SHIP projects, seeking public subsidy from the Council or Scottish Government,
are required to meet basic design and building standards (of the Housing for Varying
Needs Standard as a minimum) and should incorporate adequate provision to meet
any additional identified particular needs. Prioritisation of projects will give due weight
to those which incorporate elements of design or additional specifications for specialist
forms of housing where the local profile of need and demand indicates such a
requirement. The committed and planned programme include provision for elderly and
disabled residents and through the close partnership working with Health & Social
Work, including Occupational Therapists, the SHIP will continue to ensure the strategic
aims of the LHS in this respect are carried forward. 
In particular, the post of dedicated Housing OT which was established in October 2018
to co-ordinate and promote these needs through the SHIP group, was made
permanent in 2021, funded in full by the council Housing Services but working very
closely with RSLs and the HSCP. In practice, this commitment to equalities principles
will ensure: 
 building all new affordable housing to HfVN Standards;
 implementing design solutions which help to meet the needs of disabled and
infirm households;
 assessing and seeking to resolve the needs and aspirations of households with
community care needs in partnership;
 developing communities with a good mix of households;
 allocating housing via HOME Argyll and national RSL partners who have strong
commitments to equal opportunities; and
 providing affordable housing in rural areas which enables young and old people
to remain within their communities. 
Housing for Varying Needs (HfVNs) is a Design Guide published in two volumes (Parts
1 and 2). While not mandatory, the standards outlined in the guide have been used as
the basis for standards for housing developments seeking grant funding support. The
standards are intended to ensure that the housing is accessible, adaptable for different
8) SPECIALIST PROVISION INCLUDING WHEELCHAIR HABITABLE
HOUSING

Page 46

needs and over its lifetime represents good value for money. They are based on the
principle that the design of a property should not hinder a person’s ability to live as
independently as possible and should recognise the needs of people as they age,
become less able or whose mobility, dexterity, cognitive function, hearing or sight is
impaired.   
The idea of designing all housing to accommodate the needs of less able people is
known as “barrier free” design and this is reflected in the core guidance of the design
guide; but the guide also recognises that barrier free design in itself is not a substitute
for homes designed specifically for people with particular needs so it identifies
additional features that should be included to address these needs. 
Analysis of the HOMEArgyll Common Housing Register in 2022 suggests that around
4% of applicants could benefit from some form of specialist provision. Three percent
(93) applicants requested wheelchair accessible accommodation; although 55 of
these applicants also select some other form of accommodation, including general
needs/ mainstream housing. Only 38 applicants only selected wheelchair housing. 
Applicants requesting wheelchair provision required homes with the following number
of bedrooms:
 48 (52%) of wheelchair applicants required a 1 bedrooms
 26 (28%) of wheelchair applicants required 2 bedrooms 
 11 (12%) of wheelchair applicants required 3 bedrooms 
 8 (9%) of wheelchair applicants required 4+ bedrooms 
The Health, Care & Housing Needs Assessment (2018) identified the following key
points:- 
Correlating the data sources may suggest that a majority of wheelchair users are
satisfactorily housed or do not aspire to social rented properties. However, some
wheelchair users who could benefit from suitable, specialist provision in the social
rented sector may not apply due to lack of awareness or misperceptions regarding the
suitability and availability of stock. This was identified as a key area for further research
and analysis, and in 2019/20 an in-house study completed jointly by the council’s
strategy team and the Housing OT.   A key finding of this study, collated with national
research, is that wheelchair users and those who might benefit from wheelchair
accommodation are not a homogenous group. Hence, a variety of housing solutions
are required.                                                                                       
Solutions such as aids and adaptations or support services will have a crucial role to
play, nevertheless, the SHIP will continue to require a target of 10% of the new build
programme to provide some form of specialist provision (to include retirement
 Around 350 wheelchairs are issued each year to people in Argyll & Bute
 The majority of wheelchairs issued are manual chairs
 Over 1,300 people in Argyll and Bute have wheelchairs on issue
 55% of people with wheelchairs are aged 75+
 Up to 280 people a year may be new wheelchair users
 There could be 240 additional people needing wheelchairs by 2027
 The most common reason for a wheelchair is cerebrovascular disease (stroke) but the
main reasons for wheelchair vary by age with Cerebral palsy being the most common
reason in people under 25.

