WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
GENERAL SERVICES CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
PERIOD END DATE
PERIOD 4
Spend to Date Spend to
Date
£000 £000
Red
25 21.2% 33,964 36.9% 25 21.2% 895 30.4%
Amber
0 0.0% 0 0.0% 0 0.0% 0 0.0%
Green
93 78.8% 58,000 63.1% 93 78.8% 2,053 69.6%
118 100% 91,964 100% 118 100% 2,949 100%
Budget Spend to
Date
Forecast
Spend
Forecast
Variance Budget Spend to
Date
Forecast
Spend
Actual
Variance Slippage Over/ (Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
65,866 33,964 65,697 (169) 16,510 895 5,000 (11,510) (10,772) (738)
0 0 0 0 0 0 0 0 0 0
205,657 58,000 203,603 (2,054) 49,077 2,053 46,447 (2,630) (1,488) (1,142)
271,523 91,964 269,300 (2,222) 65,587 2,949 51,447 (14,140) (12,260) (1,880)
(271,523) (91,964) (269,300) 2,222 (65,587) (2,949) (51,447) 14,140
0 0 0 0 0 0 0 0
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
TOTAL EXPENDITURE
TOTAL RESOURCES
NET EXPENDITURE
Projects are forecast to be overspent and/or significant delay to
completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green
TOTAL EXPENDITURE
Project Status Analysis
Project Life Financials Current Year Financials
Red
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
31 July 2022
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of Projects
at RAG Status
% Projects at
RAG Status
% Project
Spend at
RAG Status
Number of
Projects at RAG
Status
% Projects at
RAG Status
% Project
Spend at
RAG Status
Red
Projects are forecast to be overspent and/or experience material delay to
completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 9 0 0% 9 0 0%
Current Year Financials 3 0 0% 0 (3) -100%
Project Description
Project Manager David Thomson
Chief Officer David Thomson
Project Lifecycle 31-Mar-23 31-Mar-23
2
Project Life Financials 0 3 0% 3 3 0%
Current Year Financials 0 3 0% 3 3 0%
Project Description
Project Manager David Thomson
Chief Officer David Thomson
Project Lifecycle 31-Mar-23 31-Mar-23
3
Project Life Financials 33 0 0% 33 0 0%
Current Year Financials 33 0 0% 0 (33) -100%
Project Description
Project Manager Alan Douglas
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
Legal Case Management System
Legal Case Management System
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment
Requisition ICT Equipment.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget remains unspent and is likely to be carried forward into FY 23/24.
Mitigating Action
Valuation Joint Board - ICT Refresh FY 22/23
Replacement of laptops, monitors and other ICT equipment.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Replacement of laptops, monitors and other ICT equipment. No further spend anticipated.
Mitigating Action
None available at this time.
Anticipated Outcome
Replacement of laptops and ICT equipment
None available at this time.
Anticipated Outcome
Requisition of ICT Equipment.
Forecast End Date
Main Issues / Reason for Variance
Budget has been rephased from 2021/22.  The project could not proceed as originally planned as Officers are required to access the
office and hardware the system will run on and COVID-19 restrictions have prevented this.  The project will have to go back out to
tender following the upgrade to Microsoft 365.  The project will not be completed in this financial year. 
Mitigating Action
Legal to discuss impact of Microsoft 365 with ICT.
Anticipated Outcome
Project to be completed in 2023/24.
Planned End Date

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment4
Project Life Financials 61 3 5% 64 3 5%
Current Year Financials 55 0 0% 58 3 5%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
5
Project Life Financials 342 237 69% 347 5 1%
Current Year Financials 110 0 0% 20 (90) -82%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
6
Project Life Financials 80 19 24% 80 0 0%
Current Year Financials 61 1 1% 30 (31) -51%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Further orders have been raised and await invoices. Total expenditure this financial year estimated to be £0.030m with the rest of the
funding to be carried forward into next financial year.
Mitigating Action
None available at this time
Anticipated Outcome
Anticipate some spend this year and the remainder to be rephased into 2023/24.
Forecast End Date
Mitigating Action
Opportunities to mitigate are limited at this stage. 
Anticipated Outcome
Complete in 2022/23.
Energy Projects quick wins
Spend to Save projects.
Planned End Date Forecast End Date
Installation of Solar PV at Clydebank Leisure Centre
Installation of Solar PV at Clydebank Leisure Centre.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Await chimney inspection report and appointment of consultant for HUB CEC. Due to complications in installing heat pump anticipate
only design fees spend this year and release of the retention for works at St Marys Primary School, Alexandria.
Mitigating Action
None available at this time.
Anticipated Outcome
Retention for St Mary's Primary School and design fees this year. Insufficient budget available to carry out Hub works.
Main Issues / Reason for Variance
Technical scope delayed due to prioritising controls upgrade. Aim to pass tender document to Procurement by the end of August
2022.
Replace obsolete boilers (plant greater than 30 years old).
Replace obsolete boilers (plant greater than 30 years old).
Planned End Date

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment7
Project Life Financials 344 86 25% 344 0 0%
Current Year Financials 258 0 0% 15 (243) -94%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
8
Project Life Financials 160 0 0% 160 0 0%
Current Year Financials 152 0 0% 80 (72) -47%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
9
Project Life Financials 750 0 0% 0 (750) -100%
Current Year Financials 750 0 0% 0 (750) -100%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Dec-22 30-Jun-23
Upgrade obsolete heating controls (BEMS) across Council estate
Upgrade obsolete heating controls (BEMS) across Council estate.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Tender documentation currently being prepared. Work scheduled between October 2022 and March 2023 but suspect it will carry
forward into the new financial year due to necessary disruption to heating in the buildings.
Mitigating Action
None available at this time.
Anticipated Outcome
Delivery of project within budget.
Anticipated Outcome
Project delivered within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works initiated to install a heat pump to complement HUB CEC boiler. Liaising with BAM FM and Asset Management to decide which
site to install solar PV following successful installation at St Peters. Works will cross into next financial year.
Mitigating Action
None available at this time
Zero Carbon Fund
Zero Carbon Fund.
Viresco Studios and Arts Centre
Viresco Studios and Arts Centre in Alexandria, aimed to encourage wider participation in the arts,
creative enterprises and cultural activity in West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Due to factors outwith the Council's control, progress couldn’t be made on a timeline that would be acceptable to funders and as a
result Scottish Government will withdraw the grant offer.
Mitigating Action
None available at this time.
Anticipated Outcome
Repurposing and restoration of B listed former St Andrew's church in Alexandria for community arts uses.

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment
10
Project Life Financials 22,100 1,807 8% 22,100 (0) 0%
Current Year Financials 7,465 39 1% 2,851 (4,614) -62%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
11
Project Life Financials 382 388 102% 388 6 2%
Current Year Financials 0 6 0% 6 6 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-21 31-Mar-21
12
Project Life Financials 2,375 87 4% 2,375 (0) 0%
Current Year Financials 1,090 3 0% 28 (1,063) -97%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-24
Mitigating Action
None available at this time.
Anticipated Outcome
New build community facility.
New Westbridgend Community Centre
New Westbridgend Community Centre
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Various delays due to Covid and other utility issues. Planning was previously delayed but now resolved. Building warrant applications
will be submitted August 2022 with a view to tender being issued December 2022. Anticipated to be onsite by April 2023.
Mitigating Action
None available at this time.
Anticipated Outcome
New sports changing facility completed.
New Sports Changing Facility at Duntocher
New Sports Changing Facility at Duntocher
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project completed over budget due to ground conditions on site.  Final costs now charged.
LUF
Year one LUF spend includes acquisition cost of Artizan Centre, and design development for
Glencairn House and Connecting Dumbarton
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Connecting Dumbarton and Glencairn House are progressing per the agreed programme. A future programme for the Artizan Centre
based on the Redevelopment Options consultancy will be reported to IRED, after which proposed in year spend may be adjusted.
Costs will continue to be monitored by the LUF Project Board. Update due to IRED September 2022
Mitigating Action
None available at this time.
Anticipated Outcome
Redevelopment of the Dumbarton Town Centre

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment13
Project Life Financials 400 47 12% 400 0 0%
Current Year Financials 357 3 1% 100 (257) -72%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Oct-23 31-Oct-23
14
Project Life Financials 2,646 3,118 118% 3,210 565 21%
Current Year Financials 844 752 89% 844 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-23
Posties Park Sports Hub - New sports hub to include gym & running track
Creation of a sports hub at Posties/Marinecraft to include a new changing pavilion/Gym, new all-
weather 6 lane running track, conversion of blaze sports pitch to grass, new fencing, upgrade of
existing floodlights and additional car parking.  This combines the budget approved by the Council
in February 2015 for Community Sports Facilities at Posties Park, draw down of budget from the
generic sports facilities budget line.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project start was delayed due to planning issues and COVID-19 restrictions. Work commenced January 2021 with a proposed
completion date of March 2022 which has been extended to October 2022 due to design changes required by Planning. There is still a
significant amount of work to be undertaken to complete the project and the cost of this work has been affected by Brexit and supply
chain issues. A forecast is uncertain at this time pending discussions and negotiations with the contractor.
Mitigating Action
None required at this time.
Anticipated Outcome
New all weather running track and gymnasium.
Anticipated Outcome
Two new allotment sites with 80 plots and community growing space.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Two sites are being developed at Dillichip Loan Bonhill and Overburn Dumbarton. These sites will provide eighty traditional allotment
plots together with community food growing facilities. It is anticipated that project works will commence in February 2023 with a
completion date of October 2023.
Mitigating Action
None available at this time.
Allotment Development
To develop an allotment site.

