Prepared for the Members of West Dunbartonshire Council and the Controller of Audit
9 November 2022
West
Dunbartonshire
Council
Proposed 2021/22 Annual Audit Report
APPENDIX 3

Page 2

West Dunbartonshire Council Proposed 2021/22 Annual Audit Report | 2
Contents 
Key messages 3
Introduction 5
1. Audit of 2021/22 annual accounts 8
2. Financial management 20
3. Financial sustainability 29
4. Governance and transparency 36
5. Best Value 39
Appendix 1. Action plan 2021/22 45
Appendix 2. Wider audit dimension risks 48
Appendix 3. Summary of 2021/22 national performance reports and briefing
papers 50

Page 3

Key messages | 3 
Key messages 
2021/22 annual accounts 
1 Our audit opinions on the annual accounts of the council, its group and its
section 106 charities administered by the council are unmodified. The
financial statements give a true and fair view and were properly prepared in
accordance with the financial reporting framework.
2 The management commentary, annual governance statement and
remuneration report were all consistent with the financial statements and
properly prepared in accordance with the relevant regulations and guidance.
3 A number of errors were identified in the accounting for non-current assets.
While the errors have been corrected, procedures need to be improved to
ensure the accuracy of the non-current asset figures in the 2022/23 annual
accounts, before they are approved for audit.
Financial management 
4 Financial management is effective and the council operated within budget in
2021/22. Elected members receive regular updates to ensure they are kept
up to date with the impact on services.
5 The Covid-19 pandemic continues to have a significant impact on the
council’s finances. The use of two new Scottish Government financial
flexibilities added £1.454 million of income on top of £4.488 million of direct
unearmarked Covid-19 funding. At 31 March 2022, £3.445 million of Covid-19
funding was unspent for use in future years. 
6 The council’s outstanding loans total £578.408 million. Recent interest rate
rises may present a longer-term risk for the council.
7 A trend of significant levels of delay to capital projects continues, with 42% of
planned capital expenditure slipping beyond milestones, although the impact
of the pandemic was a significant factor.
8 The innovative Clydebank district heating network is operational, funded by a
significant investment from the council and managed by its own green energy
company

Page 4

Key messages | 4 
Financial sustainability 
9 The budget for 2022/23 is £252.394 million, with a range of cost-saving
measures used to close a budget gap of £5.508 million.
10 The council faces significant financial challenges in the years ahead, with the
estimated budget gap growing to £19.849 million by 2024/25. Total usable net
reserves have decreased by £5.158 million.
11 Transformational change aligned with effective medium and longer-term
planning is required to address the impacts of the Covid-19 pandemic
together with growing inequalities, cost-of-living pressures, and the changing
needs of citizens.
Governance and transparency
12 Following the May 2022 local government elections, the council has a new
administration. A comprehensive training programme is in place to support
new and returning elected members.
13 Effective governance and decision-making arrangements were in place
during 2021/22. The council conducts itself in an open and transparent
manner.
Best Value 
14 The council has made good progress in demonstrating improvement in its
services, but the capital programme continues to fall behind as a result of the
pandemic.
15 Residents’ satisfaction with council services overall is high, but performance
indicators show challenges in tackling sickness absence levels, empty council
homes and recycling.
16 The council has a climate strategy and action plan to address the challenge
of reaching net zero by 2045.Service performance levels in 2021/22 were in
line with agreed targets.

Page 5

Introduction | 5 
Introduction 
1.  This report summarises the findings arising from the 2021/22 audit of West
Dunbartonshire Council (the council) and its group. 
2.  The scope of the audit was set out in our 2021/22 Annual Audit Plan
presented to the 2 March 2022 meeting of the Audit Committee. This report
comprises the findings from: 
• an audit of the annual accounts
• consideration of the four audit dimensions that frame the wider scope of
public audit set out in the Code of Audit Practice 2016 namely, financial
management, financial sustainability, governance and transparency and
value for money.
Adding value through the audit
3.  We add value to the council through the audit by:
• identifying and providing insight on significant risks, and making clear
and relevant recommendations 
• sharing intelligence and good practice through our national reports
(Appendix 4) and good practice guides 
• providing clear and focused conclusions on the appropriateness,
effectiveness and impact of corporate governance, performance
management arrangements and financial sustainability
Responsibilities and reporting
4.  The council has primary responsibility for ensuring the proper financial
stewardship of public funds. This includes preparing annual accounts that are in
accordance with proper accounting practices. 
5.  The council is also responsible for compliance with legislation, and putting
arrangements in place for governance and propriety that enable it to
successfully deliver its objectives.
6.  Our responsibilities as independent auditor appointed by the Accounts
Commission are established by the Local Government in Scotland Act 1973, the
Code of Audit Practice 2016 and supplementary guidance, and International
Standards on Auditing in the UK.
7.  As public sector auditors we give independent opinions on the annual
accounts. Additionally, we conclude on:

Page 6

Introduction | 6 
• the effectiveness of the council’s performance management
arrangements, 
• the suitability and effectiveness of corporate governance arrangements,
and financial position
• the arrangements for securing financial sustainability and,
• Best Value arrangements. 
8.   Further details of the respective responsibilities of management and the
auditor can be found in the Code of Audit Practice 2016. and supplementary
guidance.
9.  This report raises matters from our audit. Weaknesses or risks identified are
only those which have come to our attention during our normal audit work and
may not be all that exist. Communicating these does not absolve management
from its responsibility to address the issues we raise and to maintain adequate
systems of control.
10.  Our annual audit report contains an agreed action plan at Appendix 1
setting out specific recommendations, responsible officers and dates for
implementation. It also includes outstanding actions from last year and the
steps being taken to implement them.
Auditor Independence 
11.  Auditors appointed by the Accounts Commission or Auditor General must
comply with the Code of Audit Practice and relevant supporting guidance. When
auditing the financial statements auditors must comply with professional
standards issued by the Financial Reporting Council and those of the
professional accountancy bodies. We can confirm that we comply with the
Financial Reporting Council’s Ethical Standard. We can also confirm that we
have not undertaken any non-audit related services and therefore the 2021/22
audit fee of £280,840 as set out in our Annual Audit Plan remains unchanged.
We are not aware of any relationships that could compromise our objectivity
and independence.
12.  This report is addressed to both the council and the Controller of Audit and
will be published on Audit Scotland's website www.audit-scotland.gov.uk in due
course. We would like to thank the management and staff who have been
involved in our work for their cooperation and assistance during the audit.
Audit appointment from 2022/23
13.  The Auditor General for Scotland is responsible for the appointment of
external auditors to central government bodies. 2021/22 is the last year of the
current appointment round.
14.  The procurement process for the new round of audit appointments was
completed in May 2022. From financial year 2022/23, Mazars will be the
appointed auditor for West Dunbartonshire Council. We will work closely with
the new auditors to ensure a well-managed transition.

Page 7

Introduction | 7 
15.  A new Code of Audit Practice applies to public sector audits for financial
years starting on or after 1 April 2022. It replaces the Code issued in May 2016.
16.  There are several significant changes introduced by the new Code, namely
the integration of Best Value work into wider scope audit work and the audit of
Best Value across the Integration Joint Boards.
17.  We would like to thank members, Audit Committee members, management
and other staff, particularly those in finance, for their co-operation and
assistance over the past six years.

Page 8

1. Audit of 2021/22 annual accounts | 8 
1. Audit of 2021/22 annual
accounts
The principal means of accounting for the stewardship of resources and
performance 
Main judgements
Our audit opinions on the annual accounts of the council, its group and its section
106 charities administered by the council are unmodified. The financial statements
give a true and fair view and were properly prepared in accordance with the
financial reporting framework. 
The management commentary, annual governance statement and remuneration
report were all consistent with the financial statements and properly prepared in
accordance with the relevant regulations and guidance. 
A number of errors were identified in the accounting for non-current assets. While
the errors have been corrected, procedures need to be improved to ensure the
accuracy of the non-current asset figures in the 2022/23 annual accounts, before
they are approved for audit.
Our audit opinions on the annual accounts are unmodified 
18.  The accounts for the council and its group for the year ended 31 March
2022 were approved by the Audit Committee on 09 November 2022. As
reported in the independent auditor’s report:
• the financial statements give a true and fair view and were properly
prepared in accordance with the financial reporting framework 
• the audited part of the remuneration report, management commentary
and the annual governance statement were all consistent with the
financial statements and properly prepared in accordance with the
relevant regulations and guidance 
19.  We concluded that there were no matters upon which we are required to
report, by exception, to the Accounts Commission.

Page 9

1. Audit of 2021/22 annual accounts | 9 
The annual audit report and accounts were submitted in line
with our agreed audit timetable 
20.  Submission dates for the audited annual accounts and the annual audit
report for 2019/20 and 2020/21 were deferred in line with the later dates for
producing the annual accounts because of the impact of Covid-19. As the audit
team were aware that Covid-19 would have an impact on the staff resources
available and delays in receiving some supporting documentation, we agreed to
work to the revised submission deadlines of 30 November 2022.
21.  The unaudited annual report and accounts were received in line with our
agreed audit timetable on 30 June 2022. The working papers provided with the
unaudited accounts were of a good standard and finance staff provided good
support to the audit team during the audit. 
There were no objections raised to the annual accounts 
22.  The Local Authority Accounts (Scotland) Regulations 2014 require local
government bodies to publish a public notice on its website that includes details
of the period for inspecting and objecting to the accounts. This must remain on
the website throughout the inspection period. No objections were raised to the
2021/22 Annual Accounts.
Our audit testing reflected the calculated materiality level of
£5.418 million
23.  We apply the concept of materiality in both planning and performing the
audit and in evaluating the effect of identified misstatement on the audit and of
uncorrected misstatements, if any, on the financial statements and in forming
the opinion in the auditor’s report. We identify a benchmark on which to base
overall materiality, such as gross expenditure, and apply what we judge to be
the most appropriate percentage level for calculating materiality values. 
24.   The determination of materiality is based on professional judgement and is
informed by our understanding of the entity and what users are likely to be most
concerned about in the annual accounts. In assessing performance materiality,
we have considered factors such as our findings from previous audits, any
changes in business processes and the entity’s control environment including
fraud risks. 
Our initial assessment of materiality for the annual accounts was carried out
during the planning phase of the audit. These materiality levels were reported in
our Annual Audit Plan presented to the Audit Committee in March 2022. On
receipt of the unaudited 2021/22 annual accounts we recalculated our
materiality levels based on the financial results for the year ended 31 March
2022. Our audit approach and testing were adapted to reflect the recalculated
materiality levels in Exhibit 1.

