WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
PERIOD END DATE
PERIOD 10
Spend to Date Spend to
Date
£000 £000
Red
33 27.7% 10,486 10.4% 33 27.7% 3,854 32.5%
Amber
0 0.0% 0 0.0% 0 0.0% 0 0.0%
Green
86 72.3% 90,064 89.6% 86 72.3% 8,002 67.5%
119 100% 100,550 100% 119 100% 11,856 100%
Budget Spend to
Date
Forecast
Spend
Forecast
Variance Budget Spend to
Date
Forecast
Spend
Actual
Variance Re-profiling Over/ (Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
92,574 10,486 93,291 717 28,487 3,854 6,176 (22,311) (22,404) 93
0 0 0 0 0 0 0 0 0 0
180,347 90,064 174,538 (5,808) 38,089 8,002 25,091 (12,998) (8,084) (4,913)
272,921 100,550 267,829 (5,091) 66,576 11,856 31,267 (35,309) (30,488) (4,820)
(272,921) (100,550) (267,829) 5,091 (66,576) (11,856) (31,267) 35,309
0 0 0 (0) 0 0 0 0
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
TOTAL EXPENDITURE
TOTAL RESOURCES
NET EXPENDITURE
Projects are forecast to be overspent and/or significant delay to
completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green
TOTAL EXPENDITURE
Project Status Analysis
Project Life Financials Current Year Financials
Red
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
31 January 2023
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of Projects
at RAG Status
% Projects at
RAG Status
% Project
Spend at
RAG Status
Number of
Projects at RAG
Status
% Projects at
RAG Status
% Project
Spend at
RAG Status
Red
Projects are forecast to be overspent and/or experience material delay
to completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 9 0 0% 9 0 0%
Current Year Financials 3 0 0% 0 (3) -100%
Project Description
Project Manager Russell Hewton
Chief Officer Russell Hewton
Project Lifecycle 31-Mar-23 31-Mar-23
2
Project Life Financials 0 3 0% 3 3 0%
Current Year Financials 0 3 0% 3 3 0%
Project Description
Project Manager Russell Hewton
Chief Officer Russell Hewton
Project Lifecycle 31-Mar-23 31-Mar-23
3
Project Life Financials 40 5 12% 40 (0) 0%
Current Year Financials 35 0 0% 0 (35) -100%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 30-Sep-23 30-Sep-23
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment
Requisition ICT Equipment.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget remains unspent and is likely to be carried forward into FY 2023/2024.
Mitigating Action
Valuation Joint Board - ICT Refresh FY 22/23
Replacement of laptops, monitors and other ICT equipment.
Planned End Date Forecast End Date
Mitigating Action
None available at this time.
Anticipated Outcome
Replacement of laptops and ICT equipment
None available at this time.
Anticipated Outcome
Requisition of ICT Equipment.
Enhancements to Cash Receipting System
Main Issues / Reason for Variance
Budget was rephased to 2022-2023 as this is a number of mini projects and the first part is the version upgrade which is actively
progressing, currently on phase 2. After this upgrade we can move onto other enhancements which are anticipated to finish in
September 2023. Budget has been reprofiled to FY 2023-2024.
Mitigating Action
None required at this time.
Anticipated Outcome
Enhancements to the cash receipting system including PCI compliant telephone payment system.
Main Issues / Reason for Variance
Replacement of laptops, monitors and other ICT equipment. No further spend anticipated.
To enhance the cash receipting system in the way payments are made and allocated to back
office by increasing the level of security that is required for online payments made by customers
Planned End Date Forecast End Date

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment4
Project Life Financials 60 6 10% 60 0 0%
Current Year Financials 25 1 6% 3 (22) -88%
Project Description
Project Manager Adrian Gray
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 28-Feb-23
5
Project Life Financials 33 0 0% 33 0 0%
Current Year Financials 33 0 0% 0 (33) -100%
Project Description
Project Manager Alan Douglas
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
6
Project Life Financials 61 3 5% 61 (0) 0%
Current Year Financials 55 0 0% 5 (50) -91%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
Mitigating Action
None possible at this time.
Anticipated Outcome
Development of Agresso system later than originally anticipated but within original budget.
Legal Case Management System
Forecast End Date
Main Issues / Reason for Variance
Budget has been rephased from 2021/22.  The project could not proceed as originally planned as Officers are required to access the
office and hardware the system will run on and COVID-19 restrictions have prevented this.  The project will have to go back out to
tender following the upgrade to Microsoft 365.  The project will not be completed in this financial year. 
Mitigating Action
Legal to discuss impact of Microsoft 365 with ICT.
Agresso development
Planned End Date Forecast End Date
Project to be completed in 2023/24.
Planned End Date
The purpose of this project is to carry out an upgrade of the Agresso Finance System which was
last upgraded in 2015. The requirement to upgrade is to maintain a level of support available from
Unit 4 who have advised that support for older versions of the system is being reduced.
Main Issues / Reason for Variance
Continued issues with server space have hampered progress on data clean-up. ICT working on a solution which will allow some
progress prior to financial year-end however upgrade work will need to be paused while Finance are working on20 22-2023 final
accounts. The project will recommence in summer and need to be carried over to 2023-24 financial year.
Legal Case Management System
Mitigating Action
Opportunities to mitigate are limited at this stage. 
Anticipated Outcome
Complete in 2023/24.
Installation of Solar PV at Clydebank Leisure Centre
Installation of Solar PV at Clydebank Leisure Centre.
Planned End Date
Anticipated Outcome
Main Issues / Reason for Variance
Specification delayed due to other priority works. Expect full spend in 2023-2024.
Forecast End Date

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment
7
Project Life Financials 83 0 0% 83 0 0%
Current Year Financials 83 0 0% 5 (78) -94%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-23
8
Project Life Financials 290 63 22% 290 0 0%
Current Year Financials 216 0 0% 2 (214) -99%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-23
9
Project Life Financials 16 14 85% 14 (2) -15%
Current Year Financials 2 0 0% 0 (2) -100%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-23Planned End Date Forecast End Date
Main Issues / Reason for Variance
All meters complient for water loggers. Budget not required.
Mitigating Action
None required
Water Meter Downsize
Water Meter Downsize.
Anticipated Outcome
Delivery of project within budget.
Anticipated Outcome
Main Issues / Reason for Variance
Existing controls have been found to be obsolete and not compatible with a new AHU controls. Additional timelines and work involved.
Design team established and project specification and tender being compiled. Work will be carried out in 2023/2024.
Mitigating Action
All works to be complete in one tender package.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works are integrated with the new Baths refurbishment. Received and approved initial design proposals from Vital. Waiting on final
design and costings. Works to be complete by 31 March 2023 to compliment the district heating installation.
Mitigating Action
None available at this time.
Replace existing main hall Air Handling unit at Clydebank Town Hall
Replace existing main hall Air Handling unit at Clydebank Town Hall.
Anticipated Outcome
Physical works being carried out by 31/3/23.
Leisure Energy projects - air handling units, upgrade lighting, circulating pumps, and draught proofing
All works to be completed next financial year 2023/24.
Measures to be installed at both Meadow Centre & Vale of Leven Swimming Pool; new pool hall
Air Handling Units, upgrade lighting, circulating pumps Vale of Leven Swimming Pool, internal and
external lighting and draught proofing.

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment
10
Project Life Financials 2,188 462 21% 1,651 (538) -25%
Current Year Financials 1,651 462 28% 775 (876) -53%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
11
Project Life Financials 750 0 0% 0 (750) -100%
Current Year Financials 750 0 0% 0 (750) -100%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Dec-22 30-Jun-23
None available at this time.
Anticipated Outcome
Improved town centres and strategic sites across West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Due to factors outwith the Council's control, progress couldn’t be made on a timeline that would be acceptable to funders and as a
result Scottish Government will withdraw the grant offer.
Mitigating Action
None available at this time.
Anticipated Outcome
Viresco Studios and Arts Centre
Viresco Studios and Arts Centre in Alexandria, aimed to encourage wider participation in the arts,
creative enterprises and cultural activity in West Dunbartonshire.
Project will not go ahead.
Regeneration/Local Economic Development
Budget to facilitate the delivery of Regeneration throughout West Dunbartonshire, aligned to the
Economic Strategy. External funding will be sought to maximise opportunities for redevelopment
of these sites.
Forecast End Date
Main Issues / Reason for Variance
LED budget is invested across our town centres and strategic sites and is used to develop and implement projects as well as providing
match funding to lever in external funding. During 2022/2023 the key projects to be developed and delivered include a contribution
towards Smollett Fountain public realm,  development costs associated with Dumbarton Waterfront, the Arc of Attraction Strategy and
in Clydebank implementation of the Development Framework Activity Centre in Clydebank will be delivered in 2023/2024. Many
regeneration projects are subject to factors outwith Council control and close monitoring of the programming is required. Enabling
works at Mitchell Way  have been delayed as they are subject to the timescale of the developer. A contingency is included for
increasing costs and new funding opportunities.
Mitigating Action
Planned End Date

