Learning Estate Investment Programme (Leip): Mull Campus Update

Argyll and Bute Council · 25 April 2024
Back to Argyll and Bute Council — 25 April 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

1 
ARGYLL AND BUTE COUNCIL                                                         COUNCIL                                                                          
COMMERCIAL SERVICES, EDUCATION
AND FINANCIAL SERVICES                                          25TH APRIL 2024 
LEARNING ESTATE INVESTMENT PROGRAMME (LEIP) 
MULL CAMPUS UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 The purpose of this report is to update Council on the Council’s Learning Estate
Investment Programme (LEIP) project to deliver a New Campus on Mull.  LEIP
is the Scottish Government’s flagship investment programme for Education
which was a competitive bidding process, and it was confirmed in October 2023
that Mull had been successful in winning access to the fund.  This has created
an exciting opportunity to create a once in a generation investment in Education
community infrastructure for the island, however the level of financial
commitment from the Council is significant and must be carefully considered. 
Mull was chosen to be the Council’s sole bid to LEIP and number one priority
for strategic investment in Education due to being the only secondary school in
Argyll and Bute to be graded as ‘Poor’ in terms of learning suitability. 
1.2 This report follows on from, and should be considered in conjunction with the
associated update reports, discussion and minutes on the same subject matter
from Policy & Resources Committee dated 15th February and Council dated
22nd February.  It is also noteworthy there was a Deputation made at the Council
meeting in February by community members on Mull, including Parent Council
representatives in relation to this subject matter. 
1.3 At the 22nd February Council meeting it was agreed that no decision, as to
whether or not to proceed with the Mull Campus should be taken at that time
and that officers were asked to prepare a further report with more detail
regarding the financial aspects and affordability of LEIP and hold a Members
Seminar.  This report aims to fulfil that request and it is confirmed that a
Members Seminar took place on 12th April.  
1.4 In the context of the additional detail contained here within, Members must now
determine whether they consider the LEIP project to be affordable – or not -
and require to adequately plan for capital and revenue implications of that
preferred outcome.  This must be done whilst being aware of the economic,
community and educational implications of their decision.

Page 2

2 
ARGYLL AND BUTE COUNCIL                                                         COUNCIL
COMMERCIAL SERVICES, EDUCATION                                         25TH APRIL 2024
AND FINANCIAL SERVICES 
LEARNING ESTATE INVESTMENT PROGRAMME (LEIP)
MULL CAMPUS UPDATE 
2.0 INTRODUCTION 
2.1 This report follows on from, and should be considered in conjunction with the
associated update reports, and minutes from the Policy & Resources
Committee of 15th February and the Council of 22nd February 2024.  Members
will recall that there was a Deputation heard at the Council meeting on 22nd
February by community members on Mull, including Parent Council
representatives in relation to LEIP, and it was decided:- 
“in the light of the update on funding, that no decision as to whether or not to
proceed be taken at this time and that officers prepare a further report with more
detail regarding the financial aspects and affordability of LEIP, to be the
subject of a Members Seminar and then brought to the Council meeting in April
2024 for members’ consideration.” 
3.0 RECOMMENDATIONS 
3.1 Council are asked to: 
a) Note the capital and revenue implications of the LEIP / Mull Campus project
which are of a strategic financial nature; 
b) Determine in light of the financial  information provided, whether they
consider the project to be affordable at this time and if so, agree that up to
£5m from the previously earmarked LEIP funding be used to; commence the
Business Case, undertake engagement exercises, commence site selection
process and establish governance arrangements with updates being brought
back to Members at appropriate gateway points; 
c) Acknowledge that if they consider the LEIP / Mull Campus is unaffordable
then an allocation of funding for the refurbishment for the existing Tobermory
Campus will be required with details to be brought back to a future meeting
of the Policy & Resources Committee for approval;