Page 47

housing, amenity housing, and other specially adapted properties); and within that,
half (i.e. 5% of the total new builds) should be built to the fully wheelchair habitable
standard as defined in the relevant Section of the current HfVN standards guidance.
In 2021/22 there were a total of 22 affordable homes designed for particular needs
delivered within the SHIP programme, amounting to 15% of the year’s total, which
exceeds the annual target of 10% overall (5% wheelchair and 5% other models of
specialist provision, excluding adaptations to existing stock). The new build units
included 13 wheelchair accessible homes (9% of total) and 9 amenity/older person
units (6%). This is an enormous achievement and a vast improvement on provision
in the previous two years where 8 units were delivered (7 in one year and 1 in the
following year). 
As far as possible, the wheelchair housing targets will also be encouraged within the
private sector, across all tenures, on all developments where this would be
appropriate. The SHIP Officers Group and the Strategic Housing Forum approved
this policy with immediate effect in 2020. RSL partners also continue to explore with
the HSCP requirements for extra care provision and possible new housing models
for people being housed in the community which is in accordance with the HSCP
aspiration to enable those with additional needs to live as independently as possible.
The council will strive to incorporate housing models which promote independent
living within the SHIP programme as it rolls forward. 
Argyll and Bute Council continues to support the Scottish Government’s 
commitment to improve the lives of our Gypsy/Traveller communities; and to
prioritise joint working with ACHA (who own and manage the two official, operational,
Travelling Person sites in Argyll and Bute) and other stakeholders to drive forward
positive improvements for this client group. 
The council continues to allocate ACHA an annual grant from the Strategic Housing
Fund as a contribution towards the operation and maintenance of the two remaining
Travelling Persons Sites at Bayview near Oban, and Duncholgan near Lochgilphead.
A Minute of Agreement set up at the point of stock transfer in 2006 set the sum at
£30k plus annual indexation. In 2018, the sum payable was reduced to reflect the
withdrawal of the Torlochan site near Dunoon, which was deemed to be surplus to
requirements due to the lack of demand. Recent council investment in the official
sites is summarised below: 
TABLE 10: ACHA Gypsy/Traveller Sites – Annual Council Funding  
Year 2017/18 2018/19 2019/20 2020/21 2021/2022 5 year Total
Grant £41,228 £31,001 £28,939 £29,338 £31,639 £162,145 
As part of the comprehensive refresh of the Housing Need and Demand Assessment
for Argyll and Bute, the council carried out a dedicated study to assess the
accommodation and support needs of Gypsy/ Travellers in the area. This included
an assessment of any “bricks and mortar” mainstream accommodation that may be
required. The study has involved extensive primary engagement with
9) GYPSY/TRAVELLER SITES