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment12
Project Life Financials 747 40 5% 747 0 0%
Current Year Financials 747 40 5% 90 (657) -88%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Dec-22 30-Jun-23
13
Project Life Financials 22,213 2,065 9% 22,100 (113) -1%
Current Year Financials 7,465 297 4% 680 (6,785) -91%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-25 31-Mar-25
14
Project Life Financials 11,220 0 0% 11,220 0 0%
Current Year Financials 3,720 0 0% 0 (3,720) -100%
Project Description
Project Manager Craig Jardine
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Kier is appointed to design and deliver the Activities Centre at Clydebank Town Centre. Design of the project is underway and a
commencement date for construction has been confirmed as April 2023. The budget will slip into 2023-2024 however some spend on
design development expected in the current financial year.
There were delays to Connecting Dumbarton (due to procurement issues) and Glencairn House (design development issues) resulting
in reduced projected spend for 2022/2023. A future programme for the Artizan Centre based on the Development Strategy report was
reported to IRED in September 2022. Costs will continue to be monitored by the LUF Project Board.
Mitigating Action
None available at this time.
Anticipated Outcome
Main Issues / Reason for Variance
Network expansion to GJNH (Golden Jubilee National Hospital) will commence pending approval to proceed by the GJNH Board.
Budget to be reprofiled to next financial year.
Mitigating Action
None available at this time.
Anticipated Outcome
New community-run activities centre in Clydebank Town Centre.
Project will be delivered on budget.
District Heating Network Expansion
District Heating Network Expansion.
Planned End Date Forecast End Date
LUF
Year one LUF spend includes acquisition cost of Artizan Centre, and design development for
Glencairn House and Connecting Dumbarton
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Clydebank Can On The Canal
New activities centre in Clydebank Town Centre.
Anticipated Outcome
Mitigating Action
None available at this time.
Redevelopment of the Dumbarton Town Centre
Planned End Date Forecast End Date

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment
15
Project Life Financials 1,590 0 0% 1,590 0 0%
Current Year Financials 1,590 0 0% 0 (1,590) -100%
Project Description
Project Manager Michelle Lynn/ Sarah Christie
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-24 31-Mar-24
16
Project Life Financials 8,535 299 4% 8,535 (0) 0%
Current Year Financials 1,715 180 10% 750 (965) -56%
Project Description
Project Manager Sharon Jump/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-25 31-Mar-25
17
Project Life Financials 382 388 102% 388 6 2%
Current Year Financials 0 6 0% 6 6 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-21 31-Mar-21
Mitigating Action
None available at this time.
Anticipated Outcome
New sports changing facility completed.
New Sports Changing Facility at Duntocher
New Sports Changing Facility at Duntocher
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project completed over budget due to ground conditions on site.  Final costs now charged.
Project business case will be brought back to project board, IRED and Council.
Depot Rationalisation
Depot Rationalisation.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Design Team have been appointed to develop feasibility options for the DRP Project, currently in stage 1 of this phase reviewing
service requirements.  The conclusion of the feasibility report will provide input for the options appraisal exercise.  The intention would
be to bring a business case to a future IRED Committee in 2023.
Mitigating Action
None available at this time.
Anticipated Outcome
Main Issues / Reason for Variance
This project is linked to Glencairn House and Depot Rationalisation and will free up the current museum store and office space in
Poplar Road. Opportunities exist to attract external funding. Detailed design work will not commence until Spring 2023.
Mitigating Action
None available at this time.
Anticipated Outcome
Re-development of Strathleven Place
Strathleven Place
Re-development of Strathleven.
Planned End Date Forecast End Date

Page 8

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment
18
Project Life Financials 2,375 87 4% 2,375 (0) 0%
Current Year Financials 1,090 3 0% 28 (1,063) -97%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-24
19
Project Life Financials 78 0 0% 0 (78) -100%
Current Year Financials 78 0 0% 0 (78) -100%
Project Description
Project Manager Martin Feeney
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-23 31-Mar-23
20
Project Life Financials 45 0 0% 0 (45) -100%
Current Year Financials 45 0 0% 0 (45) -100%
Project Description
Project Manager Martin Feeney
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
This budget is no longer required.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within budget.
Anticipated Outcome
Project delivered within budget.
Elevated Platforms (Building Services)
Elevated Platforms (Building Services).
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget is no longer required.
Mitigating Action
None available at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
New build community facility.
Purchase of 3 Welfare Units
The purchase of 3 Welfare Units as a spend-to-save proposal.
New Westbridgend Community Centre
New Westbridgend Community Centre
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Various delays due to Covid and other utility issues. Planning was previously delayed but now resolved. Building warrant applications
submitted and tender to be issued. Anticipated to be onsite by April 2023.

Page 9

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment
21
Project Life Financials 400 47 12% 222 (178) -44%
Current Year Financials 357 3 1% 100 (257) -72%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Oct-23 31-Oct-23
22
Project Life Financials 2,712 4,075 150% 4,266 1,555 57%
Current Year Financials 910 1,708 188% 1,900 990 109%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-23
Posties Park Sports Hub - New sports hub to include gym & running track
Creation of a sports hub at Posties/Marinecraft to include a new changing pavilion/Gym, new all-
weather 6 lane running track, conversion of blaze sports pitch to grass, new fencing, upgrade of
existing floodlights and additional car parking.  This combines the budget approved by the Council
in February 2015 for Community Sports Facilities at Posties Park, draw down of budget from the
generic sports facilities budget line.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project start was delayed due to planning issues and COVID-19 restrictions. Work commenced January 2021 with a proposed
completion date of March 2022 which has been extended to May 2023 due to design changes required by Planning. There is still a
significant amount of work to be undertaken to complete the project and the cost of this work has been affected by Covid, Brexit and
supply chain issues. Additional budget will be required to complete this project.
Mitigating Action
None required at this time.
Anticipated Outcome
New all weather running track and gymnasium.
Anticipated Outcome
Two new allotment sites with 80 plots and community growing space.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Two sites are being developed at Dillichip Loan Bonhill and Overburn Dumbarton. These sites will provide eighty traditional allotment
plots together with community food growing facilities. It is anticipated that project works will commence in June 2023 with a completion
date of October 2023. This project has successfully attracted £0.1 from Scottish Government Vacant and Derelict Land Fund. As
agreed at Council on 22 December 2022 the budget has been reduced by £178k.
Mitigating Action
None available at this time.
Allotment Development
To develop an allotment site.

Page 10

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment23
Project Life Financials 817 286 35% 817 (0) 0%
Current Year Financials 553 23 4% 150 (403) -73%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
24
Project Life Financials 217 3 1% 217 0 0%
Current Year Financials 214 0 0% 0 (214) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
25
Project Life Financials 400 358 90% 400 0 0%
Current Year Financials 42 0 0% 0 (42) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
Main Issues / Reason for Variance
Project is now being developed for tendering, with project commencing May 2023 and completion expected by 31 March 2024.  It is
anticipated that £0.150m will be spent this financial year mainly on consultant costs and enabling works.
Mitigating Action
None available at this time.
Anticipated Outcome
Extension to existing cemetery providing a sustainable burial environment.
Vale of Leven Cemetery Extension
Extension of existing cemetery in Vale of Leven.
Planned End Date Forecast End Date
Anticipated Outcome
To improve journey times and reliability of bus services.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Officers working with external partners to identify projects to support funding. Investigation on going however unlikely works will be
able to progress this financial year.
Mitigating Action
None required at this time.
Bus Rapid Deployment Fund
Funding has been awarded from Sustrans to assist with social distancing measures required as a
result of the COVID-19 pandemic.
Auld Street Clydebank - Bond
Completion of roadworks associated with Auld Street housing development. Creation of a footpath
to Golden Jubilee Hospital.
Planned End Date Forecast End Date
To complete remaining civil works required.
Road construction works completed in previous years. Remaining funds are insufficient to complete footpath construction. Works on
hold until such time as additional funds can be secured.
Mitigating Action
None available at this time.
Anticipated Outcome

Page 11

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment26
Project Life Financials 12 17 134% 17 4 34%
Current Year Financials 12 17 134% 17 4 34%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
27
Project Life Financials 1,000 0 0% 1,000 0 0%
Current Year Financials 1,000 0 0% 0 (1,000) -100%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Main Issues / Reason for Variance
Budget will be used for any service work carried out by Scottish Power before or after column replacement works.
Mitigating Action
None available at this time.
Anticipated Outcome
Intention is to complete works within budget.
Street lighting and associated electrical infrastructure
WDC is responsible for the maintenance of 18,000 street lighting columns and associated
illuminated signs and bollards.  This budget is required for this infrastructure.
Planned End Date Forecast End Date
Vehicle Replacement Strategy
Replacement of refuse collection vehicles.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Larger vehicles will be delayed due to supply chain issues. Delivery timescales anticipated at 18 months.
Mitigating Action
None available.
Anticipated Outcome
Replacement of refuse collection vehicles.