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment15
Project Life Financials 817 263 32% 817 (0) 0%
Current Year Financials 553 0 0% 150 (403) -73%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 30-Sep-22
16
Project Life Financials 217 3 1% 217 0 0%
Current Year Financials 214 0 0% 0 (214) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
17
Project Life Financials 400 358 90% 400 0 0%
Current Year Financials 42 0 0% 0 (42) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
Road construction works completed in previous years. Remaining funds are insufficient to complete footpath construction. Works on
hold until such time as additional funds can be secured.
Mitigating Action
None available at this time.
Anticipated Outcome
To complete remaining civil works required.
Main Issues / Reason for Variance
Project is now being developed for tendering, with project commencing February 2023 and completion expected by 31 October 2023. 
It is anticipated that £0.150m will be spent this financial year mainly on consultant costs and enabling works.
Mitigating Action
None available at this time.
Anticipated Outcome
Extension to existing cemetery providing a sustainable burial environment.
Vale of Leven Cemetery Extension
Extension of existing cemetery in Vale of Leven.
Planned End Date Forecast End Date
Anticipated Outcome
To improve journey times and reliability of bus services.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Officers working with external partners to identify projects to support funding. Investigation on going however unlikely works will be
able to progress this financial year.
Mitigating Action
None required at this time.
Bus Rapid Deployment Fund
Funding has been awarded from Sustrans to assist with social distancing measures required as a
result of the COVID-19 pandemic.
Auld Street Clydebank - Bond
Completion of roadworks associated with Auld Street housing development. Creation of a footpath
to Golden Jubilee Hospital.
Planned End Date Forecast End Date

Page 8

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment18
Project Life Financials 500 11 2% 500 0 0%
Current Year Financials 220 0 0% 0 (220) -100%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
19
Project Life Financials 1,000 0 0% 1,000 0 0%
Current Year Financials 1,000 0 0% 0 (1,000) -100%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
20
Project Life Financials 2,817 0 0% 2,817 0 0%
Current Year Financials 2,817 0 0% 600 (2,217) -79%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Vehicle Replacement
Replacement of vehicles which have reached end of programmed lifespan (7 year heavy vehicles,
10 year light vehicles).
Project to be delivered within budget.
Awaiting Scottish Government recommendations.
Mitigating Action
None available at this time.
Anticipated Outcome
Mandatory 20mph Residential communities
Mandatory 20mph Residential communities.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Replacement of fleet within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Vehicles are being ordered for delivery in this financial year but larger vehicles will be delayed into financial year 2023/2024.
Mitigating Action
None Required.
Replacement of refuse collection vehicles.
Anticipated Outcome
Vehicle Replacement Strategy
Replacement of refuse collection vehicles.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Larger vehicles will be delayed due to supply chain issues. Delivery timescales anticipated at 18 months.
Mitigating Action
None available.
Anticipated Outcome

Page 9

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment21
Project Life Financials 199 223 112% 199 0 0%
Current Year Financials 9 34 354% 34 25 258%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Oct-22 31-Oct-22
22
Project Life Financials 924 0 0% 924 0 0%
Current Year Financials 154 0 0% 40 (114) -74%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-23 31-Mar-23
23
Project Life Financials 1,400 0 0% 1,400 0 0%
Current Year Financials 280 0 0% 40 (240) -86%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None available at this time.
Anticipated Outcome
Community Alarm Upgrade
Replacement of Care First
Replacement of Care First
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The replacement of CareFirst has been delayed because of challenges in respect of the recruitment of a Digital Business Lead to take
forward the project. Work is ongoing with HR colleagues in order to consider how the recruitment challenge may be addressed.
Mitigating Action
None available at this time
Anticipated Outcome
Replacement of Care First
Anticipated Outcome
Project delivered within amended timescales.
Free School Meals
Provision of Capital Funding from Scottish Government to implement free school meal initiative.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project is complete other than snagging works which can only be completed when school is closed however project end date is still on
target. Additional budget required in relation to electrical phasing which was unknown at the time of project inception.
Mitigating Action
None available at this time
Community Alarm upgrade
To upgrade Community Alarm
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Work is ongoing with HR colleagues in order to appoint a project manager to this post and it is anticipated that spend will progress in
the final half of the financial year.

Page 10

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment24
Project Life Financials 27,531 27,266 99% 27,531 0 0%
Current Year Financials 42 55 130% 55 13 30%
Project Description
Project Manager Sharon Jump/ Craig Jardine
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-22 31-Mar-22
25
Project Life Financials 379 42 11% 379 (0) 0%
Current Year Financials 0 0 0% 46 46 0%
Project Description
Project Manager Arun Menon
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-30 31-Mar-30
Project complete with a slight overspend due to additional works required in relation to roof vents which required to be installed.
Main Issues / Reason for Variance
Mitigating Action
The statement of final account has been signed and financial risk exposure should be reduced through efforts to dispose of the
existing properties at the earliest opportunity.
Anticipated Outcome
Dumbarton Care Home opened 2017.  Clydebank Care Home was certified complete on 9 November 2020.
Replace Elderly Care Homes and Day Care Centres
Design and construction of replacement elderly care homes and day care centres in Dumbarton
and Clydebank areas.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Work continues on developments resulting in some spend in the current year
Mitigating Action
None required.
Anticipated Outcome
Development of Workforce Management System.
Development of Workforce Management System
Project to develop the Workforce Management System.
Planned End Date Forecast End Date

Page 11

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 30 0 0% 30 0 0%
Current Year Financials 30 0 0% 30 0 0%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-23
2
Project Life Financials 50 43 86% 51 1 1%
Current Year Financials 7 0 0% 8 1 10%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-23
3
Project Life Financials 40 5 12% 40 (0) 0%
Current Year Financials 35 0 0% 35 0 0%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 30-Sep-23 30-Sep-23
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
Payment Card Industry Data Security Standard (PCIDSS)
Module would ensure that WDC were compliant with the current requirements of PCIDSS for card payments
without the need for numerous costly workarounds
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget was rephased to 2022-23 as version upgrade of the Council's cash receipting system is required beforehand and is currently underway.
Anticipated Outcome
Upgraded Electronic Insurance System.
Enhancements to Cash Receipting System
Main Issues / Reason for Variance
Budget rephased to 2022-23 as this is a number of mini projects and the first part is the version upgrade which is actively progressing. After this
upgrade we can move onto other enhancements which are anticipated to finish in September 2023.
Mitigating Action
None required at this time.
Anticipated Outcome
Enhancements to the cash receipting system including PCI compliant telephone payment system.
To enhance the cash receipting system in the way payments are made and allocated to back office by
increasing the level of security that is required for online payments made by customers
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The various claim forms and departmental reports have been reviewed and updated and the relevant online request forms were submitted to the
Digital Sub-Group to be converted to Online Achieve Forms.  The various claim forms and departmental reports have now been converted to
Online Achieve Forms and are in the process of being tested. Once complete, the supplier will take matters forward with their design team. An
anticipated timeline for completion of the project, taking into account the various stages i.e. development, testing, going live etc. will be drawn up
in conjunction with the supplier at that time.  Budget spend anticipated in 2022/23.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Upgraded version with PCI compliant telephone payment system.
Electronic Insurance System
Acquisition of a claims/incident management system supported by an electronic document management
system.

