Democracy Spraffa

October 2023 Weather Event - Update

Argyll and Bute Council · 25 April 2024
Back to Argyll and Bute Council — 25 April 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL COUNCIL 
ROAD AND INFRASTRUCTURE
SERVICES 
25 APRIL 2024 
OCTOBER 2023 WEATHER EVENT – UPDATE 
1.0 INTRODUCTION
1.1 Following a period of wet weather which left ground conditions very wet and in many
cases saturated, over a months’ worth of rain fell over a 36 hour period starting Friday
6 October 2023 and running into Saturday 7 October 2023. 
1.2 Conditions were so severe that by mid-morning on Saturday 7 October, Police Scotland
had declared a major incident and a multiagency tactical response was assembled to
ensure that the incident could be managed across the many agencies and communities
involved. 
1.3 Transport connections into and out of Argyll and Bute were severely compromised on
Saturday 7 October and for a period of time, all of the trunk roads and many of the local
roads were impassable. Numerous people became stranded due to flood waters,
landslips and damaged structures. Mountain rescue were deployed along with the
coastguard who arranged ground units and a helicopter to support the response to assist
Police Scotland who were coordinating the responses in line with protocol for major
incident response. 
1.4 The Council response was significant with reception centres and catering put in place
to accommodate individuals who were unable to get home, together with many staff
from Roads and Infrastructure assisted by several contractors involved in responding to
the chaos and disruption to public infrastructure caused by the event. 
2.0 RECOMMENDATIONS
2.1 It is recommended that Council consider and note this report. 
3.0 DETAIL
3.1 We are seeing an increasing number of weather events locally, nationally and
internationally no doubt linked to climate change.  In recent years in Argyll and Bute we
have had several weather events including:- 
• West of Mull bridge wash out At the foot of Ben More July 2012;
• Clachan snow event March 2013 – significant snow fall blocked the road and
the weight of frozen snow on power lines resulted in power lines breaking and
several thousand households being without power;

Page 2

• Beast from the east February 2018;
• Sea wall wash out Bute December 2021;
• Numerous flood events in locations such as Lochavullin Oban, East and West
Clyde Street Helensburgh, Rothesay, Campbeltown (flood prevention works
underway) Lochgilphead Front Green etc. 
3.2 The map below shows each of the locations where there was disruption caused (road
closed or traffic restricted) across Argyll and Bute’s road network on 7 October 2023. It
is interesting to note that the weather band was very localised sweeping through the
central part of Argyll and Bute, this is illustrated with the damage caused. Also, and
perhaps quite unusual, is that the majority of damage caused took place inland rather
than on the coast. This very local weather and damage is peculiar to this storm event.
As Members will be all too familiar with, often Argyll and Bute, with over 3000 miles of
coastline, regularly suffers coastal damage during storms, the recent example being the
sea wall on Bute where around 100m was extensively damaged in December 2021. 
3.3 Regular updates were provided to Members and the public following the October rain

Page 3

event and two separate Members Seminars were held in November and December
2023 – copies of these slides can be provided on request.   
3.4 The works carried out by following the rain event were extensive with dozens of locations
requiring attention from simple cleansing of a small drain to significant landslides and
bridge replacements. 
3.5 The majority of locations where damage occurred have been reinstated and permanent
works are in place. The following table summarises locations where works are still
outstanding: 
Location Ongoing works Scheduled completion
Kilmelford  Bridge parapet, bridge training walls,
scour protection along upstream and
downstream and narrow footway on the
upstream side of the bridge
Late Summer / Autumn
2024 
Kilninver  Rock amour protection to the south east
banking which abuts the bridge
Late Summer / Autumn
2024 
C30 Ford to
Dalavich 
Finalising rock protection and vehicle
barrier 
End of April 2024
Glen Lean B836  Construction of permanent bridge and
removal of temporary structure 
Late Summer / Autumn
2024
A816 Kintraw
catch pits at base
of unstable slope 
Catch pits and bunds to be completed
following the completion of the last of the
temporary works land agreement 
License agreement
anticipated soon with
approximately  4-6
weeks of work following
signing of the agreement   
This will allow traffic
back onto the original
route of the road subject
the hillside being stable
(monitored via cctv
system, hillside
saturation level and
forecast rainfall).
Temporary diversion to
be used should there be
a risk of material flow
from the hillside 
A816 Kintraw
convoy system ‘v’
fixed traffic lights
Convoy system continues to operate.
Subject to safety audit sign off it is the
intention to put in place fixed hard wired
End of April 2024