Page 10

1. Audit of 2021/22 annual accounts | 10 
Exhibit 1
Materiality values 
Materiality level Council Group
Overall materiality: This is the figure we calculated to
assess the overall impact of audit adjustments on the
financial statements. It has been set at 1% of gross
expenditure for the year ended 31 March 2022.
£5.418 million £5.444 million
Performance materiality: This acts as a trigger point. If
the aggregate of errors identified during the financial
statements audit exceeds performance materiality this
would indicate that further audit procedures should be
considered. Using our professional judgement, we have
calculated performance materiality at 50% of planning
materiality.
£2.709 million £2.722 million
Reporting threshold: We are required to report to those
charged with governance on all unadjusted
misstatements more than the ‘reporting threshold’
amount. This has been calculated at 4% of planning
materiality.
£0.215 million £0.220 million
Source: Audit Scotland
We have significant findings to report on the audited annual
accounts
25.  International Standard on Auditing (UK) 260 requires us to communicate
significant findings from the audit to those charged with governance, including
our view about the qualitative aspects of the body’s accounting practices. We
have reported a number of issues from the work done on the identified risks of
material misstatement. These are included in the action plan at Appendix 1. 
26.  The qualitative aspects of the council’s accounting practices, accounting
policies, accounting estimates and accounts disclosures are satisfactory and
appropriate to the council. 
27.  The significant findings are summarised in Exhibit 2. In addition to the
issues set out below, and in accordance with normal audit practice, a number of
presentational and disclosure amendments were discussed and agreed with
management.

Page 11

1. Audit of 2021/22 annual accounts | 11 
Exhibit 2
Significant findings from the audit of the financial statements 
Issue Resolution 
1. Overstated value of council dwellings due to
capitalisation of improvements
Expenditure to improve council dwellings (such as
kitchens, bathrooms and heating systems) had
been capitalised as property, plant and equipment
additions over a number of years. The total value
carried on the Balance Sheet at 31 March 2022 for
this category was £78.224 million.
This accounting treatment is correct, based on
these being capital enhancing works which
improve the quality of the housing stock. However,
the impact of these improvements was already
reflected in the overall valuation of council
dwellings which took place in 2020/21, and this
was carried forward into the balances for 2021/22.
As a result, the total value of the council dwellings
should have adjusted when the revaluation was
processed.  
The annual accounts have been
amended for both the current year and
the prior year comparator. 
Once prior years and depreciation
values were taken into account, this had
the effect of reducing the disclosed
value of council dwellings by £80.636
million.
The council should review its capital
accounting procedures, with a view to
improving the systems used to record
entries, compliance with accounting
requirements, review processes and
communication with asset owners.
Recommendation 1
(Refer Appendix 1, action plan) 
2. The value of property and council dwellings
did not match those provided by the valuer
The council revalues its non-current assets on a
‘rolling’ cycle, with each category of asset revalued
at least every five years. 
Our review of the fixed asset register found that the
net book values of newly-revalued assets did not
match those provided by the valuer. The
depreciation charges, and subsequent accounting
entries, were incorrect as a result. This was
because the valuation had been treated as if it
occurred on 1 April 2021, when in fact it took place
as at 31 March 2022. 
In addition, £35.306m of new council dwellings
were transferred from assets under construction to
council dwellings during the year. These were
valued at cost, rather than fair value. A revaluation
of these properties took place late in the audit
process and resulted in a decrease of £23.206
million to the value of council dwellings. 
The annual accounts have been
amended accordingly. 
The timing issue had the effect of
undervaluing assets by around £1.200
million in 2021/22. As this error had also
occurred in previous years, the
cumulative effect was to increase the
valuation of the affected non-current
assets by approximately £16.768
million.

Page 12

1. Audit of 2021/22 annual accounts | 12 
Issue Resolution 
3. Misclassification of non-current assets 
Our review identified that some significant assets
classified as ‘assets under construction’ were, in
fact, operational. This included the new district
heating energy centre in Clydebank, which has
been operational since 2020/21. 
Depreciation should be charged on an asset if it
can be operated as intended. Assets totalling
£30.877 million required to be classified as
infrastructure or land and buildings assets, and
additional depreciation charges were necessary as
a result. 
The annual accounts have been
amended accordingly. An additional
depreciation charge of £1.466 million
was made as a result.  
4. Capitalisation of salary costs
The unaudited accounts included approximately
£4.397 million (£3.984 million in 2020/21) of
employee costs which had been capitalised for the
development of a number of assets, for example
surveying or legal costs. 
Although this treatment is permitted under
International Accounting Standard 16 (property
Plant and Equipment) in specific circumstances,
the related costs had not been eliminated from the
income and expenditure statement. This had no
effect on the overall net expenditure figure.
Management has made the necessary
amendments in the accounts for the
current and prior year figures.
5. Overstatement of debtors and creditors
Our review of working papers identified that funds
relating to the European Social Fund (ESF) and
the Construction Industry Scheme (CIS) were
double counted overstating both debtors and
creditors by £2.343 million and £1.238 million
respectively. We also identified an overall credit
balance of £0.359 million misclassified within
debtors.
The necessary amendments have been
made in the accounts. These
adjustments decreased debtors and
creditors by £3.222 million, having a nil
effect on net assets.
Management should review the year-
end procedures to ensure that debtors
and creditors are correctly accounted
for.
Recommendation 2
(Refer Appendix 1, action plan)  
Source: Audit Scotland
28.  Other findings we identified:
• Depreciation charges: A depreciation charge is an expense
representing how much of a non current asset's value has been 'used

Page 13

1. Audit of 2021/22 annual accounts | 13 
up' in a year. Following production of the unaudited accounts,
management identified that the depreciation charge on some assets
was incorrect due to formula errors. This gross misstatement of £1.197
million resulted in a net increase to the net book value assets of £0.361
million.
• Group subsidiaries: Two of the council’s subsidiaries (Clydebank
Property Company and the Common Good Fund) had a balance of
£7.863 million incorrectly classified as property, plant and equipment,
and investments. They should have been shown as investment
properties, which has implications for the way these are accounted for.
This was a classification issue with a nil effect on total assets.
Management have made the necessary corrections.
• Accounting policies: Common Good assets with a value of £3.489
million are held as investment properties, per the accounting standards
these assets must be held at fair value and revalued each year. There
is no accounting policy in the unaudited accounts relating to common
good or investment properties. Management have now revalued these
assets, which has had a negligible effect, and updated the accounting
policy to revalue these assets each year.
• Capital commitments: A planned spend of £2 million in relation to the
Scottish Marine Technology Park was not included in the capital
commitments disclosures.
• Fully depreciated assets: Our review of non-current assets identified
that fully depreciated assets are removed from the asset register and
are no longer recognised in the annual accounts. This is the appropriate
accounting treatment where an asset has been disposed of. However, if
the council continues to use assets that are fully depreciated, they
should consider whether they should be revalued and depreciated over
the estimated further useful life. To identify fully depreciated assets
which remain in use, management should undertake an asset
verification exercise of material assets. Appropriate accounting
adjustments should then be made for material assets which remain
operational assets of the organisation. 
29.  We have obtained audit assurances over the identified significant risks of
material misstatement to the financial statements. Exhibit 3 sets out the
significant risks of material misstatement to the financial statements we
identified in our 2021/22 Annual Audit Plan audit. It summarises the further audit
procedures we performed during the year to obtain assurances over these risks
and the conclusions from the work completed. 
30.  Our most significant findings in 2021/22 relate to the accounting treatment
of non-current assets. This area involves complex calculations and estimates
which can materially alter the largest values on an organisation’s balance sheet.
Auditors and regulators across the public and private sectors have increased
their focus on areas where more judgement is exercised, such as property
valuations.

Page 14

1. Audit of 2021/22 annual accounts | 14 
31.  While the errors have been corrected, procedures need to be improved to
ensure the accuracy of the non-current asset figures in the 2022/23 annual
accounts, before they are presented for audit.
Recommendation 1
The council should review its capital accounting procedures for non current
assets, with a view to improving the systems used to record entries, compliance
with accounting requirements, review processes, and communication with asset
owners.
Exhibit 3
Significant risks of material misstatement reported in the 2021/22 Annual Audit Plan
Audit risk Audit response to risk Results and conclusions
1. Risk of material
misstatement due to the
fraud caused by the
management override of
controls
As stated in International
Standard on Auditing (UK)
240, management is in a
unique position to perpetrate
fraud because of
management’s ability to
override controls that
otherwise appear to be
operating effectively. 
• Assess the design and
implementation of controls
over journal entry
processing.
• Make inquiries of
individuals involved in the
financial reporting process
about inappropriate or
unusual activity relating to
the processing of journal
entries and other
adjustments.
• Test journals entries with a
focus on significant risk
areas.
• Evaluate significant
transactions outside the
normal course of business
identified through audit
testing of income and
expenditure, accruals and
cut off transactions.
• Assess the adequacy of
controls in place for
identifying and disclosing
related party relationship
and transactions in the
financial statements.
• Review accounting
estimates for evidence of
management bias
including assessing any
Results: We assessed the
design and implementation of
controls over journal entry
processing. No significant
issues were noted.
Management did not identify
any inappropriate or unusual
activity with journals or other
adjustments.
Journal adjustments were
tested, and no indications of
management override of
controls were found.
We reviewed transactions
during the year - no issues
were highlighted of significant
transactions outside the
normal course of business.
Judgements and estimations
applied were tested to
confirm they were appropriate
and reasonable.
Conclusion: There was no
evidence of management
override of controls from the
work we performed.

