WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer: Regulatory and Regeneration
Council: 21 December 2022
Subject: Glasgow City Region City Deal - Update
1. Purpose
1.1 To note the progress with the implementation of the Glasgow City Region
City Deal.
2. Recommendations
2.1 It is recommended that Council notes the progress of the Glasgow City
Region programme.
3. Background
3.1 The Glasgow City Region City Deal Infrastructure programme equates to
£1.13bn of investment during period 2015-2035. Projects are progressing
and have reached various stages from Strategic, Outline and Full Business
Case stages of approval.
3.2 Previous reports, listed in background papers, have identified progress of the
Council’s City Deal project at the Exxon site.
4. Main Issues
4.1 The Council is progressing the Exxon Project, which includes working with
Balfour Beatty via the Scape Framework as part of the pre-construction
agreement to allow the detailed design elements of the project to commence
and provide greater certainty regarding the budget position. In October
Council approved expenditure of £5.74M on design and construction of the
Western Underpass prior to approval of the Full Business Case, anticipated
to be in June 2023. The contract with Network Rail for the design has now
been concluded and regular progress meetings will take place.
Glasgow City Region City Deal Update
4.2 The Glasgow City Region Cabinet met on 8 November 2022. Agenda items
included two separate presentations on the future of the Clyde, both
advancing the case for collective management of the Clyde as an asset in a
way that isn’t constrained by administrative boundaries. It is anticipated that
Clyde Mission will play a role in this.
4.3 The Quarterly Performance Report was also presented, and included the
recommendation to approve the Change Control Request from West
Dunbartonshire Council that was approved at August Council. The Change
ITEM 8

Page 2

Control Request sought a delay to the submission of Final Business Case
until June 2023, and an accelerated drawdown of an additional £2.61m from
total Glasgow City Region contribution. The Council’s efforts to secure
additional funding for complementary projects in the wider Exxon masterplan
were noted, specifically the Scottish Government Vacant and Derelict Land
fund for greenspace and community access proposals.
4.4 Glasgow City Region Chief Executives Group met on 7 December. Agenda
items included a Change Control Request from Glasgow City Council on
Holland Street/Pitt Street Public Realm and a proposal to establish an Anchor
Network to advance Community Wealth Building in the Region. The Interim
Performance report provided an update on the appointment of transport
consultants to progress a Region-wide strategy for Electric Vehicle charging;
noted a funding gap for developing proposals for the Clyde Climate Forest for
which Member Authorities will be asked to contribute from Shared Prosperity
Fund; and a call for Member Authorities to harmonise their funding criteria for
green business support.
4.5 Due to escalating construction costs having an impact on the ability to deliver
all the projects across the Region, the City Region Programme Management
Office is working with Chief Executives on a project reprogramming exercise
with the objective of prioritising projects with the most economic impact. The
information will be analysed by the PMO and a report will be presented to
April Cabinet.
Green Freeport Bid
4.5 No decision has been taken on successful bid.  
Shared Prosperity Fund
4.6 Notification of the outcome of the Glasgow City Region Shared Prosperity
Fund investment Plan that was submitted to UK Government on behalf of
the Member Authorities is imminent. Approval by UK Government had been
anticipated in October but as a result of the two Budgets that happened in
quick succession, has been delayed until the end of the year. The
Department of Levelling Up, Housing and Communities issued a press
release on 5 December stating that the spending plans had been approved.
The Council is awaiting details.
Clyde Bridge
4.7 The Clyde Bridge Contractor maintains a website with regular updates on the
project. A viewer at the top of the website home page shows a video of
progress which is updated monthly. This can be accessed at:
www.graham.co.uk/clyde-waterfront
4.8  Since the last report the Contractor has continued to develop the detailed
designs for the project, based on the consented specimen design and
continued dialogue with key stakeholders and landowners. Previously agreed
accommodation works and boundary fencing is well progressed for
landowners within the project area. Work on drainage has commenced to the

