WEST DUNBARTONSHIRE COUNCIL APPENDIX 1
HRA REVENUE BUDGETARY CONTROL 2022/23
PERIOD END DATE
Subjective Summary
Total Budget
2022/23 
£000
Spend to
Date
2022/23 
£000
Forecast
Spend
£000
Annual RAG
Status
Employee Costs 6,690 3,454 6,989 299 4% 
Property Costs 2,030 1,008 1,969 (61) -3% 
Transport Costs 112 75 129 17 0% 
Supplies, Services And Admin 395 131 382 (13) -3% 
Support Services 2,724 0 2,613 (111) -4% 
Other Expenditure 532 544 580 48 9% 
Repairs & Maintenance 12,942 7,472 13,231 289 2% 
Bad Debt Provision 1,060 538 923 (137) -13% 
Void Loss (Council Tax/Lost Rents) 857 1,269 1,727 870 102% 
Loan Charges 12,175 6,088 12,309 134 1% 
CFCR 7,501 3,750 6,203 (1,298) -17% 
Total Expenditure 47,018 24,329 47,055 37 0% 
House Rents 45,215 25,465 45,213 2 0% 
Lockup Rents 210 113 213 (3) -1% 
Factoring/Insurance Charges 1,316 760 1,302 14 1% 
Other rents 115 57 116 (1) -1% 
Interest on Revenue Balance 55 18 30 25 45% 
Transfer from Reserves 0 0 60 (60) 0% 
Miscellaneous income 107 35 121 (14) -13% 
Total Income 47,018 26,448 47,055 (37) 0% 
Net Expenditure 0 (2,119) 0 0 
Forecast Variance 2022/23
£000               %
31 October 2022

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
HRA REVENUE BUDGETARY CONTROL 2022/23
ANALYSIS FOR VARIANCES OVER £50,000
MONTH END DATE 31 October 2022
PERIOD 7
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
EMPLOYEE COSTS 6,690 6,989 299 4% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
PROPERTY COSTS 2,030 1,969 (61) -3% 
Main Issues
Mitigating Action No mitigating action is required.
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
SUPPORT SERVICES 2,724 2,613 (111) -4% 
Main Issues
Mitigating Action No mitigating action is required.
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
REPAIRS & MAINTENANCE 12,942 13,231 289 2% 
Main Issues
Mitigating Action
Anticipated Outcome
This budget covers electricity, gas, rates, rents, cleaning  and insurance costs.
Variance Narrative
A favourable variance is expected due to the revised probable calculations for utilities,
based on 21/22 actual outturn plus required inflation rates.
A year end underspend is anticipated
Variance Analysis
Subjective Analysis forecast Variance
Subjective Description
It is not possible to mitigate against an agreed pay award however managers will continue to
review any possible reductions in costs where possible to try and partially offset some of this
The adverse  variance within Repairs & Maintenance is due to additional work being carried
out to catch up with both jobbing  repairs and void repairs. Additional capacity to do this has
been achieved through use of sub contractors as well as continuing with HMTA work so in
effect more than a typical year worth of work is expected to be completed in 2022/23,
therefore the cost will be higher than usual.
Variance Narrative
Variance Narrative
This budget covers all repair and maintenance expenditure to houses and lockups
Subjective Description
A year end underspend is anticipated
A year end overspend is anticipated
In order to get back  to pre - COVID levels of voids and repairs , it is considered necessary
to pursue this increased activity for 2022/23 albeit at a financial cost . It should be noted that
in previous years, costs were lower than budgeted due to lower activity in lockdown / COVID
restrictions .
Budget Details
This budget covers all employees charged directly to the HRA including caretakers.
Variance Narrative
This adverse variance is mainly due to the agreed pay award being higher than the 2%
budgeted . Also £60K of this adverse variance relates to the increased pay awarded to
caretakers  following  job evaluation panel on 7 April.  This £60K is offset by a transfer from
HRA service improvement reserve which is shown in the income section .
A favourable variance is expected with the assumption that the 2022/23 forecast outturn for
support services is expected  to be in line with the 2021/22 outturn adjusted for pay uplifts
etc. This charge is calculated each year end based on HRA's percentage usage of the total
cost of WDC support services. The 2022/23 HRA budget was set before this 2021/22
outturn was known so was based on 2020/21 charge which was higher.
Service Description
Budget Details Variance Analysis
Subjective Analysis forecast Variance
Budget Details Variance Analysis
Subjective Analysis forecast Variance
A year end overspend is anticipated
This budget covers central support recharges to the HRA
Budget Details Variance Analysis
Subjective Analysis forecast Variance
Subjective Description