Page 15

1. Audit of 2021/22 annual accounts | 15 
Audit risk Audit response to risk Results and conclusions
changes to the methods
and underlying
assumptions used to
prepare accounting
estimates compared to the
prior year. 
2. Estimation in the
valuation of Property, Plant
and Equipment
West Dunbartonshire
Council’s property, plant and
equipment had a net book
value of £1,111,227 million as
at 31 March 2021.
There is a significant degree
of subjectivity in the valuation
of this category of assets.
Valuations are based on
specialist and management
assumptions, and changes in
these can result in material
changes to financial
disclosures.
• Review of the work of
the valuer, including
focused substantive
testing of the
classification and
valuation of assets. 
• Evaluate the
competence,
capabilities, and
objectivity of the
professional valuer. 
• Confirm asset values in
valuation certificates are
fairly reflected within the
2021/22 accounts
• Review the annual cycle
of valuations to ensure
that assets have been
valued within the five-
year rolling programme. 
• Evaluate the approach
taken to ensure that
assets not subject to
revaluation in 2021/22
are not materially
misstated.
• Assess the adequacy
disclosures in the
accounts covering the
valuation of the property,
plant and equipment. 
Results: Our review of the
council of the internal and
external valuation team
confirmed the
appropriateness of the
methodology and
assumptions used. 
Conclusion: We have made
a number of findings in
relation to non-current assets
which are detailed in Exhibit
2. 
Recommendation 1
The council should review
its capital accounting
procedures, for non current
assets, with a view to
improving the systems
used to record entries,
compliance with
accounting requirements,
review processes, and
communication with asset
owners.   
Other areas of audit focus
32.  We identified in our 2021/22 Annual Audit Plan areas where we considered
there to be other risks of material misstatement to the financial statements.
Based on our assessment of the likelihood and magnitude of the risk, we did not
consider these to represent significant risks. The areas of specific audit focus
were:

Page 16

1. Audit of 2021/22 annual accounts | 16 
• The pension liability valuation due to the material value and significant
assumptions used in the calculation of the liability.
• The consolidation and disclosures for the West Dunbartonshire Energy
LLP company due to this being the first year of consolidation for this
entity into the council’s Group.
• The loans fund holiday due to use of the Covid-19 financial flexibilities
available to the council.
33.  We kept these areas under review throughout our audit. We identified
improvements to some of the disclosures relating to the loans fund holiday and
the consolidation of the energy company: 
• Following its first year of inception, the new council-owned West
Dunbartonshire Energy LLP was reported in the accounts as having a
net liability at 31 March 2022 of £0.397 million, funded as a working
capital advance from the council. This is likely to be repaid over a
number of years at a market interest rate. This capital amount of £0.397
million was accounted for a debtor in the council’s accounts, however it
is more appropriate to re-classify this as an investment held within non-
current assets. We have commented positively on this innovative
scheme in paragraph 80. 
• The finance circular which permitted use of capital receipts to fund
Covid-related expenditure required the approval of full council.
Retrospective agreement is expected to be sought for this in October
2022. 
34.  Management made the necessary adjustments for these issues and there
are no further matters which we need to bring to your attention. 
Identified misstatements of £138.610 million were adjusted in
the annual audited accounts 
35.  We identified misstatements with a gross value of £138.610 million in the
unaudited annual accounts. As the total was above our performance materiality
level, we considered the need to revise our audit approach. We reviewed the
nature and causes of these misstatements to consider the need for additional
audit testing. As a result of the errors identified, we undertook additional testing
in some areas to address these areas of risk.
36.  Management has adjusted the accounts to correct all the misstatements.
These adjustments have contributed to the total comprehensive net income
increasing by £31.776 million, with a corresponding increase in total reserves.
Further details of some of the more significant adjustments are included in
Exhibit 2.

Page 17

1. Audit of 2021/22 annual accounts | 17 
The council applied the statutory override for the accounting
for infrastructure assets included in its property plant and
equipment assets 
37.  The Code of Practice for Local Authority Accounting in the United Kingdom
(the Code) requires infrastructure assets to be measured using the historical
cost measurement basis and carried at depreciated historical cost. Where a
component of an asset is replaced, the carrying amount (i.e., net book value) of
the old component shall be derecognised to avoid double counting and the new
component shall be reflected in the carrying amount of the infrastructure asset.
38.  Due to practical difficulties in applying component accounting for the
recognition and derecognition of replaced components of infrastructure assets,
in large part due to data limitations, the Scottish Government approved a
Statutory Override - Accounting for Infrastructure Assets that is applicable to 31
March 2024. The statutory override is formed of two parts:
• Statutory Override 1: For accounting periods commencing from 1 April
2021 until 31 March 2024 a local authority is not required to report the
gross cost and accumulated depreciation for infrastructure assets.
• Statutory Override 2: For accounting periods commencing from 1 April
2010 until 31 March 2024 the carrying amount to be derecognised in
respect of a replaced part of an infrastructure asset is to be taken to be
and accounted for as a nil amount. No subsequent adjustment shall be
made to the carrying amount of the asset with respect to that part.
39.  Where a local authority chooses to adopt either or both statutory overrides,
this should be disclosed within the relevant note to the annual accounts.
40.  West Dunbartonshire Council applied both parts of the statutory override in
its 2021/22 annual accounts. As part of our audit, we reviewed the infrastructure
assets disclosures and the related notes, including the relevant disclosure in the
accounting policies. We are satisfied that these disclosures reflect the statutory
override and adequately explain the approach adopted to the readers of the
annual accounts.
The council’s 2021/22 management commentary provides a fair
and balanced picture of its performance and operational
activity for the year 
41. Management commentaries included within the annual accounts should
provide information on its main objectives and the principal risks faced. It should
provide a fair, balanced and understandable analysis of an organisation’s
performance as well as helping stakeholders understand the financial
statements. 
42.  The management commentary in the 2021/22 annual accounts provides a
good analysis of the council’s financial performance throughout the year. It
explains how the council has performed against its budget and how this is
reconciled to the financial statements. The council has also included a good
level of disclosure on the principal risks it is facing going forward. This includes

Page 18

1. Audit of 2021/22 annual accounts | 18 
details on the scale of financial challenges, including those as a result of the
pandemic, which will continue to be an area of focus for the foreseeable future. 
43.  In our view, the 2021/22 disclosure represents a fair and balanced
commentary on the council’s performance in 2021/22 
We have given an unqualified opinion on the financial
statements for the charities administered by the council
44.  Due to the interaction of section 106 of the Local Government in Scotland
Act 1973 with the charities legislation, a separate independent auditor's report is
required for the statement of accounts of each registered charity where
members of West Dunbartonshire Council are sole trustees, irrespective of the
size of the charity. 
45.  West Dunbartonshire Council administer the Dr A K Glen and West
Dunbartonshire Charitable Trusts, a registered charity that incorporates five
trust funds. A single statement of accounts is produced each year covering the
five trust funds and as at 31 March 2022 a cumulative balance of £0.262 million
was held in these funds.
46.  Our audit opinions on the Section 106 charities are unmodified. 
47. Our duties as auditors of the charities administered by West
Dunbartonshire Council are to:
• express an opinion on whether the charity’s financial statements
properly present the charity’s financial position and are prepared in
accordance with charities legislation
• read the trustees’ annual report and express an opinion as to
whether it is consistent with the financial statements
• report on other matters by exception to the trustees and to the Office
of the Scottish Charity Regulator (OSCR)
48. We have given an unqualified opinion on the financial statements for
the charities administered by the council and have nothing to report in
respect of other matters.
49. Two wider dimension risks were identified during the planning process.
These related to the potential dormancy of certain charitable trusts, and
the governance and investment documentation for the following charitable
trusts:
• Dunbartonshire Educational Trust Scheme 1962
• McAuley Prize for Mathematics
• UIE Award
50.  These trusts continue to face prolonged legal and administrative
challenges in order for them to discharge their obligations, which we have

Page 19

1. Audit of 2021/22 annual accounts | 19 
reported in previous years. The Dunbartonshire Education Trust requires a
meeting of the governors appointed from four local authorities in order to
formally adopt a reorganisation scheme. The McAuley Prize bequest is
without governing documentation, and so requires a new trust deed. We
understand that the council is seeking to agree new trustees for the UIE
award, which is dormant, and a court petition is required to made a formal
appointment. As a result, they are included in the agreed action plan at
Appendix 1. Action plan 2021/22
51. Only one of the charitable trusts made a payments during 2021/22,
which was a single award of £19,800 from the Dr A K Glen fund. Since our
report last year, the council has provided further information on its website
on the charitable trusts, including an application form. However, only one
application was made in-year. As the appointed auditors of the Section
106 charities administered by the council, we are required to consider
whether the funds held within the trusts are being used for the purposes
intended. This includes reporting any inappropriate use of funds or
prolonged lack of activity - the 'public benefit' test.
52. A charity is not failing the public benefit test if they are not providing benefit
in any particular year. However, if no benefit is being delivered for an extended
period then the charity could be considered to be dormant. If a dormant charity
has no clear plans to rectify that, it may be appropriate for us as external
auditors to report this to the Office of the Scottish Charity Regulator (OSCR)
Refer recommendations CH1 and CH2 in the Action Plan. 
Recommendation CH1
The trustees of the charities should continue to seek a resolution to legal and
administrative barriers which prevent charitable objectives being achieved. 
This should include taking steps to make their existence more widely known, and
applications more accessible.
Good progress was made on prior year recommendations 
53.  The council has made good progress in implementing our prior year audit
recommendations. For actions not yet implemented, revised responses and
timescales have been agreed with management, and are set out in Appendix 1.

