WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer - Resources
Council: 31 August 2022
Subject: Unaudited 2021/22 Annual Accounts
1. PURPOSE
1.1 The purpose of this report is to provide Council with a copy of the unaudited
2021/22 Annual Accounts together with information as to the 2021/22 outturn
as set out in the draft accounts.
2. RECOMMENDATIONS
2.1 Members are asked to:
a) note the unaudited 2021/22 Annual Accounts
b) note the information provided in relation to the financial
performance of the Council’s services and capital plan for
2021/22
c) note the current position regarding the Council’s reserves;
d) note that a report on the audited accounts will be submitted to
either Council or Audit Committee by 31 October 2022 for
approval
e) if required to meet the timetable for submission, Council agrees to
delegate authority to the Audit Committee to formally approve the
audited accounts by 31 October 2022, prior to submission to the
Accounts Commission.
3. BACKGROUND
3.1 The annual accounts set out the financial statements of the Council and its
group for the year ended 31 March 2022. Its main purpose is to demonstrate
the stewardship of public funds entrusted to the Council. The requirements
governing the format and content of local authorities’ annual accounts are
contained in the Code of Practice on Local Authority Accounting in the
United Kingdom (the Code). The 2021/22 accounts have been prepared in
accordance with this Code.
3.2 There is a statutory requirement to prepare a set of accounts and submit
them to the Controller of Audit. The date set by the Scottish Government for
the submission of the unaudited annual accounts is 30 June each year.
4. MAIN ISSUES
4.1 The Council’s draft 2021/22 annual accounts, including the group accounts,
were submitted the Controller of Audit before the 30 June 2022 deadline and
our external auditors (Audit Scotland) have commenced their audit.
Item 13

Page 2

4.2 The draft accounts show that the Council has been successful in managing
its 2021/22 expenditure within the budgets approved for the General Fund
with the Housing Revenue Account (HRA) reporting an in-year deficit which
is in line with the HRA financial plan to fund some capital from revenue to
reduce the cost of borrowing.
4.3 Since 2010/11, local authorities have been required to prepare financial
statements following International Financial Reporting Standards (IFRS).
Under the Local Authority Accounts (Scotland) Regulations 2014 there is a
requirement to include a management commentary in the accounts. The
contents of the annual accounts are summarised in the paragraphs that
follow.
4.4 Management Commentary: outlines the key messages regarding the
objectives and strategy of the Council and its financial performance for the
year. It also looks forward, outlining the future financial plans for the
organisation and the challenges and risks which are faced by the Council.
4.5 Statement of Responsibilities for the annual accounts: outlines the
Council’s responsibilities and also the responsibilities of the Council’s
Section 95 Officer.
4.6 Annual Governance Statement: this details the view on the adequacy of its
governance and internal control system. It is the Council’s view that the
systems for governance and internal control are operating effectively within
the Council during 2021/22 and that there are no significant weaknesses.
4.7 Remuneration Report: provides details of the remuneration policy,
remuneration and pension benefits of senior councillors and senior officers in
addition to detail on employee exit packages.
Comprehensive Income and Expenditure Statement (CIES):
4.8 This statement shows the accounting cost of providing services rather than
the amount to be funded from taxation. The Council is required to make
various statutory accounting adjustments to the net cost of services as
reported in the budgetary outturn in order to comply with the Code. These
accounting adjustments include depreciation, loans fund principal repayment
and accrued holiday leave not taken by 31 March 2022.
4.9 The Council ended the year with a surplus of £102.966m for 2021/22, this is
the accounting surplus based on the IFRS compliant accounts rather than
the movement in the General Fund Balance. The total Comprehensive
Income and Expenditure comprises of a deficit on the provision of services of
£41.992m, which is reduced by a surplus on the revaluation of Long Term
Assets of £4.917m and an actuarial gain on the pension fund assets/liability
of £140.041m.
4.10 The table below, sets out a reconciliation of the deficit on the provision of
services of £41.992m as noted in the Statement of Comprehensive Income

Page 3

and Expenditure to the revenue budget outturn of £0.159m underspend.
4.11 Balance Sheet: The Balance Sheet shows that the net worth of the Council
has increased by £102.967m from £318.629m as at 31 March 2021 to
£421.596m as at 31 March 2022. The major changes are set out in the table
below.
Movement in Reserves Statement
4.12 This shows the movement on the different reserves held by the Council,
analysed into usable reserves (resource backed reserves which can be used
to fund expenditure) and unusable reserves (required purely for accounting
purposes and are not backed by resources).
4.13 The total Council reserves have increased from £318.629m at 31 March
2021 to £421.595m at 31 March 2022, an increase of £102.966m.
4.14 The balance of unusable reserves has increased by £108.125m from
£294.418m as at 31 March 2021 to £402.543m as at 31 March 2022. The
main reason for this increase is a material reduction in the pension scheme

