WEST DUNBARTONSHIRE COUNCIL APPENDIX 1
HRA REVENUE BUDGETARY CONTROL 2022/23
PERIOD END DATE
Subjective Summary
Total Budget
2022/23 
£000
Spend to
Date
2022/23 
£000
Forecast
Spend
£000
Annual RAG
Status
Employee Costs 6,690 2,414 6,844 154 2% 
Property Costs 2,030 677 2,000 (30) -1% 
Transport Costs 112 53 151 39 0% 
Supplies, Services And Admin 395 89 382 (13) -3% 
Support Services 2,724 845 2,536 (188) -7% 
Other Expenditure 532 409 580 48 9% 
Repairs & Maintenance 12,942 997 12,293 (649) -5% 
Bad Debt Provision 1,060 309 923 (137) -13% 
Void Loss (Council Tax/Lost Rents) 857 819 1,684 827 96% 
Loan Charges 19,676 6,559 19,676 0 0% 
Total Expenditure 47,018 13,171 47,069 51 0% 
House Rents 45,215 16,680 45,239 (24) 0% 
Lockup Rents 210 75 206 4 2% 
Factoring/Insurance Charges 1,316 545 1,308 8 1% 
Other rents 115 37 116 (1) -1% 
Interest on Revenue Balance 55 4 10 45 82% 
Transfer from Reserves 0 0 60 (60) 0% 
Miscellaneous income 107 44 136 (29) -27% 
Total Income 47,018 17,385 47,075 (57) 0% 
Net Expenditure 0 (4,214) (6) (6) 
Forecast Variance 2022/23
£000               %
31 August 2022

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
HRA REVENUE BUDGETARY CONTROL 2022/23
ANALYSIS FOR VARIANCES OVER £50,000
MONTH END DATE 31 August 2022
PERIOD 5
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
EMPLOYEE COSTS 6,690 6,844 154 2% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
SUPPORT SERVICES 2,724 2,536 (188) -7% 
Main Issues
Mitigating Action No mitigating action is required.
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
REPAIRS & MAINTENANCE 12,942 12,293 (649) -5% 
Main Issues
Mitigating Action No mitigating action is required.
Anticipated Outcome
The need for additional staffing is regularly reviewed and will be reduced when service
requirements allow.
The favourable variance within Repairs & Maintenance is due to a couple of factors.  The
first being other maintenance relating to Gas Maintenance, Lift Maintenance etc. is
expected to be lower than anticipated at time of budget setting when comparing to previous
years trends.  The second factor, similarly when looking at previous years trends we can
expect the recoveries from owners to be higher than anticipated at time of budget setting. 
These combined results in the projected favourable variance in 2022/23.
Variance Narrative
Variance Narrative
This budget covers all repair and maintenance expenditure to houses and lockups
Subjective Description
A year end underspend is anticipated
A year end underspend is anticipated
This budget covers all employees charged directly to the HRA including caretakers.
Variance Narrative
£60K of this adverse variance relates to the increased pay awarded to caretakers  following
job evaluation panel on 7 April.  This is offset by a transfer from HRA service improvement
reserve which is shown in the income section . The remaining variance is due to additional
temp posts being added to assist with backlogs/ staff absences. 
A favourable variance is expected with the assumption that the 2022/23 forecast outturn for
support services is expected  to be in line with the 2021/22 outturn adjusted for pay uplifts
etc. This charge is calculated each year end based on HRA's percentage usage of the total
cost of WDC support services. The 2022/23 HRA budget was set before this 2021/22
outturn was known so was based on 2020/21 charge which was higher.
Service Description
Budget Details Variance Analysis
Subjective Analysis forecast Variance
Budget Details Variance Analysis
Subjective Analysis forecast Variance
A year end overspend is anticipated
This budget covers central support recharges to the HRA
Budget Details Variance Analysis
Subjective Analysis forecast Variance
Subjective Description