Page 20

2. Financial management | 20 
2. Financial management
Financial management is about financial capacity, sound budgetary
processes and whether the control environment and internal controls
are operating effectively.
Main judgements
Financial management is effective and the council operated within budget in
2021/22. Elected members receive regular updates to ensure they are kept up to
date with the impact on services. 
The Covid-19 pandemic continues to have a significant impact on the council’s
finances. The use of two new Scottish Government financial flexibilities added
£1.454 million of income on top of £4.488 million of direct unearmarked Covid-19
funding. At 31 March 2022, £3.445 million of Covid-19 funding was unspent for
use in future years. 
The council’s outstanding loans total £578.408 million. Recent interest rate rises
may present a longer-term risk for the council. 
A trend of significant levels of delay to capital projects continues, with 42% of
planned capital expenditure slipping beyond milestones, although the impact of
the pandemic was a significant factor. 
The innovative district heating network is operational, funded by a significant
investment from the council and managed by its own green energy company
The council’s financial management processes are effective
54. During the 2021/22 annual budget setting process we observed that elected
members were provided with projected funding gaps and savings options to
enable them to make soundly based decisions on closing any funding gaps.
Based on our observations of the budget setting process, we are satisfied that
the council’s budget setting process operates effectively.
55. Performance against budget and projected outturn was reported to
members during the year through budgetary control reports, allowing action to
be taken on any unplanned variances. Additionally, Covid-19 update papers at
council meetings provided information on additional funding and financial
pressures on services.

Page 21

2. Financial management | 21 
The council operated within budget in 2021/22, with spending
tightly controlled to deliver a small surplus of £0.159 million 
56.  The council approved its 2021/22 budget in March 2021 (22 March 2021).
The initial budget was set at £231.919 million, and was further revised
throughout the year as more information on additional Covid-related funding
was released. By the year-end, total budgeted expenditure had increased to
£252.986 million, with £6.460 million income attributable for Covid-19 purposes. 
57.  The results from a previous consultation with West Dunbartonshire
residents, held in 2019, were used in the 2021/22 budget setting process as the
outcomes of the previous process were considered to remain valid in closing
the budget gap in 2021/22. The updated budget paper presented to the Council
on 23 March 2022 projected a favourable variance on the revenue budget of
£0.057m (0.02% of total budget), with agreed savings of £3.212 million reported
as on track to be achieved. The actual in-year surplus delivered was £0.159
million against the budget.
58.  The main favourable variances against budget, particularly within corporate
and education services, were due to actions such as control of staff vacancies
and efficiency reviews, as well as less than anticipated demand for services.
59.  The changes in the budget position were reported in revenue budget control
reports presented to members throughout the year. These reports contained a
good level of detail on the forecast outturn position, as well as details on the
costs of Covid-19 and the funding received in support of this.
The council received £4.488 million of direct unearmarked
Covid-19 funding, and administered around £14 million of
agency income, to alleviate the impact of the Covid-19
pandemic on individuals, businesses and the economy
60.  At the time of setting the 2021/22 budget, the council had moved on from
the initial emergency response to the pandemic but was continuing to respond
to unprecedented challenges to the delivery of services. Ongoing restrictions,
Covid-19-related staff absences and the uncertain nature of the pandemic, for
example the emergence of the Omicron variant, resulted in adaptation and
disruption to service provision. The unprecedented impact on public finances of
the Covid-19 pandemic has been reported in the Local Government in Scotland
Overview 2022.  
61.  West Dunbartonshire Council received £4.488 million in Covid-19 related
funding in 2021/22 (£20.43 million in 2020/21), plus £1.973 million which had
been carried forward from 2020/21. The council used two new financial
flexibilities made available by the Scottish Government to mitigate the financial
impact of Covid-19 in 2021/22. This provided a further £1.454 million of
additional funding, although will come at a cost to the council in future years as
loan fund payments increase. The flexibilities permit:
• capital receipts being used to finance Covid-19 revenue expenditure

Page 22

2. Financial management | 22 
• a Loans Fund repayment holiday to defer loans fund repayments due to
be repaid in 2021/22.
62.  A total of £3.445 million Covid funding was transferred to the council’s
general reserve. This will be used to manage the ongoing budget pressures
resulting from the pandemic in 2022/2023 and beyond.
63.  Throughout 2021/22 the council has played a key role in supporting
individuals and families through the financial burden of the pandemic. This
included facilitating support for:
• those self-isolating
• provision of free school meals
• funding for education recovery
• advice to businesses
64.  The council was responsible for administering £14.284 million of payments
to various business and support grant schemes. Due to grant conditions, these
business support funds are considered to represent an agency agreement.
Agency payments are those paid out by the council on behalf of another
organisation, in this case the Scottish Government. As such, the £14.284 million
does not appear in the council’s annual accounts, except for being appropriately
disclosed in its management commentary. 
65.  We reviewed the council’s accounting treatment for each of the grants
against the applicable guidance and concluded that the council had classified,
and where required, correctly accounted for the grants in its 2021/22 annual
accounts.
66.  Despite the impact of the pandemic on the economy, the council's in-year
collection of council tax increased slightly from 94.18% in 2020/21 to 94.53% in
2021/22. This may be due to eased payment terms and follow-up processes to
assist residents.
The housing revenue account reported an overall deficit 
of £4.630 million funded through a use of reserves
67.  The council is required by legislation to maintain a separate housing
revenue account and to ensure that rents are set a level which will at least
cover the costs of its social housing provision. As at the end of March 2022,
West Dunbartonshire Council owned 10,378 housing units.
68.  In March 2021, the council approved a 1.5% increase in the average weekly
rent levels for tenants for 2021/22. The rent level was set to reflect the income
required to fund the revenue budget of £46.168 million. In 2021/22, the council
recorded a deficit on HRA services of £4.63 million which has been funded
through use of reserves, which at the start of the year stood at £7.364 million.
This is in line with the HRA financial plan to fund some capital from revenue to
reduce the costs of borrowing.

Page 23

2. Financial management | 23 
69.  The standing Council policy is that an HRA Prudential Reserve of 2% of
gross expenditure should be maintained, which equates to £0.923m for
2021/22. The balance available to the HRA for future use is £2.734m.
70.  Last year we noted that issues relating to the Housing Repair telephone
contact centre had been reported, with tenants facing a lengthy wait to resolve
problems. The council acknowledged the deterioration in service and put in
place measures to alleviate this, including planned recruitment. 
71.  The net surplus on the housing maintenance trading account was £0.568
million from a total budget of £1.4 million. Continuous high levels of Covid-
related absence, together with the national skills shortage and higher supplies
costs, caused difficulties in addressing the council’s repairs and maintenance
backlog. The reduction in repairs and maintenance activity during the year will
likely have a knock-on effect on the level of such activity required in future
years.  
72.  In March 2021, the Council approved the Housing Capital Programme
2021-2026, with an expenditure budget of £83.393m for the affordable housing
supply programme. 
73.  Through the Council’s Strategic Housing Investment Plan, supported by the
Scottish Government’s Affordable Housing Programme, more than 1000 new
social homes for rent were completed in West Dunbartonshire by the council
and private sector partners by April 2022, including 467 new council homes. In
2021/22, the council delivered 211 new-build homes.
A trend of significant levels of delay to the council’s capital
projects continues, with 42% of planned capital expenditure
slipping beyond milestones
74. We reported in the Best Value Assurance Report (June 2018) that there has
been a trend of significant levels of capital slippage at the council over a
number of years and recommended that the council review its project
management processes and consider performing self-assessments to identify
areas for improvement. In response to this recommendation the council agreed
improvement actions to address the level of slippage. These actions were
completed during 2018/19 and the council anticipated these would lead to
improvements in the delivery of the capital programme going forward.
75. The council’s overall capital programme includes a number of high-profile
and ambitious projects, such as redevelopment of the ExxonMobil site in
Bowling, and regeneration of Dumbarton town centre. For 2021/22, the council
had a budgeted capital programme of £105.054 million split between £56.726
million for planned general services capital projects and £48.328 million for HRA
capital works. 
76. Total capital expenditure in 2021/22 was £64.219 million of which £33.619
million related to general services and £30.600 million to the HRA capital
programme. The total in-year slippage was £44.883 million (42 per cent), with
slippage of £24.958 million (44 per cent) against the general services
programme and £19.925 million (42 per cent) against the HRA programme.

Page 24

2. Financial management | 24 
77. Overall, 42% of planned capital expenditure slipped beyond anticipated
milestone (in 2020/21 this percentage was 34%). The pandemic was noted as
being the main factor behind these reductions, with material shortages and
longer lead times impacting on the supply chain.
Exhibit 6
Summary of significant under/overspends against budget
Project
Budgeted
Spend in
2021/22
Actual
Spend Slippage 
(£m) (£m) (£m) (%) Explanation for slippage
General Services 
District heating
network
expansion
3.600 0.000 3.600 100 Network expansion to
Golden Jubilee National
Hospital will commence
pending positive
commercial discussions.  
Heritage
Capital Fund
2.550 0.875 1.676 66% COVID impacted on the
timescale for delivery of a
number of projects
including Clydebank Town
Hall, the Clydebank
Museum, and the Dalmuir
Library and Gallery. Work
is now underway to get
these projects progressed.
Vehicle
Replacement 
3.042 1.442 1.600 53% Delay due to the vehicle
build time associated with
the specialist vehicles and
the delivery lead time from
the date of supply order
placement.
Schools Estate
Improvement
Plan 
6.200 4.180 2.020 33% As a result of COVID Skills
School was rephased
during 2021/22 and further
costs are still expected for
Renton Campus.
HRA 
New house
build
20.281 7.389 12.892 64% Due to a number of
different complexities there
were delays to getting on
site across each of the
new build sites.

