Page 1
WEST DUNBARTONSHIRE COUNCIL APPENDIX 1 HRA REVENUE BUDGETARY CONTROL 2022/23 PERIOD END DATE Subjective Summary Total Budget 2022/23 £000 Spend to Date 2022/23 £000 Forecast Spend £000 Annual RAG Status Employee Costs 6,690 3,454 6,989 299 4% Property Costs 2,030 1,008 1,969 (61) -3% Transport Costs 112 75 129 17 0% Supplies, Services And Admin 395 131 382 (13) -3% Support Services 2,724 0 2,613 (111) -4% Other Expenditure 532 544 580 48 9% Repairs & Maintenance 12,942 7,472 13,231 289 2% Bad Debt Provision 1,060 538 923 (137) -13% Void Loss (Council Tax/Lost Rents) 857 1,269 1,727 870 102% Loan Charges 12,175 6,088 12,309 134 1% CFCR 7,501 3,750 6,203 (1,298) -17% Total Expenditure 47,018 24,329 47,055 37 0% House Rents 45,215 25,465 45,213 2 0% Lockup Rents 210 113 213 (3) -1% Factoring/Insurance Charges 1,316 760 1,302 14 1% Other rents 115 57 116 (1) -1% Interest on Revenue Balance 55 18 30 25 45% Transfer from Reserves 0 0 60 (60) 0% Miscellaneous income 107 35 121 (14) -13% Total Income 47,018 26,448 47,055 (37) 0% Net Expenditure 0 (2,119) 0 0 Forecast Variance 2022/23 £000 % 31 October 2022
Page 2
WEST DUNBARTONSHIRE COUNCIL APPENDIX 2 HRA REVENUE BUDGETARY CONTROL 2022/23 ANALYSIS FOR VARIANCES OVER £50,000 MONTH END DATE 31 October 2022 PERIOD 7 Budget Forecast Spend RAG Status £000 £000 £000 % EMPLOYEE COSTS 6,690 6,989 299 4% Main Issues Mitigating Action Anticipated Outcome Budget Forecast Spend RAG Status £000 £000 £000 % PROPERTY COSTS 2,030 1,969 (61) -3% Main Issues Mitigating Action No mitigating action is required. Anticipated Outcome Budget Forecast Spend RAG Status £000 £000 £000 % SUPPORT SERVICES 2,724 2,613 (111) -4% Main Issues Mitigating Action No mitigating action is required. Anticipated Outcome Budget Forecast Spend RAG Status £000 £000 £000 % REPAIRS & MAINTENANCE 12,942 13,231 289 2% Main Issues Mitigating Action Anticipated Outcome This budget covers electricity, gas, rates, rents, cleaning and insurance costs. Variance Narrative A favourable variance is expected due to the revised probable calculations for utilities, based on 21/22 actual outturn plus required inflation rates. A year end underspend is anticipated Variance Analysis Subjective Analysis forecast Variance Subjective Description It is not possible to mitigate against an agreed pay award however managers will continue to review any possible reductions in costs where possible to try and partially offset some of this The adverse variance within Repairs & Maintenance is due to additional work being carried out to catch up with both jobbing repairs and void repairs. Additional capacity to do this has been achieved through use of sub contractors as well as continuing with HMTA work so in effect more than a typical year worth of work is expected to be completed in 2022/23, therefore the cost will be higher than usual. Variance Narrative Variance Narrative This budget covers all repair and maintenance expenditure to houses and lockups Subjective Description A year end underspend is anticipated A year end overspend is anticipated In order to get back to pre - COVID levels of voids and repairs , it is considered necessary to pursue this increased activity for 2022/23 albeit at a financial cost . It should be noted that in previous years, costs were lower than budgeted due to lower activity in lockdown / COVID restrictions . Budget Details This budget covers all employees charged directly to the HRA including caretakers. Variance Narrative This adverse variance is mainly due to the agreed pay award being higher than the 2% budgeted . Also £60K of this adverse variance relates to the increased pay awarded to caretakers following job evaluation panel on 7 April. This £60K is offset by a transfer from HRA service improvement reserve which is shown in the