Page 48

Gypsy/Travellers and their representatives; and this work has informed the
development of the latest LHS for Argyll and Bute. 
ACHA secured £108k from the Scottish Government’s Capital Fund for Improving
Gypsy/Traveller Sites. This was invested during 2021/22 to make interim
improvements to both official sites at Bayview (near Oban) and Duncholgan (near
Lochgilphead). ACHA are hoping to secure further funding to improve
Gypsy/Traveller sites. 
Scottish Ministers have made an ongoing commitment to end homelessness in
Scotland and consequently set up a national Homelessness and Rough Sleeping
Action Group (HARSAG) to bring forward recommendations to address this. A key
proposal was that each local authority should develop a Rapid Rehousing Transition
Plan (RRTP) by December 2018, covering a 5-year period, or longer if required, to
enable the implementation of this new approach. The RRTP maximises prevention
and sets out the council’s approach to minimise the time a household remains
homeless and to ensure that they can access appropriate suitable accommodation
as soon as possible. 
Local Rapid Rehousing Transition Plans should be reflected in the LHS and also be
fully integrated into Health & Social Care Partnership strategic plans. The Argyll and
Bute RRTP has consequently been included in the current Housing Contribution
Statement to ensure it forms part of the planning framework. This SHIP’s strategic
housing priorities are aligned and consistent with the proposed RRTP priorities and
outcomes. A crucial objective is to facilitate and deliver more affordable housing via
the SHIP.
In the report “Scotland’s transition to rapid rehousing”, produced by the Indigo Group
on behalf of the Scottish Government’s HARSAG in June 2018, two specific
recommendations were made in relation to the SHIP: 
 Rapid Rehousing Transition Plans could be seen as an integral part of the
SHIPs, and should be annually reviewed as part of the SHIP process 
 The Scottish Government and Scottish Housing Regulator should improve
data collection from local authorities or housing associations on completions
and lettings relative to housing need. 
With this in mind, Argyll and Bute Council continues to liaise with RSL partners and
other key stakeholders to develop and implement the RRTP; and will aim to ensure
that homelessness remains a critical factor in the SHIP process. This includes
homelessness as one criterion for assessing need, prioritising projects, and
awarding grants from the Strategic Housing Fund. SHIP projects are expected to
contribute directly or indirectly to alleviating homelessness across Argyll and Bute
(for example, as a result of direct allocations or via consequential lets to existing
properties freed up on transfer of occupants to new build properties). The
performance of developing landlords in respect of the proportion of allocations to
homeless households and time taken to rehouse these clients will continue to be
10) HOMELESSNESS/ RAPID REHOUSING TRANSITION PLANS 
& RAPID REHOUSING TRANSITION PLANS

Page 49

material considerations in SHIP programming decisions and resource allocation
moving forward. 
During 2021/22 Rapid Rehousing Funding of £241,496 was utilised to progress the
transition of Rapid Rehousing and Housing First in Argyll and Bute. The RRTP
budget allocation for 2022/23 is £111,570, which is significantly less than the
previous year. 
In 2022 Argyll and Bute Council agreed a statement (Annex 1) with the Scottish
Government which would provide a streamlined approach for any acquisition for
secondhand stock where the work costs do not exceed £75,000 of ASHP grant. 
This approach could increase the supply of affordable housing especially for priority
property types and sizes in areas of high demand (particularly where stock has
historically been depleted through Right to Buy). The Millknowe project in the previous
SHIP is an example of a buy-back property converted into a dementia friendly home.
This SHIP could use AHSP funding to purchase existing properties for people with
particular needs or for large families. Whether this approach should be used will be
assessed on a case-by-case basis. 
RSLs are currently considering the viability of private acquisitions in areas of the local
authority where there is identified need and demand. 
Off-the-shelf purchases- 
While it is expected that the majority of homes will be delivered through the SHIP
occasionally, the most appropriate approach to meeting particular needs may be best
satisfied by an ‘off the shelf’ purchase from developers. These will be considered on
a case-by-case basis. 
SHIP 2017/18 to 2022/23: 
Building on the 305 units completed between 2017/18 and 2019/20, there were a
further 143 units completed in 2021/22; bringing the five-year cumulative total to 448
affordable home. The equates to 81% of the Housing Supply Target outlined in the
previous LHS considerably higher numbers would have been completed by Covid
lockdowns shut down sites even when site were allowed to reopen there were
considerable restrictions on workforce numbers allowed on site resulting in slippage.
However, given the extremely challenging conditions of 2020/21 and 2022/23,
resulting from the pandemic and the resultant supply chain issues this is very positive
outcome. 
11) BUYBACKS, SECOND-HAND ACQUISITIONS AND OFF SHELF 
12) UPDATE FROM THE PREVIOUS SHIP 
Over the last five years 448 affordable homes have been created in Argyll and Bute.

