Item 15 - Appendices 3 to 7

West Dunbartonshire Council · 31 August 2022
Back to West Dunbartonshire Council — 31 August 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

APPENDIX 3
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
MONTH END DATE
PERIOD 4
Spend to
Date Spend to Date
£000 £000
Red
0 0.0% 0 0.0% 0 0.0% 0 0.0%
Amber
2 7.7% 1,679 31.9% 2 7.7% 1,668 31.7%
Green
24 92.3% 3,577             68.1% 24 92.3% 3,587                68.3%
26 100% 5,256 100% 26 100% 5,256 100%
Budget Spend to
Date
Forecast
Spend Forecast Variance Budget Spend to Date Forecast
Spend
Forecast
Variance Slippage Over/
(Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
0 0 0 0 0 0 0 0 0 0
115,267 1,679 115,767 500 41,645 1,668 42,145 500 0 500
100,816 3,577 100,636 (181) 23,922 3,587 23,742 (181) 0 (181)
216,084 5,256 216,403 319 65,567 5,256 65,887 319 0 319
216,084 5,256 216,403 (319) 65,567 5,256 65,887 (319)
0 0 0 0 0 0 0 0
TOTAL RESOURCES
NET EXPENDITURE
Projects are forecast to be overspent and/or significant delay to
completion
Amber
Projects are either at risk of being overspent and/or delay in
completion (although this is unquantifiable at present) or the project
has any issues that require to be reported at this time
Green
Projects are on target both in relation to overall budget and the
forecast stages in the project life cycle and no issues are anticipated
at this time
TOTAL EXPENDITURE
The in-year adverse variance reflects the 20/21 Scottish Government grant in relation to future developments which cannot be drawndown prior to spend (£0.850m).  This is offset by £0.511m additional  Scottish Government Grant income which is generated off of the Buy Back Scheme and can be used to support the Affordable Housing Supply Programme.  Overall, there is a favourable project life variance of £0.702m which relates to an additional £1.308m grant income as successfully negotiated by Officers in relation to the increased grant per unit at Aitkenbar and Haldane and the additional grant generated from the buyback scheme within the current year and previous financial years.  However,  this is offset by an under recovery in grant of £0.606m which reflects changes to the actual number of units compared to budget at individual sites and the change in funding composition at St Andrews whereby the grant was originally budgeted higher based on a partnership with another registered social landlord.   However, disc
Project Status Analysis
Project Life Financials Current Year Financials
Red
Projects are on target both in relation to overall budget and the
forecast stages in the project life cycle and no issues are anticipated
at this time
31 July 2022
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project Spend at
RAG Status
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project
Spend at RAG
Status
Red
Projects are forecast to be overspent and/or experience material
delay to completion
Amber
Projects are either at risk of being overspent and/or delay in
completion (although this is unquantifiable at present) or the project
has any issues that require to be reported at this time
Green

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF AMBER PROJECTS
MONTH END DATE
PERIOD 4
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials 8,384 660 8% 8,884 500 6%
Current Year Financials 2,000 660 33% 2,500 500 25%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
2
Project Life Financials 106,883 1,019 1% 106,883 0 0%
Current Year Financials 39,645 1,008 3% 39,645 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
TOTAL OF AMBER
PROJECTS
Project Life Financials 115,267 1,679 1% 115,767 500 0%
Current Year Financials 41,645 1,668 4% 42,145 500 1%
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
Void house strategy programme
Spend on Void Properties to bring them up to letting standard 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Void works to continue into 22/23 to bring void properties up to a lettable standard.  The high number of voids has led to a
higher than expected demand for this budget, resulting in a projected overspend in 22/23. 
Mitigating Action
None available at this time
Anticipated Outcome
Void properties to be brought up to lettable standard
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Progress will continue to be monitored as the year progresses.  The project has been moved into amber due to issues around
the Clydebank East site. Following additional and more detailed site investigations it now appears likely that there will be
significant additional costs to deliver the ground remediation strategy.  These additional costs place the development at risk due
to affordability issues.  It is expected full information to make an assessment will be available in early September and  an update
will be given to the Housing and Communities Committee when this has been achieved . Site specific updates as follows:-
Clydebank East - 88 units to be completed on the site.  Estimated Start Date October 2022 and estimated completion October
2024.  Full planning received and Officers are working through the planning conditions site with start date anticipated October
2022, subject to costs which will be received August 2022.
Queens Quay Site B - 29 units to completed on the site with site completion expected August 2022.  Rental income forecast
from end of September 2022.
Affordable Supply Programme
Affordable Housing Supply Programme
Bonhill Gap Site - 32 units to be completed on site.  Estimated start date April 2023 and estimated completion October 2024. 
The project is currently at design stage.
Mitigating Action
None required at this time
Anticipated Outcome
Project to complete and meet revised spend targets
Queens Quay Site C - 20 units to be completed on site.  Estimated start date March 2023 and estimated completion March
2024.
Pappert - 27 units to be completed on site.  Estimated completion early  2023.  Officers currently working on the design and
build contract.
Bank Street - 20 units to be completed on the site.  Estimated start date July 2023, estimated completion July 2024.  Project is
currently at feasibility stage.
Clydebank Health Centre - Units on site to be confirmed.  Acquisition to be agreed with NHS on agreement of purchase cost. 
Willox Park Phase1 - 17 units to be completed on site.  Estimated start date March 2023 and estimated completion March. 
17/18 units demolition complete, and site investigation under way.  Officers ready to submit to for full planning.
Mount Pleasant - 25 units to be completed on site.  Estimated start date March 2023 with estimated completion March 2024. 
Demolition of current site to go to the August 2022 tendering committee.