Page 3

3 
d) Note the information provided in regard to the Economic, Community &
Educational implications relative to the proposed Mull Campus as outlined in
the bid and previous reports and that these will be considered further if the
project proceeds to a full business case; and 
e) Note if Members do proceed with LEIP / Mull Campus Project then capital
and revenue budget provision will require to be built into future budget
estimates and approved as part of budget setting process. 
4.0 DETAIL 
4.1 LEIP and Partnership Model  
Background 
4.1.1 Unlike previous and other funding delivery models for new school projects (like
Oban High School or Campbeltown Grammar), LEIP is not a grant nor does it
address the total cost of a project. This is the third round of LEIP Funding and
the first time Argyll & Bute have applied to access the fund and there have been
10 successful projects in this latest round including Orkney, Moray and
Shetland.  The LEIP funding will cover up to 50% of eligible costs and Scottish
Government (SG) will then pay their contribution over 25 years.  Given that
capital costs are, in effect, split over a period of time by the Council and SG this
is referred to as a partnership model where both parties seek to achieve shared
outcomes within parameters of a national set of metrics.  This means that the
total project cost including construction, design, fees, land acquisition (if
required) and build costs will require to be met -up front - by the Council with up
to 50% being recouped in coming years.  The Council is aware of other local
authorities in earlier LEIP phases whose settlement rates have been much
lower than 50% of overall project costs.   This is because their design or
circumstances will include a number of ‘non eligible costs’ – which is covered
in detail below and at Appendix A. 
4.1.2 The LEIP funding model is also predicated on achieving a number of quality,
environmental, space, function and condition standards.  In effect, this will
create a high standard of building that should be sustainable and flexible – this
is a higher benchmark standard to any new buildings (including schools) the
Council has delivered in recent years.  Ensuring the buildings are digitally
enabled and support local economic development is also encouraged.  The full
list of conditions is as follows:- 
• Internal Environmental Quality -suitable internal environment for building
users is vital for their health, wellbeing and learning. 
• Internal Monitoring (use of sensors to ensure the highest quality internal
environment is delivered as a response to Covid 19 in terms of ventilation
and CO2 levels)
• Zero Emissions Heating
• Electrical Vehicle Charging

Page 4

4 
• Healthier Learning Environments
• Infrastructure Technology 
4.1.3 Scottish Government (SG) funding will be available through the Outcomes
Based Funding (OBF) model.  The outcomes include:
• Condition - Local authorities must provide evidence, through their annual
returns that the facility is kept in condition A or B for a period of 25 years.
Note if it falls below ‘B’ then there is risk that Council will not receive full
payment from SG.   
• Energy Efficiency – Must meet a threshold energy efficiency rating during
use throughout life of building with building users active.  Note if this
standard is not met during building operation there is risk the Council will
not receive full payment from SG. 
• Digitally Enabled Learning – This condition will be achieved at completion
of build so funding will be guaranteed.   
• Economic Growth - This condition will be achieved at completion of build
so funding will be guaranteed.   
• Construction Embodied Carbon - This condition will be achieved at
completion of build so funding will be guaranteed.   
4.1.4 Building modern schools to high digital and environmental standards comes at
a cost premium and this increases significantly when island weighting is applied
due to the logistical challenges of getting labour and materials to site. The LEIP
funding structure as outlined means if progressed the Mull Campus Project will
be one of highest value projects the Council has ever delivered in terms of up-
front costs so strong commitment to the project and its resourcing is required.
As a comparison Oban High School which was completed in the last 5 years
and catering for a roll of 1,300 pupils cost under £40m. 
Eligible Costs 
4.1.5 It should be noted that not all overall project costs are LEIP ‘eligible’.  This needs
to be considered carefully during the design development phases and in the
context of overall affordability because they would not be funded at all by the
SG and Council would need to meet 100% of cost or identify another funding
source. In summary terms, LEIP eligible costs are educational learning spaces
(school rooms / facilities) or ‘like for like’ community styled facilities that already
exist at the current Tobermory Campus – for example a community library,
college rooms or pitches.  Examples of ‘Non-eligible’ costs include purchasing
of land (if required), creation of Community Spaces that are not currently
present like a swimming pool or Customer Contact Point.  School Hostel
accommodation is also clearly not eligible expenditure and out of scope of the
project at this stage.  The cost of borrowing or financing the project is also not
an eligible cost and will not be paid for by SG payment.