Page 50

TABLE 11:  SHIP New Build Homes by HMA & Project, 2021/22
Housing Market Area Projects Completions % of
total
Cowal Cairndow (Fyne Homes) 6 4%
Lorn Kirk Road (Dunbeg) (WHHA) 4 3%
Dunbeg phase 3 (Link) 115 80%
Helensburgh and Lomond Garelochhead (ACHA) 10 7%
Islay, Jura and Colonsay Imereval Phase 3 (WHHA) 8 6%
TOTAL 143 100% 
Four of the local RSLs contributed to the total programme. ACHA delivered 10 of the
new builds; Fyne Homes provided 6; West Highland completed 4; and Link completed
115 (This is partial completion of 300 units for Dunbeg Phase 3, with the remaining
units to be completed by 2023). In terms of tenure, 2 units (1.4%) were for shared
equity. 
The current year, 2022/23, is covered by the Strategic Local Programme Agreement
(SLPA) between the council, the Scottish Government, and the developing RSLs, and
the previous SHIP (approved in 2021); while this new SHIP will commence from
2023/24. The programme is subject to ongoing change as either barriers to progress
or windfall opportunities arise. Consequently, the following tables simply summarise
all proposals at the time of writing (August 2022), including those projects which were
expected to complete in 2022/23 and for which funding has already been drawn down.
It should be noted that the status of many future projects, particularly in the later years,
remains provisional and purely indicative at this stage; some may not proceed, or
complete, within the timescale. However there is also scope for additional proposals
to be brought forward or included in the programme. 
Further details of the programme and individual projects are outlined in the electronic
reports recorded on the Scottish Government’s Housing and Regeneration
Programme (HARP) system. 
TABLE 12: SHIP Projects Completions/Anticipated Completions in 2022/23
Project address Developer Units
Anticipated
Completion
Date
Inveraray Phase 2 ACHA 10 Completed
June 2022
Tarbert Phase 2 ACHA 4 Nov 2022
Millknowe Campbeltown ACHA 2 September
2022
Tom-A-Mhoid Road  Dunoon FYNE HOMES 1 March 2023
Dunbeg Phase 3 (remaining units) LINK 185 March 2023
Sawmillfields Helensburgh Wheatley Group 36 March 2023
Jura (Craighouse) WHHA 10
Completed
July 2022
Argyll & Bute 2022/23 Total Completions (est.) 248 March 2023
13) THE REVISED PROGRAMME

Page 51

If this programme is successfully delivered in full within the planning period (plus
completions in 2022/23), it could provide over 1,204 new affordable homes across
Argyll and Bute by March 2028. Projects islands account for 17% of houses to be
developed by the SHIP the rural mainland accounts for 18% of the programme; while
51% of units are in the key strategic settlements of Oban and Dunbeg; 10% in
Helensburgh; with 3% in the other main towns of Dunoon, Campbeltown and
Lochgilphead. 
There is an expectation that the majority of these units will be built to allow for future
adaptation to meet changing needs over time; and in addition approximately 10% (i.e.
120 units, if the above programme is delivered in full) should be purpose-designed to
medium or high dependency standards with potentially 60 of those units (5% of the
total) being fully wheelchair accessible.                                                                                                                                               
However, the council is currently in ongoing discussions with the HSCP to review and
explore potential housing models to meet the HSCP objective for enabling
independent living. 
In addition to this core programme, a number of other potential proposals are being
developed for further consideration in later years of the SHIP, subject to robust
assessments of need and demand, site assembly or acquisition, and available funding.
Some of these projects therefore remain notional at this stage or are subject to
development constraints that require to be addressed/ mitigated before they can
proceed. These projects are also dependent on clarification of local need or potential
demand to support growth and recovery agendas; and will be considered in future
updates of the SHIP. 
The council will also continue to actively explore other sites and projects out with the
core SHIP funding programme, as outlined in previous sections of this plan, where
these are consistent with LDP policy/housing land provisions and align with high
quality fit-for-purpose assessments of local housing need and demand.