income section . A favourable variance is expected with the assumption that the 2022/23 forecast outturn for support services is expected to be in line with the 2021/22 outturn adjusted for pay uplifts etc. This charge is calculated each year end based on HRA's percentage usage of the total cost of WDC support services. The 2022/23 HRA budget was set before this 2021/22 outturn was known so was based on 2020/21 charge which was higher. Service Description Budget Details Variance Analysis Subjective Analysis forecast Variance Budget Details Variance Analysis Subjective Analysis forecast Variance A year end overspend is anticipated This budget covers central support recharges to the HRA Budget Details Variance Analysis Subjective Analysis forecast Variance Subjective Description
Page 3
WEST DUNBARTONSHIRE COUNCIL APPENDIX 2 HRA REVENUE BUDGETARY CONTROL 2022/23 ANALYSIS FOR VARIANCES OVER £50,000 MONTH END DATE 31 October 2022 PERIOD 7 Budget Forecast Spend RAG Status £000 £000 £000 % BAD DEBT PROVISION 1,060 923 (137) -13% Main Issues Mitigating Action No mitigating action is required. Anticipated Outcome Budget Forecast Spend RAG Status £000 £000 £000 % VOID LOSS 857 1,727 870 102% Main Issues Mitigating Action Anticipated Outcome Budget Forecast Spend RAG Status £000 £000 £000 % LOAN CHARGES 12,175 12,309 134 1% Main Issues Mitigating Action Anticipated Outcome Budget Forecast Spend RAG Status £000 £000 £000 % CFCR 7,501 6,203 (1,298) -17% Main Issues Mitigating Action Anticipated Outcome Variance Narrative The main reason for this variance is interest payments being higher than anticipated at time of budget setting. None available A year end oversend is anticipated Subjective Analysis forecast Variance Service Description Loan Charges is made up of repayments of principle sums, and the payments of interest and expenses Budget Details Variance Analysis A year end overspend is anticipated Variance Narrative The Bad Debt Provision expected to be required for 2022/23 is less than estimated at time of budget setting, resulting in a favourable variance. This assumes that the provision required in 2022/23 will be similar to the 2021/22 provision. Budget Details Variance Analysis Subjective Analysis forecast Variance Service Description This budget allows for the provision for bad and doubtful debts to be maintained at an appropriate level A year end underspend is anticipated Service Description This budget covers the contribution from revenue to Capital Variance Narrative In order to offset the cost pressures on the revenue HRA in 2022/23 , it will be necessary to reduce the contribution to Capital to allow the HRA account to break even. Due to a large part of the planned Capital spend on new builds being reprofiled into 2023/24 this reduced contribution will not create any issues for the remaining Capital programs being delivered in 2022/23. None available Budget Details Variance Analysis Subjective Analysis forecast Variance Subjective Analysis forecast Variance Service Description A year end underspend is anticipated Variance Narrative The main reason for the projected adverse variance relates to the number of void properties being higher than expected at time of budget setting. The budget was set on the assumption that backlogs following COVID delays in getting voids turned around would be resolved early in year however the numbers continue to be high . Budget Details Variance Analysis A void working group has been reviewing the issues and have been implementing actions and working with Housing Maintenance managers to improve the situation and it is expected that the void figures will start to decrease significantly over the next few months. This budget covers the rents lost on void houses and lockups and the cost of council tax on void properties.