Page 5

5 
4.1.6 LEIP funding will also cover some costs if there are challenging ground
conditions once a site has been selected and ground investigations have been
undertaken if both parties agree there are ‘excessive abnormal costs’.  The
maximum SG will underwrite is 50% of these costs.  Dealing with abnormal site
conditions is well established industry practice for major projects and can
include scenarios that may arise if there is substantial rock cutting required,
issues with utility connections, peat removal for example.  None of this can be
clarified at this stage as no site has been selected and no ground investigations
undertaken. 
4.1.7 The SG and Scottish Futures Trust (SFT) have also intimated that a project on
Mull may be eligible for additional funding due to its island location, recognising
it costs significantly more to construct major complex buildings in remote
locations.  Whilst this additional ‘locational uplift’ is not currently written into the
conditions of funding or LEIP agreement they have confirmed there is precedent
with other rural and island LEIP projects and it is likely  a similar approach could
be applied to the Mull Campus project.  Locational factors would cover the
known additional costs that relate to construction in island or rural areas such
as cost of raw materials, costs of labour, travel, extra build time, extreme
weather and waste disposal.   
4.1.8 An indicative table of eligible costs is provided in Appendix A for ease of
reference. 
4.1.9 The Mull Campus Team and Financial Services have met with SG and SFT
since the Council meeting on 22nd February.  They have confirmed that based
on current information relating to the Mull Campus Project and LEIP Funding
Model at present that the scenarios outlined in this report and at the Members
Seminar are reasonable assumptions to be attributed to SG funding that would
be provided.  The new ‘Locational’ factor referenced at para 4.1.7 above may
improve the situation however, it must be stressed these are theoretical
forecasts at this stage and the costs and percentages will change as the project
develops, site and design are progressed and costs crystalise.  The final cost
will not be confirmed until financial close and contract awards currently
programmed for FQ4 2026. 
4.2 Financial Modelling 
4.2.1 At the time of writing this report, the estimated total project cost for developing
a new Campus on Mull is £43m, with £41m considered to be an eligible LEIP
cost as outlined above.  There has been no preferred site selected at this stage
and an indicative £1m has been included in the total project costs in the event
that land will need purchased and developed as well as a further £1m of
moveable fixtures and IT – both these costs are not eligible for LEIP funding. 
The construction costs are based on nationally recognised metrics for
construction of LEIP projects across Scotland that have been tailored to a
school the size of Mull and also by applying an island weighting factor.  The
construction costs are estimates, they are not tender prices but rather justified
financial forecasts at this stage based on industry experience.  Factors that will
significantly impact costs include; the preferred site selected, design of campus,

Page 6

6 
community facilities and availability of infrastructure. Any delays or unforeseen
increases in inflation or construction materials (ie global factors as we have
seen in recent years) would also impact cost estimates. 
4.2.2 The location of the Campus also has the potential to impact on the total project
cost and other operational/pupil transport costs within the Council’s revenue
budget. 
4.2.3 A number of financial scenarios are detailed within Appendix B. Scenarios A
to C are based on the costs of construction remaining at current estimated
levels with varying levels of funding contribution from the Scottish Government
with a best case scenario of 50% in Option A reducing down to 45% in Option
B and 40% in Option C. 
4.2.4 Scenarios D to F are based on the costs of construction increasing by 10% and
again with the varying levels of funding contribution from the Scottish
Government. 
4.2.5 The funding model for LEIP sees the Council paying the total project cost up
front with the LEIP contribution from the Scottish Government paid over 25
years.  The Council has £9m set aside within earmarked reserves towards the
new school, however, there will be a requirement for the Council to borrow for
the remaining value.  In line with the Council’s treasury strategy, borrowing for
a school would be repaid over a 60 year term, being the period where we are
expected to get benefit from the asset.     
4.2.6 The interest on borrowing is significant due to the level of borrowing and the
period of borrowing.  In scenarios A to C the interest is £75m and in scenarios
D to F the interest is £84m.  When adding the interest onto the Council share
of the project costs, the total cost that the Council will be funding is between
£98m and £113m.  This produces a much higher contribution rate than was
originally envisaged by the 50:50 funding model, with the contribution from the
Council being closer to 85%.  This is due to the Council having to borrow for
both some of their share of the cost and also for the share that the SG is
contributing to (the SG do not pay for the financing costs).     
4.2.7 The cost of borrowing will be a pressure on the Council’s revenue budget.  As
outlined within the scenarios in Appendix B the cost of borrowing is estimated
to be between £1.004m to £1.319m over the first 25 years, rising to between
£1.822m and £2.038m for the next 35 years when the contribution from the
Scottish Government ends.  This is a significant cost pressure on an already
challenging budget outlook position.  The new ‘Locational’ factor referenced at
para 4.1.7 above may improve the financial sum paid by the SG but at this stage
the 50% - 40% scenarios are considered a fair reflection of potential outcomes. 
4.2.8 The Council will need to consider whether this level of cost pressure is
affordable or not.  It will only be affordable if Council accept that difficult
decisions will be required in order to pay for the new school.  For example, the
cost of borrowing in the first 25 years could be paid by an additional 2% in
Council Tax or it could be paid by reducing/removing some other Council

