Page 1

Argyll and Bute Council
Comhairle Earra-Ghàidheal Agus Bhòid 
Executive Director:  Douglas Hendry 
Kilmory, Lochgilphead, PA31 8RT
Tel:  01546 602127  Fax:  01546 604435
DX 599700 LOCHGILPHEAD 
23 November 2022 
SUPPLEMENTARY PACK 3 
ARGYLL AND BUTE COUNCIL - ON A HYBRID BASIS IN THE COUNCIL CHAMBER,
KILMORY, LOCHGILPHEAD AND BY MICROSOFT TEAMS on THURSDAY, 24 NOVEMBER
2022 at 10:30 AM 
I enclose herewith amended appendices 1 and 2 in relation to item 16 (DUNOON PRESENTS -
APPROVAL OF BUSINESS IMPROVEMENT DISTRICT BALLOT SUBMISSION AND
BUSINESS PROPOSAL - THIRD BALLOT') which should replace those previously issued with
the Agenda for the above meeting. 
Douglas Hendry
Executive Director 
AMENDED APPENDICES 
16. DUNOON PRESENTS - APPROVAL OF BUSINESS IMPROVEMENT DISTRICT
BALLOT SUBMISSION AND BUSINESS PROPOSAL - THIRD BALLOT' 
(Pages 3 - 60)  
Appendix 1 and Appendix 2 
Argyll and Bute Council 
Contact: Hazel MacInnes  Tel: 01546 604269
Public Document Pack

Page 2

This page is intentionally left blank

Page 3

Dunoon Presents 
Town Centre
Business Improvement District 
Business Proposal 
BID Term 15/04/2023 to 14/04/2028 
Page 3 Agenda Item 16

Page 4

Contents 
Section Content Page(s) 
BID Proposal - Compliance with Legislation 1 – 6
1.0 Forward by BID Board Chair 7
2.0 Executive Summary 8
2.1 Mission Statement of the Dunoon Presents BID 8
2.2 Aims and Objectives of the Dunoon Presents BID 8
2.3 Key Findings 8
3.0 Introduction 8
3.1 What is a Business Improvement District (BID)? 8
3.2 Background to BIDs 9
4.0 Dunoon’s Position 9
4.1 Why does Dunoon need a BID? 9
4.2 The History of BIDs in Dunoon 10
4.3 How does Dunoon benefit from a BID? 10
4.4 Local Authority Support 11
5.0 The BID Area 11
5.1 The BID Map and Streets 11
6.0 BID Management 16
6.1 BID Development Staff 16
6.2 BID Development BID Board 17  
6.3 Management of the BID 17
7.0 The Consultation Process 18
7.1 Introduction 18
7.2 Business Survey 19 
7.3 The Key Findings 19
8.0 Proposed Improvements 20
9.0 The BID Levy 20
Page 4

Page 5

9.1 Who will pay the levy? 20
9.2 Exclusions 22
9.3 The Levy Table 22
9.4 Collection of the BID levy 23
9.5 Enforcement  23
10.0 The Voting Process 23
10.1 Pre-Ballot 23 
10.2 The Ballot 24 
10.3 BID Timetable 25 
11.0 Public Sector BID Involvement 28
11.1 Baseline Services 28 
12.0 Measuring Success 29
12.1 Measuring the Success of the BID 29 
12.2 Marketing Communications and Social Media 29
13.0 Finances 30
13.1 Estimated Income and Expenditure  30 
13.2 Financial Management Arrangements 30
13.3 Dunoon presents’ BID Projected Income and Expenditure 31
14.0 Contact information 31
Appendix 1 Support for the BID 
Appendix 2 Details of Consultation 
Appendix 3 BID Business Plan 
Appendix 4 Database of Properties and Persons Eligible to Vote 
Appendix 5 Instruction to Hold a Ballot (56-day notification letter) 
Appendix 6 Baseline Services 
Appendix 7 Board Agreement  
Appendix 8 Copy of Ballot Funding Letter - Dunoon Presents 
Appendix 9 Board Minutes - Signing Off and Agreement to the BID Area, BID Levy,
Exemptions to the BID Levy, BID Business Plan and BID Proposal. 
Page 5

Page 6

Appendix 10 Draft Operating Agreement – to be updated following a positive ballot
result. 
Page 6

Page 7

Business Proposal
Page 1
BID Proposal Compliance with Legislation 
In accordance with Business Improvement District (Scotland) legislation we acknowledge, as the BID
Proposer, we must submit to Argyll and Bute Council and Scottish Ministers the following in respect
of BID Proposals, Renewal Proposals and Alteration Proposals: - 
1.0  A document, which demonstrates a cross section of at least 5% of the electorate, within the
BID area supports the BID Proposals. 
Please refer to Appendix 1 (Support for the BID) and Section 7.2 Business Survey on page 19 of this
Proposal. Following the surveys of the businesses our canvassing confirmed the number of eligible
persons (those eligible to vote in the ballot) 7.79% by number and 14% by rateable value were in
favour of the BID. 
2. Summary of the consultation the BID has undertaken with those eligible to vote. 
The Dunoon Presents BID Board oversaw the process of consultation with the businesses. The
consultation took the form of hard copy surveys, meetings and events, letters, telephone calls, e-mails,
website, social media and one to one consultation. 
Please refer to Appendix 2 (Details of Consultation) and Section 7.0 The Consultation Process on page
18 of this Proposal for a summary of the consultation. 
3. The Proposed Business Plan 
A copy of the BID Business Plan will be issued to all those eligible to vote in the ballot. Please refer to
Appendix 3 (BID Business Plan). 
4. The Financial Arrangements of the BID body. 
Please refer to Section 13.2 Financial Management Arrangements on page 30 of this Proposal. 
5. The Arrangements for periodically providing the LA and billing body with information on the
finances of the BID body (i.e., after a successful ballot) 
The BID finances will form an integral part of a monthly report issued to the BID Board of Directors. 1
representative from Argyll and Bute Council will sit on the BID Board and will automatically be
provided with the BID finance details. It is also expected that regular finance meetings with Argyll and
Bute Council will be held. An independent review of the BID finances will also take place through an
independent auditor. 
6. The names and addresses of all those eligible to vote and a description (address) of each
relevant property. 
Please refer to Appendix 4 (Database of voters).
Page 7

Page 8

Business Proposal
Page 2 
7. A notice in writing requesting that the local authority hold the ballot.
In accordance with legislation, please find attached the notice in writing “requesting the local
authority to instruct the ballot holder to hold a BID ballot.” 
Please refer to Appendix 5. 
8. Provide the LA and billing body with such information as they shall reasonably require
satisfying themselves the BID Proposer or BID body has enough funds to meet the costs of the
BID ballot. 
Dunoon Presents has agreed in their letter of the Date 25.09.2022 to the Argyll and Bute Council to
pay for the costs of the ballot. Please refer to Appendix 8. 
9. A statement of the works or services to be provided, the name of the person responsible or
body for the implementation (delivery) of these works and services and the status of such
person/s; both on and after the date the BID Proposals come into effect. 
Please refer to Appendix 3 (BID Business Plan) for the proposed works and services. 
On a successful renewal ballot outcome, the Dunoon Presents BID Company (a not-for-profit company
limited by guarantee with no share capital) will continue, as before, with directors elected from the
eligible persons (the levy payers), limited to one eligible person from each eligible property. The
directors will oversee and give direction to the delivery of the projects and services; and renew current
staff contracts to ensure the continued delivery of the BID projects and services. For full details please
refer to section 6.3 Management of the BID on page 17 of this Proposal. 
10.0 A statement of existing baseline services provided by the local authority, police and other
agencies. 
Please refer to Appendix 6 (Baseline Services). 
11.0 A precise description of the geographical area of the BID, including a map, which defines exactly
the boundaries of the BID area. 
Please refer to Section 5.1 The BID Map and Streets on page 11 of this Proposal for a GIS map and a
list of the streets and roadways in the BID area. 
12. A statement providing details of any additional financial contributions, or additional actions
for the purpose of enabling the projects specified in the BID Proposals, i.e., where a BID
project is expected to cost £X and the proposed levy raises a smaller amount £Y then the BID
Proposals must state how that funding gap £X - £Y s to be met and by whom. 
Page 8

Page 9

Business Proposal
Page 3
The projects specified in the BID Proposal (Please refer to Section 13.3 Dunoon Presents BID Projected
Income and Expenditure on page 30 have been identified and the levy calculated and apportioned to
deliver the projects as defined in the Proposed Projects section of this Proposal. 
It is expected that the BID will attract additional funding from other sources including the local
authority however, this has not been allowed for at this stage. 
13. A statement of which aspects of the BID Proposals and or Business Plan may be altered
without the need for an alteration ballot to be undertaken. 
The BID Board of Directors will have the authority to adapt or alter the projects and services from year
to year to reflect any change in economic circumstances or any new opportunities that may arise. This
will be in the best interests of the levy payers and without recourse to an alteration ballot. 
Please refer to section 6.3 Management of the BID on page 17 of this Proposal for the statement. 
14. A statement of the proposed start and end dates of the BID Arrangements and the term of the
BID. The BID arrangements must commence no later than a year after the date of the
statement. 
Following a successful renewal ballot on [02/03/2023] the Dunoon Presents BID will continue its
activities to the end of the existing term [14/04/2023] and continue onto a third term from
[15/04/2023]. As the Dunoon Presents BID will be for a term of five years, it will cease its activities on
[14/04/2028]. 
15.0 BID Proposals shall specify the apportionment of BID levy in respect of relevant properties
and who will be liable to pay the levy: - proprietors, tenants, occupiers or if appropriate a specific
business sector or sectors or businesses who will participate. It is advisable to include caps,
thresholds, or other arrangements reflecting local circumstances or ability to pay. 
The BID improvement levy will be paid by the occupier (the eligible person liable to pay the non-
domestic rate), however, the property owner will be liable to pay the levy where a property is vacant
or empty on the day the levy invoice is issued and for all the period thereafter when the property is
vacant. 
Please refer to Section 9 The BID Levy on page 20 of this Proposal for full details of the BID Levy. 
16. Confirmation the levy is to be calculated as a % of the RV or how the charge was arrived at. 
It has been agreed by the BID Board, (please refer to the meeting minute dated [07/09/2022] -
Appendix 9) the levy rate will be a fee structure based on the rateable value of the property on the
day of the ballot, 02.03.2023 and throughout the 5-year term of the BID. 
Please also refer to Section 9 - The BID Levy on page 20 of this Proposal for full details of the BID Levy
and how the charge was arrived at; and to Appendix 10 - Operating Agreement.
Page 9