Page 4
APPENDIX 3 WEST DUNBARTONSHIRE COUNCIL HRA CAPITAL PROGRAMME OVERALL PROGRAMME SUMMARY MONTH END DATE PERIOD 7 Spend to Date Spend to Date £000 £000 Red 6 22.2% 5,056 38.7% 6 22.2% 5,056 38.7% Amber 0 0.0% 0 0.0% 0 0.0% 0 0.0% Green 21 77.8% 8,017 61.3% 21 77.8% 8,017 61.3% 27 100% 13,073 100% 27 100% 13,073 100% Budget Spend to Date Forecast Spend Forecast Variance Budget Spend to Date Forecast Spend Forecast Variance Reprofiled Over/ (Under) £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 136,980 5,056 139,063 2,083 46,191 5,056 19,927 (26,264) (28,346) 2,083 0 0 0 0 0 0 0 0 0 0 79,140 8,017 78,959 (181) 19,413 8,017 19,232 (181) 0 (181) 216,120 13,073 218,022 1,902 65,604 13,073 39,159 (26,444) (28,346) 1,902 216,120 13,073 218,022 (1,902) 65,604 13,073 39,159 26,444 0 0 0 0 0 0 0 0 Projects are on target both in relation to overall budget and the forecast stages in the project life cycle and no issues are anticipated at this time 31 October 2022 Project Status Analysis Project Life Status Analysis Current Year Project Status Analysis Number of Projects at RAG Status % Projects at RAG Status % Project Spend at RAG Status Number of Projects at RAG Status % Projects at RAG Status % Project Spend at RAG Status Red Projects are forecast to be overspent and/or experience material delay to completion Amber Projects are either at risk of being overspent and/or delay in completion (although this is unquantifiable at present) or the project has any issues that require to be reported at this time Green Project Status Analysis Project Life Financials Current Year Financials Red TOTAL RESOURCES NET EXPENDITURE Projects are forecast to be overspent and/or significant delay to completion Amber Projects are either at risk of being overspent and/or delay in completion (although this is unquantifiable at present) or the project has any issues that require to be reported at this time Green Projects are on target both in relation to overall budget and the forecast stages in the project life cycle and no issues are anticipated at this time TOTAL EXPENDITURE
Page 5
WEST DUNBARTONSHIRE COUNCIL APPENDIX 4 HRA CAPITAL PROGRAMME ANALYSIS OF RED PROJECTS MONTH END DATE PERIOD 7 Budget Forecast Spend £000 £000 % £000 £000 % 1 Project Life Financials 10,963 398 4% 10,963 0 0% Current Year Financials 2,500 398 16% 1,500 (1,000) -40% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 2 Project Life Financials 566 134 24% 658 92 16% Current Year Financials 108 134 124% 200 92 86% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 3 Project Life Financials 5,092 1,467 29% 6,209 1,117 22% Current Year Financials 969 1,467 151% 2,086 1,117 115% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 31 October 2022 Budget Details Project Life Financials Spend to Date Variance Doors/window component renewals Doors/Windows Component Renewals Planned End Date Forecast End Date Main Issues / Reason for Variance Officers working to meet revised targets. Additional external support has been programmed in from August onwards to assist with window installs, feedback from officers have highlighted challenges with resource levels from back-up contractor. This will be monitored closely, however approximately £1m will need to reprofiled into 23/24. Mitigating Action Building Services actively redeploying internal resurces to assist with installs and working with external support to maximise contribution. Anticipated Outcome Anticipated to meet reduced forecast spend Main Issues / Reason for Variance Projected to exceed budget, this is necessary work to meet demand and comply with legislation. Mitigating Action None available. Anticipated Outcome Budget to overspend. Statutory/regulatory compliance works (lifts/electrical/legionnella/fire etc) This budget will be used to upgrade / replace components / installations in order to comply with the relevant standards / legislation / health and safety in relation to housing stock. Planned End Date Forecast End Date Mitigating Action None available since essential spend. Anticipated Outcome Budget to overspend. Heating improvement works Carry out works to renew inefficient boilers/full systems as identified from the stock condition survey and renewal of obsolete/damaged boilers. Planned End Date Forecast End Date Main Issues / Reason for Variance An overspend is anticipated on this budget, as experienced in recent years as demand has exceeded expectations. Current progress continues this trend. Due to the nature of this project (ensuring heating and hot water availability) there is no option for a conscious reduction of installs.