Page 7

7 
services, for example, toilets, library services, swimming pools, amenity
services, roads maintenance.  None of these alternatives are easy or would be
what we would like to reduce, however, the reality of the future budget outlook
means that difficult decisions will be required to balance the budget without the
new school, but even more difficult decisions will be required to balance the
budget with the additional cost that a new school brings. 
4.2.9 A decision is required as to whether to progress with the plans for a new school
campus on Mull with a final decision expected once the Final Business Case
and tender prices are known.  If Council do agree to progress, then there will
be significant expenditure incurred prior to the final decision, for example,
project team, consultations, outline business case, site selection and full
business case.  It is estimated that costs could be in the region of up to £5m
and would be funded from the current earmarked reserve set aside for the
school.  This is not additional to the project costs outlined in paragraph 4.2.1
but Members need to be aware that should the Council, after tender prices are
known, decide not to proceed, these costs will be abortive costs and would
therefore reduce the level of funding available for any refurbishment.     
4.3 Community, Economic & Education Implications 
4.3.1 Given the financial implications of LEIP the main purpose of this paper is to
outline the possible financial scenarios and in order to consider affordability. 
However, as signposted in the bid and acknowledged during debate at the
Council meeting on February 22nd February, finance is only one factor, albeit
an important one, that needs to be considered in reaching a decision.  The
paragraphs that follow outline the other issues to be considered.     
Community Implications 
4.3.2 The Council’s Learning Estate Strategy 2021 outlines ambition for our assets
to not simply function as schools but be available for the community much more
broadly as key community infrastructure. The Council already has ‘Campus’
facilities in Rothesay and Lochgilphead with all the Secondary Schools
providing varying degree of community facilities – some bookable through Live
Argyll. 
4.3.3 Community spaces that would be included within the LEIP funding would be a
comparable sized to existing sports hall, pitches (MUGA, 3G and grass), library
and further education facilities that the community could access.  These would
be modern and enhanced facilities in comparison to those currently at
Tobermory.  A range of other community spaces – which are unlikely to be LEIP
eligible – may be identified through the design process and if agreed would
required to be funded 100% by Council or other funding sources. 
4.3.4 A modern campus – plus the indirect achievement increases that a new building
can bring - also has potential to be a wider attraction for families wishing to stay
on, or relocate to the island and thereby having positive impact on socio-
demographics.  Some families who currently board their secondary school age
children in Oban or plan to do so in the future may reconsider this if a new

Page 8

8 
Campus on Mull fits their needs and desires.  However, it is acknowledged that
this is a personal matter for each family to consider and may prefer their children
to attend Oban High School.   
Economic Implications 
4.3.5 The level of investment that is forecast with LEIP would make it one of the most
substantial community infrastructure projects on the island in a generation.  
Investment on this scale has potential to act as an anchor development and
create other inward investment or unlock other funding streams.  For example,
we have seen new a school development in Helensburgh act as a growth point
with new supermarket, business park and housing either now built or achieving
planning permission adjacent to it.   
4.3.6 New learning facilities also have the potential to attract business investment
from certain vocational industries. There are examples of ‘commercial hubs’ for
industries such as renewable energies and aquaculture being developed in
schools and colleges across the north of Scotland and UHI Argyll  have multiple
local links with employers looking to upskill the workforce in Argyll and Bute. 
Such opportunities would be explored further as part of the business case
development process. 
4.3.7 The LEIP conditions also carry a requirement for skills and economic benefits
to be shared with the local community and workforce.  This will be a significant
construction programme with many of subcontractors and suppliers either
directly or indirectly impacted by a major new building.  New and modern
technologies and construction methods will be deployed focusing on energy
efficiency and there will be opportunities for apprenticeships, learning and
legacy of skills. 
4.3.8 In addition to the direct benefits of the capital works being done on Mull the
building of a new campus building will also send out a powerful message to
existing, and new residents, that the island of Mull is a community with a
strong and vibrant future. This supports the Council’s central ambition to grow
our economy through a growing population and underscores the value the
Council places on education and how it improves people’s life choices.  The
new school will also help facilitate a range of different services and activities
that will positively impact on people’s health and wellbeing helping again to
sustain economic growth on this island. Community wellbeing will be an
overarching theme of our new economic strategy with the importance of skills
and education emphasised as a key element of this. 
4.3.9 Education Implications 
4.3.10 A new Campus on Mull will ensure that accessibility for all including learners
with disabilities complies with the Council’s Accessibility Strategy and the
Equality Act (2010).  It will be designed in such a way as to promote accessible
and inclusive learning which will meet the needs of all learners including those
with Additional Support Needs.

