WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
HRA CAPITAL PROGRAMME
CAPITAL PROJECTS FORECAST OUTTURN AND REPROFILING REQUIRED 2022/23
Budget
Forecast
Outturn
Reprofiling
required
Over / 
(Under)
Recovery
RESOURCES £000 £000 £000 £000
New Build Grant 30,006 10,480 0 19,526
Prudential Borrowing 26,287 21,549 0 4,738
Buy Backs 0 417 0 (417)
Contribution towards Noise Insulation Project 96 0 0 96
CFCR 9,215 5,386 0 3,829
Total Resources 65,604 37,832 0 27,772
Budget
Forecast
Outturn
Reprofiling
required
(Over) /
Under
Spend
CAPITAL EXPENDITURE £000 £000 £000 £000
OTHER CAPITAL EXPENDITURE £2,039 £2,125 £283 (368)
Special Needs 474 474 0 0
Capitalised Minor Works 431 800 0 (369)
Better Homes Priority Budget 664 664 0 0
Community Safety 17 17 0 (0)
QL Development 185 94 91 0
Airport Noise Insulation Scheme 192 0 192 0
Redeployable CCTV Cameras 36 36 0 0
Gypsy Travellers Site Upgrades 40 40 0 0
MAJOR COMPONENT REPLACEMENTS £14,344 £12,727 £3,755 (2,139)
Targeted SHQS compliance works 0 0 0 0
Targeted EESSH compliance works 4,455 4,455 0 0
Building external component renewals 4,955 2,700 2,255 0
Doors/window component renewals 2,500 1,000 1,500 0
External stores/garages/bin stores 75 75 0 0
Secure entry component renewals 91 91 0 0
Statutory/regulatory compliance works 108 200 0 (92)
Heating improvement works 969 2,600 (1,631)
Energy improvements/energy efficiency works 54 54 0 0
Modern facilities and services 1,035 1,450 0 (415)
Non Traditional/Traditional Improvement Works 103 103 0 0
VOID CAPITAL £2,000 £3,500 £0 (1,500)
Void house strategy programme 2,000 3,500 0 (1,500)
CONTINGENCIES £181 £0 £0 181
Contingencies 181 0 0 181
STRUCTURAL & ENVIRONMENTAL £2,872 £2,983 £287 (399)
Defective structures/component renewals 887 600 287 0
Environmental renewal 969 1,368 0 (399)
Asbestos management works 215 215 0 0
MSF Fire Risk Assessment Works 800 800 0 0
SUPPORT COSTS £2,504 £2,504 £0 0
Direct Project Support 2,504 2,504 0 0
AFFORDABLE SUPPLY PROGRAMME £41,664 £13,991 £27,346 326
New Builds 39,645 11,972 27,346 326
Buy Backs 2,019 2,019 0 0
TOTAL 65,604             37,831         31,671            (3,899)