Page 12

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment28
Project Life Financials 2,817 460 16% 2,817 0 0%
Current Year Financials 2,817 460 16% 600 (2,217) -79%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
29
Project Life Financials 1,980 0 0% 1,980 0 0%
Current Year Financials 180 0 0% 45 (135) -75%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Vehicle Replacement
Replacement of vehicles which have reached end of programmed lifespan (7 year heavy vehicles,
10 year light vehicles).
Anticipated Outcome
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Vehicles are being ordered for delivery in this financial year but larger vehicles will be delayed into financial year 2023/2024.
Mitigating Action
None Required.
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within budget.
Waste Transfer Station
The design, development and construction of a recycling and bulk waste transfer facility that will
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultant project nearing completion and spend will be made thereafter.
Replacement of fleet within budget.

Page 13

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment30
Project Life Financials 29,450 659 2% 29,450 (0) 0%
Current Year Financials 2,797 563 20% 800 (1,997) -71%
Project Description
Project Manager Sharon Jump/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-26 31-Mar-26
31
Project Life Financials 750 638 85% 750 0 0%
Current Year Financials 113 1 1% 0 (113) -100%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
Schools Estate Improvement Plan - next Phase - Faifley Campus
Improvement of Schools Estate.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The next phase of the Schools Estate Improvement Plan involves the development of a new Campus provision in the Faifley area.
WDC has been successful in securing funding from the Scottish Government Learning Estate Improvement Programme. SFT
confirmed the indicative funding allocation for this project at £18.416m on the 4 May 2021, this will be received as a revenue stream
over the 25 years of the Scottish Government financial support (subject to the Council adhering to the funding criteria). Site Options
Appraisal has taken place and Members approved the recommendation to proceed with the new Faifley Campus on the St Joseph's
site at Education Committee on 9th June 2021.  The design team and main contractor have been appointed and the next phase will
see the design development for the new Campus taking place. The statutory consultation process was launched in September 2021
and a report was brought back to the Educational Services committee in March 2022 concluding the process. RIBA Stage 2 Design
development slightly behind programme but this will not have an impact on the overall Phase 1 completion date for the project.
Mitigating Action
None available at this time.
Forecast End Date
Main Issues / Reason for Variance
A new contractor has been appointed and looking at the programme of works.
Mitigating Action
None available at this time.
Delivery of the project will be on time.
Anticipated Outcome
Anticipated Outcome
Project delivered on budget.
Planned End Date
Choices Programme - to assist young people who require additional support
Bringing together Central Support Services which will include relocation of Choices Programme.

Page 14

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment32
Project Life Financials 924 0 0% 924 0 0%
Current Year Financials 154 0 0% 40 (114) -74%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-23 31-Mar-23
33
Project Life Financials 379 42 11% 425 46 12%
Current Year Financials 0 0 0% 46 46 0%
Project Description
Project Manager Arun Menon
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-30 31-Mar-30
Mitigating Action
None available at this time
Main Issues / Reason for Variance
Work continues on developments resulting in some spend in the current year.
Mitigating Action
None required.
Anticipated Outcome
Development of Workforce Management System.
Development of Workforce Management System
Project to develop the Workforce Management System.
Planned End Date Forecast End Date
Community Alarm upgrade
To upgrade Community Alarm
Planned End Date
Anticipated Outcome
Forecast End Date
Main Issues / Reason for Variance
Work is ongoing with HR colleagues in order to appoint a project manager to this post and it is anticipated that spend will progress in
the final half of the financial year.
Community Alarm Upgrade

Page 15

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 30 10 33% 20 (10) -33%
Current Year Financials 30 10 33% 16 (14) -47%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-24 31-Mar-24
2
Project Life Financials 50 43 86% 51 1 1%
Current Year Financials 7 0 0% 8 1 10%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-23
3
Project Life Financials 5 0 0% 5 0 0%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Jackie Nicol Thomson
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-23
IFRS 16 Database
This is a system which will ensure that WDC has the correct level of information and adheres to correct
reporting of IFRS16 - Leasing. 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The purchase of software to allow new accounting treatment of leases to be appropriately reported is on track. Full spend anticipated FY
2022/2023.
Mitigating Action
None required
Anticipated Outcome
Purchase of software for accounting for leases.
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Payment Card Industry Data Security Standard (PCIDSS)
Module would ensure that WDC were compliant with the current requirements of PCIDSS for card payments
without the need for numerous costly workarounds
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget was rephased to 2022-2023 as version upgrade of the Council's cash receipting system is required beforehand and is currently
underway. The Module for this has been secured and anticipated timescales for Go Live is May 2023. Initial project meeting has taken place and
system installed in test, work in progress to test and sign off by May 2023. As agreed at Council on 21 December 2023 this budget has been
Anticipated Outcome
Upgraded Electronic Insurance System.
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Upgraded version with PCI compliant telephone payment system.
Electronic Insurance System
Acquisition of a claims/incident management system supported by an electronic document management
system.
Main Issues / Reason for Variance
The various claim forms and departmental reports have been reviewed and updated and the relevant online request forms were submitted to the
Digital Sub-Group to be converted to Online Achieve Forms.  The various claim forms and departmental reports have now been converted to
Online Achieve Forms and are in the process of being tested. Once complete, the supplier will take matters forward with their design team. An
anticipated timeline for completion of the project, taking into account the various stages i.e. development, testing, going live etc. will be drawn up
in conjunction with the supplier at that time.  Budget spend anticipated in 2022/23.
Mitigating Action
None required at this time.

Page 16

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
4
Project Life Financials 1,000 141 14% 1,000 0 0%
Current Year Financials 1,000 141 14% 250 (750) -75%
Project Description
Project Manager Gillian McNeilly
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-23
5
Project Life Financials 53 13 25% 53 0 0%
Current Year Financials 33 0 0% 33 0 0%
Project Description
Project Manager Alan Douglas
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
6
Project Life Financials 30 10 33% 30 0 0%
Current Year Financials 10 10 100% 10 0 0%
Project Description
Project Manager Pamela Clifford
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-23
Anticipated Outcome
Preservation of Historic Site.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Council's capital contribution towards the multi-partner (five local authorities and Historic Environment Scotland) Rediscovering the Antonine Wall
project.
Mitigating Action
None Required.
Re -imagine Antonine Wall  
Council's capital contribution towards the multi-partner (five local authorities and Historic Environment
Scotland) Rediscovering the Antonine Wall project which is also funded by the Heritage Lottery Fund.
Trainee solicitor in place. Budget will be fully spent.
Mitigating Action
None required at this time.
Anticipated Outcome
Solicitor support for Capital Projects, with full budget spend anticipated.
Cost of Living
To support Council and community organisations with capital costs for cost of living initiatives.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Working Group currently developing proposals for initiative. The budget will be spread equally over four years and £0.75m has been rephased.
Mitigating Action
None required
Anticipated Outcome
Initialive will assist with cost of living crisis
Main Issues / Reason for Variance
Solicitor Project Support for Capital Projects
Solicitor costs to directly support capital projects
Planned End Date Forecast End Date

Page 17

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
7
Project Life Financials 155 0 0% 155 0 0%
Current Year Financials 155 0 0% 155 0 0%
Project Description
Project Manager Pamela Clifford
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-23
8
Project Life Financials 342 238 69% 347 5 1%
Current Year Financials 110 1 1% 1 (109) -99%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
9
Project Life Financials 20 14 69% 20 0 0%
Current Year Financials 7 1 9% 7 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None required.
Anticipated Outcome
Delivery of project with full budget spend.
Replace failed heating controls/valves & recommission
Replace failed heating controls/valves & recommission.
Planned End Date Actual End Date
Main Issues / Reason for Variance
Further works ordered. Expect full spend by 31 March 2023.
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress beyond committed expenditure.
Mitigating Action
None required.
Anticipated Outcome
Project will be removed as agreed at Council on 21st December 2022.
Replace obsolete boilers (plant greater than 30 years old).
Replace obsolete boilers (plant greater than 30 years old).
Planned End Date Forecast End Date
Demolition 215 Main Street Alexandria
Demolition of 215 Main Street Alexandria.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Emergency works carried out to former St Andrews Church resulting in complete demoliton to remove a dangerous structure. Budget was agreed
by special powers.
Mitigating Action
None Required.
Anticipated Outcome
Demolition of unsafe building