Page 9

9 
4.3.11 It will also provide an improved wireless-enabled learning environment to allow
use of devices throughout the campus, and promote digital literacy and
independence in learning.  Further, the increased use of devices would promote
the use of specialist and alternative technologies for pupils with additional
support needs as they access the wider learning environment across the
campus. 
Equity of access to broader opportunities; 
4.3.12 A new campus on Mull, with shared and flexible learning spaces, would
encourage staff to work more collaboratively and provide increased
opportunities for pupils to work co-operatively, supporting depth, pace, and
challenge in learning.  It will provide excellent facilities for children, families, and
other users out with core school hours and will support engagement across the
community. Education is more than just the building, schools are at the heart of
their communities and learning is enriched when pupils can access the
community as part of both their formal and informal education.  
4.3.13 Spaces for learning will be designed in such a way as to allow a range of
learning and teaching approaches including active, interdisciplinary, and
outdoor learning.  New and flexible learning environments inspire pupils and
have a positive impact on health and wellbeing.  They can also improve ethos,
aspirations, attainment, achievement, and positive destinations beyond school.    
The environment for learning 
4.3.14 A new building will be fully responsive to future learning requirements and the
design process will ensure that all spaces support learning and teaching styles
of the 21st Century.  It will be designed to be an inspiring learning environment
which is fully able to support new and innovative digital learning and engage
pupils with the curriculum. 
4.3.15 Facilities such as science labs, technology workshop, Gaelic immersion space,
music suites, and library will support and enhance learning. These facilities will
also benefit pupils who access mainstream or learning centre provision learning
arrangements across the wider campus.  Outdoor Learning will also be
improved for all learners and will be at the heart of the design process. This will
provide enhanced opportunities for learning beyond the classroom for all
learners.    
Improved educational outcomes. 
4.3.16 All of these educational benefits will deliver improved educational outcomes for
children and young people included further developing positive ethos
engendered by the inspiring surroundings and environment, and the pride
pupils, families and the whole community feel in a new Campus.

Page 10

10 
4.4 Programme 
4.4.1 There has been approximately 1 year delay in the funding announcement from
the SG, however the Mull Campus Team have updated the project delivery plan
which can be found at Appendix C  –with key milestones being as follows if the
project is considered affordable and proceeds at today’s meeting:- 
• Q2 2024 – Engagement/Consultations begin (community / statutory)
• Q2 2024 – Site Selection process begins
• Q2 2025 – Design development, cost plan begin 
• Q4 2025 – Planning, detailed cost, contracts to construct
• Q4 2025 – Outline Business Case Approval*
• Q4 2026 – Full Business Case Approval (approve tender)*
• Q4 2026 to Q4 2028 – Construction 
• Q4 2028 – new campus open 
*Subject to full Council meeting and gateway or key decision point (see
para 4.4.3)  
4.4.2 Members must note that the original requirement to open the campus by
December 2027 remains in place in the funding letter received in October 2023. 
This does not have regard to the delay occasioned by the delay in the funding
announcement.  Therefore, it remains a risk that our project if delivered to the
forecast timescales as outlined above may not be eligible for funding due to not
meeting timescale conditions.  SFT are aware of this issue – which is shared
with other Council’s in LEIP3 – and there are other projects which have been
granted extensions in earlier phases.  It would be the intention of the Mull
Campus Team to inform the SG formally about an extension if the project is
deemed affordable and is to proceed with an updated programme. 
4.4.3 If the project is to proceed, an Officers Team will be established to undertake
the operational work necessary to drive the project forward.  This will include a
number of professional officers from Education, Commercial, Financial and
other relevant services plus external advisors or consultants as
appropriate. There will be ‘gateways’ or ‘key decision points’ of the project
which will be taken to Members at appropriate stages for consideration and
approval.  This is likely to be key milestone points such as; approval of outlined
business case + site selection (expected late 2025), approval of full business
case and acceptance of tender price to construct (expected late 2026).  At all
of these stages overall affordability will be reviewed and certainty over cost will
be crystallised as the project develops.   
4.5 REFURBISHMENT OPTION 
4.5.1 If the LEIP project is considered unaffordable then an alternative programming
of works will require to be devised, for the refurbishment project of the
Tobermory Campus progressed and appropriately funded. At the existing
Tobermory Campus there is a range of school buildings in terms of style,
condition and age from 1930’s to 2010’s.  A bespoke approach will be taken to
each depending on need and available resources.  Approximately £1.3m has