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 4
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials 2,487 0 0% 2,487 0 0%
Current Year Financials 474 0 0% 474 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
2
Project Life Financials 2,266 0 0% 2,266 0 0%
Current Year Financials 431 0 0% 431 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
3
Project Life Financials 1,557 0 0% 1,557 0 0%
Current Year Financials 664 0 0% 664 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
4
Project Life Financials 271 0 0% 271 0 0%
Current Year Financials 185 0 0% 185 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No issues. Development of QL system to carry on through 22/23.
Mitigating Action
None required
Mitigating Action
None required
Anticipated Outcome
Full budget spend
QL Development
This budget relates to the costs associated with the development of the Integrated Housing
Management System
Better Homes Priority Budget
Priority projects as prioritised by the Better Homes Group 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
A number of priority initiatives, supported by the Better Homes Project Board,  are being investigated and are envisaged to have
a positive impact on the current council housing stock and budget, with works expected to progress in 22/23.
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
None required
Anticipated Outcome
Full budget spend
Capitalised minor works
Gypsy/ Traveller Site improvements 
Planned End Date  Forecast End Date 
Adaptations to Housing for Special Needs 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
31 July 2022
Budget Details Project Life Financials
Spend to Date Variance
Special needs adaptations

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 4
Budget Forecast Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details Project Life Financials
Spend to Date Variance
5
Project Life Financials 170 0 0% 170 0 0%
Current Year Financials 40 0 0% 40 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
6
Project Life Financials 17 0 0% 17 0 0%
Current Year Financials 17 0 0% 17 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
7
Project Life Financials 192 0 0% 192 0 0%
Current Year Financials 192 0 0% 192 0 0%
Project Description
Project Lifecycle 31-Mar-23 31-Mar-23
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Awaiting receipt of the airport scheme outline from Glasgow Airport before works can planned.  Project expected to make
progression in 22/23.
Mitigating Action
None required
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Airport Noise
Noise Insulation Project
Community Safety Projects
Community Safety Projects 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Gypsy Travellers Site
Gypsy/ Traveller Site improvements 
Planned End Date  Forecast End Date

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 4
Budget Forecast Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details Project Life Financials
Spend to Date Variance
8
Project Life Financials 19,841 0 0% 19,841 0 0%
Current Year Financials 4,455 0 0% 4,455 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
9
Project Life Financials 17,607 1,654 9% 17,607 0 0%
Current Year Financials 4,955 1,654 33% 4,955 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
10
Project Life Financials 10,963 109 1% 10,963 0 0%
Current Year Financials 2,500 109 4% 2,500 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
11
Project Life Financials 257 0 0% 257 0 0%
Current Year Financials 75 0 0% 75 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Anticipated Outcome
Full budget spend
External stores/garages/bin stores/drainage component renewals
This budget is to focus on external stores/garages/bin stores etc. component renewals as
identified and recommended from the housing stock condition survey. 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Project is anticipated to meet revised targets.  Additional external support will be available from August to assist with window
installs.
Mitigating Action
None required at this time
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Doors/window component renewals
Doors/Windows Component Renewals
Roof Coverings
Building external component renewals, roofs/chimneys/flashings/fascias/gutters/svp 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Currently behind monthly targets, however tentatively anticipated to meet full spend and targets. Current tiled roof progress is
behind cumulative monthly targets but overall output is anticipated to increase with the new metal and flat roof framework
contract coming on board contributing to a wider range of roof types being completed.
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets. Current progress is slightly behind cumulative monthly targets, work is
progressing and additional resources will be coming on board shortly with new framework contractor.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Targeted SHQS /EESSH compliance works
This budget is to focus on work required to maintain the SHQS compliance and energy
efficiency  with WDC housing stock.   
Planned End Date  Forecast End Date