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
HRA REVENUE BUDGETARY CONTROL 2022/23
ANALYSIS FOR VARIANCES OVER £50,000
MONTH END DATE 31 August 2022
PERIOD 5
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
BAD DEBT PROVISION 1,060 923 (137) -13% 
Main Issues
Mitigating Action No mitigating action is required.
Anticipated Outcome
Budget Forecast
Spend
RAG
Status
£000 £000 £000 %
VOID LOSS 857 1,684 827 96% 
Main Issues
Mitigating Action
Anticipated Outcome
Subjective Analysis forecast Variance
Service Description
A year end underspend is anticipated
A year end overspend is anticipated
Variance Narrative
The Bad Debt Provision expected to be required for 2022/23 is less than estimated at time
of budget setting, resulting in a favourable variance. This assumes that the provision
required in 22/23  will be similar to the 21/22 provision.
Budget Details Variance Analysis
Subjective Analysis forecast Variance
Service Description
This budget allows for the provision for bad and doubtful debts to be maintained at an appropriate level
Variance Narrative
The main reason for the projected adverse variance relates to the number of void properties
being higher than expected at time of budget setting. The budget was set on the
assumption that backlogs following COVID delays  in getting voids turned around would be
resolved early in year however the  numbers continue to be high .
Budget Details Variance Analysis
A void working group has been reviewing the issues and have been implementing actions
and working with Housing Maintenance managers to improve the situation and it is
expected that the void figures will start to decrease significantly over the next few month
This budget covers the rents lost on void houses and lockups and the cost of council tax on void properties.

Page 4

APPENDIX 3
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
MONTH END DATE
PERIOD 5
Spend to
Date Spend to Date
£000 £000
Red
0 0.0% 0 0.0% 0 0.0% 0 0.0%
Amber
2 7.7% 2,663 35.9% 2 7.7% 2,650 35.7%
Green
24 92.3% 4,755             64.1% 24 92.3% 4,765                64.3%
26 100% 7,417 100% 26 100% 7,416 100%
Budget Spend to
Date
Forecast
Spend Forecast Variance Budget Spend to Date Forecast
Spend
Forecast
Variance Slippage Over/
(Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
0 0 0 0 0 0 0 0 0 0
115,267 2,663 115,767 500 41,645 2,650 39,581 (2,064) (2,564) 500
100,816 4,755 100,636 (181) 23,922 4,765 23,742 (181) 0 (181)
216,084 7,417 216,403 319 65,567 7,416 63,322 (2,245) (2,564) 319
216,084 7,417 216,403 (319) 65,567 7,416 63,322 2,245
0 0 0 0 0 0 0 0
Projects are on target both in relation to overall budget and the
forecast stages in the project life cycle and no issues are anticipated
at this time
31 August 2022
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project Spend at
RAG Status
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project
Spend at RAG
Status
Red
Projects are forecast to be overspent and/or experience material
delay to completion
Amber
Projects are either at risk of being overspent and/or delay in
completion (although this is unquantifiable at present) or the project
has any issues that require to be reported at this time
Green
Project Status Analysis
Project Life Financials Current Year Financials
Red
TOTAL RESOURCES
NET EXPENDITURE
Projects are forecast to be overspent and/or significant delay to
completion
Amber
Projects are either at risk of being overspent and/or delay in
completion (although this is unquantifiable at present) or the project
has any issues that require to be reported at this time
Green
Projects are on target both in relation to overall budget and the
forecast stages in the project life cycle and no issues are anticipated
at this time
TOTAL EXPENDITURE