Page 11

11 
been expended on the buildings in the last 7 years however suitability remains
at a Category C ‘Poor’ grading for certain elements due to age and layout of the
buildings which were provided for education of a previous era.  There is no, low
cost option and persistent fabric issues with water ingress and roughcasting
remain. 
4.5.2 The majority of expenditure for a refurbishment would require to be spent on
building fabric issues such as roof upgrades, window replacements, render
works, rewiring and electrical works to extend the lifespan of the asset and
address other current known issues.  The Council’s School estate is varied and
there are some buildings even dating back to the early 1900’s that have been
upgraded to high standard – Dunoon Primary School is a prime example of this
and refurbishment can extend functional lifespan of building for decades.  In all
buildings the importance of proactive maintenance is essential to prolong
quality of the asset. 
4.5.3 The refurbishment option would aim to address some suitability (quality of
learning spaces) issues identified in the building however it will not be able to
address all of them.  For example, the large number of level changes / stairs,
separate buildings and in places narrow corridors and general accessibility
issues will largely remain as per existing. 
5. CONCLUSION 
5.1 The successful bid for LEIP funding has been a welcomed opportunity for
Members to closely consider the construction of a new Campus on Mull.  Without
LEIP funding there would be insufficient funds available to the Council to consider
a new facility of this scale on the island. The Council has a strong track record of
building new schools over the past 15 years in Argyll and Bute, however for
reasons set out in Section 4, above, the overall costs and budget implications for
the Council are large and therefore must be financially planned for now and in
future years if deemed to be affordable. 
6.0 IMPLICATIONS
6.1 Policy  - The Council’s Learning Estate Strategy 2021 sets out an ambition to
have Schools in category A or B in terms of suitability and condition plus a
number of other modern standards.  Delivering a new Campus on Mull is No1
priority in that overall strategy and is also a Corporate Priority. However, this
ambition must be weighted up in reality of resources available to the Council
and ability to set a balanced budget.  
6.2 Financial - Accessing LEIP is a significant financial commitment to the Council
due to the partnership model outlined above.  The SG would then provide up to
50% of eligible capital costs back over 25 year annual payment if criteria is met. 
There is risk in this model should criteria not be met and also in terms of risk of
construction in current climate so specific financial and affordability advice from
Section 95 Officer has been afforded.  This is one of largest ever capital projects
ever undertaken by the Council is of strategic financial importance.

Page 12

12 
6.3  Legal - Accessing LEIP is a significant contractual and legal commitment to
the Council which will be duly considered if move to next stage. 
6.4  HR -  None at this stage.  Considered at future stages as Mull Campus Team
is established if progress.
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics – A new Campus on Mull
would create a more accessible Learning Environment than current
Tobermory Campus arrangements.  Assessments will be scoped during
business case development. 
6.5.2   Socio-economic Duty – The level of investment in a new Campus will
be substantial and Scottish Government have set requirements to
deliver socio economic benefits if progressed.  Assessments will be
scoped during business case development. 
6.5.3  Islands Duty - If progressed this investment will bring positive
infrastructure to the Mull and wider impacts / implications will be fully
assessed as part of Business Case development and design process. 
Assessments will be scoped during business case development.
6.6 Climate Change - The construction of the building is taking into consideration
climate change and there are specific funding conditions relating to Climate
Change and low energy construction. 
6.7 Risk - Risks exists both in terms of financial and reputational.  If progress to
next project stages a risk register will be developed.  
6.8  Customer Service - Pre-engagement was undertaken as part of the bid
process and will be ongoing throughout the development of the business case
if progressed.  
6.9 The Rights of the Child (UNCRC) - Pre-engagement was undertaken with
young people in Schools across Mull and surrounding islands as part of the bid
process and will be ongoing throughout the development of the business case
and project if progressed.   
Douglas Hendry
Executive Director with responsibility for Commercial Services & Education 
Kirsty Flanagan
Executive Director for Financial Services + S95 Officer 
16th April 2024