Page 4

liability from a liability of £163.315m in 2020/21 to a liability of £55.690m in
2021/22 (a decrease of £107.625m).  
4.15 In respect of the General Fund Balance movement, there has been a small
decrease of £0.008m from a balance of £15.028m to £15.020m.  Of that total
£11.525m is earmarked for specific purposes.  The Council has agreed to
hold a contingency balance equivalent to 2% net expenditure (excluding
requisitions) and this amounts to £3.123m. The remaining General Fund
balance (unearmarked balance) amounts to £0.372m.
4.16 Cash Flow Statement: The Cash Flow Statement shows the changes in
cash and cash equivalents of the Council during the financial year. The Cash
and Cash Equivalents decreased by £10.101m to £2.140m.
4.17 Notes to the Financial Statement: The notes section provides further
information and explanation on some of key figures included within the
Accounts. The notes conform to the guidance issued by CIPFA/LASAAC
within the Code of Practice on Local Authority Accounting.
4.18 Council Tax Income Account: This account shows the gross income raised
from council tax levied and deductions made under the Local Government
Finance Act 1992. The resultant net income is transferred to the CIES.
Council Tax rate for Band D was £1,293.55 for 2021/22 which was identical
to 2020/21 due to a council tax freeze agreed by Council as part of the
budget setting process. The income transferred to the general fund for
Council Tax in 2021/2221 was £38.207m. This compared to £36.765m in
2020/21.
4.19 Non Domestic Rate Income Account: This account is an agent’s
statement that reflects the statutory obligation for billing authorities to
maintain a separate Non Domestic Rate Account. Net Non Domestic Rate
Income to the Consolidated Income and expenditure Account amounted to
£81.408m for 2021/22. This compares to £55.963m in 2020/21, which was
artificially reduced due to the package of measures introduced by the
Scottish Government to support the Scottish businesses affected by the
COVID outbreak.
4.20 Housing Revenue Account
In relation to the HRA, the draft accounts show a balance of £2.734m as at
31 March 2022. Of this balance £1.794m is earmarked to assist in a number
of areas, including the regeneration of the Housing estate, as agreed by a
previous Council decision, leaving an un-earmarked balance of £0.940m,
which is in line with the prudential reserve target. 
4.21 Capital Programmes
Details of the capital programmes are shown in Appendix 4 (General Fund)
and Appendix 5 (HRA) and are summarised below. The appendices detail
the outturn of the projects within 2021/22 and provide further information on
the projects which have been identified as red status (i.e. those projects

Page 5

which are likely to be significantly overspent and/or to have significant delays
in completion). A list of the main capital projects progressed during 2021/22
is provided on page 16 of the Annual Accounts. The year end position is
summarised as follows:
Budget Spend Variance Overspend Underspend Slippage
£,000 £,000 £,000 £,000 £,000 £,000
General Services 56,727 33,620 (23,107) 1,934 (83) (24,958)
HRA 48,328 30,600 (17,728) 3,701 (1,503) (19,926)
Total 105,055 64,220 (40,835) 5,635 (1,586) (44,884)
4.22 The main areas of slippage in the year were:
General Services
District Heating
Expansion
Network expansion to Golden Jubilee National
Hospital will commence pending positive
commercial discussions.  
Heritage
Capital Fund
COVID impacted on the timescale for delivery of a
number of projects including Clydebank Town Hall,
the Clydebank Museum, and the Dalmuir Library
and Gallery. Work is now underway to get these
projects progressed. 
Vehicle
Replacement
Delay due to the vehicle build time associated with
the specialist vehicles and the delivery lead time
from the date of supply order placement.
Schools Estate
Improvement
Plan
As a result of COVID Skills School was rephased
during 2021/22 and further costs are still expected
for Renton Campus.
HRA
New house
build
Due to a number of different complexities there
were delays to getting on site across each of the
new build sites.
Projects to
deliver housing
strategies (Buy
Backs)
These are subject to stringent criteria to ensure
accountability and value for money for tenants and
involves several key stakeholders which resulted
in time delays
Doors/Windows Installations are behind original planned targets
due to internal and external contractor resource
issues