Page 18

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
10
Project Life Financials 80 21 27% 50 (30) -37%
Current Year Financials 61 3 4% 10 (51) -84%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
11
Project Life Financials 85 55 64% 55 (30) -36%
Current Year Financials 30 0 0% 0 (30) -100%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None required.
Anticipated Outcome
Project will be removed as agreed at Council on 21st December 2022.
Automatic Meter Readers - Water
Automatic Meter Readers.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress beyond committed expenditure.
Mitigating Action
None required.
Anticipated Outcome
Project will be removed as agreed at Council on 21st December 2022 once committed projects have been completed.
Energy Projects quick wins
Spend to Save projects.
Planned End Date Forecast End Date

Page 19

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
12
Project Life Financials 344 86 25% 101 (243) -71%
Current Year Financials 258 0 0% 15 (243) -94%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
13
Project Life Financials 160 0 0% 28 (132) -83%
Current Year Financials 152 0 0% 20 (132) -87%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
14
Project Life Financials 50 9 18% 9 (41) -82%
Current Year Financials 50 9 18% 9 (41) -82%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None required.
Anticipated Outcome
Project will be removed as agreed at Council on 21st December 2022.
Main Issues / Reason for Variance
Forecast End Date
Lighting upgrades to LED in schools and Corporate buildings
Upgrade lighting in schools and corporate buildings.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.
Mitigating Action
None required.
Anticipated Outcome
Project will be removed as agreed at Council on 21st December 2022.
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.
Upgrade obsolete heating controls (BEMS) across Council estate
Upgrade obsolete heating controls (BEMS) across Council estate.
Planned End Date
Zero Carbon Fund
Zero Carbon Fund.
Anticipated Outcome
Project will be removed as agreed at Council on 21st December 2022.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.
Mitigating Action
None required.

Page 20

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
15
Project Life Financials 9,982 4,987 50% 9,997 15 0%
Current Year Financials 2,423 89 4% 90 (2,333) -96%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
16
Project Life Financials 1,166 1,166 100% 1,166 0 0%
Current Year Financials 143 143 100% 143 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-23
17
Project Life Financials 1,456 780 54% 1,456 0 0%
Current Year Financials 1,317 641 49% 991 (326) -25%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-23
Anticipated Outcome
Progress towards delivery of planned projects from Economic Development Strategy and Charrette Action Plans albeit later than originally
anticipated.
Town Centre Fund
Scottish Government funding to help improve local town centres.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The remaining Town Centre Fund will be spent on the Smollett Fountain public realm works which will be completed by the end of the financial
year.
Mitigating Action
None available at this time.
Anticipated Outcome
Regenerated Town Centres.
Mitigating Action
Programme involves  expenditure over a number of projects led by different services. Regular reporting between services will help early
identification of risk.
Anticipated Outcome
Place-based improvements that advance Scottish Government's priorities of 20 minute neighbourhoods and carbon zero.
Place Based Investment Programme
Scottish Government Funding to establish a Place-Based Investment Programme to ensure that all place
based investments are shaped by the needs and aspirations of local communities.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The budget includes a £0.641m contribution to Titan Boulevard at Queens Quay and £0.676m towards implementation of Alexandria Masterplan
projects.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The remaining Regeneration Fund projects are Dumbarton Waterfront Path; the contribution towards the costs of Glencairn House; Connecting
Dumbarton; and the Scottish Marine Technology Park at the former Carless site. As Levelling Up Fund is programmed to be spent before
Regeneration Fund for Glencairn House and Connecting Dumbarton, it is not anticipated that any Regeneration Fund will be spent on these
projects during this financial year and will be carried forward. Spend against The £2.0m Clyde Mission funding for SMTP will continue during the
financial year 2022/2023 before an agreement is reached on the £2.0m of Regeneration Fund investment. Dumbarton Waterfront Path will be
developed according to landowner timescales, and there is no spend anticipated in 22/23.
Mitigating Action
Programme management approach to delivery.
Regeneration Fund
Funding to implement major regeneration projects linked to community charrettes.

Page 21

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
18
Project Life Financials 125 99 79% 125 0 0%
Current Year Financials 69 42 62% 69 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 30-Jun-23
19
Project Life Financials 34,050 2,908 9% 34,049 (1) 0%
Current Year Financials 986 228 23% 1,304 318 32%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-27 31-Mar-27
20
Project Life Financials 15 4 24% 4 (11) -76%
Current Year Financials 11 0 0% 0 (11) -100%
Project Description
Project Manager Stephen Daly
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-23 31-Mar-23
Anticipated Outcome
Project will be removed as agreed at Council on 21st December 2022.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.
Mitigating Action
None required.
Mitigating Action
None required.
Anticipated Outcome
Delivery of the project on time and within the increased budget.
Telephone System Upgrade
To improve Housing Repairs telephone platform for incoming calls, providing improved Management
Information.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Regular updates are provided at every Council meeting and monthly Project Board meetings and to City Deal.  The main issues contained within
the new Council's approved Outline Business Case are still valid, which include Exxon's remediation strategy, land transfer arrangements and
issues relating to adjoining owners.  WDC Consultants are monitoring the remediation process to ensure compliance with specification, also
Esso are independently monitoring the remediation works.  Final Business Case submission is June 2023. Through the Scape framework we are
working closely with Balfour Beatty to achieve a formal pre construction agreement to allow the detailed design works to commence and the full
construction programme to be developed. Agreements in principle are progressing with third party land owners.
Levelling Up
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and
transformational regeneration.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This capacity funding was awarded by UK Government to assist with development of LUF bids. WDC has been awarded a grant from LUF
Round 1 and the capacity funding will be used in part to produce Artizan Centre redevelopment options. The balance will be used for
Roads/Transportation to develop a major transportation bid for LUF2.
Mitigating Action
None available at this time.
Anticipated Outcome
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and transformational regeneration.
Exxon City Deal
As part of the City Deal project the WDC Exxon site at Bowling regeneration with alternative A82 route
included.

Page 22

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
21
Project Life Financials 421 300 71% 421 (0) 0%
Current Year Financials 91 71 77% 71 (21) -22%
Project Description
Project Manager David Main
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-24 31-Mar-24
22
Project Life Financials 3,998 1,353 34% 4,010 13 0%
Current Year Financials 1,673 166 10% 1,672 (1) 0%
Project Description
Project Manager Sarah Christie/Michelle Lynn
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-23 31-Mar-23
23
Project Life Financials 40 0 0% 0 (40) -100%
Current Year Financials 40 0 0% 0 (40) -100%
Project Description
Project Manager John Anderson
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None required.
Anticipated Outcome
Project will be removed as agreed at Council on 21st December 2022.
Alexandria Community Centre Sports Hall re-flooring
Alexandria Community Centre Sports Hall re-flooring
Planned End Date Forecast End Date
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.
Heritage Capital Fund
Heritage Capital Fund.
Main Issues / Reason for Variance
Work is underway to progress furniture replacement at Dumbarton, Duntocher and Parkhall libraries during 2022/2023.  Budget has been
rephased to next financial year for Dalmuir library as work is currently scheduled for 2023/2024.
Mitigating Action
None required.
Anticipated Outcome
Project carried forward to align with Asset Management programme.
Anticipated Outcome
Project to be delivered on budget and within revised timescale.
Planned End Date Forecast End Date
None available at this time.
Transformation of Infrastructure Libraries and Museums
To improve performance and efficiency of Council's Libraries and Cultural Services.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The original projected spend has been affected by internal and external delays due to the Covid 19 recovery, a reduction in the scope of the
Clydebank Town Hall project, a change in the delivery date for the Clydebank Museum at Clydebank Library during the contract award stage,
while the new Dalmuir Library and Gallery had to be rescheduled for approval in August 2021. Officers are now making progress to get projects
back on track, projects will still be delivered in full, and a review of optimism bias will be undertaken in the projections for 2022/23. As agreed at
Council on 21 December 2022 the budget has been reducd and the project will not ncontinue beyond 2022/23.
Mitigating Action

Page 23

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
24
Project Life Financials 1,912 1,984 104% 1,912 0 0%
Current Year Financials 1,912 1,984 104% 1,984 73 4%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-23 31-Mar-23
25
Project Life Financials 350 9 3% 350 0 0%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-24 31-Mar-24
26
Project Life Financials 150 16 11% 150 0 0%
Current Year Financials 134 0 0% 134 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-21 31-Mar-23
Anticipated Outcome
To deliver new sports changing facility.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project had been delayed due to a number of COVID-19 related issues and utilities issues.  Unit is now in production but delay to site due to the
utility disconnection and demolition works. Demolition works complete and waiting for a date for installation.
Mitigating Action
None available at this time.
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
Main Issues / Reason for Variance
The budget for this project has been rephased to FY 2023/2024.
Mitigating Action
None available at this time.
Anticipated Outcome
To deliver new sports changing facility.
Anticipated Outcome
Full budget spend anticipated.
New Sports Changing Facility Dumbarton West (Old OLSP site) 
New Sports Changing Facility Dumbarton West (Old OLSP site) 
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works progressing.
Mitigating Action
None available at this time.
Building Upgrades and H&S - lifecycle & reactive building upgrades
Lifecycle and reactive building upgrades.