Page 12

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
4
Project Life Financials 60 5 8% 60 0 0%
Current Year Financials 25 0 0% 25 0 0%
Project Description
Project Manager Adrian Gray
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-22 31-Oct-22
5
Project Life Financials 5 0 0% 5 0 0%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Jackie Nicol Thomson
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-23
6
Project Life Financials 53 13 25% 53 0 0%
Current Year Financials 33 0 0% 33 0 0%
Project Description
Project Manager Alan Douglas
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
Trainee solicitor in place. Budget will be fully spent.
Mitigating Action
None required at this time.
Anticipated Outcome
Solicitor support for Capital Projects, with full budget spend anticipated.
Planned End Date Forecast End Date
Anticipated Outcome
Development of Agresso system later than originally anticipated but within original budget.
Agresso development
The purpose of this project is to carry out an upgrade of the Agresso Finance System which was last
upgraded in 2015. The requirement to upgrade is to maintain a level of support available from Unit 4 who
have advised that support for older versions of the system is being reduced.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Delays in completion of required data cleansing prior to the upgrade have caused the start of the upgrade to be deemed too close to the financial
year end to risk disruption to preparation of the draft final accounts. The upgrade will be delayed until October 2022.
IFRS 16 Database
This is a system which will ensure that WDC has the correct level of information and adheres to correct
reporting of IFRS16 - Leasing. 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The purchase of software to allow new accounting treatment of leases to be appropriately reported is on track. Full spend anticipated FY
2022/2023.
Mitigating Action
None required
Anticipated Outcome
Purchase of software for accounting for leases.
Main Issues / Reason for Variance
Mitigating Action
None possible at this time.
Solicitor Project Support for Capital Projects
Solicitor costs to directly support capital projects

Page 13

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
7
Project Life Financials 30 0 0% 30 0 0%
Current Year Financials 10 0 0% 10 0 0%
Project Description
Project Manager Pamela Clifford
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
8
Project Life Financials 83 0 0% 83 0 0%
Current Year Financials 83 0 0% 83 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
9
Project Life Financials 20 13 66% 20 0 0%
Current Year Financials 7 0 0% 7 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
Replace existing main hall Air Handling unit at Clydebank Town Hall.
Mitigating Action
None required.
Anticipated Outcome
Delivery of project with full budget spend.
Replace failed heating controls/valves & recommission
Replace failed heating controls/valves & recommission.
Planned End Date Actual End Date
Main Issues / Reason for Variance
Further works ordered. Expect full spend by 31 March 2023.
Re -imagine Antonine Wall  
Council's capital contribution towards the multi-partner (five local authorities and Historic Environment
Scotland) Rediscovering the Antonine Wall project which is also funded by the Heritage Lottery Fund.
Anticipated Outcome
Physical works being carried out by 31/3/23.
Anticipated Outcome
Preservation of Historic Site.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Council's capital contribution towards the multi-partner (five local authorities and Historic Environment Scotland) Rediscovering the Antonine Wall
project will be paid by the end of the financial year.
Mitigating Action
None Required.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works are integrated with the new Baths refurbishment. Await design proposals from Vital for approval. Works to be complete by 31 March 2023
to compliment the district heating installation.
Mitigating Action
None available at this time.
Replace existing main hall Air Handling unit at Clydebank Town Hall

Page 14

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
10
Project Life Financials 290 63 22% 290 0 0%
Current Year Financials 216 0 0% 205 (11) -5%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
11
Project Life Financials 85 55 64% 85 (0) 0%
Current Year Financials 30 0 0% 27 (3) -10%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
12
Project Life Financials 16 14 85% 16 0 0%
Current Year Financials 2 0 0% 2 (0) 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
Water Meter Downsize.
Anticipated Outcome
Delivery of project within budget.
Mitigating Action
None required.
Anticipated Outcome
All works to be completed 2022/23.
Automatic Meter Readers - Water
Automatic Meter Readers.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Water meter works to be carried out in the last quarter of the year. Previous works with electricity meter supplier did not meet expectations. Await
resolutions before issuing further orders.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project integrated with Water AMR project. All works to be carried out in the last quarter of the year. Expect full spend.
Mitigating Action
None required
Water Meter Downsize
Anticipated Outcome
All works to be completed next financial year 2023/24.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works to be passed to Consultancy Services and meeting has been arranged. Consultancy Services compiling all elements of the tender
together. Added to procurement pipeline. Finalisation of controls upgrade for centre should be completed by the end of August 2022.
Mitigating Action
All works to be complete in one tender package.
Leisure Energy projects - air handling units, upgrade lighting, circulating pumps, and draught proofing
Measures to be installed at both Meadow Centre & Vale of Leven Swimming Pool; new pool hall Air Handling
Units, upgrade lighting, circulating pumps Vale of Leven Swimming Pool, internal and external lighting and
draught proofing.

Page 15

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
13
Project Life Financials 50 0 0% 50 0 0%
Current Year Financials 50 0 0% 50 0 0%
Project Description
Project Manager Steven Milne/ John McKenna
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
14
Project Life Financials 2,188 66 3% 1,651 (538) -25%
Current Year Financials 1,651 66 4% 1,450 (201) -12%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-24
15
Project Life Financials 9,782 4,935 50% 9,797 15 0%
Current Year Financials 2,223 37 2% 2,075 (148) -7%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
Anticipated Outcome
Progress towards delivery of planned projects from Economic Development Strategy and Charrette Action Plans albeit later than originally
anticipated.
Lighting upgrades to LED in schools and Corporate buildings
Upgrade lighting in schools and corporate buildings.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The remaining Regeneration Fund projects are Dumbarton Waterfront Path; the contribution towards the costs of Glencairn House; Connecting
Dumbarton; and the Scottish Marine Technology Park at the former Carless site. As Levelling Up Fund is programmed to be spent before
Regeneration Fund for Glencairn House and Connecting Dumbarton, it is not anticipated that any Regeneration Fund will be spent on these
projects during this financial year and will be carried forward. Spend against The £2.0m Clyde Mission funding for SMTP will continue during the
financial year 2022/2023 before an agreement is reached on the £2.0m of Regeneration Fund investment. Dumbarton Waterfront Path will be
developed according to landowner timescales, and only some spend is anticipated this year.
Mitigating Action
Programme management approach to delivery.
Mitigating Action
None available at this time.
Anticipated Outcome
Improved town centres and strategic sites across West Dunbartonshire.
Regeneration Fund
Funding to implement major regeneration projects linked to community charrettes. 
Regeneration/Local Economic Development
Budget to facilitate the delivery of Regeneration throughout West Dunbartonshire, aligned to the Economic
Strategy. External funding will be sought to maximise opportunities for redevelopment of these sites.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
LED budget is invested across our town centres and strategic sites and is used to develop and implement projects as well as providing match
funding to lever in external funding. During 2022/2023 the key projects to be developed and delivered include a contribution towards Smollett
Fountain public realm, enabling works at Mitchell Way subject to the timescale of the developer, development costs associated with Dumbarton
Waterfront, the Arc of Attraction Strategy and in Clydebank implementation of the Development Framework and delivery of the Activities Centre.
Many regeneration projects are subject to factors outwith Council control and close monitoring of the programming is required. A contingency is
included for increasing costs and new funding opportunities.
Access to schools has been restricted. Surveys to be initiated this month. Expect full spend by 31 March 2023.
Mitigating Action
None available at this time.
Anticipated Outcome
Works complete 2022/23

Page 16

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
16
Project Life Financials 1,166 1,023 88% 1,166 0 0%
Current Year Financials 143 0 0% 143 0 0%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
17
Project Life Financials 1,456 139 10% 1,456 0 0%
Current Year Financials 1,317 0 0% 1,112 (205) -16%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 31-Mar-23
18
Project Life Financials 747 0 0% 747 0 0%
Current Year Financials 747 0 0% 747 0 0%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Dec-22 30-Jun-23
Kier is appointed to design and deliver the Activities Centre at Clydebank Town Centre. Design of the project is underway and a commencement
date for construction is to be confirmed however this will be later than anticipated due to some administrative delays.
Mitigating Action
None available at this time.
Anticipated Outcome
New community-run activities centre in Clydebank Town Centre.
Main Issues / Reason for Variance
New activities centre in Clydebank Town Centre.
Planned End Date Forecast End Date
Town Centre Fund
Scottish Government funding to help improve local town centres.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The remaining Town Centre Fund will be spent on the Smollett Fountain public realm works which will be completed by the end of the financial
year.
Mitigating Action
None available at this time.
Anticipated Outcome
Regenerated Town Centres.
Clydebank Can On The Canal
Mitigating Action
Programme involves  expenditure over a number of projects led by different services. Regular reporting between services will help early
identification of risk.
Anticipated Outcome
Place-based improvements that advance Scottish Government's priorities of 20 min neighbourhoods and carbon zero.
Place Based Investment Programme
Scottish Government Funding to establish a Place-Based Investment Programme to ensure that all place
based investments are shaped by the needs and aspirations of local communities.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The budget includes a £0.641m contribution to Titan Boulevard at Queens Quay and £0.441m towards implementation of Alexandria Masterplan
projects.