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
HRA REVENUE BUDGETARY CONTROL 2022/23
ANALYSIS FOR VARIANCES OVER £50,000
MONTH END DATE 31 October 2022
PERIOD 7
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
BAD DEBT PROVISION 1,060 923 (137) -13% 
Main Issues
Mitigating Action No mitigating action is required.
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
VOID LOSS 857 1,727 870 102% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
LOAN CHARGES
12,175 12,309 134 1% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
CFCR 7,501 6,203 (1,298) -17% 
Main Issues
Mitigating Action
Anticipated Outcome
Variance Narrative
The main reason for this variance is  interest payments being higher than anticipated at time
of budget setting.
None available
A year end oversend is anticipated
Subjective Analysis forecast Variance
Service Description
Loan Charges is made up of repayments of principle sums, and the payments of interest and expenses
Budget Details Variance Analysis
A year end overspend is anticipated
Variance Narrative
The Bad Debt Provision expected to be required for 2022/23 is less than estimated at time
of budget setting, resulting in a favourable variance. This assumes that the provision
required in 2022/23  will be similar to the 2021/22 provision.
Budget Details Variance Analysis
Subjective Analysis forecast Variance
Service Description
This budget allows for the provision for bad and doubtful debts to be maintained at an appropriate level
A year end underspend is anticipated
Service Description
This budget covers the contribution from revenue to Capital
Variance Narrative
In order to offset the cost pressures on the revenue HRA in 2022/23 , it will be necessary to
reduce the contribution to Capital to allow the HRA account to break even. Due to a large
part of the planned Capital spend on new builds being reprofiled into 2023/24 this reduced
contribution will not create any issues for the remaining Capital programs being delivered in
2022/23.
None available
Budget Details Variance Analysis
Subjective Analysis forecast Variance
Subjective Analysis forecast Variance
Service Description
A year end underspend is anticipated
Variance Narrative
The main reason for the projected adverse variance relates to the number of void properties
being higher than expected at time of budget setting. The budget was set on the assumption
that backlogs following COVID delays  in getting voids turned around would be resolved
early in year however the  numbers continue to be high .
Budget Details Variance Analysis
A void working group has been reviewing the issues and have been implementing actions
and working with Housing Maintenance managers to improve the situation and it is expected
that the void figures will start to decrease significantly over the next few months.
This budget covers the rents lost on void houses and lockups and the cost of council tax on void properties.

Page 4

APPENDIX 3
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
MONTH END DATE
PERIOD 7
Spend to
Date Spend to Date
£000 £000
Red
6 22.2% 5,056 38.7% 6 22.2% 5,056 38.7%
Amber
0 0.0% 0 0.0% 0 0.0% 0 0.0%
Green
21 77.8% 8,017            61.3% 21 77.8% 8,017                61.3%
27 100% 13,073 100% 27 100% 13,073 100%
Budget Spend to
Date
Forecast
Spend Forecast Variance Budget Spend to Date Forecast
Spend
Forecast
Variance Reprofiled Over/
(Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
136,980 5,056 139,063 2,083 46,191 5,056 19,927 (26,264) (28,346) 2,083
0 0 0 0 0 0 0 0 0 0
79,140 8,017 78,959 (181) 19,413 8,017 19,232 (181) 0 (181)
216,120 13,073 218,022 1,902 65,604 13,073 39,159 (26,444) (28,346) 1,902
216,120 13,073 218,022 (1,902) 65,604 13,073 39,159 26,444
0 0 0 0 0 0 0 0
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
31 October 2022
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project Spend at
RAG Status
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project
Spend at RAG
Status
Red
Projects are forecast to be overspent and/or experience material delay
to completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green
Project Status Analysis
Project Life Financials Current Year Financials
Red
TOTAL RESOURCES
NET EXPENDITURE
Projects are forecast to be overspent and/or significant delay to
completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
TOTAL EXPENDITURE

