WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
HRA REVENUE BUDGETARY CONTROL 2021/2022
PERIOD END DATE
Subjective Summary
Total Budget
2021/22                         
£000
Spend to
Date
2021/22 
£000
Actual
Spend
£000
Annual RAG
Status
Employee Costs 6,272 6,068 6,068 (204) -3% 
Property Costs 1,917 1,800 1,800 (117) -6% 
Transport Costs 110 121 121 11 0% 
Supplies, Services And Admin 394 358 358 (36) -9% 
Support Services 2,677 2,485 2,485 (192) -7% 
Other Expenditure 510 715 715 205 40% 
Repairs & Maintenance 12,860 12,581 12,581 (279) -2% 
Bad Debt Provision 1,060 1,131 1,131 71 7% 
Void Loss (Council Tax/Lost Rents) 648 1,635 1,635 987 152% 
Loan Charges 11,878 10,520 10,520 (1,358) -11% 
CFCR 7,821 13,175 13,175 5,354 68% 
Total Expenditure 46,147 50,589 50,589 4,442 10% 
House Rents 44,419 44,223 44,223 196 0% 
Lockup Rents 208 206 206 2 1% 
Factoring/Insurance Charges 1,235 1,268 1,268 (33) -3% 
Other rents 114 117 117 (3) -3% 
Interest on Revenue Balance 71 7 7 64 90% 
Transfer from Reserves 0 4,706 4,706 (4,706) 0% 
Miscellaneous income 100 137 137 (37) -37% 
Total Income 46,147 50,664 50,664 (4,517) -10% 
Net Expenditure 0 (75) (75) (75) 
Forecast Variance 2021/22                          
£000               %
31 March 2022

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
HRA REVENUE BUDGETARY CONTROL 2021/2022
ANALYSIS FOR VARIANCES OVER £50,000
MONTH END DATE 31 March 2022
PERIOD 12
Budget Actual
Spend RAG Status
EMPLOYEE COSTS 6,272 6,068 (204) -3% 
Main Issues
Budget Actual
Spend RAG Status
£000 £000 £000 %
PROPERTY COSTS 1,917 1,800 (117) -6% 
Main Issues
Budget Actual
Spend RAG Status
SUPPORT SERVICES 2,677 2,485 (192) -7% 
Main Issues
OTHER EXPENDITURE 510 715 205 40% 
Main Issues
Budget Actual
Spend RAG Status
£000 £000 £000 %
REPAIRS & MAINTENANCE 12,860 12,581 (279) -2% 
Main Issues
Variance Narrative
This budget covers central support recharges to the HRA
Variance Narrative
forecast
Variance
Budget Details
Subjective Analysis
The year end recharge for the use of central support services was lower than anticipated
resulting in a favourable variance.
Variance Analysis
The main reason for this overspend relates to an increase in rent abatement payments in
21/22 with higher costs than anticipated at time of budget setting. 
Service Description
This budget covers all repair and maintenance expenditure to houses and lockups
Budget Details
Subjective Analysis
Variance Analysis
forecast
Variance
Subjective Description
Subjective Description
This budget covers electricity, gas, rates, rents, cleaning  and insurance costs.
Variance Narrative
The main reasons for this underspend relates to the recharge for the cost of property
insurance will be more in line with last year's actual than assumed within budget.  Other
costs also have come in below budget including electricity, gas and contract cleaning.
Budget Details Variance Analysis
Subjective Analysis forecast
Variance
The underspend is attributable to a few factors.  Maintenance service contracts have been
obtained at a lower cost than budgeted.  General repairs have been less than budgeted
since the focus has been on dealing with larger jobs which fall under capital budgets rather
than revenue.  It has also not been possible to identify many suitable projects to utilise the
WDTRO budget therefore this budget remains unspent in 21/22.
Budget Details Variance Analysis
Subjective Analysis forecast
Variance
Subjective Description
This budget covers all employees charged directly to the HRA including caretakers.
Variance Narrative
The main reason for the the favourable varaince is due to recharges to HRA revenue being
lower than anticpated at time of budget setting.
Subjective Description
This budget covers rent abatements, membership fees and tenancy sustainment
Variance Narrative

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
HRA REVENUE BUDGETARY CONTROL 2021/2022
ANALYSIS FOR VARIANCES OVER £50,000
MONTH END DATE 31 March 2022
PERIOD 12
Budget Actual
Spend RAG Status
£000 £000 £000 %
BAD DEBT PROVISION 1,060 1,131 71 7% 
Main Issues
Budget Actual
Spend RAG Status
£000 £000 £000 %
VOID LOSS 648 1,635 987 152% 
Main Issues
Budget Actual
Spend RAG Status
£000 £000 £000 %
LOAN CHARGES 11,878 10,520 (1,358) -11% 
Main Issues
Budget Actual
Spend RAG Status
£000 £000 £000 %
CFCR 7,821 13,175 5,354 68% 
Budget Details Variance Analysis
Subjective Analysis forecast
Variance
Subjective Analysis forecast
Variance
Service Description
Loan Charges is made up of repayments of principle sums, and the payments of interest and expenses
Variance Narrative
The main reason for this varaince is the due to the principal repayment being lower than
anticipated at time of budget setting.
Service Description
CFCR is made up of the cost of capital funded from current reserves (CFCR)
Variance Narrative
Variance Narrative
The main reason for this adverse variance relates to the number of void properties being
higher than budgeted.  Despite restrictions being lifted and best efforts to relet properties
towards the end of 20/21, the recovery to normal numbers was not possible.  Therefore,
void numbers are starting higher in 21/22 than assumed within the budget. This is reflected
in a higher cost for void rent loss and void council tax against budget.
Budget Details Variance Analysis
Subjective Analysis forecast
Variance
Service Description
This budget covers the rents lost on void houses and lockups and the cost of council tax on void properties.
Budget Details Variance Analysis
Service Description
This budget allows for the provision for bad and doubtful debts to be maintained at an appropriate level
Variance Narrative
The Bad Debt Provision required for 21/22 was more than estimated at time of budget
setting, resulting in an adverse variance.
Budget Details Variance Analysis
Subjective Analysis forecast
Variance

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
HRA REVENUE BUDGETARY CONTROL 2021/2022
ANALYSIS FOR VARIANCES OVER £50,000
MONTH END DATE 31 March 2022
PERIOD 12
Main Issues
Budget Actual
Spend RAG Status
£000 £000 £000 %
INTEREST ON REVENUE BALANCES 71 7 64 90% 
Main Issues
Budget Actual
Spend RAG Status
£000 £000 £000 %
TRANSFER FROM RESERVES 0 4,706 (4,706) 0% 
Main Issues
Service Description
Interest received based upon the balances contained within the revenue account.
Variance Narrative
Budget set too high.  Balances vary year on year, thus making it more difficult to accurately
budget.
The main reason for the adverse varaince is due to higher than expected and an additonal
CFCR from reserves being required in 21/22.
Budget Details Variance Analysis
Subjective Analysis forecast
Variance
Budget Details Variance Analysis
Subjective Analysis forecast
Variance
Service Description
Amount transferred from reserves.
Variance Narrative
This favourable variance is due to transfer from reserves, consisting of additonal CFCR
and relase of covid funds in relation to repairs.