ARGYLL AND BUTE COUNCIL  COUNCIL  
DEVELOPMENT AND 
ECONOMIC GROWTH   
22ND FEBRUARY 2024 
HOUSING EMERGENCY – WORKER ACCOMMODATION PROPOSALS 
1.0 EXECUTIVE SUMMARY 
1.1  The main purpose of this report is to provide information on worker
accommodation proposals in areas of Argyll and Bute to enable essential
services to be delivered to our communities and to request Strategic Housing
Fund grants to support these proposals. 
1.2  The report confirms the requirement for the Council to work with partners to
enable innovative housing solutions on Coll, Tiree, Mull and in the Lorn area.
1.3 It is recommended that Council:-
i. Approve a grant of £100,000 from the Strategic Housing Fund to enable 2
NHS properties on Coll to be brought back into use for HSCP staff delivering
health and social care services on the island.
ii. Approve a grant of £160,000 from the Strategic Housing Fund to enable a
Council owned property on Tiree to be brought back into use for HSCP staff
delivering health and social care services on the island.
iii. Approve a contingency of up to £250,000 from the Strategic Housing Fund
to enable the important first phase of delivering worker accommodation
properties at Tobermory on Mull.
iv. Approve a grant or loan of £200,000 from the Strategic Housing Fund to
enable the refurbishment of an ACHA owned 4 bedroom property in Lorn
and enable accommodation for HSCP staff and staff contracted by the
HSCP to deliver care to households in the community.
v. Delegate to the Executive Director with responsibility for Development and
Economic Growth, in consultation with the Executive Director with
responsibility for Legal and Regulatory Support, the terms and conditions
to be attached to any grant and / or loan agreement required as a
consequence of this report.

Page 2

ARGYLL AND BUTE COUNCIL  COUNCIL  
DEVELOPMENT AND 
ECONOMIC GROWTH 
22nd FEBRUARY 2024 
HOUSING EMERGENCY – WORKER ACCOMMODATION PROPOSALS 
2.0 INTRODUCTION 
2.1 As the strategic housing authority for Argyll and Bute, the Council has a statutory
duty to assess the need and demand for housing in the area and to ensure that
any unmet need for housing is addressed through the Local Housing Strategy
(LHS) and the Strategic Housing Investment Plan (SHIP).  
2.2 The Council declared a housing emergency in June 2023. One of the main issues
identified was the lack of worker accommodation in Argyll and Bute. If the lack of
worker accommodation is not addressed there will be a serious impact on the
general economy but more specifically there will be a risk that essential health
and social care services will not be delivered in communities across the local
authority area. 
2.3 A housing summit took place in Oban on 27th November 2024. The 4 broad
themes of the summit focused on the delivery of more market homes, the delivery
of more affordable housing, the delivery of more workforce housing and how
partners make best use of existing housing. The proposals in this paper will help
to tackle the issue of delivering more workforce homes through a combination of
making best use of existing housing and also delivering more affordable housing. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that Council:-
i. Approve a grant of £100,000 from the Strategic Housing Fund to enable 2
NHS properties on Coll to be brought back into use for HSCP staff delivering
health and social care services on the island.
ii. Approve a grant of £160,000 from the Strategic Housing Fund to enable a
Council owned property on Tiree to be brought back into use for HSCP staff
delivering health and social care services on the island.
iii. Approve a contingency of up to £250,000 from the Strategic Housing Fund
to enable the important first phase of delivering worker accommodation
properties at Tobermory on Mull.
iv. Approve a grant or loan of £200,000 from the Strategic Housing Fund to
enable the refurbishment of an ACHA owned 4 bedroom property in Lorn