Page 6
WEST DUNBARTONSHIRE COUNCIL APPENDIX 4 HRA CAPITAL PROGRAMME ANALYSIS OF RED PROJECTS MONTH END DATE PERIOD 7 Budget Forecast Spend £000 £000 % £000 £000 % 31 October 2022 Budget Details Project Life Financials Spend to Date Variance 4 Project Life Financials 8,384 1,064 13% 9,384 1,000 12% Current Year Financials 2,000 1,064 53% 3,000 1,000 50% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 5 Project Life Financials 5,092 775 15% 5,292 200 4% Current Year Financials 969 775 80% 1,169 200 21% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 6 Project Life Financials 106,883 1,219 1% 106,556 (326) 0% Current Year Financials 39,645 1,219 3% 11,972 (27,673) -70% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 Sites to be reprofiled £m Aitkenbar Primary School (374) Clydebank East (13,754) Queens Quay Site B (629) Queens Quay Site C (878) Pappert (4,481) Bank Street (575) Willow Park Phase 1 (1,989) Mount Pleasant (2,420) Future New build sites (2,246) TOTAL OF ALL PROJECTS (27,346) Planned End Date Forecast End Date Main Issues / Reason for Variance Void works to continue into 22/23 to bring void properties up to a lettable standard. The high number of voids has led to a higher than expected demand for this budget, resulting in a projected overspend in 22/23. Mitigating Action None available at this time Void house strategy programme Spend on Void Properties to bring them up to letting standard Anticipated Outcome Void properties to be brought up to lettable standard Environmental renewal works, paths/fences/walls/parking area's Environmental renewal works, paths/fences/walls/parking areas Anticipated Outcome Full budget spend, with overspend anticipated. Planned End Date Forecast End Date Main Issues / Reason for Variance An overspend is anticipated in 22-23 due to level of demand and material costs being higher than expected at time of budget Mitigating Action None available at this time. Main Issues / Reason for Variance Progress will continue to be monitored as the year progresses. The £27.673 variance is made up of £0.326m underspend and a reprofiling of £27.346m into 2023/24 onwards . Summary of reprofiled sites together with site specific updates as follows:- Affordable Supply Programme Affordable Housing Supply Programme Planned End Date Forecast End Date
Page 7
WEST DUNBARTONSHIRE COUNCIL APPENDIX 4 HRA CAPITAL PROGRAMME ANALYSIS OF RED PROJECTS MONTH END DATE PERIOD 7 Budget Forecast Spend £000 £000 % £000 £000 % 31 October 2022 Budget Details Project Life Financials Spend to Date Variance TOTAL OF ALL PROJECTS Project Life Financials 136,980 5,056 4% 139,063 2,083 2% Current Year Financials 46,191 5,056 11% 19,927 (26,264) -57% Clydebank East - 88 units to be completed on the site. Project spend now requires to be reprofiled. Anticipated site start of June 2022 has been delayed as a result of assessing remediation strategy options, while the exercise has proved to be a lengthy process the options have identified an affordable method which is estimated to be around £9m less costly than the original proposed method. We expect revised tender costs early in November and anticipate a site start before the end of the year. The remediation methods will take longer and will be the first phase of the development and the construction of the new homes will likely commence in April 2023. £13.754m of the £18.754m current year budget will be required to be reprofiled into 23/24. Queens Quay Site B - 29 units now completed on the site. Project spend now requires to be reprofiled. Retention figure of £0.629m budgeted to be paid out in 2022/23 will now be reprofiled to be paid in 2023/24 to allow time to finalise account. Queens Quay Site C – 20 units to be completed on site. Project spend now requires to be reprofiled. The budget provision is to acquire additional land within Queens Quay to enhance the Site C proposals, the discussions with CRL/Rydens have been protracted but we intend to make an offer shortly subject to the DV valuation being received. This will be reprofiled into 2022/23 (£1.878m). Pappert - 27 units to be completed on site . Projects spend now requires to be reprofiled. The anticipated site start of October 2022 will not be realised due to a number of factors that have caused the project to miss a number of milestones, notably a longer than anticipated procurement process and the subsequent delay in developing a contract/tender preparation forced us to miss a pricing window from the contractor, we anticipate a new cost price in November with a site start of March 23. It is expected £0.500m will be paid out in 2022/23 withthe remaining £4.481m to be reprofiled into 2023/24 Future New Build gap sites – Project spend now requires to be reprofiled. Ongoing work to acquire private and Council owned sites to finalise wider strategy . Expected that there will be spend of £0.500m this during 2022/23 so £2.246m will be reprofiled into 2023/24. Aitkenbar - Fully complete. Project spend now requires to be reprofiled. Retention figure of £0.374m budgeted to be paid out in 2022/23 will now be reprofiled to be paid in 2023/24 to allow time to finalise account. Anticipated Outcome Project will still complete and will meet revised spend profiles . Bank Street - 20 units to be completed on the site. Project spend needs reprofiled due to wider strategic reasons and potential reprovisioning of sheltered accommodation which will require consultative exercise . Revised estimated start date July 2023, estimated completion January 2025. Project is currently at feasibility stage. Likely outturn for 22/23 for the Bank Street site is expected to be circa. £0.420m with £0.575m therefore required to be reprofiled to 23/24. Willox Park Phase1 - 17 units to be completed on site. Project spend now requires to be reprofiled . Pre planning discussions were more involved than anticipated and required some re designing which has resulted in delay to estimated start date from January 2023 to June 2023 with estimated completion May 2024. Demolition complete, and site investigation under way. Officers ready to submit to for full planning. Tender application expected to go out April 23. At this stage spend in the current year is expected to be £0.400m against budget of £2.390m resulting in reprofiling rquirement of £1.989m. Mount Pleasant - 25 units to be completed on site. Project spend now requires to be reprofiled. Unanticipated longer time frame for demolition (9 months) has delayed this project by 6 months, now estimating a March 2023 site start, although demolitions are planned for next month. £0.100m expected costs in 22/23, resulting in reprofiling requirement of £2.420m to 23/24. Bonhill Gap Site - 32 units to be completed on site. Estimated start date July 2023 and estimated completion September 2024. The project is currently at design stage with spend of £0.420m expected in 22/23 . No reprofilng required . Mitigating Action Staff will work closely with all stakeholders to try and ensure timely resolutions of issues as they arise.
Page 8
APPENDIX 5 WEST DUNBARTONSHIRE COUNCIL HRA CAPITAL PROGRAMME ANALYSIS OF GREEN PROJECTS MONTH END DATE PERIOD 7 Budget Forecast Spend £000 £000 % £000 £000 % 1 Project Life Financials 2,487 253 10% 2,487 0 0% Current Year Financials 474 253 53% 474 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 2 Project Life Financials 2,266 187 8% 2,266 0 0% Current Year Financials 431 187 43% 431 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 3 Project Life Financials 1,557 30 2% 1,557 0 0% Current Year Financials 664 30 5% 664 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 4 Project Life Financials 271 0 0% 271 0 0% Current Year Financials 185 0 0% 185 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 31 October 2022 Budget Details Project Life Financials Spend to Date Variance Special needs adaptations None available at this time Anticipated Outcome Full budget spend, possibility of overspend. Capitalised minor works Gypsy/ Traveller Site improvements Planned End Date Forecast End Date Adaptations to Housing for Special Needs Planned End Date Forecast End Date Main Issues / Reason for Variance No Issues, anticipated to meet full spend and targets. Possibility of overspend due to price increases and demand levels rising. Mitigating Action Better Homes Priority Budget Priority projects as prioritised by the Better Homes Group Planned End Date Forecast End Date Main Issues / Reason for Variance A number of priority initiatives, supported by the Better Homes Project Board, are being investigated and are envisaged to have a positive impact on the current council housing stock and budget, with works expected to progress in 22/23. Main Issues / Reason for Variance No Issues, anticipated to meet full spend and targets. Mitigating Action None required Anticipated Outcome Full budget spend Planned End Date Forecast End Date Main Issues / Reason for Variance No issues. Development of QL system to carry on through 22/23. Mitigating Action None required Mitigating Action None required Anticipated Outcome Full budget spend QL Development This budget relates to the costs associated with the development of the Integrated Housing Management System Anticipated Outcome Full budget spend
Page 9
WEST DUNBARTONSHIRE COUNCIL HRA CAPITAL PROGRAMME ANALYSIS OF GREEN PROJECTS MONTH END DATE PERIOD 7 Budget Forecast Spend £000 £000 % £000 £000 % 31 October 2022 Budget Details Project Life Financials Spend to Date Variance 5 Project Life Financials 170 0 0% 170 0 0% Current Year Financials 40 0 0% 40 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 6 Project Life Financials 17 0 0% 17 0 0% Current Year Financials 17 0 0% 17 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 7 Project Life Financials 36 0 0% 36 0 0% Current Year Financials 36 0 0% 36 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 8 Project Life Financials 192 0 0% 192 0 0% Current Year Financials 192 0 0% 192 0 0% Project Description Project Lifecycle 31-Mar-23 31-Mar-23 Main Issues / Reason for Variance No Issues, anticipated to meet full spend and targets. Mitigating Action None required Anticipated Outcome Full budget spend Gypsy Travellers Site Gypsy/ Traveller Site improvements Planned End Date Forecast End Date Mitigating Action None required Anticipated Outcome Full budget spend Redployable CCTV Cameras Purchase of 5 redeployable CCTV cameras for Housing use Community Safety Projects Community Safety Projects Planned End Date Forecast End Date Main Issues / Reason for Variance No Issues, anticipated to meet full spend and targets. Anticipated Outcome Full budget spend Airport Noise Noise Insulation Project Planned End Date Forecast End Date Planned End Date Forecast End Date Main Issues / Reason for Variance 5 redeployable cameras to be purchased as planned. No issues anticipated. Mitigating Action None required Main Issues / Reason for Variance Awaiting receipt of the airport scheme outline from Glasgow Airport before works can planned. Project expected to make progression in 22/23. Mitigating Action None required Anticipated Outcome Full budget spend