Page 24

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
27
Project Life Financials 750 750 100% 750 0 0%
Current Year Financials 86 86 100% 86 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-23
28
Project Life Financials 150 0 0% 0 (150) -100%
Current Year Financials 150 0 0% 0 (150) -100%
Project Description
Project Manager Michelle Lynn
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-25 31-Mar-25
29
Project Life Financials 912 832 91% 912 0 0%
Current Year Financials 80 35 44% 80 0 0%
Project Description
Project Manager Elaine Troup
Chief Officer Peter Barry
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None required at this time.
Anticipated Outcome
Full spend is anticipated on this year's budget.
Invest in "Your Community Initiative"
Capital budget to support the roll out of Your Community,  an initiative designed to achieve coordinated
service delivery in response to community need. This is complimented by community capacity building,
empowering WD citizens to do more for their own communities (leading to less reliance on council).  Also
included is the implementation of participatory budgeting to support and build capacity in communities.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Application process is planned for later in this financial year.
Changing Places Toilet Provision
Changing places toilet provision in various public buildings.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.
Mitigating Action
None required.
Anticipated Outcome
Project will be removed as agreed at Council on 21st December 2022.
Main Issues / Reason for Variance
Project now complete.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered on budget.
Holm Park & Yoker Athletic FC
Develop a new 3G pitch to act as a home venue for Clydebank FC with extensive community access.
Planned End Date Forecast End Date

Page 25

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
30
Project Life Financials 100 27 27% 87 (13) -13%
Current Year Financials 17 4 25% 4 (13) -75%
Project Description
Project Manager Graham Watters
Chief Officer Peter Barry
Project Lifecycle 31-Mar-30 31-Mar-30
31
Project Life Financials 200 0 0% 200 0 0%
Current Year Financials 50 0 0% 50 0 0%
Project Description
Project Manager John Kerr
Chief Officer Peter Barry
Project Lifecycle 31-Mar-30 31-Mar-30
32
Project Life Financials 405 37 9% 405 0 0%
Current Year Financials 405 37 9% 405 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None required at this time.
Anticipated Outcome
Better access with parks, cemeteries and open spaces.
Public non-adopted paths and roads
Upgrades to drainage and lighting to enhance the lifespan of paths and roads within  facilities in public parks,
cemeteries and civic spaces.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects are currently being developed to deliver better access in our parks, cemeteries and open spaces. Full budget spend anticipated in
2022/2023.
Main Issues / Reason for Variance
The Council is currently trying to secure new funding to provide new accommodation within the Dennystoun Forge site. This may require some
redesign of the existing site and has resulted in proposed works to provide additional play and security measures being held until future design
proposals are confirmed.
Mitigating Action
Officers carried out some proactive consultative work to establish the tenant priorities this will allow the work programme to be developed
timeously.
Anticipated Outcome
It is expected the works programme  will be completed during 2022/2023.
Anticipated Outcome
Project will be removed as agreed at Council on 21st December 2022.
Dennystoun Forge Site Improvements
Dennystoun Forge Site Improvements
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.
Mitigating Action
None required.
Integrated Housing Management System
Development of IHMS system.

Page 26

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
33
Project Life Financials 1,726 1,724 100% 1,726 0 0%
Current Year Financials 13 11 83% 13 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
34
Project Life Financials 50 37 73% 50 (0) 0%
Current Year Financials 13 0 0% 13 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
35
Project Life Financials 220 214 97% 220 0 0%
Current Year Financials 7 0 0% 7 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 03-Apr-21 31-Mar-22
Anticipated Outcome
Improvements to the environment of West Dunbartonshire.
Kilmaronock Cemetery Extension
Extension of existing cemetery at Kilmaronock. 
Planned End Date Actual End Date
Anticipated Outcome
Sustainable burial environment for local residents.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
None required at this time.
Environmental Improvement Fund
This fund has been created to deliver environmental improvement projects for communities throughout West
Dunbartonshire.
Planned End Date Forecast End Date
This budget will be used to develop an area of the existing Cemetery for additional burials.  Project scope has now been developed and will be
tendered under the minor civils framework.  Budget spend anticipated in 2022/2023.
Mitigating Action
None required at this time.
Anticipated Outcome
New all weather tennis courts.
Project works complete.  Retentions to be paid in 2022/2023.
Mitigating Action
None required at this time.
Main Issues / Reason for Variance
Sports Facilities Upgrades - Argyll Park - Construction of 3 All Weather Tennis Courts
Project is part of wider investment in sporting facilities and is dependent on match funding from Sports
Scotland. Agreement in principle to wider WDC strategic priorities.
Main Issues / Reason for Variance
Remaining budget rephased from 2021/2022 to progress with tree planting in 2022/2023 in line with the Councils Climate Change and
Biodiversity action plans.  Full budget spend anticipated.

Page 27

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
36
Project Life Financials 200 0 0% 200 0 0%
Current Year Financials 30 0 0% 30 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
37
Project Life Financials 1,444 59 4% 1,444 (0) 0%
Current Year Financials 201 0 0% 201 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
38
Project Life Financials 210 0 0% 210 0 0%
Current Year Financials 10 0 0% 10 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 30-Nov-23 30-Nov-23
Development of play areas to improve accessibility and inclusiveness of play areas throughout West Dunbartonshire. Projects are being
developed for implementation over the next five years.
Mitigating Action
None required at this time.
Anticipated Outcome
Renewal of play parks
East End Park Resurfacing
Resurfacing of 3G pitch at East End Park.
Main Issues / Reason for Variance
Planned End Date Forecast End Date
Play Parks Grant Funding
Renew and replace play park equipment
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultant and design team fees for resurfacing of 3G pitch at East End Park.
Mitigating Action
None required.
Anticipated Outcome
Resurfacing of 3G pitch at East End Park.
Balloch Mountain Bike Track
Develop a mountain bike skills trail at Balloch Castle Country Park.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Design fees to develop Mountain bike skills trail in Balloch country park. Application will be submitted to Sport Scotland for match funding. Project
to commence April 2023 and works to be complete by November 2023.
Mitigating Action
None required at this time.
Anticipated Outcome
Mountain bike track

Page 28

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
39
Project Life Financials 25 19 75% 25 0 0%
Current Year Financials 25 19 75% 25 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
40
Project Life Financials 228 55 24% 228 0 0%
Current Year Financials 228 55 24% 228 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
41
Project Life Financials 740 350 47% 350 (390) -53%
Current Year Financials 390 0 0% 0 (390) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Jul-22 31-Jul-22
Nature Restoration Fund
Spaces for People
Mitigating Action
None required at this time.
Planned End Date
Anticipated Outcome
To provide people of West Dunbartonshire additional space to help adhere to social distancing guidelines.
Supply and install extra large litter bins as a pilot project within hotspot problem areas. Project has commenced and completion is anticipated by
March 2023.
Mitigating Action
None required at this time.
Anticipated Outcome
Nature resource for Faifley Community
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Large bins provided for high traffic areas
Nature resource for Faifley Community
Large bins for high traffic areas (pilot)
Supply and install extra large litter bins as a pilot project within hotspot problem areas.
Planned End Date Forecast End Date
Funding has been awarded from Sustrans to assist with social distancing measures required as a result of
the COVID-19 pandemic.
Funding received from Nature Restoration Fund to build nature resource for Faifley community has been completed and additional funding has
been received and projects are currently being developed and to be delivered by March 2023.
Mitigating Action
None required at this time.
Anticipated Outcome
Main Issues / Reason for Variance
Forecast End Date
Main Issues / Reason for Variance
The programme is now complete and there will be no further expenditure.