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials 10,963 398 4% 10,963 0 0%
Current Year Financials 2,500 398 16% 1,500 (1,000) -40%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
2
Project Life Financials 566 134 24% 658 92 16%
Current Year Financials 108 134 124% 200 92 86%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
3
Project Life Financials 5,092 1,467 29% 6,209 1,117 22%
Current Year Financials 969 1,467 151% 2,086 1,117 115%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
31 October 2022
Budget Details Project Life Financials
Spend to Date Variance
Doors/window component renewals
Doors/Windows Component Renewals 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Officers working to meet revised targets.  Additional external support has been programmed in from August onwards to assist with
window installs, feedback from officers have highlighted challenges with resource levels from back-up contractor. This will be
monitored closely, however approximately £1m will need to reprofiled into 23/24.
Mitigating Action
Building Services actively redeploying internal resurces to assist with installs and working with external support to maximise
contribution.
Anticipated Outcome
Anticipated to meet reduced forecast spend
Main Issues / Reason for Variance
Projected to exceed budget, this is necessary work to meet demand and comply with legislation.
Mitigating Action
None available.
Anticipated Outcome
Budget to overspend.
Statutory/regulatory compliance works (lifts/electrical/legionnella/fire etc)
This budget will be used to upgrade / replace components / installations in order to comply with
the relevant standards / legislation / health and safety in relation to housing stock. 
Planned End Date  Forecast End Date
Mitigating Action
None available since essential spend.
Anticipated Outcome
Budget to overspend.
Heating improvement works
Carry out works to renew inefficient boilers/full systems as identified from the stock condition
survey and renewal of obsolete/damaged boilers. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
An overspend is anticipated on this budget, as experienced in recent years as demand has exceeded expectations. Current
progress continues this trend. Due to the nature of this project (ensuring heating and hot water availability) there is no option for a
conscious reduction of installs.

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2022
Budget Details Project Life Financials
Spend to Date Variance
4
Project Life Financials 8,384 1,064 13% 9,384 1,000 12%
Current Year Financials 2,000 1,064 53% 3,000 1,000 50%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
5
Project Life Financials 5,092 775 15% 5,292 200 4%
Current Year Financials 969 775 80% 1,169 200 21%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
6
Project Life Financials 106,883 1,219 1% 106,556 (326) 0%
Current Year Financials 39,645 1,219 3% 11,972 (27,673) -70%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Sites to be reprofiled £m
Aitkenbar Primary School (374)
Clydebank East (13,754)
Queens Quay Site B (629)
Queens Quay Site C (878)
Pappert (4,481)
Bank Street (575)
Willow Park Phase  1 (1,989)
Mount Pleasant (2,420)
Future New build sites (2,246)
TOTAL OF ALL PROJECTS (27,346)
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Void works to continue into 22/23 to bring void properties up to a lettable standard.  The high number of voids has led to a higher
than expected demand for this budget, resulting in a projected overspend in 22/23. 
Mitigating Action
None available at this time
Void house strategy programme
Spend on Void Properties to bring them up to letting standard
Anticipated Outcome
Void properties to be brought up to lettable standard
Environmental renewal works, paths/fences/walls/parking area's
Environmental renewal works, paths/fences/walls/parking areas
Anticipated Outcome
Full budget spend, with overspend anticipated.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
An overspend is anticipated in 22-23 due to level of demand and material costs being higher than expected at time of budget
Mitigating Action
None available at this time.
Main Issues / Reason for Variance
Progress will continue to be monitored as the year progresses.  The £27.673 variance is made up of £0.326m underspend and a
reprofiling of £27.346m into 2023/24 onwards . Summary of reprofiled sites together with site specific updates as follows:-
Affordable Supply Programme
Affordable Housing Supply Programme 
Planned End Date  Forecast End Date

