APPENDIX 3
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
MONTH END DATE
PERIOD 10
Spend to
Date Spend to Date
£000 £000
Red
22 71.0% 29,153 66.9% 22 71.0% 29,153 66.9%
Green
9 29.0% 14,420 33.1% 9 29.0% 14,420 33.1%
31 100% 43,573 100% 31 100% 43,573 100%
Budget Spend to
Date
Forecast
Spend Forecast Variance Budget Spend to Date Forecast
Spend
Forecast
Variance Reprofiled Over/
(Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
262,722 29,153 201,020 (61,702) 102,743 29,153 36,404 (66,339) (5,185) (61,154)
104,007 14,420 100,583 (3,423) 22,103 14,420 19,276 (2,827) 272 (3,099)
366,729 43,573 301,603 (65,125) 124,846 43,573 55,680 (69,166) (4,912) (64,253)
366,729 43,573 301,603 65,125 124,846 43,573 55,680 69,166
0 0 0 0 0 0 0 0
TOTAL RESOURCES
NET EXPENDITURE
Projects are forecast to be overspent and/or significant delay to
completion
Green
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
TOTAL EXPENDITURE
Project Status Analysis
Project Life Financials Current Year Financials
Red
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
31 January 2024
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project Spend at
RAG Status
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project
Spend at RAG
Status
Red
Projects are forecast to be overspent and/or experience material delay
to completion
Green

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 10
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials 2,814 2,509 89% 5,489 2,675 95%
Current Year Financials 525 2,509 478% 3,200 2,675 510%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
2
Project Life Financials 1,493 56 4% 1,493 0 0%
Current Year Financials 529 56 11% 154 (375) -71%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
3
Project Life Financials 10,000 0 0% 10,000 0 0%
Current Year Financials 2,000 0 0% 500 (1,500) -75%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
4
Project Life Financials 750 0 0% 750 0 0%
Current Year Financials 250 0 0% 0 (250) -100%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-25
31 January 2024
Budget Details Project Life Financials
Spend to Date Variance
Capitalised minor works
This is a budget to undertake specific minor ad hoc capital projects that arise on demand throughout the
financial year. 
Planned End Date  Forecast End Date
Better Homes Priority Budget
Priority projects as prioritised by the Better Homes Group 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
A number of priority initiatives, supported by the Better Homes Project Board,  are being investigated and are envisaged to have a positive
impact on the current council housing stock and budget.  Due to time taken to progress projects, it is likely there will be some reprofiling to
24/25.
Main Issues / Reason for Variance
Budget is expected to overspend due to costs and demand for budget being higher than anticipated at time of budget setting.
Mitigating Action
Officers in discussion to identify possible mitigation
Anticipated Outcome
Project to complete over budget
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Environmental Sensors Programme 
Environmental sensors programme, funded by enhanced housing investment programme. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Project introduced as part of the enhanced capital programme, with aim to install an environmental sensor in every Council owned property. 
Installation of sensors has commenced, albeit later than originally anticipated.  Remaining current year budget to be rephased to 24/25 for
continuation of project.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Housing CCTV Installation Programme
CCTV Installation Programme, funded by enhanced housing investment programme 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works to progress as part of enhanced capital programme for 23/24 and to be led by Council CCTV team.  Due to survey and planning
time, works are commencing later than anticipated, with unspent budget required to be rephased to 24/25 for project progression.
Mitigating Action
None required
Anticipated Outcome
Full budget spend

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 10
Budget Forecast Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details Project Life Financials
Spend to Date Variance
5
Project Life Financials 203 0 0% 103 (100) -49%
Current Year Financials 116 0 0% 16 (100) -86%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
6
Project Life Financials 209 0 0% 174 (34) -16%
Current Year Financials 71 0 1% 37 (34) -48%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
7
Project Life Financials 17 0 0% 17 0 0%
Current Year Financials 17 0 0% 0 (17) -100%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
8
Project Life Financials 36 36 99% 36 (0) -1%
Current Year Financials 36 36 99% 36 (0) -1%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Planned End Date  Forecast End Date
Main Issues / Reason for Variance 
Development of QL system to carry on through 24/25.  Salaries of staff directly involved with development of system to be coded to direct
project support.
Mitigating Action
None required
QL Development
This budget relates to the costs associated with the development of the Integrated Housing Management
System
Main Issues / Reason for Variance
Programme being progressed with work budget required to be rephased to 24/25.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Anticipated Outcome
Full budget spend
Gypsy Travellers Site
Gypsy/ Traveller Site improvements 
Planned End Date  Forecast End Date
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Redployable CCTV Cameras
Purchase of 5 redeployable CCTV cameras for Housing use
Community Safety Projects
Community Safety Projects 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Budget required to be rephased to 24/25
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works for this project complete in April 23/24.
Mitigating Action
None required