Page 29

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
42
Project Life Financials 683 6 1% 572 (110) -16%
Current Year Financials 683 6 1% 400 (283) -41%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
43
Project Life Financials 203 0 0% 107 (96) -47%
Current Year Financials 107 0 0% 0 (107) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
44
Project Life Financials 200 0 0% 5 (195) -97%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget to be used for retention payment from last years surfacing of Dumbarton East footways.
Mitigating Action
None required at this time.
Forecast End Date
Main Issues / Reason for Variance
Projects and locations still to be decided.
Main Issues / Reason for Variance
To develop projects including Balloch Cycle Way (Pier Road to Mollanbowie/Boturich Road), and other projects principally around National Cycle
Network 7 including Angus Street/Bonhill Bridge and Atlus Street/Cart Street, Clydebank and pedestrian dropped kerbs.
Mitigating Action
None required at this time.
Anticipated Outcome
To improve connectivity and enhanced Cycling routes within West Dunbartonshire.
Anticipated Outcome
To improve Footways in West Dunbartonshire.
Mitigating Action
None required at this time.
Anticipated Outcome
To improve Footways in West Dunbartonshire.
Additional Pavement Improvements
Extra funding to accelerate pavement maintenance and improvements across West Dunbartonshire.
Footways/Cycle Path Upgrades
Renewal and/or enhancement of failed footpaths/cycle paths through West Dunbartonshire.
Planned End Date
Cycling, Walking and Safer Streets
Introduction of enhanced walking routes and traffic calming schemes to introduce safer streets within West
Dunbartonshire.
Planned End Date Forecast End Date

Page 30

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
45
Project Life Financials 60 55 91% 60 0 0%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
46
Project Life Financials 314 215 68% 314 (0) 0%
Current Year Financials 100 0 0% 100 (0) 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
47
Project Life Financials 1,257 0 0% 1,257 0 0%
Current Year Financials 1,257 0 0% 0 (1,257) -100%
Project Description
Project Manager Raymond Walsh/ Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Turnberry Homes - traffic calming/ management at Turnberry housing development off Castle Road
Mitigating Action
Funding has been received from Turnberry Homes and will be used to introduce traffic calming and traffic
management measures to mitigate the impact of additional traffic accessing the housing development off
Castle Road, Dumbarton.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultation completed 2021/2022 and speed humps will be installed prior to 31 March 2023.
None required at this time.
Anticipated Outcome
Traffic calming to be installed in Dumbarton East.
Electrical Charging Points - Rapid Charge
Funding has been awarded from Transport Scotland for the Installation of electrical charging points
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Main Issues / Reason for Variance
A detailed design for Gruggies Burn will be undertaken by the end of the financial year.
Mitigating Action
None required at this time.
Anticipated Outcome
Project should be complete within budget.
Anticipated Outcome
To provide Electric Vehicle Charging points within West Dunbartonshire.
Flood Risk Management
Enhancement of drainage infrastructure to ensure compliance with Flood Risk Management Act 2009.
Planned End Date Forecast End Date
Charging points to be installed at Moss O' Balloch park by the end of this financial year.
Mitigating Action
None required at this time.

Page 31

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
48
Project Life Financials 500 0 0% 500 0 0%
Current Year Financials 500 0 0% 500 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
49
Project Life Financials 149 37 25% 149 0 0%
Current Year Financials 149 37 25% 110 (39) -26%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
50
Project Life Financials 800 181 23% 800 0 0%
Current Year Financials 620 0 0% 0 (620) -100%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
Infrastructure - Flooding
Essential renewal of failed drainage assets to minimise flood risk within West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Small value projects to tackle flooding events in various areas.
Main Issues / Reason for Variance
Plans are under consideration by officers and will be submitted to Elected Members for approval.
Mitigating Action
None required at this time.
Anticipated Outcome
Projects should be complete within budget.
Flood Prevention
Various flood prevention projects.
Forecast End Date
Anticipated Outcome
Project should be completed within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Planned End Date
Awaiting outcome of Scottish Government & SEPA deliberations.
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Intention is to complete works within budget.
River Leven Flood Prevention Scheme
River Leven Flood Prevention Scheme.

Page 32

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
51
Project Life Financials 1,627 64 4% 1,075 (552) -34%
Current Year Financials 1,627 64 4% 1,075 (552) -34%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
52
Project Life Financials 500 11 2% 280 (220) -44%
Current Year Financials 220 0 0% 0 (220) -100%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
53
Project Life Financials 3,444 288 8% 3,444 0 0%
Current Year Financials 3,444 288 8% 3,444 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23Planned End Date Forecast End Date
Main Issues / Reason for Variance
Roads Operations are progressing an extensive surfacing program and have a number of schemes to be completed by the end of the financial
year.
Mitigating Action
None required at this time.
None required.
Anticipated Outcome
Project will be removed as agreed at Council on 21st December 2022.
Infrastructure - Roads
Infrastructure - Roads.
Mandatory 20mph Residential communities
Main Issues / Reason for Variance
Anticipated Outcome
Intention is to complete various surfacing works by the end of March 2023.
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.
Mitigating Action
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements & Park and Rides
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements.
Mandatory 20mph Residential communities.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Work will be undertaken during this financial year for A8014 Kilbowie Road, Balloch Station Park and Ride and Bus Infrastructure Improvements.
A814 Congestion measures contractor arrived on site mid-August. Works are progressing well and completion expected by the end of February
2023. The budget for Balloch Station will be used for consultancy works and planning application fees.
Mitigating Action
None required at this time.
Anticipated Outcome
Improve accessibility to Public Transport and improve journey time reliability.
Planned End Date Forecast End Date

Page 33

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
54
Project Life Financials 97 35 36% 97 (0) 0%
Current Year Financials 55 0 0% 0 (55) -100%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
55
Project Life Financials 15,053 429 3% 15,053 (0) 0%
Current Year Financials 1,524 8 1% 0 (1,524) -100%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
56
Project Life Financials 2,325 1,007 43% 2,325 0 0%
Current Year Financials 693 0 0% 693 (0) 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-26 31-Mar-26
57
Project Life Financials 2,325 0 0% 2,325 0 0%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-26 31-Mar-26
Mitigating Action
None required at this time.
Anticipated Outcome
To provide an improved A813.
Main Issues / Reason for Variance
These works are not due to commence until Phase 1 has been completed.
Main Issues / Reason for Variance
Plans have been developed for carriageway widening and footway and cycleway construction between Strathleven and Lions Gate.  There are
ongoing discussions with Aggreko and other land owners in regards to access and land acquisition with construction commencing during
2022/2023.
Mitigating Action
None required at this time.
Anticipated Outcome
To provide an improved A813.
Anticipated Outcome
Project should be completed within budget.
A813 Road Improvement Phase 1
A813 Road Improvement Phase 1.
Planned End Date Forecast End Date
None available at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
Intention is to complete works within budget.
Gruggies Burn Flood Prevention
Commission of Gruggies Flood Prevention Scheme.
Depot Improvement Works
Improvement of WDC Roads Depot.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget will be utilised for depot rationalisation works during the financial year.
A813 Road Improvement Phase 2
A813 Road Improvement Phase 2.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget to be used for a detailed design for Gruggies Burn.
Mitigating Action

Page 34

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
58
Project Life Financials 4,300 4,029 94% 4,300 (0) 0%
Current Year Financials 498 227 46% 498 (0) 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-22
59
Project Life Financials 3,930 3,846 98% 3,846 (84) -2%
Current Year Financials 84 0 0% 0 (84) -100%
Project Description
Project Manager Cameron Muir
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-May-21
60
Project Life Financials 1,039 651 63% 1,039 (0) 0%
Current Year Financials 117 8 7% 0 (117) -100%
Project Description
Project Manager Cameron Muir
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
To upgrade bridges within West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works substantially complete. Additional works as a compensation event started on Wallace street in July 2022.
Mitigating Action
Works to Renton footbridge are now complete and work will commence on the other bridges.
Mitigating Action
None available at this time.
Anticipated Outcome
Mitigating Action
None required.
Anticipated Outcome
To provide an improved Lomond Bridge.
Protective overcoating to 4 over bridges River Leven
To overcoat 4 bridges over River Leven.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Anticipated Outcome
Project should be completed within budget enhancing the A814 through Clydebank.
A811 Lomond Bridge
Clydebank Charrette, A814
Clydebank Charrette, A814
Upgrade of Lomond Bridge.
Planned End Date Actual End Date
None required at this time.
Main Issues / Reason for Variance
Works to Lomond Bridge were completed May 2021. No further costs expected.

Page 35

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
61
Project Life Financials 80 0 0% 80 0 0%
Current Year Financials 40 0 0% 40 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
62
Project Life Financials 350 0 0% 0 (350) -100%
Current Year Financials 350 0 0% 0 (350) -100%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
63
Project Life Financials 300 153 51% 300 0 0%
Current Year Financials 300 153 51% 300 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
To purchase equipment.
Traffic Signal Upgrades
Upgrade Traffic Signals
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Forecast End Date
Main Issues / Reason for Variance
New Plant to be purchased
Roads Plant
Mitigating Action
None required.
Anticipated Outcome
Purchase of Roads plant and equipment.
Planned End Date
These will be included in LUF2 and we await Scottish Government decision on application.
Mitigating Action
None required.
Anticipated Outcome
To upgrade traffic signals.
Mitigating Action
None required.
Anticipated Outcome
Project will be removed as agreed at Council on 21st December 2022.
Footway Resurfacing (RAMP)
Footway resurfacing
Planned End Date Forecast End Date
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.