Page 10

Business Proposal
Page 4 
17. Confirmation the % levy or fee is to be calculated on the RV of the property on the date of the
ballot or, if not, another date that is the date, which will be used to calculate the levy or fee
over the term of the BID. 
The fee structure is based on the rateable value of the property on the day of the ballot 02.03.2023 
Please Refer to Section 9 The BID Levy on pages 20 to 23 of this Proposal for full details of the BID
Levy. 
18. The apportionment of the levy between proprietors, tenants and occupiers – providing the
BID is including tenants and proprietors in its proposals. 
The occupier (the eligible person liable to pay the non-domestic rate) will be liable for the payment of
the levy. 
The BID Proposal does not include proprietors (property owners) except where the eligible property
is vacant or empty when the property owner will be liable for the payment of the levy. 
Please Refer to Section 9 The BID Levy on pages 20 to 23 of this Proposal for full details of the BID
Levy. 
19. A statement as to how the BID Board arrived at who will pay the levy, the percentage levy and
how the levy will be split between proprietors, tenants and occupiers. 
The BID Board set the levy fee; the streets included in the BID and voted on who will pay the levy. A
copy of the minutes of the meeting 07/09/2022 at which this was decided is attached as Appendix 9.
The geographic boundary is based on the whole town. The levy amount is based on the amount
required to carry out the projects in the business plan and discussions with businesses on what they
believe is reasonable. The levy will be paid by the occupier (the eligible person liable to pay the non-
domestic rate). 
The decision to adopt the levy table and BID area was taken with the agreement of all the members
of the BID Board. Please refer to Appendix 9 (Board Minutes) and Appendix 7 (Board Agreement.) 
Please also refer to Section 9 The BID levy on page 20 of this Proposal for full details of the BID Levy. 
20. Whether any future re-assessment of RV of the property by the Rates Assessor will or will not
be taken into account in the calculation of the levy 
It has been agreed by the BID Board, the levy will be calculated on the Rateable Value of the properties
in the BID area on the day of the ballot.  There shall be no increase in levy within the first two years of
a third term, but consideration shall be given to an increase in years 3,4 and 5 that would be capped
at a maximum of 10% of the levy amount. 
Page 10

Page 11

Business Proposal
Page 5
21. A statement on why groups or individual businesses are exempt or receive a levy discount 
Please refer to Section 9.2 Exclusions on page 22 of this Proposal for full details of all exemptions to
the levy. The BID Board agreed (please refer to Appendix 7 Board Agreement and Board Group
Minutes Appendix 9) the properties exempted would receive no benefit from the BID projects and
services. 
22. A statement on whether the levy will be index linked. 
The BID levy will not be index linked. 
23. A statement on whether any of the costs incurred in developing the BID Proposals, holding of
the ballot, or implementing the BID arrangements are to be recovered through the BID levy. 
None of the above costs will be recovered through the BID levy. 
24. The constitution of the BID Company and its legal status.  A statement on who will administer
the BID, details regarding the BID board and the BID body and those who drew up BID
Proposals and Business Plan. 
Please refer to section 6.3 Management of the BID on page 17 of this proposal for details on how the
BID Company will continue to be administered. 
The Dunoon Presents BID Company, A Company Limited by Guarantee and Not Having a Share Capital,
will continue to be administered by the Board of Directors who will be drawn from the eligible persons
(liable to pay the levy) but restricted to one eligible person per eligible property. Nominations of
directors from outside of the BID, who do not pay the levy and who may or may not represent those
making voluntary or other financial contributions toward the BID, will be strictly at the discretion of
the Board of Directors. The projects and services will continue to be delivered by the existing BID team.
For full details please refer to Section 6.3 Management of the BID on page 17 of this Proposal
document. Colin Moulson, the BID Manager prepared the BID Proposals and Business Plan in full
consultation and support from the Dunoon Presents BID Board. 
25. The methodology for BID levy payers to nominate themselves or others to the BID Board of
Directors and the proposed make-up of the BID Board. 
Every eligible person, who is liable to pay the levy, will have the opportunity to nominate themselves
or someone else from within the BID area to be elected to the BID Board. Directors will be limited to
one eligible person per eligible property. Nominations of directors from outside of the BID, who do
not pay the levy and who may or may not represent those making voluntary or other financial
contributions toward the BID, will be strictly at the discretion of the Board of Directors.     
Please refer to section 6.3 Management of the BID on page 17 of this Proposal for full details on how
levy payers can participate on the Dunoon Presents Company Board of Directors.
Page 11

Page 12

Business Proposal
Page 6 
26. A statement on how the BID Proposals will be publicised prior to the ballot. 
The BID Proposer will send a copy of the BID Business Plan to all persons eligible to vote on the BID
Proposals. Should any eligible person require a copy of the BID Proposal, a copy will be provided on
request.  The Business Plan will also feature prominently on the Dunoon Presents BID website at: -
www.dunoonpresents.co.uk 
“Business” or variations of the word “business” are used throughout this document. The word
“business” in this context refers to property owners or tenants and occupiers of properties who are
liable to pay the non-domestic rate (NDR), whether they pay business rates or not. This includes all
properties listed on the Scottish Assessors Association Portal (website) with a non-domestic rateable
value, many of whom may be a charitable organisation, public sector organisation, social enterprise
or community group who may not consider themselves to be a business. 
Page 12

Page 13

Business Proposal
Page 7 
1.0 Foreword by Dunoon Presents BID   
As the Dunoon BID board, we are delighted to present this third term renewal proposal which outlines
the priorities of the business community.  We are all passionate and optimistic about the future of the
town and we are excited about how we can continue to improve
Dunoon by working together. 
The projects and ideas that are detailed in this business plan came from the levy payers, gathered
from our surveys, meetings and consultations.   They shaped the overall strategy that will allow us the
opportunity to revitalise the town. 
We have all been involved in Dunoon for many years between us now and know a
lot of the local business people. The town in that time has become a regular host for major
event activity which has stimulated hundreds of thousands of pounds into the local economy. These
events have been the catalyst for new tourists and visitors to the area from across Scotland and further
afield and we believe the town is on the cusp of major positive change in many ways.  The work of the
BID has been pivotal to the evident progress, and this now needs to be taken to the next level, with
the BID working alongside key local stakeholders to bring about much needed progress in local
infrastructure and public realm projects. 
Supporting the Dunoon presents BID for a third term is a great opportunity to collaborate and make
improvements that would not happen otherwise.  We are asking you to commit to this at a time where
many costs are rising however with this levy, we can access external funding not available to individual
businesses and we can implement projects that will help Dunoon prosper. 
Ballot papers will be distributed by post no later than 19 January 2023 You will have 6
weeks to cast your vote before the ballot closes at 5pm on 02 March 2023. Ballot
papers received after this date and time will be null and void.  We passionately believe that the town
will continue to thrive and evolve with another BID five-year term. 
Page 13

Page 14

Business Proposal
Page 8 
2.0 Executive Summary 
2.1 Mission Statement of the Dunoon Presents BID  
Dunoon Presents BID – Dunoon Presents mission is to build an identity that goes beyond its shoreline.
To showcase our beautiful area and to be an economic success through events, outdoor pursuits, and
collaboration with local groups who share this vision 
2.2 Aims and Objectives of the Dunoon Presents BID     
The principle aim of the BID is to deliver projects and services that will improve the trading
environment of the BID area to benefit businesses, their customers and visitors. 
The objectives of the BID are: - 
 To improve the economic opportunities for the businesses in the town centre 
 To increase footfall
 To improve businesses relationships with each other, the local authority and the community
 To market the area to a local, regional and national audience
 To give businesses a strong, unified voice
 To support local community groups whose aims align with the BID 
2.3 Key Findings 
The BID Board has overseen considerable research to discover what the businesses of Dunoon would
like the BID to continue to deliver and future projects, services and initiatives. The research established
the continued need for a BID and confirms the following key aspects to deliver a successful ballot and
a successful BID are in place. 
 Local need for a BID is strongly identified.
 The BID area is logical and clearly defined.
 Support of the Local Authority at both officer and political level.
 Support of The Dunoon Community Project 
3.0  Introduction 
3.1  What is a Business Improvement District (BID)? 
A Business Improvement District (BID) is a geographically defined area, where businesses come
together and agree to invest collectively in projects and services the businesses believe will improve
their trading environment. BID projects are new and additional projects and services; they do not
replace services that are already provided by Argyll and Bute Council and other statutory bodies. 
BIDs are developed, managed and paid for by those who are liable to pay non-domestic rates (NDR)
by means of a compulsory levy, which the eligible persons in the proposed BID area must vote in
favour of, before the BID can be established. Each eligible person liable to pay the BID levy will be able
to vote on whether the BID goes ahead. 
Page 14

Page 15

Business Proposal
Page 9
3.2 Background to BIDs 
The first BID was established, approximately fifty-five years ago, in Bloor West Village, Toronto,
Canada, by the district’s business community. The district’s businesses were increasingly coming
under pressure from new enclosed shopping malls being developed outside their area, diverting
shoppers away from the traditional shopping area. As a result, some businesses were forced to cease
trading and the area began to look tired and neglected 
To stop the haemorrhage of deserting shoppers, local businesses fought back to revitalise the area.
They successfully lobbied for legislation for all the businesses, in the proposed BID area, to pay a levy.
The levy money was used to improve the physical appearance of the area, and then promote the
district as a vibrant, attractive and safe place to work, shop and live. The strategy paid off and shoppers
started to return to the district in large numbers. 
The success of the Bloor West Village BID paved the way for future BIDs, not only in Toronto; but
spreading throughout Canada, and the USA in the late 1960’s and 1970’s. Today there are well over
1800 successful BIDs worldwide. 
An additional measure of BIDs success is in the renewal process. Most BIDs run for a period of five
years with the vast majority continuing, for consecutive terms, when they come up for renewal.
Currently, there are 26 BIDs in their second or third BID terms equating to 37 successful renewal
ballots demonstrating the businesses value the projects and services delivered by the BIDs. 
BIDs can support regeneration, grow local economies, create local employment and create a cleaner,
safer trading environment. A key element to their success is that the local businesses take ownership
and responsibility for their trading environment, identifying the projects necessary to resolve common
problems and issues, and overseeing their implementation, whilst also contributing to the future
direction of the town and its future development.   
The Scottish Government fully supports the development of BIDs in Scotland. 
As at 15.09.2022 there are 35 fully operational BIDs in Scotland with a further 30 in development. 
4.0  Dunoon’s Position 
4.1 Why does Dunoon continue to need a BID? 
If we do nothing, then nothing will be done and the progress that we have made over the last 10
years will be lost. 
Dunoon has started to emerge from a long period of decline but now the work to allow the town to
keep progressing must intensify even more.  The primary focus of Dunoon presents has been all
about the events and we have curated a programme that is working well for the area however it is
now time to diversify our business plan working with key local
stakeholders to deliver a wider range of projects including shopfront/premises improvements,
streetscape enhancements and improved marine facilities. 
We are really excited about The Dunoon Community Project as it will have a positive impact on the
retail businesses and holiday accommodation providers.  We want to make sure that visitors coming
to the area for these activities will spend as much time in our town centre as possible so we need to
develop plans to make the most out of the opportunities that will arise.  This multimillion-pound
Page 15