Page 10
WEST DUNBARTONSHIRE COUNCIL HRA CAPITAL PROGRAMME ANALYSIS OF GREEN PROJECTS MONTH END DATE PERIOD 7 Budget Forecast Spend £000 £000 % £000 £000 % 31 October 2022 Budget Details Project Life Financials Spend to Date Variance 9 Project Life Financials 19,841 0 0% 19,841 0 0% Current Year Financials 4,455 0 0% 4,455 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 10 Project Life Financials 17,607 4,076 23% 17,607 0 0% Current Year Financials 4,955 4,076 82% 4,955 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 11 Project Life Financials 257 9 4% 257 0 0% Current Year Financials 75 9 12% 75 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 Targeted SHQS /EESSH compliance works This budget is to focus on work required to maintain the SHQS compliance and energy efficiency with WDC housing stock. Planned End Date Forecast End Date Main Issues / Reason for Variance No Issues, anticipated to meet full spend and targets. Current progress is slightly behind cumulative monthly targets, work is progressing and additional resources will be coming on board shortly with new framework contractor. Planned End Date Forecast End Date Main Issues / Reason for Variance Currently behind monthly targets, however tentatively anticipated to meet full spend and targets. Current tiled roof progress is behind cumulative monthly targets but overall output is anticipated to increase with the new metal and flat roof framework contract coming on board contributing to a wider range of roof types being completed. Mitigating Action None required Mitigating Action None required Anticipated Outcome Full budget spend Roof Coverings Building external component renewals, roofs/chimneys/flashings/fascias/gutters/svp Anticipated Outcome Full budget spend Mitigating Action None required Anticipated Outcome Full budget spend External stores/garages/bin stores/drainage component renewals This budget is to focus on external stores/garages/bin stores etc. component renewals as identified and recommended from the housing stock condition survey. Planned End Date Forecast End Date Main Issues / Reason for Variance No Issues, anticipated to meet full spend and targets.
Page 11
WEST DUNBARTONSHIRE COUNCIL HRA CAPITAL PROGRAMME ANALYSIS OF GREEN PROJECTS MONTH END DATE PERIOD 7 Budget Forecast Spend £000 £000 % £000 £000 % 31 October 2022 Budget Details Project Life Financials Spend to Date Variance 12 Project Life Financials 273 65 24% 273 0 0% Current Year Financials 91 65 72% 91 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 13 Project Life Financials 280 0 0% 280 0 0% Current Year Financials 54 0 0% 54 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 14 Project Life Financials 5,293 935 18% 5,293 0 0% Current Year Financials 1,036 935 90% 1,036 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 15 Project Life Financials 103 0 0% 103 0 0% Current Year Financials 103 0 0% 103 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 Secure entry component renewals This budget is to focus on secure door entry component renewals as identified and recommended from the housing stock condition survey and appropriate council officer referrals. Anticipated Outcome Anticipated not to meet full spend despite best efforts. Planned End Date Forecast End Date Main Issues / Reason for Variance This programme always presents challenges with owner liaison and reaching agreements to install door entry where none exists, this contributes directly to achieving SHQS compliance for this element and reducing abeyances. The budget reflects the demand and number of installs required but it is acknowledged that full uptake is unlikely. Mitigating Action Officers continue to liaise with owners to encourage agreement for install. Planned End Date Forecast End Date Main Issues / Reason for Variance No Issues, anticipated to meet full spend and targets. Mitigating Action None required Energy improvements/energy efficiency works Energy improvements/ efficiency works (e.g. loft insulation, pipe/tank insulation, draught exclusion) Main Issues / Reason for Variance No Issues, anticipated to meet full spend and targets. Mitigating Action None required Anticipated Outcome Full budget spend Anticipated Outcome Full budget spend Modern facilities and services New Kitchens, Bathrooms and Showers Planned End Date Forecast End Date Mitigating Action None required Anticipated Outcome Full budget spend Improvement works (Risk St) Risk Street Over clad Planned End Date Forecast End Date Main Issues / Reason for Variance No Issues, anticipated to meet full spend and targets.