Page 3

south of the river and soil stabilisation work is on-going to the north, along
with works in preparation of diversion of the Yoker Burn culvert. Works
licences for the South Pier and Yoker culvert have now been issued by the
Harbour Authority and work in these areas will commence shortly. Fabrication
of the bridge structure is expected to commence off-site in Mid-December.
4.9 The Construction Contract for the Clyde Bridge project requires that
subcontract and supplier opportunities over a value of £10,000 are advertised
through the Public Contracts Scotland Tender portal. This requirement
ensures that as the large-scale project is broken into smaller work parcels,
local companies and SME’s have the opportunity to bid for packages of work.
To date 13 works packages have been advertised, five awarded, three of
which to companies within the City Region. Additionally, a commitment of a
minimum of 12 days will be spent by the Contractor undertaking supply chain
development, to encourage and coach, local organisations and SME’s how to
prepare to enable access to this and therefore other public sector work
opportunities. Thus far five sessions of training have been held.    
4.10    Next stages of works include submission of design drawings to West
Dunbartonshire Council officers for the road and drainage designs within the
West Dunbartonshire area. 
4.11    Newsletters are accessible by those who register for further updates after the
issue of the first newsletter to over 3,500 residents and businesses in the
local area. Posters advising the project website address were also delivered
to public buildings in the project area. A link to register for updates is
contained within the project webpage noted above.
5 People Implications
5.1 There are a number of senior officers involved in the Glasgow City
Region wider programme as identified at City Region Update paper at
Council on 26 August 2021.
6. Financial Implications
6.1 The approved budget to date for the City Deal Exxon project is £34.5M.
The expenditure during 2021/22 was £0.44M, and as at November 2022
the current expenditure for 2022/23 stands at £0.133M.
7. Risk Analysis
7.1 There are a number of project risks associated with the development at
the ExxonMobil project site and these are contained within the risk
register of the refreshed Outline Business Case and updated by the
project board on a regular basis.
8. Equalities Impact Assessment
8.1 An Equalities Impact Assessment is not necessary for this report as it an
update on a previously reported project.

Page 4

9. Consultation
9.1 Consultation with all key stakeholders is progressing as we continue
to work as part of the Glasgow City Region.
9.2 Legal Services, Finance and Procurement are regularly consulted
through their participation in the Exxon project board.
9.3 Wider communication is produced regarding progress of the Glasgow
City Region at its website http://www.glasgowcityregion.co.uk/
10 Strategic Assessment
10.1 At its meeting on 26 October 2022, the Council agreed that one of its
main strategic priorities for the Strategic Plan 2022 - 2027 is:
• A Strong local economy and improved employment opportunities
10.2 The proposals within this report are specifically designed to deliver on
this priority.
Alan Douglas
Chief Officer: Regulatory and Regeneration
Date: 6 December 2022
Person to Contact: Gillian McNamara
gillian.mcnamara@west-dunbarton.gov.uk
Appendix: None
Background Papers: UK Shared Prosperity Fund Report to Housing and
Communities Committee 22 August 2022
GCR Interim Performance Report- 18 Nov 2021 , GCR
Education Improvement Collaborative/West Partnership
Improvement Plan 2021/22, Glasgow City Region City
Deal – 29 Council updates since February 2016, March
2021 Elected Members briefing- Renfrew Bridge, July
2020 Members Bulletin.
ExxonMobil Commercial Agreement 24 June 2020.
Glasgow City Region City Deal - Exxon Site Outline
Business Cases 22 Feb 2017 and 28 Nov 2018
(Refreshed). 
Clyde Valley City Deal - Update and Strategic Business
Case- Council 24 June 2015. 
Clyde Valley City Deal Update- Council 25 Aug 2015 and
16 Dec 2015. 
Clyde Valley City Deal- Governance- Council 17 Dec
2014.  
Glasgow City Region City Deal- Council 13 August 2014.

Page 5

“City Deal Initiative” Clyde Valley Investment Fund-
Council 30 April 2014 (Memorandum of Understanding).
Clyde Valley Community Planning Partnership – City Deal
Initiative – Council 28 August 2013.
Equalities Impact Assessment November 2018.
Environmental Impact Assessment -DC20/088 – Planning
Application – Documents.
Wards Affected: All