Strategic Plan (2017-22) Annual report 2021/22
Priority 1. A strong local economy and improved job opportunities
Performance Indicator 2019/20 2020/21 Comments Managed
By Status Value Target Status Value Target
Percentage of school
leavers in positive and
sustained destinations
89.66
% 92.4% 90.99
% 92.5%
Between 2019/20 and 2020/21, % of school leavers in
positive and sustained destinations has increased by
1.33 percentage points.  This is 4.49 percentage points
below the Scottish average of 95.48%. 
Andrew
Brown
Average Total Tariff
SIMD Quintile 1 647 714 676 718
Between 2019/20 and 2020/21, Average tariff score
SIMD quintile 1 has increased by 29 to 676. This is 12
below the Scottish average of 688. It is 42 below the
target of 718, which has not been met for this indicator.
Andrew
Brown
Average Total Tariff
SIMD Quintile 2 914 912 912 931
Between 2019/20 and 2020/21, Average tariff score
SIMD quintile 2 has decreased by 2 to 912. This is 95
above the Scottish average of 817. It is 19 below the
target of 931, which has not been met for this indicator.
Andrew
Brown
Average Total Tariff
SIMD Quintile 3 953 967 1,100 984
Between 2019/20 and 2020/21, Average tariff score
SIMD quintile 3 has increased by 147 to 1,100. This is
125 above the Scottish average of 975. It is 116 above
the target of 984, which has been met for this indicator.
Andrew
Brown
Average Total Tariff
SIMD Quintile 4 1,083 1,119 1,121 1,184 Between 2019/20 and 2020/21, Average tariff score
SIMD quintile 4 has increased by 38 to 1,121. This is 13
Andrew
Brown
APPENDIX 2

Page 2

2
Performance Indicator 2019/20 2020/21 Comments  Managed
By Status Value Target Status Value Target
above the Scottish average of 1,108. It is 63 below the
target of 1,184, which has not been met for this indicator. 
Average Total Tariff
SIMD Quintile 5  1,208 1,157  1,315 1,163
Between 2019/20 and 2020/21, Average tariff score
SIMD quintile 5 has increased by 107 to 1,315. This is 5
below the Scottish average of 1,320. It is 152 above the
target of 1,163, which has been met for this indicator. 
Andrew
Brown
% of procurement
spent on local
enterprises (assessed
by LGBF) 
8.23% 12%  10% 14%
Target not met although representing an increase in
previous reporting periods. When SMEs who have a
presence in WD (ie other base elsewhere) are also
included, this figure increases by 33.1 percentage points
to 43.1%. 
Annabel
Travers
*Data for the Performance Indicators above, represents the latest data available due to reporting cycles for national and benchmarked data   
Performance Indicator 2020/21 2021/22 Comments Managed
By Status Value Target Status Value Target
Employment rate  70.1% 72.25
%  73.9% 72.5%
The most recent data released 16th August 2022 relates
to the period April 2021 to March 2022.  The employment
rate for West Dunbartonshire was 73.9%.  The
comparative rate for Scotland was 73.8% and Great
Britain 75.2% in the same period whist neighbouring
Glasgow was 71.8% 
Stephen
Brooks 
% of households that
are workless  19% 22%  19% 21.8% Target exceeded. Stephen
Brooks

Page 3

3
Performance Indicator 2020/21 2021/22 Comments Managed
By Status Value Target Status Value Target
Number of businesses
given advice and
assistance to start up
through Business
Gateway 
200 200  201 200 Target exceeded 
Michael
McGuinnes
s
Priority 2. Supported individuals, families and carers living independently and with dignity 
Performance Indicator 2020/21 2021/22 Comments Managed
By Status Value Target Status Value Target
% of council dwellings
that meet the Scottish
Housing Quality
Standard ( assessed
by LGBF) 
79.18
%
96.37
% 
18.17
%
86.15
%
Target not met. The key contributing factor is due to the
Electrical Installation Condition Reports (EICRs)
programme not being completed as planned by the end
of March 2022. The programme has been delayed due to
Covid restrictions and the wider consequences of these
impacting on internal and external resource availability to
deliver the programme as planned. While we have since
secured additional resource to deliver the programme as
early as possible this did not significantly reduce SHQS
failures before 31st March 2022. To ensure the
programme continues to accelerate all our housing stock
to full compliance in terms of EICRs we are undertaking
proactive communications with tenants to minimise any
access issues. 
Alan Young