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 4
Budget Forecast Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details Project Life Financials
Spend to Date Variance
12
Project Life Financials 273 35 13% 273 0 0%
Current Year Financials 91 35 39% 91 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
13
Project Life Financials 566 65 11% 566 0 0%
Current Year Financials 108 65 60% 108 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
14
Project Life Financials 5,092 295 6% 5,092 0 0%
Current Year Financials 969 295 30% 969 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Main Issues / Reason for Variance
Anticipated to meet full spend and targets and possibly overspend. This budget has overspent in recent years as demand has
exceeded expectations. Current progress continues this trend however an industry wide shortage in microchips is likely to hinder
availability of boilers and in turn will impact on spend. Due to the nature of this project (ensuring heating and hot water
availability) there is no option for a conscious reduction of installs.
Mitigating Action
None available
Anticipated Outcome
Full budget spend, possible overspend.
Anticipated Outcome
Full budget spend
Heating improvement works
Carry out works to renew inefficient boilers/full systems as identified from the stock condition
survey and renewal of obsolete/damaged boilers. 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Mitigating Action
Officers continue to liaise with owners to encourage agreement for install.
Anticipated Outcome
Anticipated not to meet full spend despite best efforts.
Statutory/regulatory compliance works (lifts/electrical/legionnella/fire etc)
This budget will be used to upgrade / replace components / installations in order to comply with
the relevant standards / legislation / health and safety in relation to housing stock.
Secure entry component renewals
This budget is to focus on secure door entry component renewals as identified and
recommended from the housing stock condition survey and appropriate council officer referrals. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
This programme always presents challenges with owner liaison and reaching agreements to install door entry where none exists,
this contributes directly to achieving SHQS compliance for this element and reducing abeyances. The budget reflects the demand
and number of installs required but it is acknowledged that full uptake is unlikely.

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 4
Budget Forecast Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details Project Life Financials
Spend to Date Variance
15
Project Life Financials 280 0 0% 280 0 0%
Current Year Financials 54 0 0% 54 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
16
Project Life Financials 5,293 73 1% 5,293 0 0%
Current Year Financials 1,036 73 7% 1,036 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
17
Project Life Financials 103 0 0% 103 0 0%
Current Year Financials 103 0 0% 103 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Anticipated Outcome
Full budget spend
Improvement works (Risk St)
Risk Street Over clad 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Modern facilities and services
New Kitchens, Bathrooms and Showers
Energy improvements/energy efficiency works
Energy improvements/ efficiency works (e.g. loft insulation, pipe/tank insulation, draught
exclusion) 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.

Page 8

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 4
Budget Forecast Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details Project Life Financials
Spend to Date Variance
18
Project Life Financials 581 0 0% 400 (181) -31%
Current Year Financials 181 0 0% 0 (181) -100%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
19
Project Life Financials 3,637 35 1% 3,637 0 0%
Current Year Financials 887 35 4% 887 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
20
Project Life Financials 5,092 295 6% 5,092 0 0%
Current Year Financials 969 295 30% 969 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
21
Project Life Financials 1,135 9 1% 1,135 0 0%
Current Year Financials 215 9 4% 215 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Asbestos management works
This budget is to fund work associated with the management of current asbestos legislation and
Environmental renewal works, paths/fences/walls/parking area's
Environmental renewal works, paths/fences/walls/parking areas 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Anticipated Outcome
Spend as required
Defective structures/component renewals
Defective structures 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, contingent budget for unplanned spend
Mitigating Action
none at this time
Contingencies
This is a contingent budget for unforeseen matters which may arise during the year.