Page 12
WEST DUNBARTONSHIRE COUNCIL HRA CAPITAL PROGRAMME ANALYSIS OF GREEN PROJECTS MONTH END DATE PERIOD 7 Budget Forecast Spend £000 £000 % £000 £000 % 31 October 2022 Budget Details Project Life Financials Spend to Date Variance 16 Project Life Financials 581 0 0% 400 (181) -31% Current Year Financials 181 0 0% 0 (181) -100% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 17 Project Life Financials 3,637 184 5% 3,637 0 0% Current Year Financials 887 184 21% 887 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 18 Project Life Financials 1,135 86 8% 1,135 0 0% Current Year Financials 215 86 40% 215 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 Contingencies This is a contingent budget for unforeseen matters which may arise during the year. Planned End Date Forecast End Date Defective structures/component renewals Defective structures Planned End Date Forecast End Date Main Issues / Reason for Variance No Issues, anticipated to meet full spend and targets. Main Issues / Reason for Variance No Issues, contingent budget for unplanned spend Mitigating Action none at this time Anticipated Outcome Spend as required Mitigating Action None required Anticipated Outcome Full budget spend Main Issues / Reason for Variance No Issues, anticipated to meet full spend and targets. Mitigating Action None required Anticipated Outcome Full budget spend Asbestos management works This budget is to fund work associated with the management of current asbestos legislation and Planned End Date Forecast End Date
Page 13
WEST DUNBARTONSHIRE COUNCIL HRA CAPITAL PROGRAMME ANALYSIS OF GREEN PROJECTS MONTH END DATE PERIOD 7 Budget Forecast Spend £000 £000 % £000 £000 % 31 October 2022 Budget Details Project Life Financials Spend to Date Variance 19 Project Life Financials 2,378 0 0% 2,378 0 0% Current Year Financials 800 0 0% 800 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 20 Project Life Financials 7,729 731 9% 7,729 0 0% Current Year Financials 2,019 731 36% 2,019 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 21 Project Life Financials 13,031 1,461 11% 13,031 0 0% Current Year Financials 2,504 1,461 58% 2,504 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 TOTAL OF ALL PROJECTS Project Life Financials 79,140 8,017 10% 78,959 (181) 0% Current Year Financials 19,413 8,017 41% 19,232 (181) -1% Mitigating Action None required Anticipated Outcome Full budget spend Buy Backs This is a budget to undertake specific projects that will deliver housing policies/strategies, example: Ex local authority and mortgage to rent buy-back scheme Multi Story Flats ( including Fire Risk Assessment Works) High Rise Fire Safety Measures Planned End Date Forecast End Date Main Issues / Reason for Variance No Issues, anticipated to meet spend and revised targets. Anticipated Outcome Budget spend anticipated, should criteria be met. Planned End Date Forecast End Date Main Issues / Reason for Variance The main objective of the Buy Back Scheme is to bring former council properties that were sold through the RTB scheme, back into council use. These properties must assist the council with reducing housing need on the waiting list and where appropriate assist with external capital works. For these reasons, any purchase is subject to stringent criteria to ensure accountability and value for money for existing tenants. Spend in 22/23 will therefore be dependent on these factors. So far this year, 8 homes have been purchased, with a further 4 under offer. The target is to deliver an additional 20 homes each year through the buyback scheme. Mitigating Action None required. Main Issues / Reason for Variance No Issues, budget for salaries and support Mitigating Action None required Anticipated Outcome Full budget spend Salaries/central support/offices Allocation of costs from other WDC services who support the HRA capital programme Planned End Date Forecast End Date