Page 16

Business Proposal
Page 10
community led leisure development, progressing rapidly around Bishop’s Glen was inspired by the
work of the Dunoon Presents BID and made our team realise that this was the way forward for the
future of the town. Dunoon Presents have and will continue to work closely with the consortium
developing this major piece of infrastructure, to ensure real and lasting legacy 
The BID board fully understands that times have been hugely challenging, and this is continuing with
local businesses increasingly worried about the availability of staff and rising costs including energy
and raw materials.  Certain things we can’t fix however what we can do is 
 work together to increase footfall, encouraging more people to Dunoon who spend money
in the local economy.
 Encouraging people to spend more time in the town by making sure it is looking clean and
attractive
 Promote the businesses better through social media, advertising and on the website
 Improving the perception of Dunoon as a place to visit with a variety of marketing activities 
We know that there is so much work still to do and the BID provides a unique opportunity for
businesses across all sectors to work together, invest collectively and undertake projects which can
contribute positively to improving the economic viability of businesses in Dunoon and securing
investment in the area.  The BID has levered over £2.8million into the Dunoon economy in the last
nine and a half years.  It’s a winning formula that will see a further £1.75million of growth in the
Dunoon economy over the next five years; providing the BID continues. 
4.2 The History of BIDs in Dunoon 
The Dunoon BID has been operating as a UK Limited Company (a not-for-profit company limited by
guarantee with no share capital) run by a volunteer board of directors to deliver the second term,
2018 to 2023 business plan, with a total budget of £120,000. Many of the projects have been
successfully delivered for the benefit of levy payers including the Argyll Rally, Dunoon 10k Coastal
Road Race, Down the Watter Revival music festival, Dunoon Ultra marathon, the Punk on the
peninsula festival and marketing campaigns for Dunoon.  The support of the Argyll and Bute Council
has been integral to this development. 
4.3 How does Dunoon benefit from a BID? 
All businesses in the town benefit from the projects and services the BID currently delivers: - 
 Support for existing groups and organisations
 An improved customer perception of accessibility and parking availability
 Improved customer knowledge of goods and services in the town centre
 Increased marketing to local, regional, national and global customers
 Cost reduction through collective investment and joint promotion
 An increased number of visitors
 Access to funding and support not available to individuals or businesses
 A local voice for businesses - business opinions included in local policy and local developments. 
 Increased B2B sales opportunities
 Increased networking opportunities
 A continued safe trading environment with increased sense of security 
Page 16

Page 17

Business Proposal
Page 11 
4.4 Local Authority Support 
A BID is a business led regeneration strategy, which contributes to the wider regeneration aspirations
of the public sector and the local community. It is essential the BID has the support of the local
authority and access to its expertise over the BID term. 
Argyll and Bute Council is supportive of the BID with one elected member attending BID Board
meetings and support given by various council officers. 
A crucial element of a BID is to review the current Baseline Service Agreement (an agreement on which
services are already provided to the area by Argyll and Bute Council, to ensure any project or service
provided by the BID is additional to the statutory services the local authority already provides. 
The Argyll and Bute Council shall (under section 41 of the Representation of people Act 1983 and The
Business Improvement Districts (Scotland) Regulations 2007) undertake and manage the postal ballot. 
5.0  The BID Area 
The BID area is generally focused on the town centre. Through one-to-one consultations, it became
clear that there were common issues crossing different sectors. 
The BID team have calculated that this equates to circa 430 properties, the eligible person of which
will be entitled to vote on 02/03/2023. Following a successful ballot all eligible persons within the BID
area will be required to pay the BID levy. 
5.1 The BID Map and Streets 
Why was this area chosen? 
The following streets were chosen to be included in the BID area as consultations with businesses in
this area highlighted several common issues of concern that could be addressed by a BID: - 
Albert Crescent
Alexander Street
Alexandra Parade
Alexandra Place
Alexandra Terrace
Alfred Street
Allan Terrace 
Ardenslate
Crescent
Ardenslate Road
Ardmhor
Ardtully Brae
Argyll Road
Argyll Street
Page 17

Page 18

Business Proposal
Page 12
Argyll Terrace 
Arthur Terrace
Ash Gardens
Ashcraig
Ash Croft
Auchamore Road
Avenue, The
Beechcroft
Belmont Lane 
Bencorrum Brae
Bishop’s Glen Brae
Bogleha Road
Brae Cottages
(Sandbank)
Brandon Street
Brooklyn Place
Broomfield Drive
Broughallan
Gardens
Broughallan Park
Broxwood Place
Bullwood Road
(Part)
Cammesreinach
Brae
Cammesreinach
Crescent
Carolina Lane
Castle Street
Cedar Grove
Cedarcroft
Charles Gardens
Charles Lane
Cherryhill
Church Square
Church Street
Clyde Street
(Dunoon)
Clyde Street (Kirn)
Coach Houses
Cowal Avenue
Cowal Place
Crawford Lane
Crochan Road
Cromlech Grove
Cromlech Road
Cromwell Street
Deercroft
Dhailling Avenue
Page 18

Page 19

Business Proposal
Page 13
Dhailling Court
Dhailing Park
Dhailling Road
Dixon Avenue
Dixon Crescent
Dixon Park
Dixon Place
Douglas Cottages
Dunclutha Lane
Eaglecroft
Eccles Road
Edward Street
Edward Place
Elizabeth Avenue
Erichtbank Drive 
Eton Avenue
Fairhaven
Ferguslie Place
Ferguslie Street
Ferry Brae
Ferry Road
Finbracken
Fir Brae
Fircroft
Fountain Quay
George Street
Gladstone Avenue
Glebe Avenue
Glebe,
The Glebe View
Cottages Glenallan
Glenmorag Avenue
Glenmorag
Crescent
Gordon Street
Gorsecroft
Greenbank Lane
Hafton Court
Hamilton Street
Hanover Street
Heathercroft
High Road (Part)
Highland Avenue
Hill Street
Hillfoot Street
Hunter Street
Hunter’s Grove
James Street
Jane Street
Jaycroft
Page 19

Page 20

Business Proposal
Page 14
Jessie Place
John Street
Johnson Terrace
Kilbride Avenue
Kilbride Road
Kimberley Terrace
King Street
Kirk Brae
Kirk Street
Kirn Brae
Kirn Court
Kirn Gardens
Ladysmith Terrace 
Lebanon Place
Leven Place
Lilyoak
Limecroft
Lochan Avenue
Lorimer Terrace
McArthur Street
McCall Terrace
MacDonald Avenue
Manse Avenue
Marine Parade
Marlborough Lane
Marshall Court
Mary Street
Massan View
Miller Court
Milton Avenue
Milton Road
Minard Place
Moir Place
Moir Street
Mount Carmel
Murrayfield
Nelson Street
Nile street
Oakfield Place
Oxford Lane
Park Avenue
Park Road
Pier Esplanade
Pier Road
Pilot Street
Port Riddell
Primrose Terrace
Prospect Avenue
Prospect Terrace
Queen Street
Page 20

Page 21

Business Proposal
Page 15
Queen’s Road
Queen’s Terrace
Rankin’s Brae
Regent Terrace
Renfield Brae
Robert’s Terrace
Robertson terrace
Rockhill Terrace
Ros Mhor Gardens
Royal Crescent 
St. Andrews Square
Salisbury Terrace
Sanda Gardens
Sandbank Road
Sanderson Drive
Sandhaven
School Brae
The Sheiling,
Shore Road
Shuna Gardens
Skye Court
Sommerville Place
Spence Court
Stanley Terrace
Stewart Street
Tom-A-Mhoid Road
Union Lane
Union Street
Valrose Terrace
Victoria Crescent
Victoria Gardens
Victoria Parade
Victoria Park
Victoria Road
(Dunoon) Victoria
Road (Hunter’s
Quay)
Victoria Square
Victoria Terrace
Wallace Court
Waverley House
Wellington Street
West Street
William Street
Willow Quay
Windsor Lane
Woodfield Terrace
Woodford Grove 
Page 21

Page 22

Business Proposal
Page 16 
There are circa 430 Properties located in the BID area. 
6.0  BID Management 
6.1 BID Staff 
The BID Manager is Colin Mouslon and is accountable to the BID Board. 
Page 22

Page 23

Business Proposal
Page 17
6.2       BID Board 
The BID Board, overseeing the renewal ballot, is made up from a cross section of the business
community in the area and includes one locally elected councilor. Advice is also given by various
Council officers. Ultimately all key decisions relating to the renewal of the BID have been taken by the
BID Board, who are as follows: 
Name Sector Name Sector
Iain Cairns Service Ross Petro   Service
Alistair Baird Services Alison Girvan  Hospitality
Jamie Mulholland   Hospitality Peter Ballard  Resident
Councillor Ross
Moreland
Argyll and Bute Council Finlay Currie Services 
6.3 Management of the BID 
Following a successful yes vote, the management and operation of the BID will continue under the
existing company structure and name.       
The Company will continue to be managed by its Board of Directors operating in an open and
transparent way and answerable to the businesses in the area. The Directors are committed to the
highest standards of management, governance and accountability; recognising good governance helps
deliver the strategic objects of the company. 
There will be a detailed set of protocols (the Operating Agreement) which will cover, as well as other
items, the billing, collection and transfer of the levy to the Company. 
There are currently 8 directors in office.  An active campaign will be launched after the successful
ballot to recruit additional directors to the Board. Every eligible person that pays the levy will have the
opportunity to nominate themselves or someone else from within the BID area to be elected to the
Company Board but limited to one eligible person from each eligible property. 
Nominations of directors, representatives, or advisors from outside the BID, who do not pay the levy
and who may or may not represent those making voluntary or other financial contributions toward
the BID, will be strictly at the discretion of the Board of Directors.   
The Company will continue to be run by the businesses for the businesses. This Board will be
responsible for all decisions relating to staff, contracts, the delivery of the approved business plan and
other activities generated by the BID. 
The Board will be representative of the businesses and stakeholders in the area. The Chair, Vice Chair
and Finance Director will be elected from the directors of the Board. The Board will include 1
representative from Argyll and Bute Council. There may also be non-voting representatives from
Page 23

Page 24

Business Proposal
Page 18
Police Scotland. Other non-voting members or local groups may be co-opted onto the Board at the
Board’s discretion.   
The BID Company Board will have the authority to adapt or alter the projects and services from year
to year to reflect any change in economic circumstances or any new opportunities that may arise. This
will be in the best interests of the levy payers and without recourse to an alteration ballot. 
Additionally, the BID Company Board reserve the right to consider creating a charitable arm of the
company to enable it to secure additional funding, which can only be sourced with charitable status. 
7.  The Consultation Process 
7.1         Introduction – 
An initial consultation was undertaken with a cross section of businesses in the form of one-to-one
interviews, which led to the creation of a bespoke Dunoon presents questionnaire, which was
distributed to all businesses in the BID area. 
Of the hard copy questionnaires distributed (135) - the businesses were also given the opportunity to
complete the questionnaire on-line, 17.6% were completed. 
The questionnaire survey was supported by one-to-one consultation with 173 businesses consulted,
which equates to 40.2% of the businesses. 
The overall aim of the consultation was to assess opinions on initiatives to further enhance and
improve the BID area, determine what additional projects and services the businesses would like
delivered over the next BID term to give an added incentive to visit and invest in the town centre. The
results of these surveys and consultations have been combined and form the basis of the Business
Plan and BID Proposal 
Businesses received letters, e-mails, telephone calls, and one-to-one visits throughout the BID
development process to keep them informed of progress. The website www.dunoonpresents.co.uk
will be kept fully updated with information throughout the development of the BID. Full details of the
consultation are shown at Appendix 2.   
New businesses to the BID area received personal visits on a one-to-one basis to inform them about
the BID. 
Following feedback received during the consultation process, the board organised 2 ‘Next Steps”
meetings at which the ‘Next Steps’ document was discussed. The Next Steps document was delivered
to those businesses unable to attend the meeting. All eligible persons were invited by e-mail and social
media. 
As the ballot approaches it is planned to visit as many businesses as possible to discuss both the new
and existing projects and services the businesses have indicated they would like the BID to deliver.
Sub appendices attached separately
 Questionnaire – 2A
 Survey Email – 2B
 Next Steps document – 2C
 Emails to businesses – 2 D 
Page 24