Page 6

Building
external
components
Resource issues has delayed the roof renewal
programme which continues into 2022/23.
Additional installations by support contractors is
underway to assist completions
4.23 Group Accounts: The Council is required to prepare Group Accounts in
addition to its own Annual Accounts. Group Accounts are prepared when a
Council has a material interest in other organisations. The purpose of the
accounts is to combine its financial information with other organisations
within its group. For 2021/22 the Council’s group consists of
(a) West Dunbartonshire Leisure Trust
(b) Dunbartonshire and Argyll and Bute Valuation Joint Board
(c) Strathclyde Partnership for Transport
(d) Strathclyde Concessionary Travel Joint Board
(e) Clydebank Property Company
(f) West Dunbartonshire Energy Company
(g) Health and Social Care Integrated Joint Board
(h) Dumbarton Common Good and Trust Funds.
4.24 The effect of combining these entities on the Group Balance Sheet is to
increase reserves and net assets by £48.600m creating an overall net asset
of £470.195m. 
4.25 Update on Transformational Projects
Following recent (but temporary) Scottish Government legislation, the
Council agreed as part of its budget for 2021/22 to use capital receipts to
fund some transformational spend. The budgeted spend approved by
Council was £0.526m, the actual spend as at 31 March 2022 was £0.383m.
Appendix 6 provides further details of these transformational projects and
the position regarding these as at 31 March 2022.
Next Steps
4.26 To enable the Council to meet its legislative requirements, Members require
to approve the audited Annual Accounts for signature no later than 31
October 2022. Therefore, depending on progress in auditing the accounts
the audited accounts will be presented to a future Council before 31 October
2022.
Charity Accounts
4.27 Appendix 7 provides Members with the accounts of the Trust Funds which
are administered by the Council. These Financial Statements are also
audited by our external auditors prior to submission to the Office of the
Scottish Charity Regulator (OSCR). The draft Financial Statements 2021/22
were presented to Audit Scotland on 28 April 2022. As noted at 4.24 above
these are also included within the Council’s Group position.

Page 7

The main movements within the Trusts are noted below – interest gained
was received for all trusts, with one grant payment made (Dr AK Glen).
Opening
Balance
£
Receipts
£
Payments
£
Closing
Balance
£
Educational Trust Scheme 90,433 62 0 90,495
McAuley Prize for
Mathematics
21,884 14 0 21,898
Alexander Cameron
Bequest
117,776 2,492 0 120,268
Dr AK Glen 24,732 16 (19,800) 4,947
UIE Award 24,741 16 0 24,757
Cash and Bank 279,565 2,600 (19,800) 262,365
Educational Trust Scheme 218 0 0 218
Investments 218 0 0 218
Overall Total 279,783 2,600 (19,800) 262,583
The audited Trust Fund accounts will be approved by the Council, together
with the Council’s Financial Statements, but will be presented to the Trust
Committees separately.
4.28 Common Good
Appendix 8 provides Members with the accounts of the Dumbarton Common
Good which are administered by the Council, also audited by our external
auditors as part of the year end process. As noted at 4.24 above this is also
included within the Council’s Group position.
The main movements within the common good are noted below:
£
Opening Balance 520,642
Income 320,272
Expenditure (259,602)
Closing Balance 581,312
CONCLUSION
4.29 The Unaudited Annual Accounts have been prepared in accordance with
professional and statutory requirements. The General Fund Balance has
decreased by £0.008m, after taking into consideration the movement during
the year, the end of year outturn position and earmarkings. The net worth
per the balance sheet has increased by £122.814m to £468.184m. Overall
the financial position of the Council remains stable.
5. PEOPLE IMPLICATIONS
5.1 There are no people implications as a consequence of this report.

Page 8

6. FINANCIAL AND PROCUREMENT IMPLICATIONS
6.1 There are no direct financial or procurement implications arising from this
report.
7. RISK ANALYSIS
7.1 No risk analysis was required
8. EQUALITIES IMPACT ASSESSMENT (EIA)
8.1 No equalities impact was required in relation to the preparation of this report.
9. CONSULTATION
9.1 The views of Legal Services have been requested on this report and have
advised there are neither any issues nor concerns with the report.
10. STRATEGIC ASSESSMENT
10.1 Sound financial practices are cornerstones of good governance and support
Council and officers to pursue the 5 strategic priorities of the Council’s
Strategic Plan.
Laurence Slavin
Chief Officer - Resources
Date:   31 August 2022
Person to Contact: Gillian McNeilly, Finance Manager, 16 Church Street, Dumbarton 
E-mail: gillian.mcneilly@west-dunbarton.gov.uk
Appendices
1. Draft Annual Accounts to 31 March 2022 for West Dunbartonshire
Council
2. General Services Budgetary Control Report to 31 March 2022 – Revenue
3. HRA Budgetary Control Report to 31 March 2022 – Revenue
4. General Services Budgetary Control Report to 31 March 2022 - Capital
5. HRA Budgetary Control Report to 31 March 2022 - Capital
6. Update on transformational spend 2021/22
7. Draft Annual Accounts to 31 March 2022 for Trust Funds
8. Draft Position to 31 March 2022 for Dumbarton Common Good
Background Papers
Budget Report to Council - 22 March 2021
Budget Report to Council - 9 March 2022
Local Government Finance Circular 4/2019 – capital receipts to fund
transformational projects