Page 3

and enable accommodation for HSCP staff and staff contracted by the
HSCP to deliver care to households in the community.
v. Delegate to the Executive Director with responsibility for Development and
Economic Growth, in consultation with the Executive Director with
responsibility for Legal and Regulatory Support, the terms and conditions
to be attached to any grant and / or loan agreement required as a
consequence of this report. 
4.0 DETAIL   
Background: The Housing Situation on Coll   
4.1 There are around 145 homes on the island, of which 25% are deemed ineffective
in terms of meeting local needs, i.e. 34 are second/holiday homes and a further 2
are empty/long term unoccupied. In addition there are a number of short term
holiday lets.  ACHA and Trust Housing Association currently provide 16 properties
for social rent; which amounts to only 11% of the total dwelling stock or 15% of
the occupied stock. This is well below national levels and indicates a potentially
imbalanced housing system with scope for further growth in the Registered Social
Landlord (RSL) sector. 
4.2 Affordability on the open market remains a significant issue for local residents.
The average achieved house price achieved on Coll is £185,000 which would
require a household income of £52,857 to be considered affordable. 62% of
residents on the island cannot afford to purchase on the open market; and
therefore require alternative affordable options such as social rent and shared
equity.  
4.3 Expressed demand for RSL housing is registered via the HOMEArgyll waiting list,
and currently there are 10 active applicants with Coll as first or second area of
preference. 7 of the 10 applicants have been awarded housing need points
(HOMEArgyll Waiting List, December 2023). Turnover of social rented property
has been low on the island resulting in a pressure ratio of 2 applicants to every
allocation rising to 4 applicants for every allocation of a 1 bedroom property. 
4.4 In March 2022 the HSCP in partnership with the Coll Collaborative Working Group
published a Health and Social Care Needs Assessment. This document clearly
outlines an expectation that there will continue to be a requirement for health
and social care on the island. Due to the nature of the provision of such services
in remote island location it is essential that the HSCP is able to provide
accommodation for key workers. 
Solution 
4.5 The Strategic Housing Fund grant will enable the HSCP to bring 2 NHS owned
properties back into use for HSCP staff or staff from other organisations
contracted by the HSCP to deliver health and social care services on the island.
The total cost of the project is £480 000. The HSCP will contribute £380 000 and
the Strategic Housing Fund will contribute £100,000 (21% of the total project cost).

Page 4

The project will result in a 2 bedroom property being brought back into use and
also a 4 bedroom property being brought back into use – both for HSCP staff who
would require accommodation on the island to deliver essential health and social
care service.   
Background: The Housing Situation on Tiree  
4.6 There are around 560 homes on the island of Tiree, of which 36% are deemed
ineffective in terms of meeting local needs i.e. 167 are second/holiday homes and
a further 36 are empty/long term unoccupied. In addition there are a number of
short term holiday lets.  ACHA and West Highland Housing Association currently
provide 40 properties for social rent; which amounts to only 7% of the total
dwelling stock or 11% of the occupied stock. This is well below national levels and
indicates a potentially imbalanced housing system with scope for further growth
in the Registered Social Landlord (RSL) sector. 
4.7 Affordability on the open market remains a significant issue for local residents.
The average achieved house price on Tiree is £227,500 which would require a
household income of £65,000 to be considered affordable. In fact the average
house price is nearly 6 times the average household income. On that basis,
around 80% of local households could not afford to purchase on the open market;
and therefore require alternative affordable options such as social rent and shared
equity.  
4.8 Expressed demand for social rented housing is registered via the HOMEArgyll
waiting list, and there are 22 active applicants with Tiree as first or second area of
preference. 18 of the 22 applicants have been awarded housing need points
(HOMEArgyll waiting list December 2023). Turnover in the social rented stock has
been low to nil in recent years resulting in a pressure ratio of 9 applicants to every
allocation of social housing. 
4.9 The HSCP has set up an Islands Strategy Working Group to gather information
in health and social care on the islands and a Tiree medical practice analysis of
out of hours activity report was produced in August 2023. This revealed a high
level of calls and required responses by health and social care. There is a clear
requirement to provide accommodation for health and social care workers on the
island. In addition a recent housing needs report published in June 2023
concluded that Tiree in common with many rural areas in Scotland has a
significant shortage of affordable housing which is negatively impacting the
community’s and local businesses economic and social sustainability. 
Solution 
4.10 The Strategic Housing Fund grant will enable the HSCP to remodel an existing
property at the Tigh a Rudah Care Home on Tiree and create a worker
accommodation property which will make it more attractive for visiting health and
social care staff to work on the island. The re-modelling of the property will deliver
two ensuite bedrooms with a shared lounge/kitchen area. The Strategic Housing
Fund contribution of £160,000 will complement the capital contribution of £44,000
in relation to roof works already completed.