Page 25

Business Proposal
Page 19 
7.2    Business Survey 
The survey questionnaires were hand delivered where possible, if not, emailed to the property within
the proposed BID area on the 27th May 2022. The businesses were also given the opportunity to
complete the questionnaire on-line. The purpose of the questionnaire survey was to consult with the
businesses within the BID area and determine their issues and concerns. The survey also sought to
establish views and opinions on specific identified issues relating to the area. 
The BID Board considered the responses from the one-to-one consultations, questionnaire survey and
public meetings as being sufficient to decide on the projects and services proposed in the business
plan. 
BID legislation requires that before a ballot can take place, a minimum of 5% of those eligible to vote
must indicate that they are in favour of a BID. The results of the consultations (both one-to-one and
questionnaire survey) indicate that 29 eligible persons e.g., 7.79% are in favour of the BID. In terms of
rateable value this equates to 14 %. 
Please refer to Appendix 1 (Support for the BID) for a list of the eligible persons who have indicated
their support for the BID to continue for a further term. 
7.3   The Key Findings 
Sector Specific Survey 
Overall, the most important areas the BID could improve included: 
1. Communication
2.  Footfall
3.  Collaboratively working with community groups and organisations
3. Marketing and Promotion
4. Business Support
5. A Vibrant and Attractive place
6. Lobbying and a Business Voice 
From the surveys it was determined that, 
Businesses would like: 
1.  A well promoted and vibrant town centre
2. To attract more visitors and see increased spend 
3.  A raised profile of the area by improving people’s perception of the town 
5.  To create a vibrant, more attractive area  
6.  To see fewer vacant units and improve their appearance
9.  A more diverse town centre to attract customers 
10. Improved business support and advice 
Page 25

Page 26

Business Proposal
Page 20
The businesses were given a final opportunity to comment on the projects and services, as detailed In
the Next Steps document, to the allow them to be included in the Business Plan. To date 6 responses
have been received. 
We asked what future projects for the town centre are most important 
The following list represents what the businesses would like the BID to address: 
 More business led projects
 Addressing unsightly vacant properties 
 Better communication
 Improve the look of the town   
8.0 Proposed Improvements 
We believe that the best way to achieve lasting and sustainable change, and best value for money, is
by working in partnership, so where appropriate we will work strategically with: - Visit Scotland, Police
Scotland, Cal Mac, Western Ferries, Community Groups, Educational Institutions – Schools and
Tourism Groups. 
The proposed projects will be progressed over the five-year period of the BID. Some projects will be
provided on an annual basis while others are one-off projects. The time frame for delivering the
projects will be decided by the Board of Directors within the agreed budget. 
The detailed projects costs are estimates only. The actual cost of the projects will depend on a variety
of factors and will not be definitive until competitive tenders have been submitted where necessary.
Some of the projects may be subject to planning permission and other statutory approval. 
The projects and services will be based on the following themes: events, space, collaboration and
Identity 
The projects will be based on the following themes, individual projects and services are detailed in the
Business Plan. 
1. Events – continue develop existing events £347,500
2. Space – New plans to make the town center look more attractive £65,500
3. Collaboration – Work closer and form new bonds with local community groups £0
4. Identity – Raise profile of Dunoon and market the businesses better £56,000 
9.0  The BID Levy 
9.1 Who will pay the levy? 
A BID levy is an equitable and fair way of funding additional projects and services, which the local
authority and other statutory bodies are not required to provide.  There are approximately 430
commercial properties in the BID area which will generate a BID investment levy income of
approximately £130,000 per annum and an estimated total levy income of £689,000 over 5 years.
Page 26

Page 27

Business Proposal
Page 21 
It has been agreed by the BID Board: -   
 The levy structure will be based on a banded fee structure fixed on the rateable value (RV) of the
property on the day of the ballot [02/03/2023 
 There shall be no increase to the levy within the first two years of a third term, but consideration
shall be given to an increase in years 3,4 and 5 that would be capped at a maximum of 10% of the
levy amount. 
 There will be no increase in the levy throughout the BID term because of a non-domestic rateable
revaluation occurring during the BID term. 
 The BID levy will be paid by the property occupier - the person liable to pay the non-domestic rate. 
 All eligible occupiers (of eligible properties) i.e., the eligible person liable to pay the non-domestic
rate that are listed on the Local Assessors Valuation Roll on the ballot date will be liable to pay the
levy. 
 The levy payments are not linked to what businesses actually pay in rates but are based on the
rateable value of the property. 
 The levy must be paid either in 1 or 2 payments in June & December within 28 days from the date
of the levy invoice or in 10 instalments by arrangement with the billing body. 
 If there is a change, in occupier to a property, until a new occupier is found, the property owner
will be responsible for paying the levy. 
 Any new commercial development, subdivision of existing properties or merging of properties or
new business with a non-domestic rateable valuation coming into the area during the 5-year term
of the business improvement district will be liable for the BID Improvement Levy. 
 If a property is vacant on the day the levy invoice is issued or any subsequent vacant periods, the
property owner will be liable to pay the levy. 
 Self-catering holiday accommodation which is not the sole or main residence of any person, and
which is available (or intended to be available) for letting on a commercial basis, with profit in
mind, for short periods totalling more than 140 days in the financial year remain liable for non-
domestic rates for the whole year and will be included. 
 The levy will apply to properties with a rateable value of £999 and above. Levy bandings will be
applied with a maximum banding at £111,000 and above. 
 The BID levy will not be index-linked to the Retail Price Index (RPI) or the Consumer Price Index
(CPI) to take account of inflation, so that those liable to pay the levy can budget accordingly for
the full five-year term. 
Businesses outside of the BID Zone, or otherwise exempt from the BID Levy, can choose to make
Voluntary Contributions. VCs from businesses will be determined by their Rateable values
Page 27

Page 28

Business Proposal
Page 22
and will be paid on an annual basis. These businesses will thereafter be entitled to benefit from
being members of Dunoon Presents.  Any business making a VC will require to at least match the Levy
threshold of £220 prior to becoming a member of the company.  There will be no limit on Voluntary
Contributions from individuals. 
Together with the Levy Payers, organisations making VCs can become a Member of the Company.
Membership benefits include access to Company information and log-in to the business section of the
Dunoon Presents website. On becoming Members, suppliers of goods and services may be given
consideration to trade with Dunoon Presents. 
9.2         Exclusions 
The BID Board decided to exclude premises that have a rateable value of less than £999.00. These
premises can pay a voluntary levy and become an “associate member” should they wish, details of
which are given in the BID Business Plan. 
The BID Board decided that there is no benefit from being part of the BID to the following categories
of property and therefore are exempt from paying the levy – schools, places of worship, non-retail
charitable organisations with a rateable value of 15K or less, Hospital, Ambulance, Fire, Coastguard,
Job Centre, Careers office, voluntary clubs, the Museum and social care establishments. 
A further concession under this proposal is that all properties designated as stores, where no trade,
commercial activity or direct operational/logistical support to a business takes place, will be exempt
from the levy at all bands. 
9.3   The Levy Table 
Rateable Value (RV) Each Week Each Month Annual Levy No of
Businesses
Total
0 to 999 Voluntary Voluntary Voluntary  £0.00
1,000 to 9,999 £4.23 £18.33 £220.00 331 £72,870.00
10,000 to 15,999 £6.88 £29.83 £358.00 50 £17,900.00
16,000 to 23,999 £10.06 £43.58 £523.00 18 £9414.00
24,000 to 39,999 £12.60 £54.58 £655.00 8 £5240.00
40,000 to 48,999 £16.83 £72.92 £875.00 3 £2625.00
49,000 to 63,999 £22.98 £99.58 £1,195.00 5 £5975.00
64,000 to 110,999 £31.63 £137.08 £1,645.00 2 £3290.00
111,000 +  £42.21 £182.92 £2195.00 6 £13170.00  
£130484.00 
Page 28

Page 29

Business Proposal
Page 23 
The BID Board decided to continue to use a fee structure, as detailed above, to calculate the levy fee.
The reasons behind this are as follows: -   
 The levy payments add up to the amount required to deliver the business plan. 
 A banding system was chosen as it represents a simple and easy way for businesses to identify
their levy payment, provides for ease of collection and represents a fair and reasonable
methodology. Everybody benefits therefore everybody pays. 
 A minimum payment of £4.23 per week is believed to be affordable for the smallest businesses. 
 Through consulting with the businesses, a maximum of £2195 is believed to be affordable for the
businesses at the higher end of the banding. 
9.4      Collection of the BID Levy 
Argyll and Bute Council will collect the investment levy on behalf of the BID, as this will be an efficient,
safe and cost-effective method of collection. Argyll and Bute Council will lodge the levy within a BID
Revenue Account. The BID levy can only be drawn down by the Board of Directors of the BID to allow
the delivery of the business plan. 
The BID Revenue Account and levy cannot be accessed by Argyll and Bute Council, nor can it be used
by the Council as an additional source of income. 
9.5  Enforcement 
In the event of any non-payment of the BID improvement levy, it will be strongly pursued by Argyll
and Bute Council (as the billing body) using the recovery powers available to the Council to ensure
complete fairness to all the businesses that have paid. Argyll and Bute Council will be entitled to charge
an additional fee to the levy amount to meet any additional costs incurred in the recovery of the levy. 
10. The Voting Process 
10.1 Pre-Ballot 
The BID Proposer must submit, at least 98 days in advance of the ballot date, the BID Proposals to the
Local Authority, the Scottish Ministers and the billing body along with a letter detailing their intention
to put the BID Proposals to ballot. The local authority has then, 28 days in which to veto or not veto
the BID Proposals. i.e., 98 – 28 = 70 – under the legislation the prescribed period is 70 days prior to
the day of the ballot. 
The local authority is required, under legislation, to notify the BID proposers and the Scottish
Government, in writing, if the authority is or is not vetoing the BID proposals. 
A ‘Notice of Ballot’ will be issued at least 42 days before the day of ballot. 
The BID Proposer will make available a copy of the BID Proposal to any person, who is eligible to vote
on the BID Proposals, who requests a copy.   
Page 29

Page 30

Business Proposal
Page 24  
10.2 The Ballot 
 Ballot papers will be posted to the eligible person responsible for casting a vote within their
business at least 42 days before the day ballot. In the case of national companies, the
responsibility for voting may lie with head office. 
 Prior to or on the date the ballot papers are issued the BID Proposer will provide to all those
eligible to vote in the ballot, with a copy of the BID Business Plan. 
 The BID ballot is a confidential postal ballot conducted by Argyll and Bute Council on behalf of
Dunoon Presents BID and in accordance with Scottish BID legislation. 
 Where an eligible property is vacant the voting papers will be sent to the property owner. 
 In the Dunoon Presents BID case, voting papers will be issued no later than 19/01/2023. 
 The last date for all ballot papers to be returned is 5pm on 02/03/2023.  Papers received after this
date and time will be deemed null and void and not be counted. 
 Voting papers are easy to complete, simply place a cross on either “yes” or “no” to the question
“are you in favour of a BID?” The ballot paper must then be signed by the person eligible to vote
and returned in the pre-paid envelope. 
 For the ballot to be successful there must be a minimum turnout of 25% (the headcount) by
number of eligible persons and by combined rateable value; and of those who turnout, the
majority must vote in favour by number and rateable value. 
 All eligible persons (i.e., those persons liable to pay non-domestic rates) will have one vote or
where a person is liable for non-domestic rates for more than one property, that individual shall
be eligible to cast more than one vote however they will be required to pay the levy for each of
the properties that they occupy. 
 The ballot papers will be counted on 03/03/2023 and the results announced by the Argyll and Bute
Council within one week. 
 Following a successful ballot, the BID will commence on 15/04/2023 and will run for a period of
five years until the 14/04/2028. 
Page 30