Page 9

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 4
Budget Forecast Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details Project Life Financials
Spend to Date Variance
22
Project Life Financials 2,378 0 0% 2,378 0 0%
Current Year Financials 800 0 0% 800 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
23
Project Life Financials 7,729 172 2% 7,729 0 0%
Current Year Financials 2,019 172 9% 2,019 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Mitigating Action
None required.
Anticipated Outcome
Budget spend anticipated, should criteria be met.
Buy Backs
This is a budget to undertake specific projects that will deliver housing policies/strategies,
example: Ex local authority and mortgage to rent buy-back scheme 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
The main objective of the Buy Back Scheme is to bring former council properties that were sold through the RTB scheme, back
into council use.  These properties must assist the council with reducing housing need on the waiting list and where appropriate
assist with external capital works.  For these reasons, any purchase is subject to stringent criteria to ensure accountability and
value for money for existing tenants.  Spend in 22/23 will therefore be dependent on these factors.  So far this year , 2 homes
have been purchased, with 3 under offer and  the targeted is to deliver an additional 20 homes each year through the buyback
scheme
Main Issues / Reason for Variance
No Issues, anticipated to meet spend and revised targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Multi Story Flats  ( including Fire Risk Assessment Works)
High Rise Fire Safety Measures 
Planned End Date  Forecast End Date

Page 10

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 4
Budget Forecast Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details Project Life Financials
Spend to Date Variance
24
Project Life Financials 13,031 835 6% 13,031 0 0%
Current Year Financials 2,504 835 33% 2,504 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
TOTAL OF GREEN
PROJECTS
Project Life Financials 100,816 3,577 4% 100,636 (181) 0%
Current Year Financials 23,922 3,587 15% 23,742 (181) -1%
Main Issues / Reason for Variance
No Issues, budget for salaries and support
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Salaries/central support/offices
Allocation of costs from other WDC services who support the HRA capital programme 
Planned End Date  Forecast End Date

Page 11

APPENDIX 6
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
MONTH END DATE
PERIOD 4
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials (48,826) 0 0% (48,826) 0 0%
Current Year Financials (30,006) 0 0% (30,006) 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
TOTAL RESOURCES
Project Life Financials 48,826 0 0% 48,826 0 0%
Current Year Financials 30,006 0 0% 30,006 0 0%
Main Issues / Reason for Variance
31 July 2022
Budget Details Project Life Financials
Spend to Date Variance
NEW BUILD GRANT
Grant to facilitate the building of new build housing 
Planned End Date  Forecast End Date
No issues, income due to be received with no problems anticipated
Mitigating Action
None required
Anticipated Outcome
Income due to be received

Page 12

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
HRA CAPITAL PROGRAMME
ANALYSIS OF AFFORDABLE HOUSING SUPPLY PROGRAMME
MONTH END DATE
PERIOD 4
Budget Spend to Date Forecast Spend
£000 £000 £000 £000 %
RAG
Status
St Andrews School 636                        34                           636                              -                         0% 
Haldane Primary School 148                        0                             148                              -                         0% 
Aitkenbar Primary School 652                        -                         652                              -                         0% 
Clydebank East 26,474                   -                         26,474                         -                         0% 
Creveul Court 58                           59                           58                                 -                         0% 
Queens Quay Site B 1,259                     858                        1,259                           -                         0% 
Queens Quay Site C 6,198                     1                             6,198                           -                         0% 
Pappert 7,332                     2                             7,332                           -                         0% 
Lilac Avenue 2,676                     -                         2,676                           -                         0% 
Bank Street 4,674                     -                         4,674                           -                         0% 
Clydebank Health Centre 6,930                     3                             6,930                           -                         0% 
Willox Park Phase1 3,817                     34                           3,817                           -                         0% 
Willox Park Phase2 6,300                     -                         6,300                           -                         0% 
Mount Pleasant 4,200                     11                           4,200                           -                         0% 
Silverton 2,100                     -                         2,100                           -                         0% 
Fees, Staffing Costs, contingency 4,005                     14                           4,005                           -                         0% 
Gap sites 12,600                   -                         12,600                         -                         0% 
Bonhill Gap Site -                         2                             -                               -                         0% 
Future New build sites 16,824                   -                         16,824                         -                         0% 
Total Expenditure 106,883 1,019 106,883 0 
31 July 2022
Site
Project Life Financials
Variance