Page 17

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
19
Project Life Financials 125 56 45% 125 0 0%
Current Year Financials 69 0 0% 69 0 0%
Project Description
Project Manager Gillian McNamara/ Michael McGuinness
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-23 30-Jun-23
20
Project Life Financials 11,220 0 0% 11,220 0 0%
Current Year Financials 3,720 0 0% 3,720 0 0%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Network expansion to GJNH (Golden Jubilee National Hospital) will commence pending approval to proceed by the GJNH Board. 
Mitigating Action
None available at this time.
Anticipated Outcome
Project will be delivered on budget.
District Heating Network Expansion
District Heating Network Expansion.
Planned End Date Forecast End Date
Levelling Up
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and
transformational regeneration.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This capacity funding was awarded by UK Government to assist with development of LUF bids. WDC has been awarded a grant from LUF
Round 1 and the capacity funding will be used in part to produce Artizan Centre redevelopment options. The balance will be used for
Roads/Transportation to develop a major transportation bid for LUF2.
Mitigating Action
None available at this time.
Anticipated Outcome
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and transformational regeneration.

Page 18

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
21
Project Life Financials 34,050 2,760 8% 34,049 (1) 0%
Current Year Financials 986 80 8% 986 (0) 0%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Peter Hessett
Project Lifecycle 31-Mar-27 31-Mar-27
22
Project Life Financials 15 4 24% 15 0 0%
Current Year Financials 11 0 0% 11 0 0%
Project Description
Project Manager Stephen Daly
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-23 31-Mar-23
Anticipated Outcome
Review of service requirements & telephony functionality will inform works to improve citizen experience.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Improvements to Contact Centre telephony were completed as scheduled during 2021/2022.  Further works have been scoped and agreed for
improvement to Housing telephony, benefiting both residents and the Council.  A review of the out of hours service is currently being undertaken
including work to upgrade telephony.  Any works will also incur professional fees for necessary scripting works.  We are also exploring call
recording technology across all the Contact Centre telephony.  It is anticipated these projects will be completed during the financial year
2022/2023.
Mitigating Action
None required.
Mitigating Action
None required.
Anticipated Outcome
Delivery of the project on time and within the increased budget.
Telephone System Upgrade
To improve Housing Repairs telephone platform for incoming calls, providing improved Management
Information.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Regular updates are provided at every Council meeting and monthly Project Board meetings and to City Deal.  The main issues contained within
the new Council's approved Outline Business Case are still valid, which include Exxon's remediation strategy, land transfer arrangements and
issues relating to adjoining owners.  WDC Consultants are monitoring the remediation process to ensure compliance with specification, also
Esso are independently monitoring the remediation works.  Final Business Case submission is November 2022. Through the Scape framework
we are working closely with Balfour Beatty to achieve a formal pre construction agreement to allow the detailed design works to commence and
the full construction programme to be developed. Agreements in principle are progressing with third party land owners.
Exxon City Deal
As part of the City Deal project the WDC Exxon site at Bowling regeneration with alternative A82 route
included.

Page 19

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
23
Project Life Financials 421 232 55% 421 (0) 0%
Current Year Financials 91 3 3% 91 (0) 0%
Project Description
Project Manager David Main
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-24 31-Mar-24
24
Project Life Financials 3,987 1,179 30% 4,000 13 0%
Current Year Financials 1,662 (8) 0% 1,662 0 0%
Project Description
Project Manager Sarah Christie/Michelle Lynn
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-23 31-Mar-23
25
Project Life Financials 1,700 34 2% 1,590 (110) -6%
Current Year Financials 1,590 34 2% 1,590 0 0%
Project Description
Project Manager Michelle Lynn/ Sarah Christie
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-24 31-Mar-24
Heritage Capital Fund
Heritage Capital Fund.
Main Issues / Reason for Variance
Work is underway to progress furniture replacement at Dumbarton, Duntocher and Parkhall libraries during 2022/2023.  Budget of £0.1m has
been rephased to  next financial year for Dalmuir library as work is currently scheduled for 2023/2024.
Mitigating Action
None required.
Anticipated Outcome
Project carried forward to align with Asset Management programme.
Main Issues / Reason for Variance
Project in design phase and planning application will be submitted August 2022.
Mitigating Action
None available at this time.
Anticipated Outcome
Re-development of Glencairn House in Dumbarton High Street to a purpose built library and museum, within budget albeit later than originally
anticipated.
Anticipated Outcome
Project to be delivered on budget and within revised timescale.
Glencairn House
Re-development of Glencairn House in Dumbarton High St to a purpose built library and museum.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
None available at this time.
Transformation of Infrastructure Libraries and Museums
To improve performance and efficiency of Council's Libraries and Cultural Services.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The original projected spend has been affected by internal and external delays due to the Covid 19 recovery, a reduction in the scope of the
Clydebank Town Hall project, a change in the delivery date for the Clydebank Museum at Clydebank Library during the contract award stage,
while the new Dalmuir Library and Gallery had to be rescheduled for approval in August 2021. Officers are now making progress to get projects
back on track, projects will still be delivered in full, and a review of optimism bias will be undertaken in the projections for 2022/23.
Mitigating Action

Page 20

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
26
Project Life Financials 40 0 0% 40 0 0%
Current Year Financials 40 0 0% 40 0 0%
Project Description
Project Manager John Anderson
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-22 31-Mar-23
27
Project Life Financials 8,535 161 2% 8,535 (0) 0%
Current Year Financials 1,715 42 2% 1,715 0 0%
Project Description
Project Manager Sharon Jump/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-25 31-Mar-25
28
Project Life Financials 1,912 296 15% 1,912 0 0%
Current Year Financials 1,912 296 15% 1,912 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
Design Team have been appointed to develop feasibility options for the DRP Project, currently in stage 1 of this phase reviewing service
requirements.  The conclusion of the feasibility report will provide input for the options appraisal exercise.  The intention would be to bring a
business case to a future IRED Committee.
Mitigating Action
None available at this time.
Anticipated Outcome
Project business case will be brought back to project board and Council.
Depot Rationalisation
Depot Rationalisation.
Planned End Date Forecast End Date
Anticipated Outcome
Full budget spend anticipated.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works progressing.
Mitigating Action
None available at this time.
Building Upgrades and H&S - lifecycle & reactive building upgrades
Lifecycle and reactive building upgrades.
Mitigating Action
None required
Anticipated Outcome
New floor fitted in Alexandria Community Sports Hall.
Alexandria Community Centre Sports Hall re-flooring
Alexandria Community Centre Sports Hall re-flooring
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The Alexandria Community Centre Sports Hall continues to be utilised as COVID-19 vaccine centre during 2022/23 and the work will be
postponed until the last quarter of the financial year.

Page 21

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
29
Project Life Financials 350 9 3% 350 0 0%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-24 31-Mar-24
30
Project Life Financials 150 16 11% 150 0 0%
Current Year Financials 134 0 0% 134 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-21 31-Mar-23
31
Project Life Financials 750 664 89% 750 0 0%
Current Year Financials 86 0 0% 86 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-23
Main Issues / Reason for Variance
Project now complete awaiting invoices.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered on budget.
Anticipated Outcome
To deliver new sports changing facility.
Holm Park & Yoker Athletic FC
Develop a new 3G pitch to act as a home venue for Clydebank FC with extensive community access.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project had been delayed due to a number of COVID-19 related issues and utilities issues.  Unit is now in production but delay to site due to the
utility disconnection and demolition works. Demolition works complete and waiting for a date for installation.
Mitigating Action
None available at this time.
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
Main Issues / Reason for Variance
The budget for this project has been rephased to FY 2023/2024.
Mitigating Action
None available at this time.
Anticipated Outcome
To deliver new sports changing facility.
New Sports Changing Facility Dumbarton West (Old OLSP site) 
New Sports Changing Facility Dumbarton West (Old OLSP site) 
Planned End Date Forecast End Date

Page 22

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
32
Project Life Financials 150 0 0% 150 0 0%
Current Year Financials 150 0 0% 150 0 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-25 31-Mar-25
33
Project Life Financials 78 0 0% 78 0 0%
Current Year Financials 78 0 0% 78 0 0%
Project Description
Project Manager Martin Feeney
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-23
34
Project Life Financials 45 0 0% 45 0 0%
Current Year Financials 45 0 0% 45 0 0%
Project Description
Project Manager Martin Feeney
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-23
Main Issues / Reason for Variance
It is anticipated that spend will be achieved by the end of the financial year 2022/2023.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within budget.
Anticipated Outcome
Project delivered within budget.
Elevated Platforms (Building Services)
Elevated Platforms (Building Services).
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Welfare Units will be purchased by the end of the financial year.
Mitigating Action
None available at this time.
Purchase of 3 Welfare Units
At Council meeting on 30th August 2017 it was agreed to purchase 3 Welfare Units as a spend-to-save
proposal.
Changing Places Toilet Provision
Changing places toilet provision in four public buildings - Balloch bus stance toilets, Concord Community
Centre, Dalmuir Community Centre and Clydebank East Community Centre.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Plans have been prepared and projects will be progressed by the end of the financial year.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within budget.