Page 13

13 
For further information contact: 
Head of Commercial Services – Ross McLaughlin
Head of Education and Lifelong Learning + Chief Education Officer – Jen Crocket
Head of Education – Learning and Teaching - Wendy Brownlie
Head of Financial Services – Anne Blue 
APPENDICES
Appendix A – Eligible Costs
Appendix B – Financial Scenarios

Page 14

14 
APPENDIX A – ELIGIBLE COSTS
ELIGIBLE LEIP COSTS (50% Funding) NOT LEIP ELIGIBLE (Council 100%)
‘Like for Like’ Learning Spaces
• Condition Project / not expansion
• Part of existing school
• Classrooms, indoor sports facilities,
ELC, ASN
• Production kitchen
• Outdoor sports – pitches, tennis
New or larger Spaces
• Eg Pool, hostel, larger gym,
Community only meeting
spaces, Service Point,
Vocational Training (salon,
garage workshop)
• Commercial Hubs – renewable
energy, aquaculture 
‘Like for Like’ Community Spaces
• Library, Gym, Sports Hall, College
Land Acquisition or Decant
Accommodation 
Excessive Abnormal Construction
Costs depending on site
Moveable IT Equipment (laptops /
computers) 
Location Factor 
• New measure from SG (% TBC) 
Design, Internal Team and Consultancy
Fees

Page 15

15 
APPENDIX B – FINANCIAL SCENARIOS 
Cost of Project
Scenario A
SG Fund 50%
£000
Scenario B
SG Fund 45%
£000
Scenario C
SG Fund 40%
£000
Scenario D
10% increase
in costs and
SG Fund 50%
£000
Scenario E
10% increase
in costs and
SG Fund 45%
£000
Scenario F
10% increase in
costs and
SG Fund 40%
£000
Cost of Construction 40,121 40,121 40,121 44,133 44,133 44,133
Estimated cost of Project Team  800 800 800 800 800 800
Costs not eligible for SG funding:      
Estimated Cost of Land 1,000 1,000 1,000 1,000 1,000 1,000
Estimated Cost of Moveable Fixtures and IT 1,000 1,000 1,000 1,000 1,000 1,000
Total estimated Project Cost 42,921 42,921 42,921 46,933 46,933 46,933
Funding previously Earmarked for LEIP (9,000) (9,000) (9,000) (9,000) (9,000) (9,000)
Total estimate Project Cost still to be
funded
33,921 33,921 33,921 37,933 37,933 37,933       
Estimated Funding from SG 20,460 18,414 16,368 22,467 20,220 17,973
Council Funding Required:       
Costs payable by Council in excess of
earmarked reserve
13,461 15,507 17,553 15,467 17,713 19,930
Earmarked Reserve 9,000 9,000 9,000 9,000 9,000 9,000
Interest cost of borrowing over 60 years 75,405 75,405 75,405 84,324 84,324 84,324
Funded by Council 97,866 99,912 101,958 108,791 111,037 113,284
Overall Funding 118,326 118,326 118,326 131,257 131,257 131,257
Percentage Funded by Council (including
borrowing)
83% 84% 86% 83% 85% 86%

Page 16

16 
Annual Borrowing Costs
Scenario A
SG Fund 50%
£000
Scenario B
SG Fund 45%
£000
Scenario C
SG Fund 40%
£000
Scenario D
10% increase
in costs and
SG Fund 50%
£000
Scenario E
10% increase
in costs and
SG Fund 45%
£000
Scenario F
10% increase in
costs and
SG Fund 40%
£000
Net cost of borrowing – first 25 years 1,004 1,085 1,167 1,139 1,229 1,319
Net cost of borrowing – remaining 35 years 1,822 1,822 1,822 2,038 2,038 2,038       
Smoothed cost of borrowing over 60 years 1,481 1,515 1,549 1,663 1,701 1,738