Page 25

2. Financial management | 25 
Project
Budgeted
Spend in
2021/22
Actual
Spend Slippage 
(£m) (£m) (£m) (%) Explanation for slippage
Projects to
deliver housing
strategies (Buy
Backs)
1.706 1.036 .670 39% These are subject to
stringent criteria to ensure
accountability and value
for money for tenants and
involves several key
stakeholders which
resulted in time delays
Doors/Windows 3.831 1.357 2.474 65% Installations are behind
original planned targets
due to internal and
external contractor
resource issues
Building
external
components
4.088 2.105 1.983 49% Resource issues has
delayed the roof renewal
programme which
continues into 2022/23.
Additional installations by
support contractors is
underway to assist
completions
Sources: Capital spend outturn report 2021/22, West Dunbartonshire Council August 2022, 
West Dunbartonshire Council unaudited annual accounts 2021/22
78.  It is important that the council addresses the slippage caused by the
pandemic. As the impact of the pandemic eases, we would anticipate a return to
pre-pandemic levels of programme delivery. In its Local Government in
Scotland: Overview 2022 report the Accounts Commission highlighted the
important role of capital investment in councils’ recovery from the pandemic. 
79.  In particular, there is a need for investment to be aligned with plans to tackle
the impact of climate change, with modernisation of councils’ estates needed to
ensure carbon reduction targets are achieved. 
The innovative Clydebank district heating network is now
operational, run by the council’s own green energy company
80.  The importance of investment in this area is something the council has
recognised in its Climate Change Strategy, published in January 2021, and is
evident in sustainable and pioneering initiatives such as the district heating
network in Clydebank, which is the first large-scale water source heat pump
scheme of its kind in Scotland.

Page 26

2. Financial management | 26 
81.  The council has established its own energy company, West Dunbartonshire
Energy LLP, to operate and manage the system, with £0.397 million of working
capital advanced from the council.
82.  The council will fund £14.458 million of the cost of the system, with the
Scottish Government funding £6.1million through the Low Carbon Infrastructure
Transition Programme. Heat is now being supplied to council offices at Aurora
House, the Titan Enterprise Centre, Clydebank Leisure Centre and the new
care home at the site, Queens Quay House. Plans are in place to supply the
Clydebank Health Centre, over 140 flats and retail units currently on site, all
other homes planned for the site, as well as Clydebank Library and Clydebank
Town Hall.
The council has high levels of debt, with outstanding loans
standing at £578.408 million. Recent interest rate rises may
present a longer-term risk for the council
83. In recent years we have reported the council’s overall levels of debt as
compared to its annual revenue, which has been among the highest levels in
Scotland. In 2020/21, the ratio of net debt to revenue was 220 per cent. Using
the same methodology this has now improved slightly to 217 per cent.
84. At 31 March 2022, the council’s total outstanding borrowing stood at
£578.408 million (excluding PPP debt of £92.485 million), an increase of
£29.749 million on the 2020/21 level of £548.659 million. Loan repayments of
£320.748 million were made during 2021/22, new loans of £350.500 million
(long-term loans of £35 million and short-term loans of £315.500 million) were
taken out during the year. 
85. As with recent years, the additional borrowing was required to help finance
the council’s capital programme and short-term borrowing was used to take
advantage of low interest rates.
86. We recognise that the council’s borrowing figure includes debt associated
with both the HRA and the council’s PPP assets which not all Scottish local
authorities have, and that the current cost of borrowing is at historically low
levels. The significant proportion of borrowing presents a risk for the council if
interest rates on debts increase. Management has indicated it intends to
conduct a review of the capital programme to report in December 2022, with
recommendations to reduce costs. Exhibit 7 shows the scale of recent
increases to the UK base interest rate since 2012.

Page 27

2. Financial management | 27 
Exhibit 7
Bank of England base interest rate since 2012 
Source: Bank of England (https://www.bankofengland.co.uk/boeapps/database/Bank-Rate.asp)
Internal controls operated effectively during 2021/22
87.  As part of our 2021/22 audit, we tested the key controls operating over the
main accounting systems. Our objective was to gain assurance that the
systems for processing and recording transactions provide a sound basis for the
preparation of the annual accounts. 
88.  Our controls work did not identify any significant risks of material
misstatement, with the internal controls providing a sound basis for the
preparation of the annual accounts. 
Internal audit provided a ‘generally satisfactory’ level of
assurance over the council’s governance, risk management,
and internal controls in place during 2021/22
89.  The internal audit service, in any organisation, is an important element of
internal control. It provides members and management with independent
assurance on risk management, internal control and corporate governance
processes as well as providing a deterrent effect to potential fraud. 
90.  We found the council’s internal audit to be operating effectively, and in line
with the Public Sector Internal Audit Standards (PSIAS) requirements. 
91.  PSIAS require the provision of an annual internal audit opinion, to inform
the council's annual governance statement. The Shared Service Manager –
Audit & Fraud issued her Annual Assurance Statement to the Audit Committee
in June 2022 which included the opinion that: The report concludes that the
majority of West Dunbartonshire Council’s established internal control
procedures operated as intended to meet management's control requirements
for each area reviewed by Internal Audit in 2021/22. The overall audit opinion
was “Generally Satisfactory with some improvement needed”. The
improvements required related to aspects of stock security and use of council
vehicles. Management is progressing actions in line with agreed timescales. 
0
0.5
1
1.5
2
2.5
2012
2013
2013
2013
2014
2014
2014
2015
2015
2015
2016
2016
2016
2017
2017
2017
2018
2018
2018
2019
2019
2019
2020
2020
2020
2021
2021
2021
2022
2022

Page 28

2. Financial management | 28 
The council has in place appropriate arrangements for the
prevention and detection of fraud and corruption
92.  The council has a range of established procedures for preventing and
detecting fraud and irregularity including a whistleblowing policy, anti-fraud
strategy and codes of conduct for members and officers. 
93.  The council continues to participate in the National Fraud Initiative (NFI).
This is a counter-fraud exercise across the UK public sector which aims to
prevent and detect fraud. By the end of March 2021, 52% of matches had been
actioned in relation to the 2020/21 exercise, with progress delayed due to
vacancies in the internal audit service. 
94.  We have concluded that the council has generally appropriate
arrangements in place for the prevention and detection of fraud and corruption.
We are not aware of any specific issues we require to bring to your attention.

Page 29

3. Financial sustainability | 29 
3. Financial sustainability
Financial sustainability looks forward to the medium and long term to
consider whether the council is planning effectively to continue to
deliver its services or the way in which they should be delivered
Main judgements
The budget for 2022/23 is £252.394 million, with a range of cost-saving measures
used to close a budget gap of £5.508 million. 
The council faces significant financial challenges in the years ahead, with the
estimated budget gap growing to £19.849 million by 2024/25. Total usable net
reserves have decreased by £5.158 million. 
Transformational change aligned with effective medium and longer-term planning
is required to address the impacts of the Covid-19 pandemic together with
growing inequalities, cost-of-living pressures, and the changing needs of citizens. 
The budget for 2022/23 is £252.394 million, with a range of cost-
saving measures used to close a budget gap of £5.508 million
95.  As part of the 2022/23 budget-setting process, a report to the Council on 9
March 2022 estimated an initial budget gap of £5.508 million. A range of options
were presented to close the gap. These included the use of reserves (£1.034
million), the continued use of financial flexibilities permitted to allow councils to
respond to Covid (£0.700 million), a 3% increase to Council tax and a proposal
to negotiate the funding split of residential child placements with the HSCP
(£1.365 million).
96.  The council approved a total net revenue budget of £251.064m for 2022/23
in March 2022. Since then additional funding, including Covid-related income,
has been provided by the Scottish Government bringing the revised net budget
to £252.394 million. 
97.  As at the end of July 2022, an overspend of £0.318m was projected for
2022/23 (0.13% of the total budget). Officers reported that from identified
savings measures of £0.276 million, £0.251 million are on target to be achieved.
A budgeted assumption to reduce residential care costs by £1.365 million – by
increasing the West Dunbartonshire Health and Social Care Partnership’s share
of costs from 50% to 77% – requires the agreement of both parties, and has not
yet been agreed.

Page 30

3. Financial sustainability | 30 
The council faces significant financial challenges in the 
years ahead, with the estimated budget gap growing to 
£19.849 million by 2024/25
98.  The budget also estimated future annual budget gaps based on a range of
assumptions including future Scottish Government funding, inflation, council tax
increases and interest rates. At the time of setting the budget in March 2022,
projections identified expected budget gaps of £13.761m in 2023/24 rising
cumulatively to £18.622m in 2024/25. 
99.  The Scottish Government's Resource Spending Review, published in May
2022, indicates intentions that local government funding will remain as ‘flat
cash’, i.e. static, at current 2022/23 levels until 2025/26 with a further £100m
added in 2026/27. This would mean requiring the council to absorb inflationary
and pay award increases, as well as increases to energy costs. In addition,
there is uncertainty over how long Covid-related funding will continue to be
made available to promote recovery. 
100.  In June 2022, the Chief Officer – Resources presented to the council an
updated assessment of the financial challenges facing the council. The
assumptions underpinning the previous budget gap projections were refined.
This included removing an assumption that council tax would increase by 3%,
higher inflation, interest rates and pay awards, and increasing utility costs. The
revised projection estimates a deteriorating position for the council, (Exhibit 10)
with a mid-range scenario now projecting a £19.849 million annual deficit
position by 2024/25 unless significant savings can be made.
101.  The local government pay settlements for 2022/23 will add substantial
pressures to the council’s budgets. The council is currently considering how the
increases will be funded.   
Exhibit 8
West Dunbartonshire Council - Identified budget gaps 2023/24 to 2024/25 (cumulative) 
Budget gap 
scenario
2023/24
£000
2024/25
£000
Best Case  13,636 18,709
Mid-Range 14,309 19,849
Worst Case 22,164 34,724
Source: Financial Update, West Dunbartonshire Council, 22 June 2022