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2022
Budget Details Project Life Financials
Spend to Date Variance
TOTAL OF ALL PROJECTS
Project Life Financials 136,980 5,056 4% 139,063 2,083 2%
Current Year Financials 46,191 5,056 11% 19,927 (26,264) -57%
Clydebank East - 88 units to be completed on the site. Project spend now requires to be reprofiled. Anticipated site start of June
2022 has been delayed as a result of assessing remediation strategy options, while the exercise has proved to be a lengthy
process the options have identified an affordable method which is estimated to be around £9m less costly than the original
proposed method.  We expect revised tender costs early in November and anticipate a site start before the end of the year.  The
remediation methods will take longer and will be the first phase of the development and the construction of the new homes will
likely commence in April 2023. £13.754m of the £18.754m current year budget will be required to be reprofiled into 23/24.
Queens Quay Site B - 29 units now completed on the site. Project spend now requires to be reprofiled. Retention figure of
£0.629m budgeted to be paid out in 2022/23 will now be reprofiled to be paid in 2023/24 to allow time to finalise account.
Queens Quay Site C  – 20 units to be completed on site. Project spend now requires to be reprofiled. The budget provision is to
acquire additional land within Queens Quay to enhance the Site C proposals, the discussions with CRL/Rydens have been
protracted but we intend to make an offer shortly subject to the DV valuation being received. This will be reprofiled into 2022/23
(£1.878m).
Pappert - 27 units to be completed on site . Projects spend now requires to be reprofiled.  The anticipated site start of October
2022 will not be realised due to a number of factors that have caused the project to miss a number of milestones, notably a longer
than anticipated procurement process and the subsequent delay in developing a contract/tender preparation forced us to miss a
pricing window from the contractor, we anticipate a new cost price in November with a site start of March 23.  It is expected
£0.500m will be paid out in 2022/23 withthe remaining £4.481m to be reprofiled into 2023/24
Future New Build gap sites  – Project spend now requires to be reprofiled. Ongoing work to acquire private and Council owned
sites to finalise wider strategy . Expected that there will be  spend of £0.500m this during 2022/23 so £2.246m will be reprofiled
into 2023/24.
Aitkenbar - Fully complete. Project spend now requires to be reprofiled. Retention figure of £0.374m budgeted to be paid out in
2022/23 will now be reprofiled to be paid in 2023/24 to allow time to finalise account.
Anticipated Outcome
Project will still complete and will meet revised spend profiles .
Bank Street - 20 units to be completed on the site. Project spend needs reprofiled due to wider strategic reasons and potential
reprovisioning of sheltered accommodation which will require consultative exercise . Revised estimated start date July 2023,
estimated completion January 2025.  Project is currently at feasibility stage.  Likely outturn for 22/23 for the Bank Street site is
expected to be circa. £0.420m with £0.575m therefore required to be reprofiled to 23/24.
Willox Park Phase1 - 17 units to be completed on site. Project spend now requires to be reprofiled  . Pre planning discussions
were more involved than anticipated and required some re designing which has resulted in delay to estimated start date from
January 2023 to June 2023 with estimated completion May 2024. Demolition complete, and site investigation under way.  Officers
ready to submit to for full planning.  Tender application expected to go out April 23.  At this stage spend in the current year is
expected to be £0.400m against budget of £2.390m resulting in reprofiling rquirement of £1.989m.
Mount Pleasant - 25 units to be completed on site. Project spend now requires to be reprofiled. Unanticipated longer time frame
for demolition (9 months) has delayed this project by 6 months, now estimating a March 2023 site start, although demolitions are
planned for next month. £0.100m expected costs in 22/23, resulting in reprofiling requirement of £2.420m to 23/24.
Bonhill Gap Site - 32 units to be completed on site.  Estimated start date July 2023 and estimated completion September 2024. 
The project is currently  at design stage with spend of £0.420m expected in 22/23 . No reprofilng required .
Mitigating Action
Staff will work closely with all stakeholders to try and ensure timely resolutions of issues as they arise.