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 10
Budget Forecast Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details Project Life Financials
Spend to Date Variance
9
Project Life Financials 96 0 0% 96 0 0%
Current Year Financials 96 0 0% 0 (96) -100%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
10
Project Life Financials 32,986 3,748 11% 32,986 0 0%
Current Year Financials 6,146 3,748 61% 4,400 (1,746) -28%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
11
Project Life Financials 242 77 32% 277 35 14%
Current Year Financials 45 77 170% 80 35 77%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Airport Noise
Noise Insulation Project 
Planned End Date  Forecast End Date
Targeted SHQS /EESSH compliance works
This budget is to focus on work required to maintain the SHQS compliance and energy efficiency  with
WDC housing stock.   
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works progressing well, however some rephasing may be required to 24/25.
Main Issues / Reason for Variance
West Dunbartonshire Council are no longer eligible for match funding from Glasgow Airport Association, following assessment of properties
within West Dunbartonshire.  West Dunbartonshire is not deemed to have any commercial or residential properties that fall within the scope
of the scheme to be eligible for match funding, and budget therefore has been reduced from £0.192m to £0.096m.  The remaining budget
will be used to develop a programme of works following engagement with an aircraft noise consultant, who will work with Officers to make
adaptations to previously identified properties.  The budget will be reprofiled as required.
Mitigating Action
None required
Anticipated Outcome
Full budget spend in future year
Mitigating Action
None available at this time
Anticipated Outcome
Full budget spend over project life
External stores/garages/bin stores/drainage component renewals
This budget is to focus on external stores/garages/bin stores etc. component renewals as identified and
recommended from the housing stock condition survey.
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Demand for budget higher than anticipated at time of budget setting, with overspend expected to occur in 23/24.
Mitigating Action
None required

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 10
Budget Forecast Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details Project Life Financials
Spend to Date Variance
12
Project Life Financials 242 12 5% 219 (23) -10%
Current Year Financials 45 12 28% 22 (23) -51%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
13
Project Life Financials 606 39 6% 543 (63) -10%
Current Year Financials 113 39 35% 50 (63) -56%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
14
Project Life Financials 9,872 1,701 17% 10,232 360 4%
Current Year Financials 1,840 1,701 92% 2,200 360 20%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
15
Project Life Financials 303 3 1% 257 (47) -15%
Current Year Financials 57 3 6% 10 (47) -82%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Secure entry component renewals
This budget is to focus on secure door entry component renewals as identified and recommended from
the housing stock condition survey and appropriate council officer referrals. 
Planned End Date  Forecast End Date
Statutory/regulatory compliance works (lifts/electrical/legionnella/fire etc)
This budget will be used to upgrade / replace components / installations in order to comply with the
relevant standards / legislation / health and safety in relation to housing stock. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
23/24 demand for budget less than anticipated at time of budget setting.  Current year underspend to be carried forward to future years.
Main Issues / Reason for Variance
This programme always presents challenges with owner liaison and reaching agreements to install door entry where none exists, this
contributes directly to achieving SHQS compliance for this element.  Any underspend in current year will be carried forward to future years.
Mitigating Action
Officers continue to liaise with owners to encourage agreement for install.
Anticipated Outcome
It is likely that this will not to meet full spend in the current year despite best efforts but officers will endeavour to gain owners agreement.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Demand has exceeded expectations.  Due to the nature of this project (ensuring heating and hot water availbility) there is no option for a
conscious reduction of installs.
Mitigating Action
Whilst demand is leading spend, officers will work to minimise any budget overspend.
Mitigating Action
None required
Anticipated Outcome
Works complete as required
Heating improvement works
Carry out works to renew inefficient boilers/full systems as identified from the stock condition survey and
renewal of obsolete/damaged boilers. 
Main Issues / Reason for Variance
23/24 demand for budget less than anticipated at time of budget setting.  Current year underspend to be carried forward to future years.
Mitigating Action
None required
Anticipated Outcome
Works complete as required
Anticipated Outcome
Full budget spend, likely overspend.
Energy improvements/energy efficiency works
Energy improvements/ efficiency works (e.g. loft insulation, pipe/tank insulation, draught exclusion) 
Planned End Date  Forecast End Date