Page 31

3. Financial sustainability | 31 
102.  Achieving the required savings for 2022-2025, against a backdrop of the
continuing financial impact of the Covid-19 pandemic and significant inflationary
cost pressures, is likely to prove challenging. 
103.  The council has a long-term financial strategy in place which is updated
annually and was refreshed in October 2021. It reflects the impact of the
pandemic on financial and service pressures, identifies budget gaps and
provides clear links to the council’s strategic objectives. The long-term
cumulative anticipated funding gaps identified have since been reviewed and
increased, as we note above. 
Transformational change aligned with effective medium and
longer-term planning is required to address the impacts of the
Covid-19 pandemic together with growing inequalities, cost-of-
living pressures, and the changing needs of citizens
104.  There remains uncertainty over the longer-term funding position for
councils. In its Local Government in Scotland: Overview 2022 report, the
Accounts Commission reports that councils have seen their underlying
cumulative funding fall by 4.2 per cent in real terms since 2013/14 (excluding
Covid-19 funding). This contrasts with an increase of 4.3 per cent in Scottish
Government funding of other areas of the budget over the same period. 
105.  This funding reduction is against the backdrop of a range of new
challenges facing councils, including decisions on what services to reinstate
and redesign, and to what level, following the Covid-19 pandemic. Councils
across Scotland have struggled in the past to bring about the level of change
that is needed to deliver public service reform, sustainable local government,
and better outcomes 
106.  Transformation programmes, aiming to improve how councils operate,
have been disrupted by Covid-19. The budgeted spend in 2021/22 for
transformational programmes was £0.526m, and the actual spend as at 31
March 2022 was £0.383m. This includes investment in digital transformation
within the council, automation projects and restructuring savings. 
Total usable net reserves have decreased by £5.159 million
107.  One of the key measures of the financial health of a body is the level of
reserves held. Usable reserves are those that the council is able to apply to
fund expenditure or reduce taxation, and comprise both capital and revenue
reserves. The level of usable reserves held by the council decreased by £5.158
million, from £24.211 million to £19.052 million during 2021/22, as shown in
Exhibit 6. This is largely attributable to the decision to fund the in-year HRA
deficit through reserves in order to reduce future borrowing costs.

Page 32

3. Financial sustainability | 32 
Exhibit 9
West Dunbartonshire Council’s usable reserves 
Reserve 31 March 2021
(£m)
31 March 2022
(£m)
General fund 15.028 15.020
Housing revenue account  7.364 2.734
Capital receipts reserve 0 0.030
Capital grants and receipts unapplied  0.042 0.042
Capital reserve 1.469 0.758
Other reserves 0.308 0.468
Total usable reserves 24.211 19.052
Source: Note 29, West Dunbartonshire Council Annual Accounts 2021/22
108.  The council’s general fund balance is £15.020m as at 31 March 2022, of
which £11.517m is earmarked for specific purposes. The council's prudential
reserves policy is to retain a prudential reserve of 2% of net expenditure
(excluding funding requisitions to bodies such as the HSCP, Valuation Joint
Board, SPT) in order to safeguard assets and protect services against financial
risk. This target equates to £3.123 million in 2021/22, therefore the council has
exceeded this target by £0.380 million. The overall position of the reserves was
considered as part of the budget process for 2022/23.
109.  General earmarked reserves have decreased by £0.174 million to £11.517
million. This includes carrying forward £6.791 of Covid-related funding to
2023/24. Exhibit 10 provides an analysis of the general fund balance over the
last five years split between the earmarked and uncommitted elements.

Page 33

3. Financial sustainability | 33 
Exhibit 10
Analysis of the general fund balance over past five years 
Source: West Dunbartonshire Council Annual Accounts 2016/17 to 2021/22
110.  Consideration of the wider context in which the council is operating in
helps to explain higher reserves balances in the past two years. The Accounts
Commission’s Local Government in Scotland: Overview 2022 report highlighted
that the increase in 2020/21 revenue reserves across most councils was largely
because of additional Covid-19 funding. The Commission recognised that this
funding had artificially inflated reserve positions, with councils unlikely to have
flexibility in the use of large elements of these reserves. This is evident from
review of the council’s total usable reserves, with Covid-19 earmarked monies
equating to 45.2% per cent (£6.791 million) of the total general fund reserve. 
0
2
4
6
8
10
12
14
16
2016/17 2017/18 2018/19 2019/20 2020/21 2021/22
£ million
Committed Uncommitted
0
2
4
6
8
10
12
14
2016/17 2017/18 2018/19 2019/20 2020/21 2021/22
£ million
Committed Uncommitted Prudential reserve

Page 34

3. Financial sustainability | 34 
111.  There are ongoing sustainability challenges of using reserves to fund
recurring expenditure, particularly as recovery and renewal from the pandemic
is progressed. The reserves accumulated in recent years may provide the
council with the opportunity to re-shape services to support sustainability going
forward. Beyond that, difficult decisions will need to be taken in the future, with
effective management of the council’s reserves key to maintaining financial
sustainability. 
The Scottish Government’s proposals for a new National Care
Service have the potential to significantly change the way that
social care services are structured and operate 
112.  Following the publication of the Independent Review of Adult Social Care
in February 2021, work is currently under way nationally to develop and
implement a new National Care Service (NCS). The Scottish Government
expects the new NCS to be operational by 2026. These proposals have the
potential to significantly change the way that social care services are structured
and operate.
113.  In its January 2022 Social Care briefing Audit Scotland noted stakeholders
concerns about the extent of the proposals for reform and the time it will take to
implement them. Many of the current issues experienced by the social care
sector, for example workforce pressures, cannot wait for the Scottish
Government to implement a new NCS. 
114.  West Dunbartonshire Council provided a formal response to the
consultation through the adoption of a response developed by Convention of
Scottish Local Authorities (CoSLA) and supplemented by the advice of the
council's chief officers. The response, agreed in November 2021, raised the
concern that “transformative change will not be achieved through the primarily
structural change that the consultation is proposing but by taking action now to
tackle the underlying causes of challenge”. 
Intention to abolish charges for non-residential care 
115.  At the June 2022 council meeting, a motion was passed with an intention
to abolish £1.5 million of non-residential care charges. The aim was that West
Dunbartonshire HSCP would cover this loss of income from the HSCP's
unearmarked reserves. At a subsequent meeting of the HSCP, voting members
were unable to agree on funding. The issue now lies with the Chief Executives
of the Health Board and the Council as per the Integration Scheme dispute
resolution process.
The council’s allocation from the Scottish Attainment fund is
set to reduce to £0.851 million by 2025/26
116.  The council’s annual Scottish Attainment Challenge (SAC) allocation is
due to reduce from £2.043 million in 2021/22 to £0.851 million in 2025/26. This
presents a challenge for the council in continuing to support improvements in
attainment levels for learners.

Page 35

3. Financial sustainability | 35 
117.  The money provided from the Attainment Scotland Fund since its launch
2015 has been targeted at supporting pupils in the nine local authorities of
Scotland with the highest concentrations of deprivation. It aims to achieve
equity in education through ensuring every child has the same opportunity to
succeed, with a particular focus on closing the poverty-related attainment gap. 
118.  In November 2021, the Cabinet Secretary for Education and Skills set out
to Parliament plans for SAC for 2022/23 to 2025/26. The allocations will taper
over four years towards a fully equitable distribution in 2025/26, ensuring
children and young people are supported across the country. The impact of this
on West Dunbartonshire Council is that its annual SAC allocation will reduce to
£1.745 million in 2022/23, with further gradual reductions to £0.851 million in
2025/26. This presents an additional challenge for the council in continuing to
support improvements in attainment levels across West Dunbartonshire.

Page 36

4. Governance and transparency | 36 
4. Governance and
transparency
The effectiveness of scrutiny and oversight and transparent reporting of
information 
Main Judgements
Following the May 2022 local government elections, the council has a new
administration. A comprehensive training programme is in place to support new
and returning elected members. 
Effective governance and decision-making arrangements were in place during
2021/22. The council conducts itself in an open and transparent manner.
Following the May 2022 local government elections, West
Dunbartonshire Council has a new administration
119.  Following the local government elections in May 2022, 22 members
representing the six multi-member wards were elected across West
Dunbartonshire. The political composition is as follows:
• Scottish Labour Party – 12
• Scottish National Party – 9
• West Dunbartonshire Community Party – 1
120.  In May 2022, at the first meeting of the new council, a Labour-led
administration was put in place succeeding the Scottish National Party who led
the council in the preceding five years. The established governance structure
has been maintained by the new administration. 
The council has a comprehensive training programme to
support new and returning councillors 
121.  Eleven new councillors were elected to the Council at the local
government elections in May 2022, with eight of those new members having
never served before. To support these new members, and continuing members,
the council provided a comprehensive induction programme which included
seminars and briefings on members’ key roles and responsibilities as
councillors. Tailored training was also provided to members based on their
specific responsibilities, such as for those sitting on the Licensing Board.

Page 37

4. Governance and transparency | 37 
122.  The council has also adopted the Continuing Professional Development
Framework, developed by the Improvement Service, for elected members to
provide feedback about their performance, and provide them with personal and
professional development opportunities.
Effective governance and decision-making arrangements were
in place during 2021/22 
123.  Elected members and management of the council are responsible for
establishing arrangements to ensure that its business is conducted in
accordance with the law and proper standards, that public money is
safeguarded and for monitoring the adequacy and effectiveness of these
arrangements. The governance and accountability arrangements we consider
include:
• council and committee structure
• overall arrangements and standards of conduct including those for
the prevention and detection of fraud, error, bribery and corruption.
This includes action in response to the National Fraud Initiative
• openness of council and committees
• reporting of performance and whether this is fair, balanced and
understandable.
124.  Audit committees and Council meetings continued to be held with a hybrid
option of attending virtually into 2021/22. This allowed members to undertake
their scrutiny role appropriately and, by June 2022, attendance in person
became more prevalent. The meetings continued to be audio streamed and
recordings made available after the meeting.
125.  Meeting papers are available on the council's website to support
transparency. The website also allows the public to access a wide range of
information including current service updates and restrictions due to Covid-19,
advice for individuals and businesses and how to contact the council or make a
complaint.
126.  No significant risks were identified from our review of the governance and
accountability arrangements in the council.
The council conducts its business in an open and transparent
manner
127. There continues to be an increasing focus on demonstrating the best use
of public money. The council support open and transparent business in several
ways such as:
• Live streaming and audio recording of council and service meetings.
This was in place prior to the pandemic and continued throughout.