Page 8

APPENDIX 5
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials 2,487 253 10% 2,487 0 0%
Current Year Financials 474 253 53% 474 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
2
Project Life Financials 2,266 187 8% 2,266 0 0%
Current Year Financials 431 187 43% 431 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
3
Project Life Financials 1,557 30 2% 1,557 0 0%
Current Year Financials 664 30 5% 664 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
4
Project Life Financials 271 0 0% 271 0 0%
Current Year Financials 185 0 0% 185 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
31 October 2022
Budget Details Project Life Financials
Spend to Date Variance
Special needs adaptations
None available at this time
Anticipated Outcome
Full budget spend, possibility of overspend.
Capitalised minor works
Gypsy/ Traveller Site improvements 
Planned End Date  Forecast End Date 
Adaptations to Housing for Special Needs 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets. Possibility of overspend due to price increases and demand levels rising.
Mitigating Action
Better Homes Priority Budget
Priority projects as prioritised by the Better Homes Group 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
A number of priority initiatives, supported by the Better Homes Project Board,  are being investigated and are envisaged to have a
positive impact on the current council housing stock and budget, with works expected to progress in 22/23.
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No issues. Development of QL system to carry on through 22/23.
Mitigating Action
None required
Mitigating Action
None required
Anticipated Outcome
Full budget spend
QL Development
This budget relates to the costs associated with the development of the Integrated Housing
Management System
Anticipated Outcome
Full budget spend

Page 9

WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2022
Budget Details Project Life Financials
Spend to Date Variance
5
Project Life Financials 170 0 0% 170 0 0%
Current Year Financials 40 0 0% 40 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
6
Project Life Financials 17 0 0% 17 0 0%
Current Year Financials 17 0 0% 17 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
7
Project Life Financials 36 0 0% 36 0 0%
Current Year Financials 36 0 0% 36 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
8
Project Life Financials 192 0 0% 192 0 0%
Current Year Financials 192 0 0% 192 0 0%
Project Description
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Gypsy Travellers Site
Gypsy/ Traveller Site improvements 
Planned End Date  Forecast End Date
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Redployable CCTV Cameras
Purchase of 5 redeployable CCTV cameras for Housing use
Community Safety Projects
Community Safety Projects 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Anticipated Outcome
Full budget spend
Airport Noise
Noise Insulation Project 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
5 redeployable cameras to be purchased as planned.  No issues anticipated.
Mitigating Action
None required
Main Issues / Reason for Variance
Awaiting receipt of the airport scheme outline from Glasgow Airport before works can planned.  Project expected to make
progression in 22/23.
Mitigating Action
None required
Anticipated Outcome
Full budget spend

Page 10

WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2022
Budget Details Project Life Financials
Spend to Date Variance
9
Project Life Financials 19,841 0 0% 19,841 0 0%
Current Year Financials 4,455 0 0% 4,455 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
10
Project Life Financials 17,607 4,076 23% 17,607 0 0%
Current Year Financials 4,955 4,076 82% 4,955 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
11
Project Life Financials 257 9 4% 257 0 0%
Current Year Financials 75 9 12% 75 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Targeted SHQS /EESSH compliance works
This budget is to focus on work required to maintain the SHQS compliance and energy
efficiency  with WDC housing stock.   
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets. Current progress is slightly behind cumulative monthly targets, work is
progressing and additional resources will be coming on board shortly with new framework contractor.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Currently behind monthly targets, however tentatively anticipated to meet full spend and targets. Current tiled roof progress is
behind cumulative monthly targets but overall output is anticipated to increase with the new metal and flat roof framework contract
coming on board contributing to a wider range of roof types being completed.
Mitigating Action
None required
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Roof Coverings
Building external component renewals, roofs/chimneys/flashings/fascias/gutters/svp
Anticipated Outcome
Full budget spend
Mitigating Action
None required
Anticipated Outcome
Full budget spend
External stores/garages/bin stores/drainage component renewals
This budget is to focus on external stores/garages/bin stores etc. component renewals as
identified and recommended from the housing stock condition survey. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.