Page 23

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
35
Project Life Financials 912 849 93% 912 0 0%
Current Year Financials 80 17 21% 80 0 0%
Project Description
Project Manager Elaine Troup
Chief Officer Peter Barry
Project Lifecycle 31-Mar-23 31-Mar-23
36
Project Life Financials 100 23 23% 100 (0) 0%
Current Year Financials 17 0 0% 17 0 0%
Project Description
Project Manager Graham Watters
Chief Officer Peter Barry
Project Lifecycle 31-Mar-30 31-Mar-30
37
Project Life Financials 200 0 0% 200 0 0%
Current Year Financials 50 0 0% 50 0 0%
Project Description
Project Manager John Kerr
Chief Officer Peter Barry
Project Lifecycle 31-Mar-30 31-Mar-30
Main Issues / Reason for Variance
Project was initially stalled due to COVID-19 restrictions, however as these are easing Officers have now carried out a consultative exercise and
initiated a site inspection to develop the work programme for 2022/2023.
Mitigating Action
Officers carried out some proactive consultative work to establish the tenant priorities this will allow the work programme to be developed
timeously.
Anticipated Outcome
It is expected the works programme  will be completed during 2022/2023.
Anticipated Outcome
Development of IHMS system.
Dennystoun Forge Site Improvements
Dennystoun Forge Site Improvements
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Development of system progressing, with full budget spend anticipated to be incurred in 2022/23.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Full spend is anticipated on this year's budget.
Integrated Housing Management System
Development of IHMS system.
Invest in "Your Community Initiative"
Capital budget to support the roll out of Your Community,  an initiative designed to achieve coordinated
service delivery in response to community need. This is complimented by community capacity building,
empowering WD citizens to do more for their own communities (leading to less reliance on council).  Also
included is the implementation of participatory budgeting to support and build capacity in communities.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Application process is planned for later in this financial year.

Page 24

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
38
Project Life Financials 405 7 2% 405 0 0%
Current Year Financials 405 7 2% 405 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
39
Project Life Financials 472 406 86% 472 0 0%
Current Year Financials 66 0 0% 66 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
40
Project Life Financials 1,726 1,718 100% 1,726 0 0%
Current Year Financials 13 5 38% 13 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None required at this time.
Anticipated Outcome
Improvements to the environment of West Dunbartonshire.
Environmental Improvement Fund
This fund has been created to deliver environmental improvement projects for communities throughout West
Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Remaining budget rephased from 2021/2022 to progress with tree planting in 2022/2023 in line with the Councils Climate Change and
Biodiversity action plans.  Full budget spend anticipated.
Main Issues / Reason for Variance
This fund has now closed. Funding to be vired to Posties Park project.
Mitigating Action
None required
Anticipated Outcome
Budget to be vired to Posties Park Project.
Community Sports Fund
Match funding of up to 75% for local sports clubs to develop business cases to improve facilities.
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Better access with parks, cemeteries and open spaces.
Public non-adopted paths and roads
Upgrades to drainage and lighting to enhance the lifespan of paths and roads within  facilities in public parks,
cemeteries and civic spaces.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects are currently being developed to deliver better access in our parks, cemeteries and open spaces. Full budget spend anticipated in
2022/2023.

Page 25

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
41
Project Life Financials 50 37 73% 50 (0) 0%
Current Year Financials 13 0 0% 13 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
42
Project Life Financials 220 214 97% 220 0 0%
Current Year Financials 7 0 0% 7 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 03-Apr-21 31-Mar-22
43
Project Life Financials 200 0 0% 200 0 0%
Current Year Financials 30 0 0% 30 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
44
Project Life Financials 581 59 10% 581 (0) 0%
Current Year Financials 122 0 0% 122 (0) 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-22
Project works complete.  Retentions to be paid in 2022/2023.
Mitigating Action
None required at this time.
Development of play areas to improve accessibility and inclusiveness of play areas throughout West Dunbartonshire.
Mitigating Action
None required at this time.
Anticipated Outcome
Renewal of play parks
East End Park Resurfacing
Resurfacing of 3G pitch at East End Park.
Anticipated Outcome
New all weather tennis courts.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Main Issues / Reason for Variance
Consultant and design team fees for resurfacing of 3G pitch at East End Park.
Mitigating Action
Resurfacing of 3G pitch at East End Park.
Play Parks Grant Funding
Renew and replace play park equipment
None required at this time.
Kilmaronock Cemetery Extension
Extension of existing cemetery at Kilmaronock. 
Main Issues / Reason for Variance
Planned End Date Actual End Date
Sports Facilities Upgrades - Argyll Park - Construction of 3 All Weather Tennis Courts
Project is part of wider investment in sporting facilities and is dependent on match funding from Sports
Scotland. Agreement in principle to wider WDC strategic priorities.
Anticipated Outcome
Planned End Date Forecast End Date
Sustainable burial environment for local residents.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget will be used to develop an area of the existing Cemetery for additional burials.  Project scope has now been developed and will be
tendered under the minor civils framework.  Budget spend anticipated in 2022/2023.
Mitigating Action
None required.
Anticipated Outcome

Page 26

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
45
Project Life Financials 210 0 0% 210 0 0%
Current Year Financials 10 0 0% 10 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 30-Nov-23 30-Nov-23
46
Project Life Financials 25 0 0% 25 0 0%
Current Year Financials 25 0 0% 25 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
47
Project Life Financials 228 0 0% 228 0 0%
Current Year Financials 228 0 0% 228 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Nature resource for Faifley Community
Large bins for high traffic areas (pilot)
Supply and install extra large litter bins as a pilot project within hotspot problem areas.
Planned End Date Forecast End Date
Funding received from Nature Restoration Fund to build nature resource for Faifley community. Project due to commence 1st April 2022 and
completion anticipated by November 2022.
Mitigating Action
None required at this time.
Anticipated Outcome
Balloch Mountain Bike Track
Develop a mountain bike skills trail at Balloch Castle Country Park.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Design fees to develop Mountain bike skills trail in Balloch country park. Project to commence April 2023 and works to be complete by November
2023.
Mitigating Action
None required at this time.
Anticipated Outcome
Mountain bike track
Main Issues / Reason for Variance
Supply and install extra large litter bins as a pilot project within hotspot problem areas. Project commences August 2022 and completion is
anticipated by March 2023.
Mitigating Action
None required at this time.
Anticipated Outcome
Nature resource for Faifley Community
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Large bins provided for high traffic areas
Knowes Nature Reserve

Page 27

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
48
Project Life Financials 740 350 47% 350 (390) -53%
Current Year Financials 390 0 0% 0 (390) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Jul-22 31-Jul-22
49
Project Life Financials 683 0 0% 566 (117) -17%
Current Year Financials 683 0 0% 566 (117) -17%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
50
Project Life Financials 203 0 0% 107 (96) -47%
Current Year Financials 107 0 0% 107 (0) 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23Forecast End Date
Main Issues / Reason for Variance
Projects and locations still to be decided.
Main Issues / Reason for Variance
To develop projects including Balloch Park Phase 2, and other projects principally around National Cycle Network 7 and further pedestrian
dropped kerbs.
Mitigating Action
None required at this time.
Anticipated Outcome
To improve connectivity and enhanced Cycling routes within West Dunbartonshire.
Spaces for People
Funding has been awarded from Sustrans to assist with social distancing measures required as a result of
the COVID-19 pandemic.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The programme is now complete and there will be no further expenditure.
Mitigating Action
None required at this time.
Anticipated Outcome
To improve Footways in West Dunbartonshire.
Footways/Cycle Path Upgrades
Renewal and/or enhancement of failed footpaths/cycle paths through West Dunbartonshire.
Planned End Date
Cycling, Walking and Safer Streets
Introduction of enhanced walking routes and traffic calming schemes to introduce safer streets within West
Dunbartonshire.
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
To provide people of West Dunbartonshire additional space to help adhere to social distancing guidelines.