Page 52

TABLE 13: SHIP Core Programme - Potential Completions by March 2028
Project address Developer Units Anticipated
Completion1
Bowmore Phase 4 ACHA 18 Year 1 (23/24)
Eton Avenue Dunoon  ACHA 4 Year 1 (23/24)
North Connel - Phase 2 ACHA 2 Year 2 (24/25)
Tighcargaman Port Ellen   ACHA 20 Year 2 (24/25)
Dalintober  ACHA 25 Year 2 (24/25)
Tarbert  ACHA 15 Year 2 (24/25)
Tarbert ACHA  15 Year 3 (25/26)
Coll  ACHA  10 Year 2 (24/25)
Keils  ACHA 4 Year 4 (25/26)
Jeanie Deans Helensburgh DUNBRITTON HA 12 Year 1(23/24)
Helensburgh Golf Club DUNBRITTON HA 62 Year 1 (23/24)
18th Tee, Helensburgh DUNBRITTON HA 16 Year 1 (23/24)
Cardross DUNBRITTON HA 37 Year 3 (25/26)
Succoth Phase 2, Arrochar DUNBRITTON HA 12 Year 4 (26/27)
Lochgilphead Riverside Drive Baddens FYNE HOMES 6 Year 1 (23/24)
Inveraray Phase 1 FYNE HOMES 16 Year 1 (23/24)
Ballochgoy Rothesay FYNE HOMES 10 Year 1 (23/24)
Rothesay Academy Phase 1 FYNE HOMES 30 Year 2 (24/25)
Inveraray Phase 2 FYNE HOMES 10 Year 2 (24/25)
Rothesay Academy Phase 2 FYNE HOMES  20 Year 4 (26/27)
Cairndow Phase 2 FYNE HOMES 4 Year 5 (27/28)
Tighnabruaich Phase 2 FYNE HOMES 10 Year 5 (27/28)
Dunbeg Phase 4 LINK 90 Year 2 (24/25)
Rosneath LINK 49 Year 3 (25/26)
Hospital Field site Oban LINK 50 Year 3 (25/26)
Lonan Drive Oban  LINK 44 Year 3 (25/26)
Glencruitten Oban LINK 100 Year 4 (26/27)
Dunbeg Phase 5 LINK 75 Year 4 (26/27)
Dunbeg Phase 6 LINK 75 Year 5 (27/28)
Port Charlotte Phase 1 WHHA 14 Year 1 (23/24)
Imeraval Phase 4 Islay WHHA 20 Year 1 (23/24)
Tobermory Phase 3  WHHA 12 Year 2 (24/25)
Port Appin Phase 1 WHHA 6 Year 2 (24/25)
Craignure  WHHA 22 Year 2 (24/25)
Colonsay WHHA 5 Year 2 (24/25)
Salen WHHA 8 Year 3 (25/26)
Port Appin Phase 2 WHHA 24 Year 5 (27/28)
Bunessan Phase 2 WHHA 4 Year 5 (27/28) 
Argyll and Bute Total  956 2023-2028 
1 NB. Timescales are indicative and subject to change; and will be monitored regularly.
Some projects could also revise their final number of units.