Page 38

4. Governance and transparency | 38 
• Council and committee meeting papers and minutes are publicly
available on the council website. Elected members briefings are also
publicly available. 
• The council website contains a wide range of information including the
annual accounts, register of members’ interests, fraud reporting policies
and complaint procedures. 
128. We conclude that the council continues to demonstrate a commitment to
conducting business in an open and transparent manner. 
Collaboration and effective leadership is more important than
ever to ensure that outcomes are improved for residents
129.  In its Local Government in Scotland Overview 2022 report, the Accounts
Commission highlighted that recovery and renewal was not about returning to
the pre-pandemic status quo, but ensuring services are reshaped to meet the
new needs of the local area. To achieve this, strong leadership from councils is
needed. The council’s new and returning councillors should be willing and able
to make difficult decisions about where and how to spend its resource, with a
willingness to embrace collaborative working within the council and with
external stakeholders critical to achieving this.
130.  The new council has shown an appetite for collaboration, in establishing,
for example, a cross-party cost of living working group. We encourage members
and senior officers at the council to maintain an open and collaborative culture.
This will help drive improvement and innovation at the council which will in turn
will lead to better outcomes for residents.

Page 39

5. Best Value | 39 
5. Best Value 
Using resources effectively and continually improving services.
Main judgements
The council has made good progress in demonstrating improvement in its
services, but the capital programme continues to fall behind as a result of the
pandemic. 
Residents’ satisfaction with council services overall is high, but performance
indicators show challenges in tackling sickness absence levels, empty council
homes and recycling. 
The council has a climate strategy and action plan to address the challenge of
reaching net zero by 2045. 
The council has made good progress in demonstrating
improvement in its services, but the capital programme
continues to fall behind as a result of the pandemic
131.  Best value is assessed over the term of our appointment, as part of the
annual audit work. In addition, a Best Value Assurance Report (BVAR) for each
council is considered by the Accounts Commission at least once during this
period.
132.  The Best Value Assurance Report (June 2018) for West Dunbartonshire
Council reported that the council had made significant improvements in how it
works since the previous Best Value report in 2007. It highlighted that the
council now demonstrates a focus on delivering Best Value and there was
evidence of continuous improvement in its services. The report also included
five recommendations which were endorsed by the Accounts Commission.
133.  At its meeting on 29 August 2018, the council agreed a Best Value
Assurance Improvement Plan which included actions to address all
recommendations included in the BVAR. An update against the plan was
reported to the Council meeting in February 2020. It noted that all
recommendations within the BVAR Improvement Plan had been fully delivered
and activity on driving Best Value will continue.
134.  In subsequent annual audit reports we reported a summary of the
progress made against the BVAR recommendations. A current position
statement on the outstanding actions from 2020/21 is summarised in Exhibit 8.

Page 40

5. Best Value | 40 
Exhibit 11
Progress against outstanding BVAR recommendations 
Recommendation Audit Scotland view on progress to date
To reduce the level of slippage
on the capital plan, the council
should review its project
management processes.
Covid-19 continues to delay progress with the capital programme
As we detail in paragraphs 65 to 68, the council has reported slippage
against the capital programme. Although the project management
improvements are complete, there are still delays in progressing projects. 
In 2021/22 these occurred for various reasons, with the pandemic and its
knock-on effect on absences and supply chains clearly a significant factor.. 
Some staff are finding the pace
of change challenging and staff
absence remains an issue. The
council is taking positive steps
to try and address this and
should continue to explore
opportunities for improvement.
Significant successes in reducing sickness levels have been 
short-lived, with 2021/22 data showing a sharp spike in staff absences
We reported in our original BV report that the council had taken a range of
action to support staff and tackle sickness absence levels. The impact of
these actions had not yet been reflected in the reported sickness absence
figures, but we accepted that delivering such improvement would be a
longer-term process.
The latest data – relating to 2020/21 – from the Local Government
Benchmarking Framework (LGBF) shows that sickness absence per
employee (excluding teachers) in West Dunbartonshire Council decreased
to an average of 8.38 FTE days per employee (11.4 days in 2019/20). This
places the council favourably below the Scotland-wide average of 9.71 days
lost. 
A similar improvement could be seen with teachers, with only 1.68 FTE days
lost in 2020/21 (5.46 FTE in 2019/20), well below the Scottish average of
4.16 days, which made West Dunbartonshire Council as the best performing
council in Scotland in this regard. 
There remain concerns. Figures from the council's annual wellbeing update
show that council-wide absences in 2021/22 have spiked significantly to
14.55 FTE days lost per employee, the highest level since at least 2015/16.
In the absence of Scotland-wide benchmarking data, which is not yet
available, it will be important to understand this deterioration within a
national context. We recognise that officers continue to treat the underlying
reasons for sickness absence as a priority. Action taken by the Employee
Wellbeing group includes employee support initiatives, work with trade
unions, monthly webinars and an employee counselling service. 
The council has effective systems in place to monitor
performance and drive continuous improvement, which
support scrutiny of service performance
135. The council has effective systems in place to monitor performance
and drive continuous improvement. Members and officers effectively
scrutinised how services perform:
• Each Strategic Service Management Team considers performance
reports during routine management meetings.
• The Performance Monitoring and Review Group considers regular
reports from across strategic areas through its online performance
management system, Pentana. This monitors the performance
indicators linked to the strategic plan.

Page 41

5. Best Value | 41 
• Service committees meet every quarter and get regular performance
information.
• Service performance is reviewed through the Corporate Services
Committee, Education Services Committee, Housing and
Communities Committee and Infrastructure, Regeneration &
Economic Development Committee and annually through the council.
• Officers and councillors have a good understanding of what the
council has achieved and the challenges that remain.
136.  Based on our attendance at Council and committee meetings during
2021/22 we have concluded that these performance monitoring and reporting
arrangements continue to operate effectively and support scrutiny of service
performance.
The council has a climate strategy and action plan to address
the challenge of reaching net zero by 2045
137.  West Dunbartonshire Council launched its Climate Change Strategy in
January 2021 which has set a target to reduce WDC carbon emissions to ‘net
zero’ by 2045, aligning with Scottish Government targets. In order to ensure it
realistically meets its 2045 net zero target, the council recognises it will require
further internal funding (capital and revenue) and support from all service areas.
Exhibit 12
Climate Change Action Plan – 10 key themes to address climate change 
Source: West Dunbartonshire Council Climate Change Action Plan 2021

Page 42

5. Best Value | 42 
138.  In the Audit Scotland Auditing Climate Change 2021 report and the
Accounts Commission’s September 2022 briefing on Scotland’s councils’
approach to addressing climate change, it was noted that while public bodies,
including councils, have declared a climate emergency, there is a need to
ensure the robustness of plans. The plans should include clarity on how targets
and timescales will be achieved. The reports also reaffirmed the important role
that citizens will have and the need for strong partnership working.
139.  The council has recognised this, and has built on its strategy with a
Climate Change Action Plan, which was approved in October 2021. This sets
out the immediate and longer term actions the council will need to take, both in
relation to mitigating and adapting to climate change. This will be reviewed
annually and every five years it will go through a full progress review. 
140.  A Climate Change Action Group has been launched involving senior
management from each Council service area. The council has committed to
develop a Climate Change Community Forum to underpin more proactive and
engaged discussions with and climate actions by the local community.
A new strategic plan 2022-27 sets out the vision and key
priorities for the council over the next five years
141.  This was the final year under the Council’s Strategic Plan 2017-22. The
plan contains five-year targets with monitoring and reporting on progress
annually. Targets are set from a baseline and reviewed over time, and
performance against these is reported to the full council each year in the annual
performance report. These measures are considered the most relevant for
evidencing the delivery of the key priority and outcome areas defined in the
Strategic Plan.
142.  The council’s new strategic plan, covering the period 2022-27, will be
considered by the council in October 2022. The strategic plan is the key
document which sets out the priorities of the council over the next five years,
and how performance against outcomes will be measured.
143.  The plan groups the council’s priorities under four key themes of ‘our
communities, our environment, our economy and our council’ and is aligned to
the Scottish Government's national priorities. More than 200 people took part in
a survey consultation to give their views.  
Residents’ satisfaction with council services overall remains
high. but performance indicators show challenges in tackling
sickness absence levels, empty council homes and recycling 
144.  The 2021/22 annual performance report is expected to go before the
Council in October 2022. From review of the most recent quarterly performance
data 2021/22, we note good progress has been made in a number of areas
including:
• An increase in overall residents’ satisfaction with Council services
(93%, up from 89% in 2020/21).

Page 43

5. Best Value | 43 
• The number of businesses given advice and assistance to start up
through Business Gateway (53 against a target of 50).
• Percentage of income due from council tax received by the end of the
year (93.3%).
145.  However, there remains particular challenges in the following areas:
• Percentage of citizens who agree the Council listen to community views
when designing and delivering services (72% against a target of 90%).
• Percentage of council rent that was lost due to houses remaining empty
(1.29% against a target of 0.88%).
• Percentage of total household waste that is recycled (34% against a
target of 60%).
• Sickness absence levels (as noted in Exhibit 8).
The council is meeting statutory performance indicators (SPIs)
expectations on reporting its performance to the public 
146.  The Accounts Commission has a statutory responsibility to define the
performance information that councils must publish. In turn, councils have their
own responsibility, under their Best Value duty, to report performance to the
public. The commission does not prescribe how councils should report this
information but expects them to provide the public with fair, balanced, and
engaging performance information.
147. The Accounts Commission issued a revised 2018 Statutory Performance
Information Direction in December 2018 which requires a council to report:
• Its performance in improving local public services provided by the
council (on its own and with its partners and communities), and
progress against agreed desired outcomes
• Its own assessment and independent audit assessments of how it is
performing against its duty of Best Value, and how it plans to improve
these assessments and how it (with its partners where appropriate) has
engaged with and responded to its diverse communities.
148. West Dunbartonshire Council continues to participate in the Local
Government Benchmarking Framework and publish this data and a range of
other performance information on the council website which adequately covers
the requirements set out in the SPI direction issued by the Accounts
Commission. 
Relevant national performance audit reports are considered by
the council
149.  Audit Scotland carries out a national performance audit programme on
behalf of the Accounts Commission and the Auditor General for Scotland.