Page 31

Business Proposal
Page 25 
10.3 BID Ballot Timetable 
Item B-n Procedure Time Date Commen
ts
1 B-154 Last day for notice of
intention to put BID
proposals to ballot.
Regulation 4
At least 154 days before the
ballot date.
By
25.08.2022 
2 B-126 BID Review.  BID proposals reviewed and
agreement reached as to
whether a positive ballot result is
achievable. If not achievable,
then the BID should not go to
ballot. 
By
28.09.2022 
3 B-98 Last day for the
submission of the BID
proposal to the local
authority and Scottish
Ministers. 
Regulation 5 (2) (a) (i)
At least 98 days* before the day
of the ballot in accordance with
regulation 4. 
*This would give the local
authority at least 28 days to
consider proposals before
deciding whether to exercise
their veto.    
By
12.10.2022 
4 B- 70 Local authority to
confirm it is or is not
vetoing the BID
proposals. 
Regulation 14 (1)
For the purposes of section 42(2)
of the 2006 Act, the prescribed
period is 70 days prior to the day
of the ballot. 
By
25.11.2022 
5 B-56 At least 98 days after
item 1 the BID Proposer
requests local authority
to instruct ballot holder
to hold ballot. 
Regulation 5 (2) (a) (ii) and (b)
The request to hold a ballot
should be at least 56 days*
before the ballot date. 
*To allow time to put in place
ballot arrangements, before
issuing ballot papers (at least 42
days before the day of ballot), it
is recommended that the request
to hold a ballot should be made
at least 56 days before the ballot
date.
By
05.01.2023 
Page 31

Page 32

Business Proposal
Page 26
6 B-56 
B-42
The local authority
instructs the ballot
holder to hold BID
ballot. 
Ballot holder puts in
place arrangements to
hold BID ballot.
Regulation 6 
Regulation 8
On receiving instruction under
Regulation 6 to hold ballot the
ballot holder puts in place the
formal arrangements to hold
ballot, including: -
Securing ballot date, publishing
notice of ballot, and preparing list
of persons entitled to vote. 
By
05.01.2023 
By
19.01.2023 
7 B-42 Publication of notice of
ballot (by ballot holder). 
Issue of ballot papers. 
Spoilt ballot papers.
Schedule 2, para. 3a 
The ballot holder shall at least 42
days before the day of ballot,
publish the notice of ballot. 
Schedule 2, para. 3
42 days before the ballot date 
Schedule 2, para. 11
Spoilt ballot papers may be
replaced at any time from the
issue of ballot papers. 
By
19.01.2023 
By
19.01.2023 
From
19.01.2023 
8 B-42 Last day for postponing
the day of the ballot by
up to 15 days.
Schedule 2, para. 2 (2) - No later
than 42 days before the day of
the ballot, the ballot holder may
postpone the day of the ballot by
up to 15 working days.
By 5pm
19.01.2023 
9 B-10 Last day for the
appointment of a proxy.
Schedule 2, para. 5 (5)
An application to appoint a proxy
shall be refused for the purposes
of a particular ballot if the ballot
holder receives it after 5 p.m. on
the tenth day before the day of
the ballot. 
By 5pm
20.02.2023 
Page 32

Page 33

Business Proposal
Page 27
10 B-7 First day for the request
for issue of
replacement of LOST
ballot paper.
Schedule 2, para. 12
Where a voter has not received
their ballot paper by the seventh
working day before the day of the
ballot, that voter may apply
(whether or not in person) to the
ballot holder for a replacement
ballot paper. 
From
21.02.2023 
11 B-5 Last day for cancellation
of proxy.
Schedule 2, para. 5 (10)
A notice under sub- paragraph (9)
by a person entitled to vote
cancelling a proxy’s appointment
shall be disregarded for the
purposes of a ballot if the ballot
holder receives it after 5 p.m. on
the fifth day before the date of
the poll at that election.  
By 5pm
25.02.2023 
12 B Ballot Day Schedule 2, para. 2 
N.B. The time-period in which a
ballot can be secured in relation to
the date the ballot holder
published the “notice of ballot is
detailed under Schedule 2,
paragraph 2 – (1) (c) “at least 42
days after, but no more than 90
days after, the date on which the
ballot holder published the notice
required by paragraph 3 (a).” (See
also Item 7).
02.03.2023 
13 B+1 The Count Schedule 2, paras. 14-16
As soon as practicable after the
day of the ballot, the ballot
holder shall make arrangements
for counting the votes cast on
such of the ballot papers as have
been duly returned (in
accordance with paragraph 13)
and record the number counted.
By
03.03.2023 
Page 33

Page 34

Business Proposal
Page 28
14 
B+1 
B+8
Declaration of results. Schedule 2, para 17
(2) The ballot holder, having
made the certification under
subparagraph (1) Shall: 
(a) forthwith make a declaration
of the matters so certified; and 
(b) Give public notice of the
matters so certified as soon as
practicable and within 7 days
after the counting of the votes. 
From
03.03.2023 
By
09.03.2023 
11.0  Public Sector BID Involvement 
11.1  Baseline Services
A baseline service agreement ensures the BID does not use the levy money to duplicate any services
provided by Argyll and Bute Council & Police Scotland. The services directly delivered by the BID
additional to any statutory services. The baseline services agreement gives an assurance to businesses
that the levy payment will only be used for additional projects which they voted on in the BID ballot.
Additionally, a baseline agreement avoids the risk that public agencies including Argyll and Bute
Council will not reduce its statutory level of service to the BID area following a successful ballot. 
For a full and detailed list of services provided in the BID area by Argyll and Bute Council, please refer
to Appendix 6 Council Baseline information and Baseline Agreement. 
The services already provided by Argyll and Bute Council 
Argyll and Bute Council provides the following services (both statutory and discretionary) within the
BID area: - 
 Trading standards and advice Services 
 Street Cleansing and Bin Emptying 
 Commercial Waste – collection and recycling
 Strategic Transportation
 Economic Development – Business Gateway
 Horticulture & Grounds Maintenance – Open Space Maintenance – Playing Fields 
 Roads Maintenance – Roads, pavements and car park maintenance  
 Street Lighting and Maintenance 
 Planning, Housing, Regulatory Services and Building Standards 
The services already provided by Police Scotland: 
 24/7 Policing response 
 Crime prevention 
Page 34

Page 35

Business Proposal
Page 29
12.0  Measuring Success 
12.1 Measuring the Success of the BID 
Throughout the lifetime of the BID, all work on the BID projects will be monitored to ensure the
projects proposed in the BID Business Plan achieve a high level of impact and are progressing to the
satisfaction of the businesses that voted for the BID. 
The BID Board of Directors will monitor and oversee the efficient delivery of the BID projects. 
The BID will undergo an independent evaluation and or Assessment and Accreditation Interim Review
(AAIR) of its activities at the halfway point and towards the end of the third term. 
The AAIR: -  
 Is a bespoke review, which recognises and accords with the Scottish BIDs legislation and the public
and private sector environment in Scotland
 Gives confidence to businesses and the Board of Directors that the practices of the BID Company
are robust and accord with good practice and
 Supplies an audit trail to support any future evaluation of the BID Company.
In developing the Interim Review, a consultation was undertaken with,
 Key stakeholders and organisations 
 key UK national businesses 
 The Scottish Retail Consortium; and
reviewed existing assessment and accreditation frameworks, including existing documents used to
assess BID Proposals in the UK, to identify key lessons.
The AAIR is recommended by Scotland’s Improvement Districts (SIDs) as good practice and is included
as one of the good practice elements of any Scottish BID Proposal and BID Business Plan.
12.2  Marketing, Communications and Social Media
To ensure openness and transparency in the management of the BID company, following a successful
ballot, the BID Board have agreed the BID Business Plan should include, but not limited to; - one to
one business engagement, business briefings, social media engagement, newsletters for those
businesses (preferring hard copy information or with no access to IT), business forums, business
networking meetings etc. 
Additionally, the following information is to be displayed on the Dunoon Presents BID website: -
 The current BID business plan.
 The annual accounts
 The BID ballot result.
 The contact details for the BID manager and other staff members.
 The names of BID board members and either the name of their business or the sector they
represent. 
Page 35

Page 36

Business Proposal
Page 30
 BID board governance structure with specific reference to how decisions are agreed and actioned.  
 Details of director Meetings the agenda and minutes - abridged where necessary
 The methods levy payers can provide feedback to the BID e.g., at the annual AGM and/or other
regular meetings. 
 An annual report detailing the BIDs the projects/services/initiatives delivered and the cost of each;
and the Dunoon Presents achievements and the value the BID provides to levy papers. 
13.0  Finances 
13.1 Estimated Income and Expenditure 
There are circa 430 eligible properties located within the BID area (this figure may change as
businesses move, expand or close). The BID levy income is calculated to be approximately £130,000
per annum. 
An amount has been set aside in the budget under ‘contingency’ to allow for any bad debt. 
The improvement levy will make it easier to obtain other sources of funding for specific projects and
these opportunities will be pursued. The BID aims to attract other investment, sponsorship and trading
income to increase the amount available to spend on your projects as they develop. Funds will be
sought from but not restricted to Visit Scotland and Argyll and Bute Council. 
As the BID progresses, more income will be attracted, and this will be invested in improving the town
centre for the benefit of the businesses and local community. 
13.2    Financial Management Arrangements 
Any variations within budgets will be reported to the Board of Directors. 
The Board will agree on an annual basis how funds for subsequent years will be allocated. This will be
based on business feedback during the previous year and the priorities for the coming year, which
allows the BID the flexibility to respond to changing business needs and requirements. 
Argyll and Bute Council will collect the levy payments on behalf of the BID and will retain these funds
in a separate account until the BID Board calls these funds down. The BID Board will manage the levy
funds that are collected by the Council. This arrangement will ensure that projects are delivered, and
any financial liabilities of the BID are transparent. 
Page 36

Page 37

Business Proposal
Page 31
13.3 Dunoon Presents BID Projected Income and Expenditure 
INCOME YEAR 1 YEAR 2 YEAR 3* YEAR 4* YEAR 5* TOTAL
BID LEVY £130,000 £130,000 £143,000 £143,000 £143,000 £689,000 
EXPENDITURE YEAR 1 YEAR 2 YEAR 3* YEAR 4* YEAR 5* TOTAL
EVENTS 65,000 65,000 72,500 72,500 72,500 347,500
SPACE 11,000 11,000 14,500 14,500 14,500 65,500
COLLABORATION 0 0 0 0 0 0
IDENTITY 10,000 10,000 12,000 12,000 12,000 56,000
OPERATING COSTS 38,000 38,000 38,000 38,000 38,000 190,000
CONTINGENCY 5,000 5,000 5,000 5,000 5,000 25,000
KPI INDICATORS 1,000 1,000 1,000 1,000 1,000 5,000
TOTAL 130,000 130,000 143,000 143,000 143,000 689,000 
*The income and expenditure tables show figures if a 10% increase in levy is made by the BID board
in years 3.4 and 5 
14.0  Contact Information 
Full details of the voting and levy arrangements will be available online prior to the postal ballot
www.dunoonpresents.co.uk/members/documents;or can be requested by email
colin@dunoonpresents.co.uk. 
If you would like more information, please visit our website www.dunoonpresents.co.uk or contact
the BID Manager by telephone, e-mail or make an appointment to see them. 
Colin Moulson, BID Manager 
T: 07765770858
E: info@pa23.org.uk. 
Page 37