Page 53

RSLs have also identified future opportunities, which they will flesh over the next year
or so. These projects could be included in the later years of the SHIP. For example,
ACHA is exploring options on Mull such as Dervaig; and 4 units on Ulva. WHHA  is
keen to develop another stage of development in Imeraval in Islay and a project in
Oban town centre. WHHA are also keen to develop in, Lochawe and/or Dalmally if
demand is generated from the Cruchan Power Station expansion programme. Fyne
Homes would like to develop 20 units in both Dunoon and Lochgilphead. 
Finally, a number of community-led projects or private developments with associated
affordable requirements but no RSL attached, may be delivered out with the core SHIP
programme but will be significant adjuncts to this process and should deliver major
synergies with the SHIP. Several projects are already progressing, and two have been
completed. While small in scale these community-based projects deliver substantial
impacts at the local level, and help to ensure the viability and sustainability of fragile
communities. The following table summarises the current programme for rural and
island projects out with the core SHIP programme. 
TABLE 14: FUNDED COMMUNITY-LED HOUSING PROJECTS NOT COMPLETED
HMA PROJECT/COMMUNI
TY
UNITS
Mull & Iona Ulva (Refurb) 6
Mull & Iona Glengorm (Refurb) 5
Islay, Jura &
Colonsay
Port Askaig, Islay 2
Islay, Jura &
Colonsay
Scalasaig, Colonsay
Phase  1
12 units in total made up of
3 Self build plots, 
3 Private Rented units (Mowi) 
6 affordable housing units of which 4 are social rent
and 2 are shared equity 
The SHIP will continue to be appraised on an annual basis by the Scottish Government
and affordable housing outcomes are monitored regularly by the Council’s Housing
Management Team; local authority Members via the corporate Pyramid performance
management system; the overarching Community Planning Partnership via the ABOIP
framework; and partners on the Strategic Housing Forum; as well as the boards and
committees of the individual SHIP partners. In addition, as appropriate, wider stakeholder
involvement will be sought via consultation with local communities, private developers
and relevant particular interest groups. All pertinent feedback will help to inform the
ongoing development and regular revisions of the SHIP.               
The council has also been exploring potential mechanisms for establishing a wider
evaluation framework to capture the broader social return on investment and economic
impacts of the SHIP programme, as well as the basic cost effectiveness and value for
money of specific projects. Working with RSL partners, the council is keen to
implement a formal evaluation procedure which will capture evidence on the wide
range of strategic benefits that the SHIP actually delivers, beyond monitoring the basic
number of completions. 
14) MONITORING& REVIEW AND IMPACT ASSESSMENTS

Page 54

In 2021/22, the council undertook a number of impact assessments during the LHS
process. The SHIP is an investment plan which sits underneath the LHS and sets out
how the LHS objectives can be delivered. Therefore, these impact assessments also
inform the SHIP. The impact assessments can be found on the council’s website.
 Equality and Socio-Economic Impact Assessment lhs_eqseia_sept_2021.pdf
(argyll-bute.gov.uk)
 Child Rights and Wellbeing Impact Assessment
childrens_rights_and_wellbeing_impact_acccessment_stage_abc_lhs_jan_202
2.pdf (argyll-bute.gov.uk)
 Health Impact Assessment APPENDIX 4: Template for scoping workshop
reports (argyll-bute.gov.uk)
 Islands and Communities Impact Assessment
lhs_island_communities_impact_assessment.pdf (argyll-bute.gov.uk)  
In future, the council will monitor and assess the impact of the SHIP and the LHS in
terms of the aforementioned impact assessments and in line with the principles of the
Fairer Scotland Duty. Any relevant findings from such assessments will be reflected in
the SHIP and future updates of the LHS and other associated plans, policies and
strategies. 
Strategic Environmental Assessment (SEA)
As the “Responsible Authority” under the terms of the Environmental (Scotland) Act
2005, the council has previously determined that the LHS (and by association it’s
ancillary component, the SHIP) does not require a full SEA.
sea_pre_screening_report_october_2021.pdf (argyll-bute.gov.uk)
The primary document in relation to land use planning is the Local Development
Plan which is subject to a full SEA and which will ultimately cover all housing projects
set out in the SHIP.

Page 55

The Argyll and Bute Strategic Housing Investment Plan for 2023/24 to 2027/28 sets out
an ambitious but realistic programme for the delivery of 956 new affordable homes; of
which the majority would be built to lifetime standards, allowing for future adaptation to
meet changing needs over time; and around 10% will be purpose-designed for specialist
needs, with half of those i.e., 5% of the total being fully wheelchair accessible. The
programme reflects a strong commitment to Argyll and Bute’s economic growth agenda
and will directly support the sustainability of fragile rural and island communities. 
The earlier years of the SHIP align with the LHS housing supply targets, published in
2022, of 215 new affordable homes per year; the later years are slightly below the target.
Several additional potential projects have also been suggested but are not as yet fleshed
out. These projects are likely to be considerations in later years, although if needs are
identified during the annual review of the programme, then these projects could be
brought forward.  In addition, new opportunities will emerge in time these combined with
the projects to be fleshed will raise the number of units in the later years of the SHIP to
align with the 5 year LHS target of 1075 affordable units. The council and its partners are
committed to maximising available resources where possible and will continue actively
to explore opportunities for growth in the programme.
The LHS targets take account of the council’s ambitious strategic objectives as well as
the potential increased demand for social housing arising from the consequences of the
coronavirus pandemic and the current economic crisis; the increased presence at the
MOD base in Helensburgh & Lomond; the anticipated impacts of the Rural Growth Deal
and other local and national resources and strategic imperatives for repopulation,
recovery and growth; and therefore the scale of the proposed programme is likely to be
more in line with actual requirements as well as our aspirational goals for Argyll and Bute. 
This SHIP clearly and directly aligns with the LHS and Argyll and Bute Outcome
Improvement Plan (ABOIP) outcomes; sets out a core programme which is feasible to
deliver; highlights the contribution of the council, developers and other partners;
evidences the support and facilitation role of the local authority; outlines the extensive
stakeholder engagement underpinning the planning and delivery of the programme; and
explicitly reflects the central importance of equality issues for all partners. 
CONCLUSION