Page 36

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
64
Project Life Financials 1,000 0 0% 0 (1,000) -100%
Current Year Financials 1,000 0 0% 0 (1,000) -100%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
65
Project Life Financials 100 0 0% 0 (100) -100%
Current Year Financials 100 0 0% 0 (100) -100%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
66
Project Life Financials 1,000 0 0% 0 (1,000) -100%
Current Year Financials 1,000 0 0% 0 (1,000) -100%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Project will be removed as agreed at Council on 21st December 2022.
Pavement improvements
Various pavement improvement projects.
None required.
Anticipated Outcome
Various road improvement projects
Planned End Date Forecast End Date
None required.
Anticipated Outcome
Planned End Date Forecast End Date
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.
Mitigating Action
Project will be removed as agreed at Council on 21st December 2022.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.
Mitigating Action
Street sign renewal
Renewal of street signs
Roads improvements
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.
Mitigating Action
None required.
Anticipated Outcome
Project will be removed as agreed at Council on 21st December 2022.

Page 37

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
67
Project Life Financials 30 0 0% 0 (30) -100%
Current Year Financials 30 0 0% 0 (30) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
68
Project Life Financials 400 0 0% 400 0 0%
Current Year Financials 400 0 0% 400 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
69
Project Life Financials 160 71 44% 160 0 0%
Current Year Financials 80 71 88% 80 0 0%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
70
Project Life Financials 1,110 244 22% 1,110 (0) 0%
Current Year Financials 441 56 13% 441 0 0%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-29 31-Mar-29
Forecast End Date
Water Safety
Mitigating Action
None required.
To develop Water Safety Policy & enhance water safety equipment in WDC
Planned End Date
Anticipated Outcome
Main Issues / Reason for Variance
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Compactors have now been delivered.
Mitigating Action
None Required.
Replacement of compactors at Dalmoak civic amenity site
The purchase of 2 compactors for the Council civic amenity site at Dalmoak.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.
Anticipated Outcome
Purchase of gritters
Purchase of gritters.
Project will be removed as agreed at Council on 21st December 2022.
Main Issues / Reason for Variance
Delivery delayed by the supplier. Full budget spend expected before the end of the financial year.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within  budget.
AV Equipment - Education
Purchase of AV Equipment for Education.
Planned End Date
Although there is re-profiling of budget caused mainly by the academic year starting several months after the financial year the project is still on
track to be completed by the planned end date.
Mitigating Action
None available at this time.
Anticipated Outcome
Forecast End Date
Project delivered within  budget.
Purchase of AV Equipment for Education.

Page 38

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
71
Project Life Financials 376 335 89% 376 (0) 0%
Current Year Financials 41 0 0% 41 0 0%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
72
Project Life Financials 20,241 15,280 75% 20,241 0 0%
Current Year Financials 1,005 464 46% 1,005 0 0%
Project Description
Project Manager Sharon Jump/ Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
73
Project Life Financials 694 472 68% 694 0 0%
Current Year Financials 504 283 56% 504 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
Free School Meals
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within amended timescales.
Provision of Capital Funding from Scottish Government to implement free school meal initiative.
Planned End Date
Anticipated Outcome
Project delivered within budget and to the revised programme, following COVID-19.
Forecast End Date
None required
Mitigating Action
None required at this time.
Anticipated Outcome
Increase the Chromebook ratio for most disadvantaged children.
Main Issues / Reason for Variance
Project is complete other than snagging works which can only be completed when school is closed however project end date is still on target.
Additional budget required in relation to electrical phasing which was unknown at the time of project inception.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Renton Campus: The overall construction is programmed to complete by 25 July 2022. (Previously April 2022 but re-programmed due to 13
week COVID-19 site closure).  Phase 1 of the project was handed over on Monday 18 October 2021, with pupils returning to the new school
campus on Wednesday 20 October 2021.  Phase 2 on schedule to be handed over 25th July 2022. There is an acceleration of spend due to part
retention being paid 2022/2023.   St Mary's:  anticipated commencement of MUGA is September 2022 which means new build kitchen will slip to
June 2023.  Pitch onsite September and dining hall will be July 2023 as cannot be onsite at the same time as pitch works.   Additional ASN
Provision: temporary accommodation for Choices will be in place by September and plans for rebuild extension ongoing. Additional scoping in
respect of vacant space at Choices and former Riverside ELC ongoing.  Skills School: scoping ongoing.  Balloch Campus, Lomond Base,
artificial grass installation is complete.
Mitigating Action
Digital Inclusion
Increase the ratio of chrome book devices for most disadvantaged children and families and support for
families with remote access.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Additional devices have been ordered to increase the ratio of devices to pupils as part of a commitment towards a 1:1 device ratio. The project is
on track to be fully spent in 2022/2023.
Schools Estate Improvement Plan
Improvement of Schools Estate.

Page 39

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
74
Project Life Financials 5,508 5,508 100% 5,508 (0) 0%
Current Year Financials 3 3 98% 3 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-22 30-Apr-22
75
Project Life Financials 8,748 8,490 97% 8,822 74 1%
Current Year Financials 795 464 58% 795 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
76
Project Life Financials 1,150 1,145 100% 1,150 (0) 0%
Current Year Financials 26 20 79% 26 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 30-Apr-22
Mitigating Action
None required.
Anticipated Outcome
Project delivered on time and within budget
Schools Estate Refurbishment Plan
Completion of condition surveys has been carried out to identify works required to bring various schools from
Condition C to Condition B.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project complete and final account to be agreed.
Mitigating Action
None required.
Mitigating Action
None required at this time.
Anticipated Outcome
Dalmonach CE Centre
To create new community facilities with additional space for early years provisions.
Early Years Early Learning and Childcare Funding
Early learning and childcare funding awarded to West Dunbartonshire Council to facilitate the expansion in
entitlement to funded ELCC to 1140 hours from August 2020.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works progressing and budget spend anticipated in 2022/2023.
Anticipated Outcome
To create new community facilities with additional space for early years provisions.
The project will be completed to deliver the requirements of the Early Years expansion plans.
Main Issues / Reason for Variance
Project complete and await final charges.

Page 40

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
77
Project Life Financials 1,053 616 59% 1,053 0 0%
Current Year Financials 1,053 616 59% 969 (84) -8%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-23 31-Mar-23
78
Project Life Financials 1,400 0 0% 1,120 (280) -20%
Current Year Financials 280 0 0% 0 (280) -100%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-23 31-Mar-23
79
Project Life Financials 73 53 73% 73 0 0%
Current Year Financials 73 53 73% 73 0 0%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
Planned End Date Forecast End Date
None available at this time
Anticipated Outcome
Renovation of Unit 11 Levenside Business Court
Main Issues / Reason for Variance
Mitigating Action
None available at this time
Anticipated Outcome
Project will be removed as agreed at Council on 21st December 2022.
The construction of an office and storage refit with a mezzanine floor within an existing workshop unit which will include associated finishes
works and electrical installations. The multi-purpose new office space will accommodate two members of staff with an office base and allow
space to set up a training facility indoors. Project expected to be completed by 31 March 2023.
Replacement of Care First
Replacement of Care First
Main Issues / Reason for Variance
As agreed at Council on 21st Decemember 2022 this project will no longer progress and therefore no further spend will occur.
Criminal Justice Adaptations
Renovation of Unit 11 Levenside Business Court.
Planned End Date Forecast End Date
None available at this time
Anticipated Outcome
Provision of adaptations and equipment to HSCP clients as anticipated.
Aids & Adaptations - Special Needs Adaptations & Equipment
Reactive budget to provide adaptations and equipment for HSCP clients.
Planned End Date Forecast End Date
Provision of aids and adaptations to clients as required.
Mitigating Action
Main Issues / Reason for Variance

Page 41

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
80
Project Life Financials 27,531 27,272 99% 27,531 0 0%
Current Year Financials 61 61 100% 61 0 0%
Project Description
Project Manager Sharon Jump/ Craig Jardine
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-22 31-Mar-22
81
Project Life Financials 1,422 676 48% 1,422 0 0%
Current Year Financials 1,422 676 48% 886 (536) -38%
Project Description
Project Manager Patricia Kerr
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-23 31-Mar-23
82
Project Life Financials 60 50 83% 60 0 0%
Current Year Financials 17 7 40% 17 0 0%
Project Description
Project Manager Patricia Kerr
Chief Officer Victoria Rogers
Project Lifecycle 31-Oct-22 31-Oct-22
Internet of Things Asset Tracking
Asset Tracking.
Mitigating Action
None available at this time.
Anticipated Outcome
Technical aspect of the project is complete and WDC assisting with user testing. Delayed but on budget.
Anticipated Outcome
Most of the capital allocated to HSCP (approx £500k) will be used to review/replace the current case management systems and will be rephased
in line with the project plan. Supply chain delays may continue to impact delivery and spend.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project complete with a slight overspend due to additional works required in relation to roof vents which required to be installed. Acceleration of
budget has been requested in relation to an overspend in the current year.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mobile phone replacements continue but many are on hold due to dependency on ITune module of Microsoft 365.  Assessing the next volume of
Chromebook replacements and continuing to liaise with Education.
Mitigating Action
Continue to escalate and meet framework suppliers to confirm delivery lead times.
Investigate other procurement routes as well as adjust the project scope to replace where stock allows.
Mitigating Action
The statement of final account has been signed and financial risk exposure should be reduced through efforts to dispose of the existing
properties at the earliest opportunity.
Anticipated Outcome
Dumbarton Care Home opened 2017.  Clydebank Care Home was certified complete on 9 November 2020.
ICT Modernisation
This budget is to facilitate ICT infrastructure and modernise working practices.
Replace Elderly Care Homes and Day Care Centres
Design and construction of replacement elderly care homes and day care centres in Dumbarton and
Clydebank areas.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Technical aspect of the project is complete and WDC are assisting with user testing. Delayed but on budget. This is funded by Scottish
Government budget.