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF AMBER PROJECTS
MONTH END DATE
PERIOD 5
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials 8,384 960 11% 8,884 500 6%
Current Year Financials 2,000 960 48% 2,500 500 25%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
2
Project Life Financials 106,883 1,703 2% 106,883 0 0%
Current Year Financials 39,645 1,691 4% 37,081 (2,564) -6%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Bonhill Gap Site - 32 units to be completed on site.  Estimated start date April 2023 and estimated completion October 2024.  The
project is currently at design stage.
Mitigating Action
None required at this time
Anticipated Outcome
Project to complete and meet revised spend targets
Queens Quay Site C - 20 units to be completed on site.  Estimated start date March 2023 and estimated completion March 2024.
Pappert - 27 units to be completed on site.  Estimated completion early  2023.  Officers currently working on the design and build
contract.
Bank Street - 20 units to be completed on the site.  Estimated start date July 2023, estimated completion July 2024.  Project is
currently at feasibility stage and probable outturn is expected to be lower than budgeted with a revised forecast spend of £0.420m
against budget of £0.995m, resulting in slippage of £0.575m
Clydebank Health Centre - 41 units to be completed on site.  Purchase cost now agreed with NHS with sale to be finalised in coming
weeks.
Willox Park Phase1 - 17 units to be completed on site.  Estimated start date June 2023 and estimated completion May 2024.  17/18
units demolition complete, and site investigation under way.  Tender application expected to go out April 23.  At this stage spend in the
current year is expected to be £0.400m against budget of £2.4m resulting in slippage of £1.989m.
Mount Pleasant - 25 units to be completed on site.  Estimated start date March 2023 with estimated completion March 2024. 
Demolition of current site to go to the tendering committee at end of September 2022.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Progress will continue to be monitored as the year progresses.  The project has been moved into amber due to issues around the
Clydebank East site. Following additional and more detailed site investigations it now appears likely that there will be significant
additional costs to deliver the ground remediation strategy.  These additional costs place the development at risk due to affordability
issues.  It is expected full information to make an assessment will be available in October and  an update will be given to the Housing
and Communities Committee when this has been achieved.  Slippage to 23/24 is expected for Bank Street and Willox Park phase 1. 
Site specific updates as follows:-
Clydebank East - 88 units to be completed on the site.  Estimated Start Date to be revised in light of required remediation strategy. 
Queens Quay Site B - 29 units were expected to complete August 22, with rental income forecast from end of September 22. This has
however have been delayed to end of September 22 completion with rental income forecast from end of October 22 due to delay with
completion certificate.
Affordable Supply Programme
Affordable Housing Supply Programme
Mitigating Action
None available at this time
Anticipated Outcome
Void properties to be brought up to lettable standard
Void house strategy programme
Spend on Void Properties to bring them up to letting standard 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Void works to continue into 22/23 to bring void properties up to a lettable standard.  The high number of voids has led to a higher than
expected demand for this budget, resulting in a projected overspend in 22/23. 
31 August 2022
Budget Details
Project Life Financials
Spend to Date Variance

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 5
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials 2,487 5 0% 2,487 0 0%
Current Year Financials 474 5 1% 474 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
2
Project Life Financials 2,266 0 0% 2,266 0 0%
Current Year Financials 431 0 0% 431 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
3
Project Life Financials 1,557 0 0% 1,557 0 0%
Current Year Financials 664 0 0% 664 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
4
Project Life Financials 271 0 0% 271 0 0%
Current Year Financials 185 0 0% 185 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Adaptations to Housing for Special Needs 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets. Possibility of overspend due to price increases and demand levels rising.
Mitigating Action
31 August 2022
Budget Details Project Life Financials
Spend to Date Variance
Special needs adaptations
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
None required at this time
Anticipated Outcome
Full budget spend, possibility of overspend.
Capitalised minor works
Gypsy/ Traveller Site improvements 
Planned End Date  Forecast End Date
Mitigating Action
None required
Anticipated Outcome
Full budget spend
QL Development
This budget relates to the costs associated with the development of the Integrated Housing
Management System
Better Homes Priority Budget
Priority projects as prioritised by the Better Homes Group 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
A number of priority initiatives, supported by the Better Homes Project Board,  are being investigated and are envisaged to have
a positive impact on the current council housing stock and budget, with works expected to progress in 22/23.
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No issues. Development of QL system to carry on through 22/23.
Mitigating Action
None required

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 5
Budget Forecast Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details Project Life Financials
Spend to Date Variance
5
Project Life Financials 170 0 0% 170 0 0%
Current Year Financials 40 0 0% 40 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
6
Project Life Financials 17 0 0% 17 0 0%
Current Year Financials 17 0 0% 17 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
7
Project Life Financials 192 0 0% 192 0 0%
Current Year Financials 192 0 0% 192 0 0%
Project Description
Project Lifecycle 31-Mar-23 31-Mar-23
Gypsy Travellers Site
Gypsy/ Traveller Site improvements 
Planned End Date  Forecast End Date
Community Safety Projects
Community Safety Projects 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Awaiting receipt of the airport scheme outline from Glasgow Airport before works can planned.  Project expected to make
progression in 22/23.
Mitigating Action
None required
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Airport Noise
Noise Insulation Project
Anticipated Outcome
Full budget spend