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 10
Budget Forecast Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details Project Life Financials
Spend to Date Variance
16
Project Life Financials 103 0 0% 0 (103) -100%
Current Year Financials 103 0 0% 0 (103) -100%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
17
Project Life Financials 13,900 5,636 41% 17,635 3,735 27%
Current Year Financials 3,000 5,636 188% 6,735 3,735 125%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
18
Project Life Financials 5,454 1,141 21% 5,454 0 0%
Current Year Financials 1,017 1,141 112% 1,540 523 51%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
19
Project Life Financials 1,212 59 5% 1,086 (126) -10%
Current Year Financials 226 59 26% 100 (126) -56%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Improvement works (Risk St)
Risk Street Over clad
Anticipated Outcome
Full budget spend
Void house strategy programme
Spend on Void Properties to bring them up to letting standard 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Budget required to be rephased to 24/25
Mitigating Action
None required
Main Issues / Reason for Variance
Void works to continue into 23/24 to bring void properties up to a lettable standard.  Based on current projections using updated anticipated
numbers it looks likely that the budget will be insufficient , resulting in a projected overspend in 23/24. 
Mitigating Action
This is a significant priority and we continue to make positive progress against internal plan and targets to reduce the number of void
houses.  We expect this to continue to reduce.
Anticipated Outcome
The cost of bringing void properties up to lettable standard will result in a overspend.
Main Issues / Reason for Variance
Work progressing well and ahead of spend targets, at this pace likely to exceed budget to meet tenant demand. Officers currenty working to
manage workload and prioritise to minimise overspend.
Mitigating Action
Officers currenty working to manage workload and prioritise to minimise overspend.
Anticipated Outcome
Full budget spend, likley to overspend.
Environmental renewal works, paths/fences/walls/parking area's
Environmental renewal works, paths/fences/walls/parking areas 
Planned End Date  Forecast End Date
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Asbestos management works
This budget is to fund work associated with the management of current asbestos legislation and the 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Budget to rephased to 24/25 for continuation of works.

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 10
Budget Forecast Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details Project Life Financials
Spend to Date Variance
20
Project Life Financials 5,050 33 1% 5,050 0 0%
Current Year Financials 1,300 33 3% 100 (1,200) -92%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Multi Story Flats  ( including Fire Risk Assessment Works)
High Rise Fire Safety Measures
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works taking longer to progress than anticipated.  Budget required to be rephased to 24/25.
Mitigating Action
None required

Page 8

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 10
Budget Forecast Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details Project Life Financials
Spend to Date Variance
21
Project Life Financials 177,132 14,013 8% 109,020 (68,112) -38%
Current Year Financials 85,209 14,013 16% 17,122 (68,087) -80%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Variance to
23/24 Budget
Site/ Spend £000  Overspend   Underspend  Reprofiling
Haldane Primary School 77 77
Clydebank East (14,340) (14,340)
Queens Quay Site B (410) (410)
Queens Quay Site C (9,422) (9,422)
Pappert (9,993) (9,993)
Bank Street (3,575) (3,575)
Clydebank Health Centre (4,701) (4,701)
Willox Park Phase1 (5,409) (5,409)
Mount Pleasant (8,527) (8,527)
Silverton (2,563) (2,563)
Gap sites (5,794) (5,794)
Fees, Staffing Costs,
contingency (3,429) (3,429)
TOTAL OF ALL PROJECTS (68,087) 77 0 (68,164)
Variance Category 
Forecast End Date
Main Issues / Reason for Variance
The £68.087m variance is made up of £0.077m overspend, and reprofiling of £68.164m into 2024/25 onwards . Summary of reprofiled sites
together with site specific updates as follows:-
Affordable Supply Programme
Affordable Housing Supply Programme 
Planned End Date