Page 11

WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2022
Budget Details Project Life Financials
Spend to Date Variance
12
Project Life Financials 273 65 24% 273 0 0%
Current Year Financials 91 65 72% 91 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
13
Project Life Financials 280 0 0% 280 0 0%
Current Year Financials 54 0 0% 54 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
14
Project Life Financials 5,293 935 18% 5,293 0 0%
Current Year Financials 1,036 935 90% 1,036 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
15
Project Life Financials 103 0 0% 103 0 0%
Current Year Financials 103 0 0% 103 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Secure entry component renewals
This budget is to focus on secure door entry component renewals as identified and
recommended from the housing stock condition survey and appropriate council officer referrals.
Anticipated Outcome
Anticipated not to meet full spend despite best efforts.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
This programme always presents challenges with owner liaison and reaching agreements to install door entry where none exists,
this contributes directly to achieving SHQS compliance for this element and reducing abeyances. The budget reflects the demand
and number of installs required but it is acknowledged that full uptake is unlikely.
Mitigating Action
Officers continue to liaise with owners to encourage agreement for install.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Energy improvements/energy efficiency works
Energy improvements/ efficiency works (e.g. loft insulation, pipe/tank insulation, draught
exclusion)
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Anticipated Outcome
Full budget spend
Modern facilities and services
New Kitchens, Bathrooms and Showers 
Planned End Date  Forecast End Date
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Improvement works (Risk St)
Risk Street Over clad 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.

Page 12

WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2022
Budget Details Project Life Financials
Spend to Date Variance
16
Project Life Financials 581 0 0% 400 (181) -31%
Current Year Financials 181 0 0% 0 (181) -100%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
17
Project Life Financials 3,637 184 5% 3,637 0 0%
Current Year Financials 887 184 21% 887 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
18
Project Life Financials 1,135 86 8% 1,135 0 0%
Current Year Financials 215 86 40% 215 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Contingencies
This is a contingent budget for unforeseen matters which may arise during the year. 
Planned End Date  Forecast End Date
Defective structures/component renewals
Defective structures 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Main Issues / Reason for Variance
No Issues, contingent budget for unplanned spend
Mitigating Action
none at this time
Anticipated Outcome
Spend as required
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Asbestos management works
This budget is to fund work associated with the management of current asbestos legislation and 
Planned End Date  Forecast End Date

Page 13

WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2022
Budget Details Project Life Financials
Spend to Date Variance
19
Project Life Financials 2,378 0 0% 2,378 0 0%
Current Year Financials 800 0 0% 800 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
20
Project Life Financials 7,729 731 9% 7,729 0 0%
Current Year Financials 2,019 731 36% 2,019 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
21
Project Life Financials 13,031 1,461 11% 13,031 0 0%
Current Year Financials 2,504 1,461 58% 2,504 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
TOTAL OF ALL PROJECTS
Project Life Financials 79,140 8,017 10% 78,959 (181) 0%
Current Year Financials 19,413 8,017 41% 19,232 (181) -1%
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Buy Backs
This is a budget to undertake specific projects that will deliver housing policies/strategies,
example: Ex local authority and mortgage to rent buy-back scheme
Multi Story Flats  ( including Fire Risk Assessment Works)
High Rise Fire Safety Measures 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet spend and revised targets.
Anticipated Outcome
Budget spend anticipated, should criteria be met.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
The main objective of the Buy Back Scheme is to bring former council properties that were sold through the RTB scheme, back
into council use.  These properties must assist the council with reducing housing need on the waiting list and where appropriate
assist with external capital works.  For these reasons, any purchase is subject to stringent criteria to ensure accountability and
value for money for existing tenants.  Spend in 22/23 will therefore be dependent on these factors.  So far this year, 8 homes have
been purchased, with a further 4 under offer. The target is to deliver an additional 20 homes each year through the buyback
scheme.
Mitigating Action
None required.
Main Issues / Reason for Variance
No Issues, budget for salaries and support
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Salaries/central support/offices
Allocation of costs from other WDC services who support the HRA capital programme 
Planned End Date  Forecast End Date