Page 56

Appendix 1 Individual Open Market Purchases Statement January 2022 
Scottish Government affordable housing supply guidance states:-
“It is expected that the majority of homes delivered through the Programme will be
new build units that are delivered either directly by grant applicants or through ‘off
the shelf’ purchases from developers. However, where it can be demonstrated
that the use of grant to acquire ‘second hand’ stock that is for sale on the open
market is the most appropriate method of meeting housing need in a particular
area, subsidy may be available to fund this, subject to agreement between the
Council and the Scottish Government. Funding may also be made available to
remodel/ rehabilitate existing properties where this is considered a strategic priority”.
Argyll and Bute Council will consider a limited number of individual, second hand
open market purchases if the following criteria are met: 
 There is a need for the size and type of housing in the town/settlement, (this
will be determined by the current housing need and demand assessment) 
 Land availability and infrastructure issues are a barrier to delivering the
affordable housing target in the area through new build development
 The purchase will not result in homelessness
 The purchase price must reflect the condition of the property. 
Second hand open market purchases will be prioritised as follows: 
1. Where the purchase will assist the RSL to meet general housing need as   
identified in the HNDA and agreed with Argyll and Bute Council.
2. Where the purchase will assist the RSL to meet particular housing need as agreed
with Argyll and Bute Council.
3. Where the purchase will bring an empty property back into occupation
4. Priority will be given to acquiring properties that are in good/reasonable condition.
Each property will require a valuation and condition survey completed by the District
Valuer or other RICS Chartered Surveyor. Vendors must pay their own costs. 
Applicants should note the following:-
 Grant requested must be the minimum level of grant required to deliver the
project.
 Grant requested should exclude costs for any works normally funded by the
Association’s capital maintenance/cyclical programme.
 Streamlined submissions for acquisition only, the maximum Scottish
Government grant will be up to £50,000 or 50% of the acquisition value,
whichever is the lower.
 Streamlined submissions for acquisition and works, grant will be up to
£75,000 maximum for each property. This will encompass the purchase price
and any works required to the property.
 Where grant required for acquisition and works cost is higher than £75,000 a
full value for money appraisal will be required and acquisitions should not be
completed before confirmation of Scottish Government and Council
agreement on the level of costs.

Page 57

APPENDIX 2: SHIP DEVELOPMENTS ACROSS ARGYLL & BUTE:
Projects in the Core Programme 2023-2028 
Projects approved in the 2022-2027 SHIP. These are
due to be completed in years 2-5 of that SHIP i.e. 2023-
2027 
New projects

Page 58

THIS DOCUMENT IS
AVAILABLE ON THE COUNCIL WEBSITE AT: 
Local Housing Strategy and Housing Need and Demand Assessment   
This document can also be made available in other formats on request. 
Contact:
LHS Team
Argyll & Bute Council
Dolphin Hall
Manse Avenue
Dunoon
Argyll & Bute Council PA23 8DQ 
Telephone: 
01369 708 679 
01631 700 058 
Email: Hristina.tarpanova@argyll-bute.gov.uk