Page 28

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
51
Project Life Financials 200 0 0% 5 (195) -97%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
52
Project Life Financials 60 55 91% 60 0 0%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
53
Project Life Financials 314 215 68% 314 (0) 0%
Current Year Financials 100 0 0% 100 (0) 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Funding has been received from Turnberry Homes and will be used to introduce traffic calming and traffic
management measures to mitigate the impact of additional traffic accessing the housing development off
Castle Road, Dumbarton.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultation completed 2021/2022 and speed humps will be installed prior to 31 March 2023.
Anticipated Outcome
To provide Electric Vehicle Charging points within West Dunbartonshire.
Anticipated Outcome
To improve Footways in West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget to be used for retention payment from last years surfacing of Dumbarton East footways.
Mitigating Action
None required at this time.
Additional Pavement Improvements
Extra funding to accelerate pavement maintenance and improvements across West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Charging points to be installed at Moss O' Balloch park by the end of this financial year.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Traffic calming to be installed in Dumbarton East.
Electrical Charging Points - Rapid Charge
Funding has been awarded from Transport Scotland for the Installation of electrical charging points
Turnberry Homes - traffic calming/ management at Turnberry housing development off Castle Road

Page 29

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
54
Project Life Financials 1,257 0 0% 1,257 0 0%
Current Year Financials 1,257 0 0% 1,257 0 0%
Project Description
Project Manager Raymond Walsh/ Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
55
Project Life Financials 500 0 0% 500 0 0%
Current Year Financials 500 0 0% 500 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
56
Project Life Financials 149 0 0% 149 0 0%
Current Year Financials 149 0 0% 149 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Intention is to complete works within budget.
Infrastructure - Flooding
Essential renewal of failed drainage assets to minimise flood risk within West Dunbartonshire.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Small value projects to tackle flooding events in various areas.
Main Issues / Reason for Variance
A detailed design for Gruggies Burn will be undertaken by the end of the financial year.
Mitigating Action
None required at this time.
Anticipated Outcome
Project should be complete within budget.
Flood Risk Management
Enhancement of drainage infrastructure to ensure compliance with Flood Risk Management Act 2009.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Plans are under consideration by officers.
Mitigating Action
None required at this time.
Anticipated Outcome
Projects should be complete within budget.
Flood Prevention
Various flood prevention projects.
Planned End Date

Page 30

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
57
Project Life Financials 800 181 23% 800 0 0%
Current Year Financials 620 0 0% 620 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
58
Project Life Financials 1,627 5 0% 1,075 (552) -34%
Current Year Financials 1,627 5 0% 1,075 (552) -34%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
59
Project Life Financials 3,444 10 0% 3,444 0 0%
Current Year Financials 3,444 10 0% 3,444 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Anticipated Outcome
Intention is to complete various surfacing works by the end of March 2023.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Roads Operations are progressing an extensive surfacing program and have a number of schemes to be completed by the end of the financial
year.
Mitigating Action
None required at this time.
Infrastructure - Roads
Infrastructure - Roads.
Main Issues / Reason for Variance
Work will be undertaken during this financial year for A8014 Kilbowie Rd, A814 Congestion Measures, Balloch Station Park & Ride and Bus
Infrastructure Improvements. All of these projects will be undertaken by Roads Services.
Mitigating Action
None required at this time.
Anticipated Outcome
Improve accessibility to Public Transport and improve journey time reliability.
Anticipated Outcome
Project should be completed within budget.
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements & Park and Rides
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Awaiting outcome of Scottish Government & SEPA deliberations, however officers are hopeful full budget spend can be incurred by the end of
the financial year.
Mitigating Action
None required at this time.
River Leven Flood Prevention Scheme
River Leven Flood Prevention Scheme.

Page 31

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
60
Project Life Financials 12 8 61% 12 0 0%
Current Year Financials 12 8 61% 12 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
61
Project Life Financials 97 35 36% 97 (0) 0%
Current Year Financials 55 0 0% 55 (0) 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
62
Project Life Financials 15,053 421 3% 15,053 (0) 0%
Current Year Financials 1,524 0 0% 1,524 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Anticipated Outcome
Project should be completed within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget to be used for a detailed design for Gruggies Burn.
Mitigating Action
None available at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
Intention is to complete works within budget.
Gruggies Burn Flood Prevention
Commission of Gruggies Flood Prevention Scheme.
Depot Improvement Works
Improvement of WDC Roads Depot.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget will be utilised for depot rationalisation works during the financial year.
Main Issues / Reason for Variance
Budget will be used for any service work carried out by Scottish Power before or after column replacement works.
Mitigating Action
None available at this time.
Anticipated Outcome
Intention is to complete works within budget.
Street lighting and associated electrical infrastructure
WDC is responsible for the maintenance of 18,000 street lighting columns and associated illuminated signs
and bollards.  This budget is required for this infrastructure.
Planned End Date Forecast End Date

Page 32

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
63
Project Life Financials 2,325 1,007 43% 2,325 0 0%
Current Year Financials 693 0 0% 693 (0) 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-26 31-Mar-26
64
Project Life Financials 2,325 0 0% 2,325 0 0%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-26 31-Mar-26
65
Project Life Financials 4,300 3,829 89% 4,300 (0) 0%
Current Year Financials 498 27 5% 498 (0) 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-22
Anticipated Outcome
Project should be completed within budget enhancing the A814 through Clydebank.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works substantially complete. Additional works as a compensation event started on Wallace street in July 2022.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
To provide an improved A813.
Clydebank Charrette, A814
Clydebank Charrette, A814
A813 Road Improvement Phase 2
A813 Road Improvement Phase 2.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
These works are not due to commence until Phase 1 has been completed.
Main Issues / Reason for Variance
Plans have been developed for carriageway widening and footway and cycleway construction between Strathleven and Lions Gate.  There are
ongoing discussions with Aggreko and other land owners in regards to access and land acquisition with construction commencing during
2022/2023.
Mitigating Action
None required at this time.
Anticipated Outcome
To provide an improved A813.
A813 Road Improvement Phase 1
A813 Road Improvement Phase 1.
Planned End Date Forecast End Date

Page 33

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
66
Project Life Financials 3,930 3,846 98% 3,846 (84) -2%
Current Year Financials 84 0 0% 0 (84) -100%
Project Description
Project Manager Cameron Muir
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-May-21
67
Project Life Financials 1,039 650 63% 1,039 (0) 0%
Current Year Financials 117 6 5% 117 (0) 0%
Project Description
Project Manager Cameron Muir
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
68
Project Life Financials 80 0 0% 80 0 0%
Current Year Financials 40 0 0% 40 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Purchase of Roads plant and equipment.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
New Plant to be purchased
Mitigating Action
None required.
Anticipated Outcome
To purchase equipment.
Main Issues / Reason for Variance
Works to Lomond Bridge were completed May 2021. No further costs expected.
Mitigating Action
None required.
Anticipated Outcome
To provide an improved Lomond Bridge.
Protective overcoating to 4 over bridges River Leven
To overcoat 4 bridges over River Leven.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works to Renton footbridge are now complete and work will commence on the other bridges.
Mitigating Action
None available at this time.
Anticipated Outcome
To upgrade bridges within West Dunbartonshire.
Roads Plant
A811 Lomond Bridge
Upgrade of Lomond Bridge.
Planned End Date Actual End Date

Page 34

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
69
Project Life Financials 350 0 0% 350 0 0%
Current Year Financials 350 0 0% 350 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
70
Project Life Financials 300 0 0% 300 0 0%
Current Year Financials 300 0 0% 300 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
71
Project Life Financials 1,000 0 0% 1,000 0 0%
Current Year Financials 1,000 0 0% 1,000 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Traffic Signal Upgrades
Upgrade Traffic Signals
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Mitigating Action
None required.
Anticipated Outcome
To upgrade traffic signals.
Roads improvements
Mitigating Action
None required.
Anticipated Outcome
Resurface footways.
Footway Resurfacing (RAMP)
Footway resurfacing
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Various road improvement projects
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Mitigating Action
None required.
Anticipated Outcome
Improvements to roads

Page 35

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
72
Project Life Financials 100 0 0% 100 0 0%
Current Year Financials 100 0 0% 100 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
73
Project Life Financials 1,000 0 0% 1,000 0 0%
Current Year Financials 1,000 0 0% 1,000 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
74
Project Life Financials 30 0 0% 30 0 0%
Current Year Financials 30 0 0% 30 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
Street sign renewal
Renewal of street signs
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Mitigating Action
None required.
Anticipated Outcome
Renewal of street signage.
Pavement improvements
Various pavement improvement projects.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Mitigating Action
None required.
Anticipated Outcome
Improvement to pavements.
Water Safety
To develop Water Safety Policy & enhance water safety equipment in WDC
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Expenditure on water safety equipment will be made as required throughout the year.
Mitigating Action
None required
Anticipated Outcome
Water safety equipment as required.