Page 5

Background: The Housing Situation on Mull 
4.11 There are around 1870 homes on the island of Mull of which 16% are deemed
ineffective in terms of meeting local needs i.e. 200 are second/holiday homes and
a further 98 are empty/long term unoccupied (Council Tax Records December
2023). In addition there are a number of short term holiday lets.  ACHA, West
Highland Housing Association and Trust Housing Association currently provide
236 properties for social rent which amounts to only 13% of the total dwelling stock
or 15% of the occupied stock. This is well below national levels and indicates a
potentially imbalanced housing system with scope for further growth in the
Registered Social Landlord (RSL) sector. 
4.12 Affordability on the open market remains a significant issue for local residents.
The average achieved house price on Mull is £233,864 which would require a
household income of £66,818 to be considered affordable. As a result at least
76% of local households could not afford to purchase on the open market; and
therefore require alternative affordable options such as social rent and shared
equity. 
4.13 Expressed demand for social rented housing is registered via the HOMEArgyll
waiting list, and there are 112 active applicants with Mull as first or second area
of preference. 68 of the 112 applicants have been awarded housing need points
(HOMEArgyll waiting list December 2023). Turnover in the social rented stock has
been low in recent years resulting in a pressure ratio of 4 applicants to every
allocation of social housing. 
4.14 The Council has worked closely with Mull and Iona Community Trust to establish
the requirement for worker accommodation to support the general economy of the
island. MICT published a Mull and Iona Key Worker Housing study in 2022 which
demonstrated a clear requirement for worker housing after consultation with local
businesses. This was followed up by the publication of a Worker Accommodation
Economic Impact Assessment in March 2023 which concluded that a shortage of
accommodation on Mull and Iona has created a major constraint on the economy. 
Solution 
4.15 The Council has agreed as part of the Rural Growth Deal to deliver worker
accommodation on Mull. A Council owned site has been identified at Rockfield
Road, Tobermory and the intention is to deliver 4 properties for workers on the
island through the Rural Growth Deal as a first phase of developing the site. The
Council has secured £700k Island Infrastructure funding from the Scottish
Government (and an additional £100k from Crown Estate Funding and Place
Based Investment Fund) to assist with the design and infrastructure works for the
whole site which will ultimately deliver 12 properties for workers in a phased
manner.  A condition of this grant is that a contract for the first phase of
infrastructure work is agreed by 31st March 2024.  The tendering process is
currently under way.  There is a marginal risk, particularly in view of the recent
experience of high Island construction costs, that the tenders which are received
for the works are above the level of grant award.  In this instance unless that

Page 6

potential gap cost can be covered, it would not be possible to award a contract
within the due date, and the grant funding could be lost.   To mitigate this risk it is
recommended that a contingency for this project of up to £250,000 from the
Strategic Housing Fund be agreed, to be used in the eventuality outlined above. 
Were this grant to be utilised, it is considered likely that it could be recovered from
the Rural Growth Deal funding at a later date.  The grant from the Strategic
Housing Fund is an important contingency to ensure continued progress in
delivery of this phased housing project which is vital to provide worker
accommodation and tackling the housing emergency. 
Background: The Housing Situation in Lorn 
4.16 There are around 9080 homes in the Lorn area of which 11% are deemed
ineffective in terms of meeting local needs i.e. 452 are second/holiday homes and
a further 506 are empty/long term unoccupied (Council Tax Records December
2023).   In addition there are a number of short term holiday lets.  ACHA, West
Highland Housing Association and LINK Housing Association currently provide
1709 properties for social rent which amounts to 19% of the total dwelling stock
or 21% of the occupied stock (RSL Annual Returns 2023). This is below national
levels and indicates a potentially imbalanced housing system with scope for
further growth in the Registered Social Landlord (RSL) sector. 
4.17 Affordability on the open market remains a significant issue for local residents.
The average achieved house price in Lorn is £186,410 which would require a
household income of £53,260 to be considered affordable. As a result at least
75% of local households could not afford to purchase on the open market; and
therefore require alternative affordable options such as social rent and shared
equity. 
4.18 Expressed demand for social rented housing is registered via the HOMEArgyll
waiting list, and there are 589 active applicants with Lorn as first or second area
of preference and have been awarded housing need points (HOMEArgyll Waiting
List December 2023). The demand for social rented stock in recent years has
resulted in a pressure ratio of 3 applicants to every allocation of social housing. 
4.19 The Council has recently appointed an Empty Homes Officer to focus on bringing
empty properties back into use for accommodation for HSCP workers. Initial work
with HSCP has identified a pressure in the Lorn area. A shortage of workers to
deliver health and social care in the community is putting the hospital under
pressure as patients cannot be discharged back to their homes due to a lack of
care provision. 
Solution 
4.20 The Empty Homes Officer has worked with Argyll Community Housing
Association (ACHA) to identify an empty 4 bedroom property in the Lorn area. The
grant or loan from the Strategic Housing Fund will enable this property to be
brought back into use as a Housing of Multiple Occupation for the exclusive use
of health and social care workers. There is an estimated £250,000 of work