Page 14
APPENDIX 6 WEST DUNBARTONSHIRE COUNCIL HRA CAPITAL PROGRAMME ANALYSIS OF RESOURCES MONTH END DATE PERIOD 7 Budget Forecast Spend £000 £000 % £000 £000 % 1 Project Life Financials (48,826) (4) 0% (48,826) 0 0% Current Year Financials (30,006) 0 0% (10,480) 19,526 -65% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 2 Project Life Financials (42,531) 0 0% (41,168) 1,363 -3% Current Year Financials (9,215) 0 0% (7,852) 1,363 -15% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 3 Project Life Financials (124,667) (13,019) 10% (124,667) 0 0% Current Year Financials (26,286) (13,019) 50% (19,945) 6,341 -24% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 Due to spend being later than anticiapted , receipt of grant will also be later than budgeted. Mitigating Action Income budget wil be reprofiled to match reprofiled spend Anticipated Outcome Income will be received in 2023/24 Main Issues / Reason for Variance 31 October 2022 Budget Details Project Life Financials Spend to Date Variance New Build Grant Grant to facilitate new build housing Planned End Date Forecast End Date CFCR This is capital spend which is funded by revenue budgets Planned End Date Forecast End Date Main Issues / Reason for Variance Income from Revenue reduced to offset adverse varainces in HRA revenue Mitigating Action None required Anticipated Outcome Reduced CFCR Prudential Borrowing Prudential borrowing is long term borrowing from financial institutions that has been approved for the purposes of funding capital expenditure Planned End Date Forecast End Date Main Issues / Reason for Variance Prudential borrowing is impacted by programme delivery therefore due to reprofiling, the requirement in 2022/23 will be less. Mitigating Action None available at this time. Anticipated Outcome While prudential borrowing requirement is likely to be less than budgeted in the current financial year this is anticipated to catch up over the programme life.
Page 15
WEST DUNBARTONSHIRE COUNCIL HRA CAPITAL PROGRAMME ANALYSIS OF RESOURCES MONTH END DATE PERIOD 7 Budget Forecast Spend £000 £000 % £000 £000 % 31 October 2022 Budget Details Project Life Financials Spend to Date Variance New Build Grant 4 Project Life Financials (96) (50) 52% (96) 0 0% Current Year Financials (96) (50) 52% (96) 0 0% Project Description Project Lifecycle 31-Mar-27 31-Mar-27 TOTAL RESOURCES Project Life Financials (216,120) (13,073) 6% (214,757) 1,363 -1% Current Year Financials (65,604) (13,069) 20% (38,373) 27,230 -42% Other Capital Income Other Income to capital Planned End Date Forecast End Date Main Issues / Reason for Variance No variance Mitigating Action None required Anticipated Outcome Income will be received
Page 16
WEST DUNBARTONSHIRE COUNCIL APPENDIX 7 HRA CAPITAL PROGRAMME ANALYSIS OF AFFORDABLE HOUSING SUPPLY PROGRAMME MONTH END DATE PERIOD 7 Budget Spend to Date Forecast Spend £000 £000 £000 £000 % RAG Status St Andrews School 636 93 290 346- -54% Haldane Primary School 148 149 167 20 13% Aitkenbar Primary School 652 214 652 - 0% Clydebank East 26,474 42 26,474 - 0% Creveul Court 58 59 58 - 0% Queens Quay Site B 1,259 402 1,259 - 0% Queens Quay Site C 6,198 1 6,198 - 0% Pappert 7,332 2 7,332 - 0% Lilac Avenue 2,676 - 2,676 - 0% Bank Street 4,674 - 4,674 - 0% Clydebank Health Centre 6,930 3 6,930 - 0% Willox Park Phase1 3,817 51 3,817 - 0% Willox Park Phase2 6,300 - 6,300 - 0% Mount Pleasant 4,200 18 4,200 - 0% Silverton 2,100 - 2,100 - 0% Fees, Staffing Costs, contingency 4,005 15 4,005 - 0% Gap sites Bonhill Gap Site 420 171 420 - 0% Future New build sites 16,824 - 16,824 - 0% Total Expenditure 94,703 1,219 94,376 (326) 31 October 2022 Site Project Life Financials Variance