Page 36

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
75
Project Life Financials 400 0 0% 400 0 0%
Current Year Financials 400 0 0% 400 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-23
76
Project Life Financials 1,980 0 0% 1,980 0 0%
Current Year Financials 180 0 0% 45 (135) -75%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
77
Project Life Financials 160 71 44% 160 0 0%
Current Year Financials 80 71 88% 71 (9) -12%
Project Description
Project Manager Kenny Lang
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
78
Project Life Financials 1,110 198 18% 1,110 (0) 0%
Current Year Financials 441 9 2% 441 0 0%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-29 31-Mar-29Forecast End Date
Main Issues / Reason for Variance
Delivery expected by September 2022 and full budget spend expected before the end of the financial year.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within  budget.
Purchase of gritters
Purchase of gritters.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultant project nearing completion and spend will be made thereafter.
Main Issues / Reason for Variance
Although there is slippage caused mainly by the academic year starting several months after the financial year the project is still on track to be
completed by the planned end date.
Mitigating Action
None available at this time.
Anticipated Outcome
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Compactors have now been delivered.
Mitigating Action
None Required.
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within budget.
Replacement of compactors at Dalmoak civic amenity site
The purchase of 2 compactors for the Council civic amenity site at Dalmoak.
Waste Transfer Station
The design, development and construction of a recycling and bulk waste transfer facility that will ensure all
recycling material can be sorted and disposed off appropriately to ensure compliance with landfill ban in
2025.
Purchase of AV Equipment for Education.
Anticipated Outcome
Project delivered within  budget.
AV Equipment - Education
Purchase of AV Equipment for Education.
Planned End Date

Page 37

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
79
Project Life Financials 376 335 89% 376 (0) 0%
Current Year Financials 41 0 0% 41 0 0%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
80
Project Life Financials 20,241 15,083 75% 20,241 0 0%
Current Year Financials 1,005 266 26% 1,005 0 0%
Project Description
Project Manager Sharon Jump/ Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24Planned End Date Forecast End Date
Main Issues / Reason for Variance
Renton Campus: The overall construction was completed as programmed (Previously April 2022 but re-programmed due to 13 week COVID-19
site closure).  Phase 1 of the project was handed over on Monday 18 October 2021, with pupils returning to the new school campus on
Wednesday 20 October 2021. There is an acceleration of spend on this project due to part retention being paid 2022/2023. St Mary's Alexandria
Refurbishment Works (condition survey works, MUGA, Dining & Kitchen extension) anticipated commencement of MUGA is September 2022
which means new build kitchen will slip to June 2023.   Additional ASN Provision – Secondary Phase - Temporary accommodation for Choices
will be in place September and plans for rebuild extension ongoing. Additional scoping in respect of vacant space at Choices and former
Riverside ELC is ongoing.
Mitigating Action
None required
Mitigating Action
None required at this time.
Anticipated Outcome
Increase the Chromebook ratio for most disadvantaged children.
Schools Estate Improvement Plan
Improvement of Schools Estate.
Anticipated Outcome
Project delivered within budget and to the revised programme, following COVID-19.
Digital Inclusion
Increase the ratio of chrome book devices for most disadvantaged children and families and support for
families with remote access.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Additional devices have been ordered to increase the ratio of devices to pupils as part of a commitment towards a 1:1 device ratio. The project is
on track to be fully spent in 2022/2023.

Page 38

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
81
Project Life Financials 29,450 95 0% 29,450 (0) 0%
Current Year Financials 2,797 0 0% 2,797 0 0%
Project Description
Project Manager Sharon Jump/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-26 31-Mar-26
82
Project Life Financials 750 637 85% 750 0 0%
Current Year Financials 113 0 0% 113 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
83
Project Life Financials 5,508 5,505 100% 5,508 (0) 0%
Current Year Financials 3 0 0% 3 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-22 30-Apr-21
Forecast End Date
Main Issues / Reason for Variance
A new contractor will be appointed in August 2022 and the programme will be reviewed at that time.
Main Issues / Reason for Variance
Project complete and await final charges.
Mitigating Action
None required.
Anticipated Outcome
Mitigating Action
None available at this time.
Planned End Date Forecast End Date
Planned End Date
Project delivered on time and within budget
Anticipated Outcome
Project delivered on budget.
Schools Estate Refurbishment Plan
Completion of condition surveys has been carried out to identify works required to bring various schools from
Condition C to Condition B.
Improvement of Schools Estate.
Planned End Date Forecast End Date
Choices Programme - to assist young people who require additional support
Bringing together Central Support Services which will include relocation of Choices Programme.
Main Issues / Reason for Variance
The next phase of the Schools Estate Improvement Plan involves the development of a new Campus provision in the Faifley area. WDC has
been successful in securing funding from the Scottish Government Learning Estate Improvement Programme. SFT confirmed the indicative
funding allocation for this project at £18.416m on the 4 May 2021, this will be received as a revenue stream over the 25 years of the Scottish
Government financial support (subject to the Council adhering to the funding criteria). Site Options Appraisal has taken place and Members
approved the recommendation to proceed with the new Faifley Campus on the St Joseph's site at Education Committee on 9th June 2021.  The
design team and main contractor have been appointed and the next phase will see the design development for the new Campus taking place.
The statutory consultation process was launched in September 2021 and a report was brought back to the Educational Services committee in
March 2022 concluding the process.
Mitigating Action
None available at this time.
Anticipated Outcome
Delivery of the project will be on time.
Schools Estate Improvement Plan - next Phase - Faifley Campus

Page 39

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
84
Project Life Financials 8,748 7,954 91% 8,748 (0) 0%
Current Year Financials 795 1 0% 795 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
85
Project Life Financials 1,150 1,136 99% 1,150 (0) 0%
Current Year Financials 26 12 45% 26 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 30-Apr-22
86
Project Life Financials 1,053 302 29% 1,053 0 0%
Current Year Financials 1,053 302 29% 969 (84) -8%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-23 31-Mar-23
The project will be completed to deliver the requirements of the Early Years expansion plans.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project complete and final account to be agreed.
Mitigating Action
None required.
Mitigating Action
None required at this time.
Anticipated Outcome
Dalmonach CE Centre
To create new community facilities with additional space for early years provisions.
Early Years Early Learning and Childcare Funding
Early learning and childcare funding awarded to West Dunbartonshire Council to facilitate the expansion in
entitlement to funded ELCC to 1140 hours from August 2020.
Planned End Date
Main Issues / Reason for Variance
Works progressing and budget spend anticipated in 2022/23.
Forecast End Date
Main Issues / Reason for Variance
Provision of aids and adaptations to clients as required.
Mitigating Action
None available at this time
Anticipated Outcome
Provision of adaptations and equipment to HSCP clients as anticipated.
Anticipated Outcome
To create new community facilities with additional space for early years provisions.
Aids & Adaptations - Special Needs Adaptations & Equipment
Reactive budget to provide adaptations and equipment for HSCP clients.
Planned End Date Forecast End Date

Page 40

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
87
Project Life Financials 73 50 68% 73 0 0%
Current Year Financials 73 50 68% 73 0 0%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-23 31-Mar-23
88
Project Life Financials 1,422 412 29% 1,422 0 0%
Current Year Financials 1,422 412 29% 950 (472) -33%
Project Description
Project Manager Patricia Kerr
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-23 31-Mar-23
89
Project Life Financials 60 50 83% 60 0 0%
Current Year Financials 17 7 40% 17 0 0%
Project Description
Project Manager Patricia Kerr
Chief Officer Victoria Rogers
Project Lifecycle 31-Oct-22 31-Oct-22Planned End Date Forecast End Date
Main Issues / Reason for Variance
Technical aspect of the project is complete and WDC are assisting with user testing. Delayed but on budget.
Forecast End Date
None available at this time.
Anticipated Outcome
Technical aspect of the project is complete and WDC assisting with user testing. Delayed but on budget.
Internet of Things Asset Tracking
Asset Tracking.
Criminal Justice Adaptations
The construction of an office and storage refit with a mezzanine floor within an existing workshop unit which will include associated finishes
works and electrical installations. The multi-purpose new office space will accommodate two members of staff with an office base and allow
space to set up a training facility indoors. Project expected to be completed by 31 March 2023.
Mitigating Action
Anticipated Outcome
Most of capital allocated to HSCP will be used to review/replace the current case management systems and will be rephased in line with the
project plan. Supply chain delays may continue to impact delivery and spend.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
All PC replacements for high schools have been replaced during the summer break. Orders for replacement Chrome books have been raised.
Supplier lead times for laptops and Chrome books have improved but exceed pre-Covid delivery times.
Mitigating Action
Continue to escalate and meet framework suppliers to confirm delivery lead times.
Investigate other procurement routes as well as adjust the project scope to replace where stock allows.
ICT Modernisation
This budget is to facilitate ICT infrastructure and modernise working practices.
Mitigating Action
Renovation of Unit 11 Levenside Business Court.
Planned End Date
None available at this time
Anticipated Outcome
Renovation of Unit 11 Levenside Business Court
Main Issues / Reason for Variance