Page 9

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 10
Budget Forecast Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details Project Life Financials
Spend to Date Variance
22
Project Life Financials 0 88 #DIV/0! 102 102 #DIV/0!
Current Year Financials 0 88 #DIV/0! 102 102 #DIV/0!
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
TOTAL OF RED PROJECTS
Project Life Financials 262,722 29,153 11% 201,020 (61,702) -23%
Current Year Financials 102,743 29,153 28% 36,404 (66,339) -65%
Haldane - Site complete, retention paid in 2023/24
Clydebank Health Centre - Demolitions planned for 2023/24, Design and Build development and contractors will be procured also  this year,
however physical site start will not be achieved until 2024/25.
Mount Pleasant -19 units to be completed on site by March 2025.  Demolition now complete and contractor award appointment made in
September.  £0.250m estimated to be spent this financial year with remaining current year budget to be reprofiled to 2024/25 for site start in
March 2024.
Bonhill Gap Site - Spend reprofiled from 2023/24 to 2024/25 as design team procurement was delayed.  Projected spend in 2023/24 will be
design and statutory fees.
Mitigating Action
Staff will work closely with all stakeholders to try and ensure timely resolutions of issues as they arise.
Anticipated Outcome
Project will still complete and will meet revised spend profiles .
Clydebank East - 88 units to be completed by March 2025.  Project delivery reprofiled due to extensive groundworks. Project on site and
programme adhering to amended delivery plan.
Queens Quay Site B - 29 units completed on site in 2022/23.  Project completed, retention figure included and associated costs in terms
with road construction.
Queens Quay Site C - 20 units to be completed on site, however no further progress due to land owner issue.  At the time it is assumed
approximately £2m will be spent on land purchase, but this will be reviewed in early 2024, with the remaining current year budget to be
reprofiled to 2024/25.
Pappert - 26 units to be completed on site by April 2025.  Planning delay negated anticipated spend profile for 2023/24, however Planning
approval received 20 September 2023 and site start in early 2024 planned.
Bank Street - 22 units to be completed on site.  Spend reprofiled from 2023/24 to 2024/25 as design team procurement was delayed. 
Projected spend in 2023/24 will be design and statutory fees.
Willox Park Phase1 - 17 units to be completed on site.   Spend reprofiled from 2023/24 to 2024/25 as design team procurement was
delayed.  Projected spend in 2023/24 will be design and statutory fees.
Demoliton related costs incurred as required
Demolitions
Costs associated with demolition of surplus stock 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Costs associated with demolition of old lock ups and stock surplus to requirements
Mitigating Action
None required
Anticipated Outcome

Page 10

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 10
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials 3,216 478 15% 3,201 (15) 0%
Current Year Financials 600 478 80% 585 (15) -3%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
2
Project Life Financials 19,286 2,769 14% 16,757 (2,529) -13%
Current Year Financials 5,679 2,769 49% 3,150 (2,529) -45%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
3
Project Life Financials 17,937 3,574 20% 17,937 0 0%
Current Year Financials 4,547 3,574 79% 4,580 33 1%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
4
Project Life Financials 6,400 0 0% 6,400 0 0%
Current Year Financials 0 0 #DIV/0! 0 0 #DIV/0!
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Main Issues / Reason for Variance
Works expected to commence next financial year, therefore no Issues to report at this time.  Project anticipated to meet full spend
and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Anticipated Outcome
Full budget spend
District Heating 
District Heating Connection to the Dalmuir and Littleholm multi storey flats 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Project is progressing well in 23/24, with 23/24 costs expected to be near current year budget.
Mitigating Action
None required at this time
Mitigating Action
None required
Anticipated Outcome
Scheduled works to complete under current year budget.
Doors/window component renewals
Doors/Windows Component Renewals
Roof Coverings
Building external component renewals, roofs/chimneys/flashings/fascias/gutters/svp 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works expected to meet revised timescales which will be less than current year budget and therefore project will report an in year
underspend.
None required
Anticipated Outcome
Full budget spend
Adaptations to Housing for Special Needs 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works progressing, small amount of reprofiling to 24/25 is possible.
Mitigating Action
31 January 2024
Budget Details Project Life Financials
Spend to Date Variance
Special needs adaptations