Page 4

4
Performance Indicator 2020/21 2021/22 Comments Managed
By Status Value Target Status Value Target
% of Council rent that
was lost due to houses
remaining empty 
1.2% 0.88%  1.29% 0.88%
Performance significantly deteriorated as a result of
Covid. Target not met, the first half of 2021/22 significant
progress was made to improve performance in this area
however the quarter has seen performance slip again.
Measures such as the void working group and target
resources are among some of the measures. This work
will continue into the coming year to improve
performance in the long term.
Nicola
Pettigrew
Number of new supply
social housing for rent  110 80  506 680
Over the last five years we had an ambitious target to
deliver 1000 new homes, in total at the end of year five
we delivered a total 942 new supply of social housing for
rent. In year five we fell slightly short of the target in
terms of delivering on the target within the final year.
Overall the project was successful, however affected by
delays as a result of the pandemic.
John Kerr 
Percentage of Children
living poverty (after
housing costs) 
26.8% 25.25
%  23.4% 25%
Target met for latest data released July 2022. 23.4% of
children aged 0-15 years in west Dunbartonshire are
living in households with below 60% median income after
housing costs, compared to 21% in Scotland.  The data
covers a period from 1 April 2020 to 31 March
2021 where additional support was provided to low-
income families during the Covid-19 pandemic, which
experts say is likely to be the reason why the numbers
slightly declined in this period.  There is now significant
fear that with the additional support removed and cost of
living rises, next year’s results for the year 2021/22 will
see a rise in child poverty levels. 
Stephen
Brooks

Page 5

5
Performance Indicator 2020/21 2021/22 Comments Managed
By Status Value Target Status Value Target
Percentage of
Households in Fuel
Poverty 
29% 23.5%  29% 23%
The most recent data released February 2021 covering
the period 2017-2019, indicate that an estimated 29% of
households were in fuel poverty in West Dunbartonshire. 
This is higher than the estimate for Scotland of 24%. 9%
were considered to be in extreme fuel poverty in West
Dunbartonshire, less than the estimated 12% for
Scotland.
Stephen
Brooks
Percentage of local
people with increased
or sustained income
through reduced debt
liability/debt
management 
86.7% 87%  90% 90%
Target met. Changes introduced by the Government
during the Covid period put a moratorium on debt
recovery on some debts which reduced the number of
people accessing support for debt.  As these changes
begin to reverse and the cost of living increases kick in,
we will expect to see an increase in the number of people
presenting to the service in 2022/23 with debt issues. 
Stephen
Brooks 
Percentage of reactive
repairs carried out
completed right first
time 
89.76
% 92%  86.49
% 90%
For a repair to be completed Right First Time, the repair
must be within the target timescale, with Covid
restrictions lifting on 26 April 2021, non-essential repairs
raised prior to this date resulted in a reduction of repairs
being completed by their classification target timescale.
Martin
Feeney 
Priority 3. Meaningful engagement with active, empowered and informed citizens who feel safe and engaged

Page 6

6
Performance Indicator 2020/21 2021/22 Comments Managed
By Status Value Target Status Value Target
% of council resources
directed by
communities 
1.07% 0.8%  0.11
% 1%
Return submitted to Scottish Government August 2022.
Although the target was missed, work continues to
identify projects and spend to meet 1% in future years by
embedding processes into services where appropriate. 
Gillian
McNeilly
% of residents who feel
safe/very safe in their
local community 
96% 98%  92% 98%
Target narrowly missed, despite this, performance overall
represents a consistently high feeling of safety
throughout the year.  Peter Barry
% of residents who feel
the Council
communicates well
with them 
75% 75%  74% 78%
Target marginally missed although performance has
improved year on year. Communication continues to be a
key priority. Over the last year communications have
been issued across a range of channels including social
media, the Council website, media releases and Housing
News as well as specific tailored communications.
Amanda
Graham
Average score for
respondents who state
they feel a sense of
control and influence in
relation to Council
decision-making and
service delivery 
5.4 5.4  5.4 5.4
This indicator is sourced from the Place Standard survey
work that is undertaken by the Council in different
communities, and repeated every 30 months. It covers
the physical elements of a place, e.g. buildings, spaces,
transport links, as well as the social aspects, including
whether people feel they have a say in decision making.
The most recent data relates to 2019/20. The next survey
will be held in 2022/23.  
Pamela
Clifford
Percentage of citizens
who agree the Council
listen to community 
67% 85%  66% 90%
Target not met. Overall performance is marginally lower
than the previous year however shows improvement over
the five year plan. As a result of Covid -19 the Council
has been restricted in the methods of consultation.
Amanda
Graham