Page 14

APPENDIX 6
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials (48,826) (4) 0% (48,826) 0 0%
Current Year Financials (30,006) 0 0% (10,480) 19,526 -65%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
2
Project Life Financials (42,531) 0 0% (41,168) 1,363 -3%
Current Year Financials (9,215) 0 0% (7,852) 1,363 -15%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
3
Project Life Financials (124,667) (13,019) 10% (124,667) 0 0%
Current Year Financials (26,286) (13,019) 50% (19,945) 6,341 -24%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Due to spend being later than anticiapted , receipt of grant will also be later than budgeted.
Mitigating Action
Income budget wil be reprofiled to match reprofiled spend
Anticipated Outcome
Income will be received in 2023/24
Main Issues / Reason for Variance
31 October 2022
Budget Details Project Life Financials
Spend to Date Variance
New Build Grant 
Grant to facilitate new build housing 
Planned End Date  Forecast End Date
CFCR
This is capital spend which is funded by revenue budgets
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Income from Revenue reduced to offset adverse varainces in HRA revenue
Mitigating Action
None required
Anticipated Outcome
Reduced CFCR
Prudential Borrowing
Prudential borrowing is long term borrowing from financial institutions that has been approved
for the purposes of funding capital expenditure
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Prudential borrowing is impacted by programme delivery therefore due to reprofiling, the requirement in 2022/23 will be less.
Mitigating Action
None available at this time.
Anticipated Outcome
While prudential borrowing requirement is likely to be less than budgeted in the current financial year this is anticipated to catch
up over the programme life.

Page 15

WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
MONTH END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2022
Budget Details Project Life Financials
Spend to Date Variance
New Build Grant 4
Project Life Financials (96) (50) 52% (96) 0 0%
Current Year Financials (96) (50) 52% (96) 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
TOTAL RESOURCES
Project Life Financials (216,120) (13,073) 6% (214,757) 1,363 -1%
Current Year Financials (65,604) (13,069) 20% (38,373) 27,230 -42%
Other Capital Income
Other Income to capital
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No variance
Mitigating Action
None required
Anticipated Outcome
Income will be received

Page 16

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
HRA CAPITAL PROGRAMME
ANALYSIS OF AFFORDABLE HOUSING SUPPLY PROGRAMME
MONTH END DATE
PERIOD 7
Budget Spend to Date Forecast Spend
£000 £000 £000 £000 %
RAG
Status
St Andrews School 636                          93                            290                                346-                          -54% 
Haldane Primary School 148                          149                          167                                20                            13% 
Aitkenbar Primary School 652                          214                          652                                -                          0% 
Clydebank East 26,474                    42                            26,474                          -                          0% 
Creveul Court 58                            59                            58                                  -                          0% 
Queens Quay Site B 1,259                      402                          1,259                            -                          0% 
Queens Quay Site C 6,198                      1                              6,198                            -                          0% 
Pappert 7,332                      2                              7,332                            -                          0% 
Lilac Avenue 2,676                      -                          2,676                            -                          0% 
Bank Street 4,674                      -                          4,674                            -                          0% 
Clydebank Health Centre 6,930                      3                              6,930                            -                          0% 
Willox Park Phase1 3,817                      51                            3,817                            -                          0% 
Willox Park Phase2 6,300                      -                          6,300                            -                          0% 
Mount Pleasant 4,200                      18                            4,200                            -                          0% 
Silverton 2,100                      -                          2,100                            -                          0% 
Fees, Staffing Costs, contingency 4,005                      15                            4,005                            -                          0% 
Gap sites
Bonhill Gap Site 420                          171                          420                                -                          0% 
Future New build sites 16,824                    -                          16,824                          -                          0% 
Total Expenditure 94,703 1,219 94,376 (326) 
31 October 2022
Site
Project Life Financials
Variance