Page 11

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 10
Budget Forecast Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details Project Life Financials
Spend to Date Variance
5
Project Life Financials 17,775 2,621 15% 17,950 175 1%
Current Year Financials 3,235 2,621 81% 3,410 175 5%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
6
Project Life Financials 500 0 0% (100) (600) -120%
Current Year Financials 100 0 0% 0 (100) -100%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
7
Project Life Financials 3,835 307 8% 3,380 (455) -12%
Current Year Financials 877 307 35% 422 (455) -52%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
8
Project Life Financials 21,073 2,479 12% 21,073 0 0%
Current Year Financials 4,435 2,479 56% 4,500 65 1%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
Anticipated Outcome
Budget spend anticipated, should criteria be met.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
The main objective of the Buy Back Scheme is to bring former council properties that were sold through the RTB scheme, back
into council use.  These properties must assist the council with reducing housing need on the waiting list and where appropriate
assist with external capital works.  From 23/24, over 5 years, the buy back back scheme is benefiting from an additional £2m
investment each year, included in this revised budget, totaling £10m over 5 years, to futher reduce the waiting list.  The progress
will be monitored and reported as the financial year progresses.
Mitigating Action
None required.
Buy Backs
This is a budget to undertake specific projects that will deliver housing policies/strategies,
example: Ex local authority and mortgage to rent buy-back scheme
Mitigating Action
None required
Anticipated Outcome
Scheduled works to complete under current year budget.
Defective structures/component renewals
Defective structures 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Works expected to meet revised timescales which will be less than current year budget and therefore project will report an in year
underspend.
Main Issues / Reason for Variance
Contingent budget held for unplanned spend.
Mitigating Action
None required
Anticipated Outcome
Spend as required
Contingencies
This is a contingent budget for unforeseen matters which may arise during the year. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Pace of installations are ahead of targets as increased budget was anticipated. Officers will work to manage outturn to revised
budget and targets with likelihood of exceeding budget as demand and cost is higher than projected.
Mitigating Action
Officers will work to minimise any overspend whilst being mindful of tenant demand.
Anticipated Outcome
Full budget spend, possibility of overspend.
Modern facilities and services
New Kitchens, Bathrooms and Showers 
Planned End Date  Forecast End Date

Page 12

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 10
Budget Forecast Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details Project Life Financials
Spend to Date Variance
9
Project Life Financials 13,984 2,191 16% 13,984 0 0%
Current Year Financials 2,629 2,191 83% 2,629 (0) 0%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
TOTAL OF RED PROJECTS
Project Life Financials 104,007 14,420 14% 100,583 (3,424) -3%
Current Year Financials 22,103 14,420 65% 19,276 (2,827) -13%
Main Issues / Reason for Variance
No Issues, budget for salaries and support
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Salaries/central support/offices
Allocation of costs from other WDC services who support the HRA capital programme 
Planned End Date  Forecast End Date