Page 38

This page is intentionally left blank

Page 39

APPENDIX 2
DUNOON PRESENTS BUSINESS PLAN 
APRIL 15, 2023 – APRIL 14, 2028
Page 39

Page 40

Contents 
1. Foreword
2. What is a BID
3. Why Dunoon needs a BID
4. Achievements to date
5. The Next 5 years
6. BID Levy
7. The voting process
8. Management of the BID
9. What if Businesses vote no?
10. The BID area 
Page 40

Page 41

Foreword 
As the Dunoon BID board, we are delighted to present this third term renewal proposal which
outlines the priorities of the business community.  We are all passionate and optimistic about
the future of the town and we are excited about how we can continue to improve
Dunoon by working together. 
The projects and ideas that are detailed in this business plan came from the levy payers, gath-
ered from our surveys, meetings, and consultations.  They shaped the overall strategy that
will allow us the opportunity to revitalise the town. 
We have all been involved in Dunoon for many years between us now and know a
lot of the local business people. The town in that time has become a regular host for major
event activity which has stimulated hundreds of thousands of pounds into the local economy.
These events have been the catalyst for new tourists and visitors to the area from across Scot-
land and further afield and we believe the town is on the cusp of major positive change in
many ways.  The work of the BID has been pivotal to the evident progress, and this now needs
to be taken to the next level, with the BID working alongside key local stakeholders to bring
about much needed progress in local infrastructure and public realm projects. 
Supporting the Dunoon presents BID for a third term is a great opportunity to collaborate and
make improvements that would not happen otherwise.  We are asking you to commit to this
at a time where many costs are rising however with this levy, we can access external funding
not available to individual businesses and we can implement projects that will help Dunoon
prosper. 
Ballot papers will be distributed by post no later than 19 January 2023 You will have 6
weeks to cast your vote before the ballot closes at 5pm on 02 March 2023. Ballot
papers received after this date and time will be null and void.  We passionately believe that
the town will continue to thrive and evolve with another BID five-year term. 
Page 41

Page 42

What is a Business Improvement District (BID)? 
A Business Improvement District (BID) is a geographically defined area, where businesses
come together and agree to invest collectively in projects and services the businesses
believe will improve their trading environment. BID projects are new and additional projects
and services; they do not replace services that are already provided by Argyll and Bute
Council and other statutory bodies. 
BIDs are developed, managed, and paid for by those who are liable to pay non-domestic
rates (NDR) by means of a compulsory levy, which the eligible persons in the proposed BID
area must vote in favour of, before the BID can be established. Each eligible person liable to
pay the BID levy will be able to vote on whether the BID goes ahead. 
“Business” or variations of the word “business” are used throughout this document. The word
“business” in this context refers to property owners or tenants and occupiers of properties
who are liable to pay the non-domestic rate (NDR), whether they pay business rates or not.
This includes all properties listed on the Scottish Assessors Association Portal (website) with
a non-domestic rateable value, many of whom may be a charitable organisation, public
sector organization, social enterprise or community group who may not consider themselves
to be a business. 
A baseline service agreement ensures the BID does not use the levy money to duplicate any
services provided by Argyll and Council and Police Scotland. The services directly
delivered by the BID additional to any statutory services. The baseline services agreement
gives an assurance to businesses that the levy payment will only be used for additional
projects which they voted on in the BID ballot. Additionally, a baseline agreement avoids the
risk that public agencies including Argyll and Bute Council will not reduce its statutory level of
service to the BID area following a successful ballot. This document is available on request. 
Page 42

Page 43

Why Does Dunoon Need a BID? 
If we do nothing, then nothing will be done and the progress that we have made over the
last 10 years will be lost. 
Dunoon has started to emerge from a long period of decline but now the work to allow the
town to keep progressing must intensify even more.  The primary focus of Dunoon presents
has been all about the events and we have curated a programme that is working well for the
area however it is now time to diversify our business plan working with key local
stakeholders to deliver a wider range of projects including shopfront/premises improve-
ments, streetscape enhancements and improved marine facilities. 
We are really excited about The Dunoon Community Project as it will have a positive impact
on the retail businesses and holiday accommodation providers.  We want to make sure that
visitors coming to the area for these activities will spend as much time in our town centre as
possible so we need to develop plans to make the most out of the opportunities that will
arise.  This multimillion-pound community led leisure development, progressing rapidly
around Bishop’s Glen was inspired by the work of the Dunoon Presents BID and made our
team realise that this was the way forward for the future of the town. Dunoon Presents have
and will continue to work closely with the consortium developing this major piece of infra-
structure, to ensure real and lasting legacy 
The BID board fully understands that times have been hugely challenging, and this is contin-
uing with local businesses increasingly worried about the availability of staff and rising costs
including energy and raw materials.  Certain things we can’t fix however what we can do is 
 work together to increase footfall, encouraging more people to Dunoon who spend
money in the local economy.
 Encouraging people to spend more time in the town by making sure it is looking
clean and attractive
 Promote the businesses better through social media, advertising and on the website
 Improving the perception of Dunoon as a place to visit with a variety of marketing
activities 
We know that there is so much work still to do and the BID provides a unique opportunity
for businesses across all sectors to work together, invest collectively and undertake projects
which can contribute positively to improving the economic viability of businesses in Dunoon
and securing investment in the area.  The BID has levered over £2.8million into the Dunoon
economy in the last nine and a half years.  It’s a winning formula that will see a further
£1.75million of growth in the Dunoon economy over the next five years; providing the BID
continues. 
Page 43

Page 44

BID ACHIEVEMENTS TO DATE 
The Dunoon BID has majored on a highly successful strategy of high end, adrenaline driven
and competitive focused outdoor events and music events.  In doing so we have created a
completely new consumer and visitor offer for the town and crucially, a renewed and
modernised sense of identity.  
The events strategy in place takes account of feedback from the first BID term and that was:
‘to develop more events that generate multi night stays in Dunoon’. This is clearly not possi-
ble at every event but has become a much more significant feature of the events calendar.   
Drive in Cinema: Immediately following the easing of the first lockdown n July 2020 a hugely
successful, full weekend sell out drive in/outdoor cinema was staged at the gasworks site in
Dunoon town centre with the significant assistance of the landowner, who also owns/runs a
local business. This was the first open/air drive in cinema staged in Scotland since the easing
of the lockdown. The event almost broke even commercially and generated a tangible feel
good emotion around the town and was only able to take place with a huge amount of hard
work from a dedicated team of local people.   
European Water Ski Racing Championships: Dunoon hosted this prestigious event for the
first time, in Autumn 2018 and around 300 competitors stayed in Dunoon for a full week
generating approx. 1300 bed nights. The event started immediately following the finish of
the Cowal Highland Gathering and therefore the local economy benefited for an extra week,
with this influx of people. This led to an ongoing relationship with the World Water Ski rac-
ing federation and the world championships remain a future possibility. 
Markets: Throughout the first year 2020 of lockdown, it still proved possible to stage four
seasonal outdoor markets within Argyll Gardens which were and managed safely alongside
strict covid protocols. The town now hosts five outdoor markets annually and this is an es-
tablished and popular aspect of community activity. 
Argyll Rally: In June 2021 at the start of the easing of the second major lockdown, the third
Argyll Rally was able to be successfully staged. This was made possible by a detailed submis-
sion from Dunoon Presents as main event sponsors, to Motorsport UK, the sport’s governing
body. This detailed the close collaboration between DP and Mull Car Club and the positive
and safe impact the event would have on the town and surrounding areas, outlining the
wider benefits to spectators and competitors’ mental health and finally, not least the much-
needed economic impact the event would generate into the local economy. Local history
was made by the event going ahead as it also marked the staging of the first ever town cen-
tre closed road stage of the rally, a new introduction and one which has subsequently set
the rally apart from any other in the UK.  The Argyll Rally is now established on the Scottish
Motorsport calendar, having first run in 2017. This event is estimated to attract over 600
competitors/crew alone, generating well over 1,100 bed nights over the course of three
days. 
Dunoon Ultra Marathon and Relay: This endurance running event has been running six
years and annually attracts around 200 runners from all over the UK to Dunoon and is now
Page 44

Page 45

firmly established in the UK ultra-marathon running scene. The event starts at Benmore Gar-
dens and finishes on Dunoon Pier  
Doon the Watter Revival Music Festival: This annual small festival comprises approximately
400 attendees who are almost entirely visitors to Dunoon from the central belt and beyond,
generating around 600 bed nights over the course of a full weekend  
Dunoon Dazzles Winterfest:  The annual Dunoon Christmas lights switch on event has grown
into a weekend of multi activities, live music, family entertainment and gigs. This community
event is one which does not specifically attract and audience from beyond Dunoon but is
however a very much anticipated annual highlight for the entire town.   
Enduro Mountain Biking: Dunoon now regularly hosts a round of the Scottish Enduro Series
Mountain biking championships over a full weekend between Spring and Autumn. The work
done by Dunoon Presents to collaborate with external partners has been the key to Dunoon
becoming a well-known and respected location in Scotland as a fast-emerging mountain bik-
ing destination and this is continuing to develop as the Dunoon Community Project emerges.
After a successful bidding process in summer 2022 Dunoon is back on the national champi-
onship circuit again for late April 2023 and this will attract approx. 350 elite competitors to
the town for a full weekend of racing, generating approx. 500 bed nights. This event also in-
cludes a spectacular closed road, town centre urban stage of competitive racing, staged on
the Saturday evening within Castle Gardens and attracts many hundreds of spectators into
the town centre to watch the action.   
Aqua Adrenaline Power Boat Championships Round 6: September 2022 saw this high-oc-
tane spectacle return to Dunoon for the first time in almost two decades and racing took
place in the East Bay all day on Saturday 10th September, with large crowds gathered on the
town promenade to beyond Kirn, enjoying this free to watch family friendly and highly visual
event. Discussions are now ongoing to decide whether this event can become an annual
town fixture 
Sunset Ceremony:  This Thursday evening pre Cowal Games family entertainment event is
now under the stewardship of Dunoon Presents and by doing so, the future of an event, val-
ued and close to the hearts of a great many locals is secured 
Cowalfest: Dunoon Presents introduced this local event for the first time in August 2021 in
an effort to address the fact the Cowal Highland Gathering (CHG) was not taking place as a
result of ongoing covid issues. This was staged in Argyll Gardens and comprised a full day of
family entertainment, music, children’s shows and dancing. Blessed by good weather, this
inaugural event proved a huge hit with locals and was repeated again in 2022 in close collab-
oration with the CHG organisers to ensure no conflict. We believe this event will now be-
come an established annual fixture in the town and ensure the final day of the CHG contin-
ues into the late evening, within the town centre.  
Dunoon Giftcard:  This was introduced in late November 2020 and is administered by Du-
noon Presents. Card(s) can be purchased in several businesses and can only be used/re-
deemed locally and are now accepted in the majority of local businesses as a method of pay-
ment. Monies owed are refunded to the business accepting the card within days. The
scheme has been a huge success and to date and has generated almost £19k in local sales
and is now a permanent and popular gift option around the local area. 
Page 45

Page 46

Punk on the Peninsula: This small indoor festival, which had been staged previously in the
town, was significantly upscaled in 2022 with the involvement and investment from DP
which resulted in the weekend of the event transforming into an outdoor festival with stage
and significantly increased attendance numbers as a result of the higher profile of bands
who were attracted, included headliners The Skids.   
Switch of BID activity during Covid:  
Due to the nature of the Dunoon BID being solely events focussed, a rapid and distinct de-
parture from the normal modus operandi was required during both main lockdowns and this
was evident in how the BID became the key ‘go to’ source of vital covid related information
cascaded to businesses around trading restrictions, emergency grants assistance, online
training seminars, issue of safety equipment such as hand sanitisers, amidst many other as-
pects. DP also provided Covid related external street signage to advise of safe distances to
operate and signage which proclaimed the ‘clean hands save lives’ public health message
during the height of the pandemic. A significant element of this activity around the end of
the first lockdown and at the point staycations were at their peak, was a Dunoon destination
marketing campaign targeting the central belt, comprising social media campaigns and road-
side billboard ads. This and much of the Covid related activity was funded from monies ap-
plied for and awarded by, the Scottish Government Recovery Resilience Funds scheme, cre-
ated to kickstart local economies. 
Page 46