Page 42

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
83
Project Life Financials 1,297 532 41% 1,297 0 0%
Current Year Financials 1,297 532 41% 950 (347) -27%
Project Description
Project Manager Brian Miller/ Patricia Kerr
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-23 31-Mar-23
84
Project Life Financials 450 256 57% 450 0 0%
Current Year Financials 173 78 45% 120 (53) -31%
Project Description
Project Manager Dorota Piotrowicz/ Patricia Kerr
Chief Officer Victoria Rogers
Project Lifecycle 30-Sep-23 30-Sep-23
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Storage Area Network (SAN) installation ongoing. Server replacement at procurement stage. Wi-Fi access equipment scoping for end of life
items and estimated potential £0.300m spend to replace up to 900 - 1000 wireless access points.  Planning procurement for secondary storage
(data domains) underway and estimated £0.150m spend. Indications are that global supply chain issues will impact Wi-Fi and storage lead times.
Mitigating Action
Monitor supply chain issues. Continue tendering processes and implementation stages for each project.
Majority of budget spent but delayed.
Project services to delivery Microsoft 365 Implementation including 3rd party supplier, training, technical
consultancy etc.
Planned End Date Forecast End Date
Anticipated Outcome
Anticipated Outcome
Anticipate two thirds of the budget being spent this financial year due to supply chain issues. Additionally, some works are planned for the last
quarter of the year for Public Sector Network (PSN) annual compliance submission.
365 Implementation
Main Issues / Reason for Variance
Project spend relates to internal and external resources to implement new systems, processes and user training skills. Mailbox migration aspect
of the project now being resumed as cloud backup solution is in place. Implementation of device management functionality in 365 is live for
corporate devices but full rollout is linked to mailbox migrations. Information governance work stream in progress. Project resourcing issues
continue due to competing demands and competitive environment for recruitment.
Mitigating Action
Continue to monitor the various work streams to accelerate aspects of the project where possible if suppliers can provide resource. Continue to
assess where a) internal skills have developed, b) external resource is needed for introducing new functionality in the future to inform future
bidding cycles and c) temporary recruitment/secondment is required.
ICT Security & DR
The project is for the enhancement of security systems, server replacement and the update of corporate
applications to ensure compliance with 15/16 PSN requirements, to enhance the disaster recovery
capabilities of WDC.

Page 43

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
85
Project Life Financials 77 77 100% 77 0 0%
Current Year Financials 30 30 100% 30 (0) 0%
Project Description
Project Manager Patricia Kerr
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-25 31-Mar-25
86
Project Life Financials 3,502 101 3% 3,502 0 0%
Current Year Financials 3,502 101 3% 3,502 0 0%
Project Description
Project Manager N/A
Chief Officer N/A
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None required.
Anticipated Outcome
Direct project support costs allocated as appropriate.
Direct Project Support
Business support cost such as reallocation of architects and project support at year end.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Salary Capitalisation in 2022/2023.
None required.
Anticipated Outcome
Completion of project by 2025
Session Initial Protocol (SIP) project Swan Trunking
This project is to replace legacy Analogue Telephony infastructure with new Digital Telephony infrastructure
due to the phasing out of the Legacy infrastructue by 2025
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This project to replace legacy Analogue Telephony infastructure with new Digital Telephony infrastructure has just started and will continue until
2025.
Mitigating Action

Page 44

WEST DUNBARTONSHIRE COUNCIL APPENDIX 9
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
PERIOD END DATE
PERIOD 10
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials (141) (99) 70% (419) (278) 197%
Current Year Financials (790) 0 0% (790) 0 0%
Project Description
Project Lifecycle 31-Mar-23 31-Mar-23
2
Project Life Financials (75,127) (33,462) 45% (76,371) (1,244) 2%
Current Year Financials (5,574) (4,605) 83% (5,574) 0 0%
Project Description
Project Lifecycle 31-Mar-30 31-Mar-30
3
Project Life Financials (35,184) (4,831) 14% (35,184) 0 0%
Current Year Financials (959) (252) 26% (959) 0 0%
Project Description
Project Lifecycle 31-Mar-26 31-Mar-26
4
Project Life Financials (12,001) (6,835) 57% (14,501) (2,500) 21%
Current Year Financials (5,038) (3,096) 61% (4,416) 622 -12%
Project Description
Project Lifecycle 31-Mar-23 31-Mar-23
Anticipated Outcome
Match funding received.
None required.
Mitigating Action
Mitigating actions are detailed within the appropriate status updates.
Anticipated Outcome
Application of resources as appropriate.
Match Funding / Other Grants and Contributions
Match Funding / Other Grants and Contributions
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Application of resources is dependent on capital project progressing in year as planned.
Mitigating Action
Application of resources is dependent on capital project progressing in year as planned.
Main Issues / Reason for Variance
General services capital grant is anticipated to be received as forecast.
Mitigating Action
None required at this time
Anticipated Outcome
General services capital grant is anticipated to be received as forecast.
Ring Fenced Government Grant Funding
This is ring fenced grant funding which is primarily anticipated to be received from the Scottish Government and
relates to Cycling, Walking, Safer Streets, Regeneration Placed Based Investment Programme, Early Years,
Gruggies Burn Flood works, Early Years funding, City Deal and Town Centre Fund.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Application of resources held on balance sheet as at 31 March 2022 as appropriate.
General Services Capital Grant
This is a general grant received from the Scottish Government in relation to General Services capital spend
Application of resources is dependent on capital project progressing in year as planned.
Spend to Date Forecast Variance
Resources Carried Forward
These are resources that have been received in previous years relating to Turnberry Homes, Town Centre Fund
Grant, Digital Inclusion, Clydebank Can on the Canal, Internet of Things Asset Tracking and Auld Street Bond.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
31 January 2023
Budget Details
Project Life Financials

Page 45

WEST DUNBARTONSHIRE COUNCIL APPENDIX 9
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
PERIOD END DATE
PERIOD 10
Budget Forecast Spend
£000 £000 % £000 £000 %
Spend to Date Forecast Variance
Resources Carried Forward
31 January 2023
Budget Details
Project Life Financials
5
Project Life Financials (25,429) (77) 0% (26,506) (1,077) 4%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Lifecycle 31-Mar-26 31-Mar-26
6
Project Life Financials (124,889) (55,245) 44% (114,745) 10,144 -8%
Current Year Financials (54,112) (3,903) 7% (19,425) 34,687 -64%
Project Description
Project Lifecycle 31-Mar-26 31-Mar-26
7
Project Life Financials (150) 0 0% (103) 47 0%
Current Year Financials (103) 0 0% (103) 0 0%
Project Description
Project Lifecycle 31-Mar-23 31-Mar-23
Anticipated Outcome
CFCR applied to relevant capital project.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Renovation of Unit 11 Levenside Business Court
Mitigating Action
None required at this time.
This is capital spend which is funded by revenue budgets
Prudential Borrowing
Prudential borrowing is long term borrowing from financial institutions that has been approved for the purposes of
funding capital expenditure
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Prudential borrowing is impacted by programme delivery therefore mitigating action is detailed in the red and amber analysis.
Mitigating Action
None available at this time.
Anticipated Outcome
While prudential borrowing requirement is likely to be less than budgeted in the current financial year this is anticipated to catch up over the
programme life.
CFCR
Capital receipts received.
Capital Receipts
These are capital receipts that are anticipated from sales of land and buildings both as part of the normal disposal
programme and also as part of the business case investment in office rationalisation, new school building and new
care home development
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Receipts budgets are based on assumptions in relation to the sale of various sites. Not all sales will be realised this financial year. The main ones
being OLSP, St James retail park, Dalreoch Care Home. Queen's Quay, Levenbank Terrace, Heather Avenue, Crosslet House. As agreed at
Council receipts received are used firstly to pay for principle and premiums.
Mitigating Action
While market conditions are out with officers control all potential receipts will be explored.
Anticipated Outcome