Page 13

APPENDIX 6
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
MONTH END DATE
PERIOD 10
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials (46,875) (585) 1% (46,875) 0 0%
Current Year Financials (28,055) (585) 2% (6,885) 21,170 -75%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
2
Project Life Financials (8,646) (432) 5% (6,917) 1,729 -20%
Current Year Financials (1,729) (432) 25% 0 1,729 -100%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
3
Project Life Financials (311,208) (35,678) 11% (261,940) 49,268 -16%
Current Year Financials (95,062) (35,678) 38% (45,795) 49,267 -52%
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
4
Project Life Financials 0 (19) #DIV/0! (3,000) (3,000) #DIV/0!
Current Year Financials 0 (19) #DIV/0! (3,000) (3,000) #DIV/0!
Project Description
Project Lifecycle 31-Mar-28 31-Mar-28
TOTAL RESOURCES
Project Life Financials (366,729) (36,713) 10% (318,732) 47,997 -13%
Current Year Financials (124,846) (36,713) 29% (55,680) 69,166 -55%
Mitigating Action
None available
Anticipated Outcome
Income will be received when due
Other Capital Income
Other Income to capital
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Grant from Scottish Government in relation to properties bought back into Council stock.
Prudential borrowing incurred as required
None required
Anticipated Outcome
Income to Capital if possible
Prudential Borrowing
Prudential borrowing is long term borrowing from financial institutions that has been approved
for the purposes of funding capital expenditure
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Prudential borrowing is impacted by programme delivery.
Mitigating Action
None available at this time.
Anticipated Outcome
Mitigating Action
Income due to be received in line with spend incurred.
Mitigating Action
None required
Anticipated Outcome
Income due to be received
CFCR
This is capital spend which is funded by revenue budgets
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Contribution to Capital from Revenue in 23/24 expected to be minimal in 23/24 due to cost pressures in revenue.
Main Issues / Reason for Variance
31 January 2024
Budget Details Project Life Financials
Spend to Date Variance
New Build Grant
Grant to facilitate the building of new build housing 
Planned End Date  Forecast End Date

Page 14

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
HRA CAPITAL PROGRAMME
ANALYSIS OF AFFORDABLE HOUSING SUPPLY PROGRAMME
MONTH END DATE
PERIOD 10
Budget Spend to Date Forecast Spend
£000 £000 £000 £000 %
RAG
Status
Haldane Primary School -                                                                             77                            77                                  77                            #DIV/0! 
Aitkenbar Primary School -                                                                             -                          -                                -                          #DIV/0! 
Clydebank East 37,992                                                                      12,370                    23,652                          14,340-                    -38% 
Creveul Court -                                                                             -                          -                                -                          #DIV/0! 
Dumbarton Harbour Ph 3  -                                                                             -                          -                                -                          #DIV/0! 
Queens Quay Site B 660                                                                            102                         250                               410-                         -62% 
Queens Quay Site C 25,175                                                                      3                              15,753                          9,422-                      -37% 
Pappert 13,276                                                                      212                         3,283                            9,993-                      -75% 
Bank Street 5,751                                                                         8                              2,176                            3,575-                      -62% 
Clydebank Health Centre 11,016                                                                      669                         6,315                            4,701-                      -43% 
Willox Park Phase1 6,185                                                                         113                         776                               5,409-                      -87% 
Willox Park Phase2 7,500                                                                         -                          7,500                            -                          0% 
Mount Pleasant 8,717                                                                         190                         190                               8,527-                      -98% 
Silverton 2,590                                                                         28                            27                                  2,563-                      -99% 
0 -                                                                             -                          -                                -                          #DIV/0! 
Gap sites
Gap sites budget remaining 9,182                                                                         -                          9,182                            -                          0% 
Bonhill Gap Site - all Bonhill Sites 245                                                                            0                              245                               -                          0% 
Bonhill Gap Site - Old Bonhill/ Campbell Street -                                                                             10                            -                                -                          
Bonhill Gap Site - O'Hare -                                                                             8                              -                                -                          0% 
Bonhill Gap Site - Braehead -                                                                             8                              -                                -                          #DIV/0! 
Clydebank Gap Sites ( prev Lilac Avenue) - unallocated 13,622                                                                      -                          13,622                          -                          0% 
Clydebank Gap Sites ( prev Lilac Avenue) - 7-9 Gilmour Avenue 50                                                                              39                            50                                  -                          0% 
Clydebank Gap Sites ( prev Lilac Avenue) - Queen Mary Avenue 50                                                                              14                            50                                  -                          0% 
Future New build sites 27,000                                                                      -                          27,000                          -                          0% 
28 Bridge Street Alexandria 23                                                                              162                         23                                  -                          0% 
Fees, Staffing Costs, contingency 8,097                                                                         -                          8,097                            -                          0% 
Total Expenditure 177,132 14,013 118,268 (58,863) 
31 January 2024
Site
Project Life Financials
Variance