Page 47

The Next 5 years
To develop our business plan, we consulted the businesses through surveys, meetings and
one to one consultation to identify the priorities for Dunoon over the next 5 years.  In
summary, businesses want us to continue delivering the projects that have been developed
over the last 2 terms but want us to expand on these, to work more effectively with partners
and to improve communication with the BID businesses.  If successful the BID board will take
the time to review our procedures, update ‘good practices’ and start the new 5-year term
with fresh vibrancy and efficiency to deliver more for your business.
Dunoon Presents recognises that local businesses and people who work in them are very
concerned about rising costs, some are still recovering from COVID enforced lockdowns and
Government restrictions.  We feel it is important for us to continue to work together in an
effort to navigate the difficult and uncertain times ahead whilst at the same time planning
and looking forward to economic recovery for Dunoon.
We have addressed your priorities over 4 main themes:
Events
Dunoon Presents has grown to become a recognised brand synonymous with high quality
events.  At renewal, the BID will build on this firm foundation, generating ever increasing visitor
numbers to the benefit of local trade and your bottom line by continuing to host events that
attract high spending customers who stay in the area for multiple night stays.  
 Increases footfall and dwell time
 Increases economic spending 
 Raises the profile of Dunoon
 Attracts visitors from further afield
 Benefits retail and accommodation providers, also indirectly supports their local
suppliers.
 We have been asked to promote the events to a wider audience more effectively
 Continue enhancing the reputation of Dunoon as a base for high-octane, outward
looking, participation sports events. This is our 'unique selling proposition', running,
Mountain Biking and Triathlon events attract athletes from the west coast, central
belt and beyond.  Competitors and visitors to these events provide by far the biggest
annual spend. Participation and spectator events such as the Argyll Rally bring
another exciting dimension to the town.   
 Dunoon Presents will seek to support sporting, music, cultural and community events
with regional appeal.  The aim is to attract a fresh new audience and demographic
profile - more visitors with more disposable income.  Dunoon Presents will act as an
enabler and may offer match funds to new, professionally run events meeting the BID
criteria, pulling people into Dunoon from beyond the immediate area with measurable
benefit to the retail and service economy. 
Page 47

Page 48

 We will deliver a series of community events to draw local people into town more
often. The BID will continue to develop the town's Christmas offering including the
street market, fairground and musical attractions.   
 The objective is to build on Dunoon’s success and attract new audiences. 
 We will evaluate the events with questionnaires to local businesses and also to the
visitors so we can gather data about those attending along with monitoring the
economic impacts. 
Identity
At the outset in 2012, available research highlighted a public perception that there was noth-
ing to do in Dunoon.  We have been working tirelessly for the last 10 years to curate a pro-
gramme of exciting events that people will travel each year to visit and attend.  We have
amazing natural resources, the water, forests, and the hills that make Dunoon and the wider
Cowal the special place that it is, lets continue to develop activities that show off our strengths
and work with others to improve the perception of the area. Ambitious events focusing on
sport, music and culture will continue to confirm Dunoon as an exciting place to live, visit and
return again and again to help create the right conditions for continued business growth in
Dunoon. 
 Prioritising the development of a marketing strategy for the next five years including
a revamp of the existing website and social media presence. 
 Be creative and use a wider network of resources and specialist media outlets to put
Dunoon on the map. Good stories sell and bring visitors to sample the Dunoon
experience for themselves. 
 Dunoon Presents will develop stronger relations and lines of communication with
other successful BID Towns to share information and best practice with a view to max-
imising the positive impact of Dunoon Presents on the local community. 
 Generate maximum PR in regional terms and via special interest titles creating regular
news features about Dunoon and its sporting, cultural and community events.   
 Marketing campaigns will set out to welcome and encourage more event
participants and visitors to Dunoon.   
 Work with tourism partners to bring visitors from a wider catchment and with higher
disposable income. 
 Targeted marketing will focus on communities of interest to generate new business
and bring increasing numbers to sporting, music, cultural and community events.     
Page 48

Page 49

 Explore printed and online business directories 
Collaboration
The pre ballot survey indicated the need for greater collaboration with the appropriate local
groups and external funders to bring about more rapid progress on infrastructural projects
that need to be brought forward/expedited.  This will hopefully bring about additional funding
opportunities by working in partnership this way.
 The business community need to have an active voice with future projects in Dunoon
 Looking to secure additional external funding with the support of local groups
 Continue to lobby our local authority and Government for improved changes to
Dunoon
 Save money through joint procurement
 New focus on sustainability, helping businesses through changes that will be
implemented by the Scottish and UK Government to deliver net zero. 
Space
With improvements to the Queens Hall, Argyll Gardens and Dunoon CARs scheme, along with
numerous events, festivals and other projects in the pipeline, the town is reestablishing itself
as a leisure tourism destination, bringing more people to the area.  Dunoon presents are aware
that there is a need to do more.  We need to continue to improve the physical appearance of
our town centre and waterfront area for this to have the maximum positive economic impact
for local businesses.
 Continue with shopfront/premises improvement grants
 A renewed focus on cleanliness
 Troubleshooting problem areas with assistance from Argyll and Bute Council
 Exploring additional plants/flowers with community partners
 Improving Marine infrastructure and gateway to the town
 Creating digital ‘What’s on’ community notice board
 Introducing vertical banners from lighting columns 
BID INCOME & EXPENDITURE 
Page 49

Page 50

INCOME YEAR 1 YEAR 2 YEAR 3* YEAR 4* YEAR 5* TOTAL
BID LEVY £130,000 £130,000 £143,000 £143,000 £143,000 £689,000 
EXPENDITURE YEAR 1 YEAR 2 YEAR 3* YEAR 4* YEAR 5* TOTAL
EVENTS 65,000 65,000 72,500 72,500 72,500 347,500
SPACE 11,000 11,000 14,500 14,500 14,500 65,500
COLLABORATION 0 0 0 0 0 0
IDENTITY 10,000 10,000 12,000 12,000 12,000 56,000
OPERATING COSTS 38,000 38,000 38,000 38,000 38,000 190,000
CONTINGENCY 5,000 5,000 5,000 5,000 5,000 25,000
KPI INDICATORS 1,000 1,000 1,000 1,000 1,000 5,000
TOTAL 130,000 130,000 143,000 143,000 143,000 689,000 
*The income and expenditure tables show figures if a 10% increase in levy is made by the
BID board in years 3.4 and 5 
BID LEVY
A BID levy is an equitable and fair way of funding additional projects and services, which the
local authority and other statutory bodies are not required to provide.  There are approxi-
mately 430 commercial properties in the BID area which will generate a BID investment levy
income of approximately £130,000 per annum and an estimated total levy income of £689,000
over 5 years. 
It has been agreed by the BID Board: -   
 The levy structure will be based on a banded fee structure fixed on the rateable value (RV)
of the property on the day of the ballot 02/03/2023 
 There will be no increase in the levy throughout the BID term because of a non-domestic
rateable revaluation occurring during the BID term.
 The board have agreed that there should be no increase in levy within the first two years
of a third term, but consideration shall be given to an increase in years 3,4 and 5 that
would be capped at a maximum of 10% of the levy amount.
 The BID levy will be paid by the property occupier - the person liable to pay the non-do-
mestic rate. 
 All eligible occupiers (of eligible properties) i.e., the eligible person liable to pay the non-
domestic rate that are listed on the Local Assessors Valuation Roll on the ballot date will
be liable to pay the levy.
 The levy payments are not linked to what businesses actually pay in rates but are based
on the rateable value of the property.
 The levy must be paid either in 1 payment, 2 payments in June & December within 28 days
from the date of the levy invoice or in 10 instalments by arrangement with Argyll and Bute
Council.
 If there is a change, in occupier to a property, until a new occupier is found, the property
owner will be responsible for paying the levy. 
 Any new commercial development, subdivision of existing properties or merging of prop-
erties or new business with a non-domestic rateable valuation coming into the area during
Page 50

Page 51

the 5-year term of the business improvement district will be liable for the BID Improve-
ment Levy. 
 If a property is vacant on the day the levy invoice is issued or any subsequent vacant peri-
ods, the property owner will be liable to pay the levy.
 Self-catering holiday accommodation which is not the sole or main residence of any per-
son, and which is available (or intended to be available) for letting on a commercial basis,
with profit in mind, for short periods totalling more than 140 days in the financial year
remain liable for non-domestic rates for the whole year and will be included.
 The levy will apply to properties with a rateable value of £999 and above. Levy bandings
will be applied with a maximum banding at £111,000 and above. 
 The BID levy will not be index-linked to the Retail Price Index (RPI) or the Consumer Price
Index (CPI) to take account of inflation, so that those liable to pay the levy can budget
accordingly for the full five-year term. 
Businesses outside of the BID Zone, or otherwise exempt from the BID Levy, can choose to
make Voluntary Contributions. VCs from businesses will be determined by their rateable val-
ues and will be paid on an annual basis. These businesses will thereafter be entitled to benefit
from being members of Dunoon Presents.  Any business making an VC will require to at least
match the Levy threshold of £220 prior to becoming a member of the company.  There will be
no limit on Voluntary Contributions from individuals.  Together with the Levy Payers, organi-
sations making VCs can become a Member of the Company.  Membership benefits include
access to Company information and log-in to the business section of the website. 
Exclusions 
The BID Board decided to exclude premises that have a rateable value of less than £999.00.
These premises can pay a voluntary levy and become an “associate member” should they
wish. 
The BID Board decided that there is no benefit from being part of the BID to the following
categories of property and therefore are exempt from paying the levy – schools, places of
worship, non-retail charitable organisations with a rateable value of 15K or less, Hospital, Am-
bulance, Fire, Coastguard, Job Centre, Careers office, voluntary clubs, the Museum, and social
care establishments. 
A further concession under this proposal is that all properties designated as stores, where no
trade, commercial activity or direct operational/logistical support to a business takes place,
will be exempt from the levy at all bands. 
Page 51

Page 52

The Levy Table 
Rateable Value (RV) Each Week Each Month Annual Levy No of Busi-
nesses
Total
0 to 999 Voluntary Voluntary Voluntary 0 £0.00
1,000 to 9,999 £4.23 £18.33 £220.00 331 £72,870.00
10,000 to 15,999 £6.88 £29.83 £358.00 50 £17,900.00
16,000 to 23,999 £10.06 £43.58 £523.00 18 £9414.00
24,000 to 39,999 £12.60 £54.58 £655.00 8 £5240.00
40,000 to 48,999 £16.83 £72.92 £875.00 3 £2625.00
49,000 to 63,999 £22.98 £99.58 £1,195.00 5 £5975.00
64,000 to 110,999 £31.63 £137.08 £1,645.00 2 £3290.00
111,000 +  £42.21 £182.92 £2195.00 6 £13170.00 
423 £130484.00 
The BID Board decided to continue to use a fee structure, as detailed above, to calculate the
levy fee. The reasons behind this are as follows: -   
 The levy payments add up to the amount required to deliver the business plan. 
 A banding system was chosen as it represents a simple and easy way for businesses to
identify their levy payment, provides for ease of collection and represents a fair and rea-
sonable methodology. Everybody benefits therefore everybody pays. 
 A minimum payment of £4.23 per week is believed to be affordable for the smallest busi-
nesses.
 Through consulting with the businesses, a maximum of £2195 is believed to be affordable
for the businesses at the higher end of the banding. 
Collection of the BID Levy 
Argyll and Bute Council will collect the investment levy on behalf of the BID, as this will be an
efficient, safe, and cost-effective method of collection. Argyll and Bute Council will lodge the
levy within a BID Revenue Account. The BID levy can only be drawn down by the Board of
Directors of the BID to allow the delivery of the business plan. 
The BID Revenue Account and levy cannot be accessed by Argyll and Bute Council, nor can it
be used by the Council as an additional source of income. 
Page 52