Page 7

7
Performance Indicator 2020/21 2021/22 Comments Managed
By Status Value Target Status Value Target
views when designing
and delivering services
However there have been in excess of 20 consultations
carried out remotely including consultations on Council
Strategy, local improvement schemes and service
delivery. In recognition of the feedback received there will
be focus on making sure communities are aware of the
opportunities to provide feedback and inform service
design.
Residents satisfaction
with Council services
overall 
89% 85%  88% 93%
Performance against target was missed in 2021/22,
however performance overall is relatively high with
almost 9 out of 10 people expressing satisfaction with the
Council. 
Amanda
Graham 
Priority 4.Open, accountable & accessible local government 
Performance Indicator 2020/21 2021/22 Comments Managed
By Status Value Target Status Value Target
% of committee
agendas published
within standing order
timescales 
100% 98.6%  100% 99% Target exceeded. Peter
Hessett
% of residents who
report satisfaction with
Council publications,
reports and documents 
97% 73%  93% 75% Target exceeded. Amanda
Graham

Page 8

8
Performance Indicator 2020/21 2021/22 Comments Managed
By Status Value Target Status Value Target
Percentage of council
buildings in which all
public areas are
suitable for and
accessible to disabled
people 
96.5% 94.5%  96.5% 92%
Target exceeded.
Craig
Jardine
No. of transactions
undertaken online  43,032 27,687  57,543 27,687 Target exceeded. Stephen
Daly
Percentage of citizens
who are satisfied with
the Council website 
87% 85%  89% 85%
Target exceeded. Stephen
Daly 
Priority 5.Efficient and effective frontline services that improve the everyday lives of residents 
Performance Indicator 2020/21 2021/22 Comments Managed
By Status Value Target Status Value Target
% of Local
Government
Benchmarking
Framework
performance indicators
prioritised by the
council that have
improved locally 
75% 70%  50% 75%
Target was not achieved for 2021/22. This equates to
improvement in 6 of the 12 PIs over time (2016/17-
2020/21). The impact of Covid has had an impact on a
number of the PIs as it affected service delivery due to
government restrictions as well as a shift in priorities
during the immediate months of the pandemic. It was
anticipated that performance in 21/22 would be affected,
and for four of the PIs that didn't show improvement
overall in the last year, they had been showing
Amanda
Graham

Page 9

9
Performance Indicator 2020/21 2021/22 Comments Managed
By Status Value Target Status Value Target
improvement in previous years suggesting that the
pandemic affected the final performance overall.
% of total household
waste that is recycled  34.2% 58%  37% 60%
Year-end target significantly missed, despite showing
some improvement from the previous year recycling rates
remain low.  Work is underway to educate the community
and help deliver change, and allow WDC to meet our
recycling objectives.
Kenny Lang
% Residents satisfied
with roads
maintenance 
46% 41.5%  38% 41.5%
The year-end target was marginally missed and
satisfaction has reduced from previous year. Review of
the winter service plan and road maintenance plan for
202/23 should help improve this. 
Liam
Greene
Number of attendances
per 1,000 population
for indoor sports and
leisure facilities 
601 6,724  3,810 5,137
Dry-side usage is lower than the target set by 9.6%.  The
Vale of Leven Swimming Pool was the only centre that
was above the target set.  Usage within the Community
Centres was below target as the main centres were still
being used as part of the vaccine roll out programme
John
Anderson
Income generated as a
% of total revenue
budget 
11.11
% 13%  10.43
% 13%
Target missed due to a one –off significant debtor’s
adjustment in 2021/22 following negotiations with
external parties. 
Gillian
McNeilly
Percentage of Council
employees who agree
or strongly agree that
in general, my morale
at work is good 
78% 75%  79% 78%  Target exceeded. Alison
McBride

Page 10

10
Performance Indicator 2020/21 2021/22 Comments Managed
By Status Value Target Status Value Target
Percentage of
educational
establishments
receiving positive
inspection reports
N/A 100% N/A 100%
The national programme of Educational Inspections has
been suspended over the last 2 years due to the Covid-
19 pandemic. 
Laura
Mason
Percentage of income
due from council tax
received by the end of
the year % 
94.18
% 93.5%  94.53
% 93.5%
Target exceeded.
Arun Menon
Proportion of
operational buildings
that are suitable for
their current use % 
93.3% 93%  93.3% 93%
Target exceeded.
Craig
Jardine
Sickness absence
days per employee
(local government)
(LGBF assessed) 
8.4 8  13.3 7
Annual target not met, year-end figures do not include
Covid related absences in line with guidance from the
LGBF programme. Attendance management continues to
be a key focus and work continues with teams to support
employees back to work.
Alison
McBride
Sickness absence
days per teacher
(LGBF assessed) 
1.7 5.2  5 5 Target met.  Alison
McBride
Street Cleanliness
Index - % Clean  84.9 92.8  94.1 93  Target exceeded. Ian Bain 
PI Status 
Target significantly missed

Page 11

11 
Target narrowly missed 