Page 4

traffic lights (wireless radio signals don’t
have a clear line of sight and would be
unreliable).
Cost options are being worked up
A816 
Kintraw –
permanent
diversion onto a
widened
alignment of the
emergency route  
Archeologist has carried out further
investigative works and have given
positive feedback. The next stage is
further design work including ground
investigation, ecology and archeological
which will allow for permissions to be
sought and a final design progressed for a
permanent solution 
Cost options are being worked  up 
2 – 5 years 
Expenditure and Bellwin Scheme Claim 
3.6 The Bellwin Scheme exists to give special financial assistance to Local Authorities
who would otherwise be faced with an undue financial burden as a result of providing
relief and carrying out immediate work due to large-scale emergencies.  As a result of
the weather incident in October, Argyll and Bute Council activated the Bellwin Scheme
with Scottish Government.  The Bellwin Scheme normally covers revenue expenditure
incurred within a 2 month period from the date of the incident, however at our request,
Scottish Government agreed to extend this period to 4 months.  Capital expenditure is
not claimable via the Bellwin Scheme.  Grant is paid at a rate of 100% of eligible
expenditure above each Local Authority’s annual threshold (Argyll and Bute Council
threshold is £0.529m and this has been covered by Crown Estate funding). 
3.7  A claim amounting to £5.356m of revenue costs was submitted to Scottish
Government at the end of the 4 month period and after deducing our threshold of
£0.529m this results in a net claim of £4.827m.  Scottish Government considered the
claim and advised us on 10 April 2024 that they were issuing payment for 90% of the
claim which is standard procedure.  The Council are required to make a further final
claim for the remaining 10% which officers are dealing with.   
3.8  In addition to receiving the funding via the Bellwin Claim, on 18 March 2024, a letter
was received from Mairi McAllan MSP, Cabinet Secretary for Net Zero and Just
Transition confirming that Argyll and Bute Councill will receive an additional £2.3m of
funding for 2024-25 as a contribution towards the additional costs incurred as a result
of the weather incident.   
3.9  The table below summarises the latest estimated cost of the weather incident, split
between what has been (or is expected to be) funded by Scottish Government and
what has been provided for in the Council’s budget. Any change to the estimates will
be reported via the Council’s budget monitoring process.

Page 5

Total
£000
Scottish
Government
£000
Council
£000
Revenue Expenditure
Claimed Via Bellwin
5,356 4,344 (already
received)
483 (final claim
due)
529
Revenue Expenditure
outwith 4 month period
839 457 (included in
£2.3m payment)
382
Capital Expenditure not
claimable via Bellwin
4,348 1,843 (included in
£2.3m payment)
2,505
Total Estimated
Expenditure
10,543 7,127 3,416 
Next Steps
3.10 Our initial focus is to complete the various works still outstanding and to continue to
monitor slopes where debris flows may affect the road network. Cost estimates are
being finalised for the convoy ‘v’ traffic lights and permanent solution for the A816
Kintraw. 
3.11 Climate change is a significant challenge to the Council for a number of reasons but not
least it is a challenge for the road and transport infrastructure. This report highlights
some of the challenges faced recently and over the last decade or so. The road and
wider transport system provides the economic backbone for our communities. We need
to have infrastructure which is fit for purpose and sufficiently resilient to withstand the
increasing weather challenges we are experiencing which are linked closely to climate
change. The building of a bypass on the A816, strengthening bridges, and modifying
roadside ditches are all adaptations being progressed to better accommodate some of
the climate changes we are seeing. However, more will be needed to be done and whilst
the works mentioned above will increase our infrastructure’s resilience to future weather
events, the network overall is fragile and unable to cope with significant weather events. 
3.12 It will be necessary to see more infrastructure investment put in place to enable climate
change adaptations to be made. The level of investment will be significant and the
Council will need to consider how its funding can be assembled and what lobbying can
be progressed with Scottish and UK Governments. 
4.0 CONCLUSION
4.1 This report summarises the rain event which caused significant travel disruption and
damage during the weekend of 7 October. The report also summarises the extent of
works that have been carried out to repair the damage and considers what our next
steps should be as detailed in paragraph 3.8 above.

Page 6

5.0 IMPLICATIONS
5.1 Policy – policies in place for climate change, coast protection etc where applicable these
policies are being worked to.
5.2 Financial – new costs pressures have no identified funds to respond to the infrastructure
damage. A Bellwin claim is being progressed for eligible costs and works not eligible for
Bellwin will need to be funded. A financial summary is being prepared for schemes which
continued after the end date of the Bellwin Scheme and therefore have no identified
funding for costs after 7th February 2024.
5.3  Legal – various land agreements necessary for individual locations.   
5.4  HR – none known.
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – none known. 
5.5.2   Socio-economic Duty – none known. 
5.5.3  Islands – none known.
5.6 Climate Change – the impact of the storm is very closely linked to climate change and
the October event has highlighted to need for further adaptation to be made to
infrastructure to increase our resilience to future weather events. The level of
investment to improve resilience is expected to be significant.  
5.7 Risk – significant risk of similar future events impacting our infrastructure.  
5.8  Customer Service – none known.  
5.9 Rights of the Child (UNCRC) – investment to improve our road network will contribute
to a safer environment for young people to thrive in. 
Kirsty Flanagan, Executive Director with responsibility for Roads and Infrastructure
Services 
April 2024 
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Service
Jim.Smith@argyll-bute.gov.uk