Page 41

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
90
Project Life Financials 1,297 237 18% 1,297 0 0%
Current Year Financials 1,297 237 18% 1,100 (197) -15%
Project Description
Project Manager Brian Miller/ Patricia Kerr
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-23 31-Mar-23
91
Project Life Financials 450 189 42% 450 0 0%
Current Year Financials 173 11 7% 150 (23) -13%
Project Description
Project Manager Dorota Piotrowicz/ Patricia Kerr
Chief Officer Victoria Rogers
Project Lifecycle 30-Sep-23 30-Sep-23
92
Project Life Financials 3,502 42 1% 3,502 0 0%
Current Year Financials 3,502 42 1% 3,502 0 0%
Project Description
Project Manager N/A
Chief Officer N/A
Project Lifecycle 31-Mar-23 31-Mar-23
Project Life Financials 1,000 0 0% 1,000 0 0%
Cost of Living
Main Issues / Reason for Variance
Project spend relates to internal and external resources to implement new systems, processes and user training skills.  Mailbox migration aspect
of the project delayed until cloud backup is implemented (procurement of backup has started and target implementation is September/October
2022).  Implementation of device management functionality in 365 is on target to go live in September 2022. Information governance work stream
baseline review is complete and action plan is drafted for review.  Recruitment of a resource to train end users has started.
Mitigating Action
Continue to monitor the various work streams to accelerate aspects of the project where possible if suppliers can provide resource. Continue to
assess where a) internal skills have developed, b) external resource is needed for introducing new functionality in the future to inform future
bidding cycles and c) temporary recruitment/secondment is required.
Anticipated Outcome
Anticipated Outcome
Anticipate the majority of budget being spent this financial year but some works are planned for the last quarter of the year for Public Sector
Network (PSN) annual compliance submission.
365 Implementation
ICT Security & DR
The project is for the enhancement of security systems, server replacement and the update of corporate
applications to ensure compliance with 15/16 PSN requirements, to enhance the disaster recovery
capabilities of WDC.
Majority of budget spent but delayed.
None required.
Anticipated Outcome
Direct project support costs allocated as appropriate.
Direct Project Support
Business support cost such as reallocation of architects and project support at year end.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
n/a
Mitigating Action
Project services to delivery Microsoft 365 Implementation including 3rd party supplier, training, technical
consultancy etc.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Storage Area Network (SAN) delivered and installation planning underway.  Switch replacement in schools completed during the summer break. 
Server replacement at scoping stage.
Mitigating Action
Monitor supply chain issues. Continue tendering processes and implementation stages for each project.

Page 42

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 4
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2022
Budget Details
Project Life Financials
Spend to Date Variance
Current Year Financials 1,000 0 0% 1,000 0 0%
Project Description
Project Manager N/A
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-23
To support Council and community organisations with capital costs for cost of living initiatives
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Working Group currently developing proposals for initiative
Mitigating Action
None required.
Anticipated Outcome
Initialive will assist with cost of living crisis

Page 43

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
PERIOD END DATE
PERIOD 4
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials (141) (99) 70% (419) (278) 197%
Current Year Financials (278) 0 0% (278) 0 0%
Project Description
Project Lifecycle 31-Mar-22 31-Mar-22
2
Project Life Financials (75,127) (30,877) 41% (76,371) (1,244) 2%
Current Year Financials (5,574) (2,020) 36% (5,574) 0 0%
Project Description
Project Lifecycle 31-Mar-30 31-Mar-30
3
Project Life Financials (35,184) (4,705) 13% (35,184) 0 0%
Current Year Financials (959) (126) 13% (959) 0 0%
Project Description
Project Lifecycle 31-Mar-26 31-Mar-26
4
Project Life Financials (10,432) (4,584) 44% (10,432) 0 0%
Current Year Financials (1,753) (845) 48% (1,753) 0 0%
Project Description
Project Lifecycle 31-Mar-22 31-Mar-22
Anticipated Outcome
Match funding received.
None required.
Mitigating Action
Mitigating actions are detailed within the appropriate status updates.
Anticipated Outcome
Application of resources as appropriate.
Match Funding / Other Grants and Contributions
Match Funding / Other Grants and Contributions
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Application of resources is dependent on capital project progressing in year as planned.
Mitigating Action
Application of resources is dependent on capital project progressing in year as planned.
Main Issues / Reason for Variance
General services capital grant is anticipated to be received as forecast.
Mitigating Action
None required at this time
Anticipated Outcome
General services capital grant is anticipated to be received as forecast.
Ring Fenced Government Grant Funding
This is ring fenced grant funding which is primarily anticipated to be received from the Scottish Government and
relates to Cycling, Walking, Safer Streets, Regeneration Placed Based Investment Programme, Early Years,
Gruggies Burn Flood works, Early Years funding, City Deal and Town Centre Fund.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Application of resources held on balance sheet as at 31 March 2022 as appropriate.
General Services Capital Grant
This is a general grant received from the Scottish Government in relation to General Services capital spend
Application of resources is dependent on capital project progressing in year as planned.
Spend to Date Forecast Variance
Resources Carried Forward
These are resources that have been received in previous years relating to Turnberry Homes, Town Centre Fund
Grant, Digital Inclusion, Clydebank Can on the Canal, Internet of Things Asset Tracking and Auld Street Bond.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
31 July 2022
Budget Details
Project Life Financials

Page 44

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
PERIOD END DATE
PERIOD 4
Budget Forecast Spend
£000 £000 % £000 £000 %
Spend to Date Forecast Variance
Resources Carried Forward
31 July 2022
Budget Details
Project Life Financials
5
Project Life Financials (25,429) (77) 0% (26,506) (1,077) 4%
Current Year Financials 0 0 #DIV/0! 0 0 #DIV/0!
Project Description
Project Lifecycle 31-Mar-26 31-Mar-26
6
Project Life Financials (125,200) (51,621) 41% (120,378) 4,822 -4%
Current Year Financials (57,013) 43 0% (42,873) 14,140 -25%
Project Description
Project Lifecycle 31-Mar-26 31-Mar-26
7
Project Life Financials (10) 0 0% (10) 0 0%
Current Year Financials (10) 0 0% (10) 0 0%
Project Description
Project Lifecycle 31-Mar-22 31-Mar-22
Anticipated Outcome
CFCR applied to relevant capital project.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Renovation of Unit 11 Levenside Business Court
Mitigating Action
None required at this time.
This is capital spend which is funded by revenue budgets
Prudential Borrowing
Prudential borrowing is long term borrowing from financial institutions that has been approved for the purposes of
funding capital expenditure
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Prudential borrowing is impacted by programme delivery therefore mitigating action is detailed in the red and amber analysis.
Mitigating Action
None available at this time.
Anticipated Outcome
While prudential borrowing requirement is likely to be less than budgeted in the current financial year this is anticipated to catch up over the
programme life.
CFCR
Capital receipts received.
Capital Receipts
These are capital receipts that are anticipated from sales of land and buildings both as part of the normal disposal
programme and also as part of the business case investment in office rationalisation, new school building and
new care home development
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Receipts budgets are based on assumptions in relation to the sale of various sites. Not all sales will be realised this financial year. The main
ones being OLSP, St James retail park, Dalreoch Care Home. Queen's Quay, Levenbank Terrace, Heather Avenue, Crosslet House. As agreed
at Council receipts received are used firstly to pay for principle and premiums.
Mitigating Action
While market conditions are out with officers control all potential receipts will be explored.
Anticipated Outcome

Page 45

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME APPENDIX 9
BUDGET VIREMENT
PERIOD END DATE
4
PERIOD
Project Name
Original
Budget       
£000    
Virement
Requested     
£000
Total Project
Budget   
£000
Committee Reason for Virement
Community Sports Fund 66 (66) 0 IRED Fund now closed and budget being
moved to Posties Park Sports Hub.
Posties Park Sports Hub  844 66 910 IRED New sports hub to include gym &
running track.
31 July 2022

Page 46

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME APPENDIX 10
BUDGET ACCELERATION
PERIOD END DATE
PERIOD 4
Project Name
Original
Budget     
£000      
Acceleration
from 2023/24       
£000
Revised
Budget  
£000
Spend to
Date
£000
Forecast
22/23
£000
Main Issues
Schools Estate
Improvement Plan 2,020               241                     2,261          265 2,261    
A request for budget acceleration from
2023/24 has been made for Renton
Primary School due to a part retention
payment which is due this financial year.
31 July 2022