Page 8

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 5
Budget Forecast Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details Project Life Financials
Spend to Date Variance
8
Project Life Financials 19,841 0 0% 19,841 0 0%
Current Year Financials 4,455 0 0% 4,455 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
9
Project Life Financials 17,607 2,211 13% 17,607 0 0%
Current Year Financials 4,955 2,211 45% 4,955 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
10
Project Life Financials 10,963 154 1% 10,963 0 0%
Current Year Financials 2,500 154 6% 2,500 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets. Current progress is slightly behind cumulative monthly targets, work is
progressing and additional resources will be coming on board shortly with new framework contractor.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Targeted SHQS /EESSH compliance works
This budget is to focus on work required to maintain the SHQS compliance and energy
efficiency  with WDC housing stock.   
Planned End Date  Forecast End Date
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Doors/window component renewals
Doors/Windows Component Renewals
Roof Coverings
Building external component renewals, roofs/chimneys/flashings/fascias/gutters/svp 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Currently behind monthly targets, however tentatively anticipated to meet full spend and targets. Current tiled roof progress is
behind cumulative monthly targets but overall output is anticipated to increase with the new metal and flat roof framework
contract coming on board contributing to a wider range of roof types being completed.
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Project is anticipated to meet revised targets.  Additional external support became available from August to assist with window
installs, feedback from officers have highlighted challenges with resource levels from back-up contractor. This will be monitored
closely.
Mitigating Action
None required at this time

Page 9

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 5
Budget Forecast Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details Project Life Financials
Spend to Date Variance
11
Project Life Financials 257 0 0% 257 0 0%
Current Year Financials 75 0 0% 75 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
12
Project Life Financials 273 35 13% 273 0 0%
Current Year Financials 91 35 39% 91 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
13
Project Life Financials 566 89 16% 566 0 0%
Current Year Financials 108 89 83% 108 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
External stores/garages/bin stores/drainage component renewals
This budget is to focus on external stores/garages/bin stores etc. component renewals as
identified and recommended from the housing stock condition survey. 
Planned End Date  Forecast End Date
Secure entry component renewals
This budget is to focus on secure door entry component renewals as identified and
recommended from the housing stock condition survey and appropriate council officer referrals. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
This programme always presents challenges with owner liaison and reaching agreements to install door entry where none exists,
this contributes directly to achieving SHQS compliance for this element and reducing abeyances. The budget reflects the demand
and number of installs required but it is acknowledged that full uptake is unlikely.
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Mitigating Action
Officers continue to liaise with owners to encourage agreement for install.
Anticipated Outcome
Anticipated not to meet full spend despite best efforts.
Statutory/regulatory compliance works (lifts/electrical/legionnella/fire etc)
This budget will be used to upgrade / replace components / installations in order to comply with
the relevant standards / legislation / health and safety in relation to housing stock.
Anticipated Outcome
Full budget spend

Page 10

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 5
Budget Forecast Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details Project Life Financials
Spend to Date Variance
14
Project Life Financials 5,092 435 9% 5,092 0 0%
Current Year Financials 969 435 45% 969 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
15
Project Life Financials 280 0 0% 280 0 0%
Current Year Financials 54 0 0% 54 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
16
Project Life Financials 5,293 73 1% 5,293 0 0%
Current Year Financials 1,036 73 7% 1,036 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
17
Project Life Financials 103 0 0% 103 0 0%
Current Year Financials 103 0 0% 103 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Main Issues / Reason for Variance
Anticipated to meet full spend and targets and possibly overspend. This budget has overspent in recent years as demand has
exceeded expectations. Current progress continues this trend however an industry wide shortage in microchips is likely to hinder
availability of boilers and in turn will impact on spend. Due to the nature of this project (ensuring heating and hot water
availability) there is no option for a conscious reduction of installs.
Mitigating Action
None available
Anticipated Outcome
Full budget spend, possible overspend.
Heating improvement works
Carry out works to renew inefficient boilers/full systems as identified from the stock condition
survey and renewal of obsolete/damaged boilers. 
Planned End Date  Forecast End Date
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Modern facilities and services
New Kitchens, Bathrooms and Showers
Energy improvements/energy efficiency works
Energy improvements/ efficiency works (e.g. loft insulation, pipe/tank insulation, draught
exclusion) 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Anticipated Outcome
Full budget spend
Improvement works (Risk St)
Risk Street Over clad 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend

Page 11

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 5
Budget Forecast Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details Project Life Financials
Spend to Date Variance
18
Project Life Financials 581 0 0% 400 (181) -31%
Current Year Financials 181 0 0% 0 (181) -100%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
19
Project Life Financials 3,637 113 3% 3,637 0 0%
Current Year Financials 887 113 13% 887 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
20
Project Life Financials 5,092 457 9% 5,092 0 0%
Current Year Financials 969 457 47% 969 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
21
Project Life Financials 1,135 30 3% 1,135 0 0%
Current Year Financials 215 30 14% 215 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, contingent budget for unplanned spend
Mitigating Action
none at this time
Contingencies
This is a contingent budget for unforeseen matters which may arise during the year.
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Anticipated Outcome
Spend as required
Defective structures/component renewals
Defective structures 
Planned End Date  Forecast End Date
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Asbestos management works
This budget is to fund work associated with the management of current asbestos legislation and
Environmental renewal works, paths/fences/walls/parking area's
Environmental renewal works, paths/fences/walls/parking areas 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required