Page 53

Enforcement 
In the event of any non-payment of the BID improvement levy, it will be strongly pursued by
Argyll and Bute Council (as the billing body) using the recovery powers available to the Council
to ensure complete fairness to all the businesses that have paid. Argyll and Bute Council will
be entitled to charge an additional fee to the levy amount to meet any additional costs in-
curred in the recovery of the levy. 
Page 53

Page 54

THE VOTING PROCESS 
Pre-Ballot 
The BID Proposer must submit, at least 98 days in advance of the ballot date, the BID Proposals
to the Local Authority, the Scottish Ministers, and the billing body along with a letter detailing
their intention to put the BID Proposals to ballot. The local authority has then, 28 days in which
to veto or not veto the BID Proposals. i.e., 98 – 28 = 70 – under the legislation the prescribed
period is 70 days prior to the day of the ballot. The local authority is required, under legisla-
tion, to notify the BID proposers and the Scottish Government, in writing, if the authority is or
is not vetoing the BID proposals. A ‘Notice of Ballot’ will be issued at least 42 days before the
day of ballot. The BID Proposer will make available a copy of the BID Proposal to any person,
who is eligible to vote on the BID Proposals, who requests a copy.   
The Ballot 
 Ballot papers will be posted to the eligible person responsible for casting a vote within
their business at least 42 days before the day ballot. In the case of national companies,
the responsibility for voting may lie with head office. 
 Prior to or on the date the ballot papers are issued the BID Proposer will provide to all
those eligible to vote in the ballot, with a copy of the BID Business Plan. 
 The BID ballot is a confidential postal ballot conducted by Argyll and Bute Council on behalf
of Dunoon Presents BID and in accordance with Scottish BID legislation. 
 Where an eligible property is vacant the voting papers will be sent to the property owner. 
 In the Dunoon Presents BID case, voting papers will be issued no later than 19/01/2023. 
 The last date for all ballot papers to be returned is 5pm on 02/03/2023.  Papers received
after this date and time will be deemed null and void and not be counted. 
 Voting papers are easy to complete, simply place a cross on either “yes” or “no” to the
question “are you in favour of a BID?” The ballot paper must then be signed by the person
eligible to vote and returned in the pre-paid envelope. 
 For the ballot to be successful there must be a minimum turnout of 25% (the headcount)
by number of eligible persons and by combined rateable value; and of those who turnout,
the majority must vote in favour by number and rateable value. 
 All eligible persons (i.e., those persons liable to pay non-domestic rates) will have one vote
or where a person is liable for non-domestic rates for more than one property, that indi-
vidual shall be eligible to cast more than one vote however they will be required to pay
the levy for each of the properties that they occupy. 
 The ballot papers will be counted on 03/03/2023 and the results announced by the Argyll
and Bute Council within one week. 
Page 54

Page 55

 Following a successful ballot, the BID will commence on 15/04/2023 and will run for a
period of five years until the 14/04/2028. 
MANAGEMENT OF THE BID
Following a successful yes vote, the management and operation of the BID will continue under
the existing company structure and name.  The Company will continue to be managed by its
Board of Directors operating in an open and transparent way and answerable to the busi-
nesses in the area. The Directors are committed to the highest standards of management,
governance, and accountability; recognising good governance helps deliver the strategic ob-
jects of the company.  There will be a detailed set of protocols (the Operating Agreement)
which will cover, as well as other items, the billing, collection, and transfer of the levy to the
Company.  Dunoon Presents will hold an AGM each year. 
There are currently 8 in office, an active campaign will be launched after the successful ballot
to recruit additional directors to the Board. Every eligible person that pays the levy will have
the opportunity to nominate themselves or someone else from within the BID area to be
elected to the Company Board but limited to one eligible person from each eligible property. 
Nominations of directors, representatives, or advisors from outside the BID, who do not pay
the levy and who may or may not represent those making voluntary or other financial contri-
butions toward the BID, will be strictly at the discretion of the Board of Directors.   
The Company will continue to be run by the businesses for the businesses. This Board will be
responsible for all decisions relating to staff, contracts, the delivery of the approved business
plan and other activities generated by the BID.  The Board will be representative of the busi-
nesses and stakeholders in the area. The Chair, Vice Chair and Finance Director will be elected
from the directors of the Board. The Board will include 1 representative from Argyll and Bute
Council. Other non-voting members or local groups may be co-opted onto the Board at the
Board’s discretion.   
The BID Company Board will have the authority to adapt or alter the projects and services
from year to year to reflect any change in economic circumstances or any new opportunities
that may arise. This will be in the best interests of the levy payers and without recourse to an
alteration ballot.   
Additionally, the BID Company Board reserve the right to consider creating a charitable arm
of the company to enable it to secure additional funding, which can only be sourced with
charitable status. 
What if businesses vote no?
Page 55

Page 56

If the Business Improvement District is unsuccessful with the ballot, all services and activities
will stop on the 1st April 2023 and the board of directors will officially wind up the company
aiming for this to be done by 14th April 2023, the last day of the 5-year term.   
There is no alternative organisation to fund and continue the projects that the BID has been
delivering for Dunoon. 
 No large-scale events will take place in Dunoon and footfall will reduce significantly
 The Dunoon Gift Card will cease to exist
 The significant potential for economic growth will be at risk
 Collaboration and partnership working will not happen on such a large scale
 External funding for any activities will no longer be able to be accessed by the
businesses
 No website to promote businesses and activities
 Social Media sites will be closed
 Marketing and advertising will stop
 Lobbying in support of the businesses will stop 
This is a sample of the activity that would no longer take place in Dunoon, we need
you to vote for us to continue this work. 
THE BID AREA
Page 56

Page 57

The BID Area includes the major shopping and commercial streets within the town – all those
included in the first BID term. 
The BID area encompasses approximately 430 properties - we believe that through the BID,
businesses in Dunoon are stronger together.   
The BID Zone proposed reflects the main business and commercial area; all businesses were
asked to contribute their ideas to the plan prior to the voting decision. 
The following streets were chosen to be included in the BID area as consultations with busi-
nesses in this area highlighted several common issues of concern that could be addressed by
a BID. 
It is proposed to include the following principal streets
Page 57

Page 58

Albert Crescent
Alexander Street
Alexandra
Parade
Alexandra Place
Alexandra
Terrace
Alfred Street
Allan Terrace
Ardenslate
Crescent
Ardenslate Road
Ardmhor
Ardtully Brae
Argyll Road
Argyll Street
Argyll Terrace
Arthur Terrace
Ash Gardens
Ashcraig
Ash Croft
Auchamore Road
Avenue, The
Beechcroft
Belmont Lane
Bencorrum Brae
Bishop’s Glen
Brae
Bogleha Road
Brae Cottages
(Sandbank)
Brandon Street
Brooklyn Place
Broomfield Drive
Broughallan
Gardens
Broughallan Park
Broxwood Place
Bullwood Road
(Part)
Cammesreinach
Brae
Cammesreinach
Crescent 
Carolina Lane
Castle Street
Cedar Grove
Cedarcroft
Charles Gardens
Charles Lane
Cherryhill
Church Square
Church Street
Clyde Street
(Dunoon)
Clyde Street
(Kirn)
Coach Houses
Cowal Avenue
Cowal Place
Crawford Lane
Crochan Road
Cromlech Grove
Cromlech Road
Cromwell Street
Deercroft
Dhailling Avenue
Dhailling Court
Dhailing Park
Dhailling Road
Dixon Avenue
Dixon Crescent
Dixon Park
Dixon Place
Douglas
Cottages
Dunclutha Lane
Eaglecroft
Eccles Road
Edward Street
Edward Place
Elizabeth Avenue
Erichtbank Drive
Eton Avenue
Fairhaven
Ferguslie Place
Ferguslie Street
Ferry Brae
Ferry Road
Finbracken
Fir Brae
Fircroft
Fountain Quay
George Street
Gladstone
Avenue
Glebe Avenue
Glebe,
The Glebe View
Cottages
Glenallan
Glenmorag
Avenue
Glenmorag
Crescent
Gordon Street
Gorsecroft
Greenbank Lane
Hafton Court
Hamilton Street
Hanover Street
Heathercroft
High Road (Part)
Highland Avenue
Hill Street
Hillfoot Street
Hunter Street
Hunter’s Grove
James Street
Jane Street
Jaycroft
Jessie Place
John Street
Johnson Terrace
Kilbride Avenue
Kilbride Road
Kimberley
Terrace
King Street
Kirk Brae
Kirk Street
Kirn Brae
Kirn Court
Kirn Gardens
Ladysmith
Terrace
Lebanon Place
Leven Place
Lilyoak
Limecroft
Lochan Avenue
Lorimer Terrace
McArthur Street
McCall Terrace
MacDonald
Avenue
Manse Avenue
Marine Parade
Marlborough
Lane
Marshall Court
Mary Street
Massan View
Miller Court
Milton Avenue
Milton Road
Minard Place
Moir Place
Moir Street
Mount Carmel
Murrayfield
Nelson Street
Nile street
Oakfield Place
Oxford Lane
Park Avenue
Park Road
Pier Esplanade
Pier Road
Pilot Street
Port Riddell
Primrose Terrace
Prospect Avenue
Prospect Terrace
Queen Street
Queen’s Road
Queen’s Terrace
Rankin’s Brae
Regent Terrace
Renfield Brae
Robert’s Terrace
Robertson
terrace
Rockhill Terrace
Ros Mhor
Gardens
Royal Crescent
St. Andrews
Square Salisbury
Terrace
Sanda Gardens
Sandbank Road
Sanderson Drive
Sandhaven 
School Brae
The Sheiling, 
Shore Road
Shuna Gardens
Skye Court
Sommerville
Place
Spence Court
Stanley Terrace
Page 58

Page 59

Stewart Street
Tom-A-Mhoid
Road
Union Lane
Union Street
Valrose Terrace
Victoria Crescent
Victoria Gardens
Victoria Parade
Victoria Park
Victoria Road
(Dunoon)
Victoria Road
(Hunter’s Quay)
Victoria Square
Victoria Terrace
Wallace Court
Waverley House
Wellington
Street
West Street
William Street
Willow Quay
Windsor Lane
Woodfield
Terrace
Woodford Grove
Page 59

Page 60

The BID Map  
THERE ARE CIRCA 430 PROPERTIES LOCATED IN THE BID AREA.  
Full details of the voting and levy arrangements will be available online prior to the postal
ballot at info@pa23.org.uk. This can be requested by email from colin@dunoon-
presents.co.uk.  Colin Moulson the BID manager can also be contacted on 07765770858.
Page 60