Page 44

5. Best Value | 44 
During 2021/22, Audit Scotland published several reports which are of direct
interest to the council. These are outlined in appendix 3. 
150.  We noted that relevant national reports, including the Local government in
Scotland: Financial overview 2020/21 and Audit Scotland - COVID-19 Guide for
Audit and Risk Committees reports, were considered by the Audit Committee.
These were accompanied by information explaining how the findings and
recommendations relate to the specific circumstances of West Dunbartonshire
Council. We welcome this positive response to our national reports.

Page 45

Appendix 1. Action plan 2021/22 | 45 
Appendix 1. Action plan
2021/22 
2021/22 recommendations
Issue/risk Recommendation  Agreed management
action/timing
1. Accounting for non-
current assets
We identified significant
errors on the processing of
non-current assets. This
included the valuation of
council dwellings,
depreciation calculations, the
capitalisation of staff costs
and misclassification of
assets.
Risk: If the accounting for
non-current assets is not
improved, future accounts
could be materially misstated.
The council should review its
capital accounting
procedures for non-current
assets, with a view to
improving the systems used
to record entries, compliance
with accounting
requirements, review
processes, and
communication with asset
owners.
Exhibit 2 
A review will be carried out to
properly understand any
process failures relating to
the management of the
Council’s asset register. This
will include giving
consideration to the
cost/benefit of replacing the
current spreadsheet based
asset register with a more
robust bespoke system. 
Chief Officer Resources
31 March 2023
2. Debtors and creditors
overstatement
We identified a number of
errors in the disclosures of
debtors and creditors. This
had the effect of reducing
both assets and liabilities by
£3.222 million.
Risk – There is a risk that the
figures in the Balance Sheet
are overstated.
Management should review
the year-end procedures to
ensure that debtors and
creditors are correctly
accounted for.
Exhibit 2 
An exercise will be carried
out to review the audit
adjustments required during
the audit of the 2021/22
annual accounts which will
inform improvement actions
in advance of the preparation
of the 2022/23 accounts. 
Chief Officer Resources
31 March 2023
Recommendations for charities administered by West Dunbartonshire Council
CH1. Governance
documentation and
dormant activity
The trustees of the charities
should continue to seek a
resolution to legal and
administrative barriers which
Further action will be taken to
raise the profile of the
charitable trusts in an attempt
to encourage greater

Page 46

Appendix 1. Action plan 2021/22 | 46 
Issue/risk Recommendation  Agreed management
action/timing
As we have previously
reported, some of the trusts
have been dormant for a
number of years, and new
deeds of trust or governing
documentation is required for
the Dunbartonshire
Educational Trust Scheme,
the UIE award and the
McAuley Prize for
Mathematics.
Risk – There is a risk that
funds are lying dormant and
do not provide public benefit
prevent charitable objectives
being achieved. 
This should include taking
steps to make their existence
more widely known, and
applications more accessible.
Paragraphs 50 to 52
applications from qualifying
parties. 
Chief Officer Resources
31 March 2023 
Follow-up of prior year recommendations
Issue/risk Recommendation  Agreed management
action/timing
PY1. Analysis of rent
arrears
Our review of the underlying
records for the Housing
Revenue Account (HRA)
identified that the council is
currently unable to analyse
overdue rent arrears by age
of the debt. 
Risk – The disclosures in the
accounts for rent arrears may
contain errors, and the
council may be unable to
adequately identify rent
arrears which should be
written off. 
The council should explore
improving its systems
capability to provide an
analysis of rent arrears by
age of the debt.
Complete
West Dunbartonshire Council
have new reporting capability
and are now able to analyse
rent arrears by age of debt.
This information has been
used to include amounts past
due for payment. 
PY2. Review of rent model
The council's current rent
model for its housing stock,
which bases charges on
property size, property type
and general quality was
implemented in June 2010 at
a meeting of the Housing,
The rent model should be
reviewed to ensure it meets
the needs of the council and
its tenants.
In Progress 
The current rent model does
not include properties built
since 2010. The rent model
has been discussed with the
Joint Rent Group who are
satisfied with the current
model. A satisfaction survey

Page 47

Appendix 1. Action plan 2021/22 | 47 
Issue/risk Recommendation  Agreed management
action/timing
Environment and Economic
Development Committee. At
that time, the committee
resolved that the model was
due for review no more than
10 years after
implementation, meaning that
the review is now overdue. 
Risk – the rent model does
not meet the needs of the
council and its tenants.
is being completed with all
residents regarding the
current rent model. The
revised model should be
presented to full council in
due course. 
Chief Officer – Housing and
Employability 
31 March 2023 
Recommendations for charities administered by West Dunbartonshire Council 
Issue/risk Recommendation 
PY CH1. Governance and investment documentation
As previously reported:
• The Deed of Trust for the Dunbartonshire Educational Trust
Scheme 1962 and UIE award require to be updated.
• The governing documentation for the McAuley Price for
Mathematics is not available and a new trust deed is
required.
Risk – There is a risk that the Trust does not hold the title to the
investment. There is also a risk of delay in issuing awards.
Superseded by
Recommendation
CH1 above.
PY CH2. Dormant Trust
As previously reported, some of the trusts have been dormant for a
number of years and annual activity on all trusts is minimal. 
Risk – There is a risk that funds are lying dormant and do not
provide public benefit.
Superseded by
Recommendation 
CH1 above.

Page 48

Appendix 2. Wider audit dimension risks | 48 
Appendix 2. Wider audit
dimension risks 
The table below sets out the risks we identified for the 2021/22 audit relating to
our wider responsibility under the Code of Audit Practice 2016 and how we
addressed each risk in arriving at our conclusion.
Audit risk Assurance procedure Results and conclusions
1. Financial sustainability
of services
The council needs to
demonstrate financial
sustainability of its services
as it faces increasing demand
for services and the
continuing service pressures
from Covid.
Covid-19 funding has
increased the council’s
reserves but these will be
needed to meet ongoing
costs. The council is
projecting funding gaps
increasing to £14.355 million
by 2024/25.
• Review the council’s
monitoring reports against
the 2021/22 budget and
long-term financial
strategy. Report the
outturn in our 2021/22
annual audit report.
• Review how the council
demonstrates the long-
term affordability of budget
decisions, including any
planned use of reserves.
• Ongoing assessment of
the council’s long-term
financial strategy.
Results & Significant
Judgements: As we have
reported in Paragraph 56. ,
the council achieved a £0.159
million surplus against
budgeted expenditure for
2021/22. 
Conclusion: There is
uncertainty over how long
Covid-related funding will
continue to be made
available to promote
recovery. The long-term
financial strategy has
identified cumulative
anticipated revenue funding
gaps within General Services
rising to £18.622 million in
2024/25.
2. Capital project delays
We have previously reported
on a trend of delays in capital
projects and capital
programme slippage. A
significant underspend is
forecast against the 2021/22
original capital budget for
2021/22. The majority of this
is due to the impact of Covid-
19 and the ongoing
restrictions on capital works.
• Review the council’s
reports for monitoring the
budget and progress with
the capital programme.
Report the outturn in our
2021/22 annual audit
report.
Results & Significant
Judgements: As we have
reported in Paragraph 76, 
42 per cent of the capital
programme has been
identified as slippage.
Conclusion: Although Covid-
19 is likely to have had a
significant impact on the
capital programme, there
remains a risk of unrealistic
or overly optimistic
scheduling. We will continue

Page 49

Appendix 2. Wider audit dimension risks | 49 
Audit risk Assurance procedure Results and conclusions
There is a risk that the
council’s ability to deliver
against its strategic plan is
affected by the delays to
completing its capital
projects.
to monitor progress in this
area. 
CH1. Governance and
investment documentation 
The Deed of Trust for the
Dunbartonshire Educational
Trust Scheme 1962 and UIE
Award require to be updated.
The governing documentation
for the McAuley Prize for
Mathematics is not available
and a new trust deed
required.
• Continue to liaise with
officers to establish
progress with updating and
replacing Deeds of Trust.
• Review updated Deeds of
Trust.
• Provide an update on
progress in our 2021/22
Annual Audit Report. 
Results & Significant
Judgements: Progress is
being made towards
replacing the deeds of trust
and governance
documentation. 
Conclusion: In progress 
CH2. Dormant Trusts
Some of the trusts have been
dormant for a number of
years, with annual activity on
all trusts minimal. There is a
risk that the trusts are not
meeting the requirement of
public benefit. 
• Continue to liaise with
officers and monitor the
activity on trusts funds.
• Provide an update on
activity in 2021/22 Annual
Audit Report.
Results & Significant
Judgements: There is
minimal activity on some
trusts, with only one award in
2021/22. 
Conclusion: In progress

Page 50

Appendix 3. Summary of 2021/22 national performance reports and briefing papers | 50 
Appendix 3. Summary of
2021/22 national performance
reports and briefing papers 
May
Local government in Scotland Overview 2021
June
Covid 19: Personal protective equipment
July
Community justice: Sustainable alternatives to custody
September
Covid 19: Vaccination programme
January
Planning for skills
Social care briefing
February
NHS in Scotland 2021
March
Local government in Scotland: Financial Overview 20/21
Drug and alcohol: An update
Scotland’s economy: Supporting businesses through the Covid 19 pandemic

Page 51

Appendix 3. Summary of 2021/22 national performance reports and briefing papers | 51  
West Dunbartonshire Council
Proposed 2021/22 Annual Audit Report 
Audit Scotland’s published material is available for download 
on the website in a number of formats. For information on our 
accessibility principles, please visit:
www.audit-scotland.gov.uk/accessibility
For the latest news follow us on social media or
subscribe to our email alerts. 
Audit Scotland, 4th Floor, 102 West Port, Edinburgh EH3 9DN
Phone: 0131 625 1500 Email: info@audit-scotland.gov.uk
www.audit-scotland.gov.uk
AS.4.0

Page 52