Page 7

required to bring the property up to standard including roof replacement and a
new heating system. The Strategic Housing Fund will contribute a grant or loan of
£200,000 to the project and ACHA will contribute the rest of the costs. 
Strategic Housing Fund 
4.21 The closing balance of the Strategic Housing Fund in 2023 was £10.1m as shown
in the table below which was reported to Council 29th June 2023. 
4.22 It can be seen from the table below that there is an estimated surplus in the
SHF over the next five years and Council could give consideration as to how
this could be used to support the housing emergency that has been declared
including the requests within this report which will make a valuable contribution
to tackling identified needs for worker accommodation in the short term. 
4.23 Officers are undertaking an assessment in regard to subsidy control issues and
this will be completed and issues addressed prior to issuing any third party grant
or loan approved by this paper.   
5.0 CONCLUSION 
5.1 The Council is asked to approve the recommendations set out in Section 3.1
based on the evidence supplied within this document with the purpose of enabling
the delivery of worker accommodation on Coll, Tiree, Mull and the Lorn area which

Page 8

will enable the phased delivery of 20 worker accommodation properties. The
Strategic Housing Fund was created to allow for allocations in support of priority
projects emerging from the Local Housing Strategy and the requirement to
address the shortage of worker housing is not only identified within the Local
Housing Strategy but has emerged as a key priority in addressing the Housing
Emergency which was declared in Argyll and Bute in June 2023. 
6.0 IMPLICATIONS 
6.1 Policy - The proposal is consistent with current Council policy including the SHIP
which supports the Local Housing Strategy vision and outcomes which are
directly aligned with the overarching objectives of the Outcome Improvement
Plan, in particular Outcome 2 – we have infrastructure that supports sustainable
growth. The proposal does exceed the delegated Officer approval for the use of
the Strategic Housing Fund to enable the delivery of affordable housing which is
£12,000 per unit. 
The Council declared a Housing Emergency in June 2023 and 1 of the 4 main
areas of concern was the lack of accommodation for workers. The proposals in
this paper address this issue and enable the Council to work with partners to
deliver increased accommodation options both on the mainland and on the
islands in the short term. 
6.2 Financial - There are sufficient funds in the Strategic Housing Fund to support the
proposal as articulated in paras 4.21 & 4.22 and an assessment of Subsidy Control
is being undertaken. 
6.3 Legal - None.   
6.4 HR – Early engagement with NHS and Council HR colleagues indicate need and
demand for worker accommodation in the 4 areas of the local authority identified
in this report. Workforce planning with HSCP and within Council Services has
identified difficulties in recruitment directly due to lack of available and suitable
accommodation.   
6.5 Equalities (Fairer Scotland Duty) - The proposals are consistent with aims and
objectives set out in the local housing strategy, which is subject to an EqSEIA. 
6.5.1 Equalities – protected characteristics - There are targets set within the SHIP to
deliver housing which meet the needs of specialist groups 
6.5.2 Socio-economic Duty - The delivery of affordable housing across Argyll and Bute
facilitates socio-economic opportunities for all. 
6.5.3 Islands - The Housing Needs and Demand Assessment process takes full
account of housing need on the islands. This proposal will enable the delivery of
affordable housing in remote, fragile island communities within the local authority
area.

Page 9

6.6 Risk - Risk assessment is an integral part of each affordable housing development.
The risk of not approving the Strategic Housing Fund request contained in the
report is that the 20 worker accommodation properties in Lorn and the Isles will not
be delivered. 
6.7 Climate Change: The improvement and refurbishment work carried out the
properties detailed in this report will improve energy efficiency with an ambition to
deliver the properties to the current Energy Efficiency Standards for Social
Housing. 
6.8 
6.9  
Customer Service - The proposals will deliver increased access to a range of
suitable, affordable housing options. 
Rights of the Child (UNCRC) – None. 
Kirsty Flanagan, Executive Director with responsibility for Development and
Economic Growth 
Councillor Robin Currie, Policy Lead for Strategic Development 
February 2024 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth   
fergus.murray@argyll-bute.gov.uk 
Matt Mulderrig, Development Policy and Housing Manager 
matt.mulderrig@argyll-bute.gov.uk 
Douglas Whyte, Team Lead – Housing Strategy
douglas.whyte@argyll-bute.gov.uk