Page 12

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 5
Budget Forecast Spend
£000 £000 % £000 £000 %
31 August 2022
Budget Details Project Life Financials
Spend to Date Variance
22
Project Life Financials 2,378 0 0% 2,378 0 0%
Current Year Financials 800 0 0% 800 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
23
Project Life Financials 7,729 319 4% 7,729 0 0%
Current Year Financials 2,019 319 16% 2,019 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
24
Project Life Financials 13,031 835 6% 13,031 0 0%
Current Year Financials 2,504 835 33% 2,504 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Multi Story Flats  ( including Fire Risk Assessment Works)
High Rise Fire Safety Measures 
Planned End Date  Forecast End Date
Buy Backs
This is a budget to undertake specific projects that will deliver housing policies/strategies,
example: Ex local authority and mortgage to rent buy-back scheme 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
The main objective of the Buy Back Scheme is to bring former council properties that were sold through the RTB scheme, back
into council use.  These properties must assist the council with reducing housing need on the waiting list and where appropriate
assist with external capital works.  For these reasons, any purchase is subject to stringent criteria to ensure accountability and
value for money for existing tenants.  Spend in 22/23 will therefore be dependent on these factors.  So far this year , 3 homes
have been purchased, with a further 8 under offer. The target is to deliver an additional 20 homes each year through the buyback
scheme.
Main Issues / Reason for Variance
No Issues, anticipated to meet spend and revised targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Mitigating Action
None required.
Anticipated Outcome
Budget spend anticipated, should criteria be met.
Main Issues / Reason for Variance
No Issues, budget for salaries and support
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Salaries/central support/offices
Allocation of costs from other WDC services who support the HRA capital programme 
Planned End Date  Forecast End Date

Page 13

APPENDIX 6
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
MONTH END DATE
PERIOD 5
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials (48,826) 0 0% (48,826) 0 0%
Current Year Financials (30,006) 0 0% (27,980) 2,027 -7%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
No issues, income due to be received with no problems anticipated
Mitigating Action
None required
Anticipated Outcome
Income due to be received
Main Issues / Reason for Variance
31 August 2022
Budget Details Project Life Financials
Spend to Date Variance
NEW BUILD GRANT
Grant to facilitate the building of new build housing 
Planned End Date  Forecast End Date

Page 14

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
HRA CAPITAL PROGRAMME
ANALYSIS OF AFFORDABLE HOUSING SUPPLY PROGRAMME
MONTH END DATE
PERIOD 5
Budget Spend to Date Forecast Spend
£000 £000 £000 £000 %
RAG
Status
St Andrews School 636                          34                            636                                -                          0% 
Haldane Primary School 148                          0                              148                                -                          0% 
Aitkenbar Primary School 652                          214                          652                                -                          0% 
Clydebank East 26,474                    -                          26,474                          -                          0% 
Creveul Court 58                            59                            58                                  -                          0% 
Queens Quay Site B 1,259                      1,292                      1,259                            -                          0% 
Queens Quay Site C 6,198                      1                              6,198                            -                          0% 
Pappert 7,332                      2                              7,332                            -                          0% 
Lilac Avenue 2,676                      -                          2,676                            -                          0% 
Bank Street 4,674                      -                          4,674                            -                          0% 
Clydebank Health Centre 6,930                      3                              6,930                            -                          0% 
Willox Park Phase1 3,817                      70                            3,817                            -                          0% 
Willox Park Phase2 6,300                      -                          6,300                            -                          0% 
Mount Pleasant 4,200                      11                            4,200                            -                          0% 
Silverton 2,100                      -                          2,100                            -                          0% 
Fees, Staffing Costs, contingency 4,005                      14                            4,005                            -                          0% 
Gap sites 12,600                    2                              12,600                          -                          0% 
Bonhill Gap Site 420                          2                              420                                -                          0% 
Future New build sites 16,824                    -                          16,824                          -                          0% 
Total Expenditure 107,303 1,703 107,303 0 
31 August 2022
Site
Project Life Financials
Variance