WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer - Resources
Council - 27 March 2024
___________________________________________________________________
Subject: Housing Revenue Account (HRA) Budgetary Control Report
to 31 January 2024 (Period 10)
1. Purpose
1.1 The purpose of the report is to provide members with an update on the
financial performance to 31 January 2024 (Period 10) for the HRA revenue
budget and the HRA capital budget.
2. Recommendations
2.1 Members are asked to:
i) note the HRA revenue account is forecasting an adverse variance of
£3.863m. The adverse variance will be offset by removing the £1.729m
budgeted contribution from revenue to capital (CFCR) and using
£2.134m of the HRA reserves.
ii) note that the use of HRA reserves to address the projected adverse
variance will lead to a closing HRA reserves balance of £0.500m which
is below the prudential target.
iii) note that work will continue to identify efficiencies across all areas of the
housing budget to allow HRA reserves to replenished and maintained in
line with the prudential target, while ensuring that services are still
delivered and that there is not a corresponding reduction in service
provision.
iv) note the HRA capital budget is forecasting an in-year underspend of
£69.166m which comprises £4.912m for projects that will be re-profiled
into 2024/25 and projects with a net underspend of £64.253m this year,
as detailed in Appendix 4.
3. Background
Revenue
3.1 The council approved a £49.643m HRA revenue budget for 2023.24 on the 1st
of March 2023
Page 1
ITEM  12

Page 2

Capital 
3.2 The council approved the updated HRA capital plan for 2023/24 on the 1st of
March 2023. The capital plan has been augmented by the re-profiling of
underspends and budget with a revised HRA capital monitoring budget for
2023/24 of £124.846m. 
4. Main Issues 
Revenue 
4.1 The budgetary position for HRA revenue account is provided in Appendix 1
with information on projected variances valued at more than £0.050m being
provided as Appendix 2. 
4.2 Previous reports to Council have highlighted the significant HRA cost
pressures in 2023/24. The HRA has seen a significant impact on its finances
because of range of external factors beyond its control, including the rising
cost of local authority borrowing, demand led pressures across the repairs
and void service, high inflation, and uncertainty and volatility surrounding
energy costs, particularly the spiralling cost of electricity. 
4.3 Previous Budgetary Control Reports have highlighted to members the severe
pressure across HRA loan charge and HRA repair and void budgets.
Members will be aware that local authority borrowing costs have increased
considerably over the past 12-18 months leading to much higher interest
payments on new borrowing and debt refinancing. The forecast is for higher
interest rates to lead to HRA debt interest payments being £2.912m more than
budget this year. HRA repair and void expenditure has been adversely
impacted by a combination of an increased volume of jobs raised as the
service has addressed COVID backlogs across the repair and void service
and by current economic conditions, where labour, materials and sub-
contractor costs have all increased significantly. The revenue impact on HRA
repair and void budgets this year is forecast at £2.675m. Furthermore, the
backlog of voids and repairs has led to a sharp increase in rent abatement
payments to tenants to compensate for disruption and inconvenience, the
forecast is for abatement payments to be £0.316m more than budget this
year. These acute cost pressures should ease as interest rates and inflation
falls and the repairs service catches up with backlogs. 
4.4 The current economic operating environment is also placing financial stress
on the HRA in terms of increasing utility and insurance costs. Electricity costs
for landlord supplies have increased by more than 60% in 2023/24 leading to
an in-year cost pressure of £0.248m. Insurance premiums are also affected by
inflation as well as risk and it is forecast that higher insurance premiums will
lead to an in-year cost pressure of £0.130m. 
Page 2

Page 3

4.5 Whist officers have taken steps in year to mitigate cost pressures through the
active management of repair and CFCR budgets, based on the information
available at this time, it is projected that the HRA will have a deficit of £3.863m
this financial year. The deficit will be offset by removing the £1.729m
budgeted contribution from revenue to capital (CFCR) and using £2.134m of
HRA reserves. 
4.6 The current forecast is for a closing HRA reserves balance of circa £0.500m
on 31 March 2024. In terms of adequacy of reserves, the forecast closing
HRA reserves balance is insufficient to deal with future financial shocks to the
HRA budget. As a result of these externally driven financial challenges,
officers will continue to focus on reducing service delivery cost across the
housing budget to replenish and maintain reserves in line with the prudential
target, while ensuring that services are still delivered and that there is not a
corresponding reduction in service provision.   
Capital 
4.7 The HRA capital summary position is shown in Appendix 3. Information on
projects that are highlighted as being within the red category is provided in
Appendix 4 and Appendix 5 provides information on the projects at Green. A
summary of anticipated resources is shown in Appendix 6. The analysis
shows that there is currently a projected in-year underspend of £69.166m
(55.4%) as detailed below. 
2023/24
Forecast
£m  
2023/24
Budget
(£m 
Variance
£m
Other Capital Expenditure 4.528 4.240 0.288
Major Component Replacement  17.902 21.813 (-3.911)
Void Capital 6.735 3.000 3.735
Contingencies 0.000 0.100 (-0.100)
Structural & Environmental  2.162 3.420 (-1.258)
Support Costs  2.629 2.629 -
Buy Back Programme  4.500 4.435 0.065
Affordable Supply Programme 17.224 85.209 (-67.985)
Total  55.680 124.846 (-69.166) 
4.8  The main cost pressures / overspends are across the budgets to deal with
large and complex repair and void works and environmental works. The
demand for and cost of these works has been incredibly high this year,
mirroring the pressure being experienced in the corresponding revenue
budgets. The capital budget has had to fund many high-cost complex works
this year as the service addressed void and repair backlogs. Void numbers
and repair backlogs have reduced significantly and going forward the capital
spend is expected to reduce considerably. 
Page 3

Page 4

4.9 From the analysis within the appendices the main projects that are expected
to require re- profiling into 2024/25 are: 
Project Name Re-profiling 
£m
EESH compliance work 1.746
Environmental Sensors 1.500
Multi-Storey Flat Strategy   1.200
Better Homes Priority Budget  0.375
Housing CCTV Installation Programme  0.250 
5. People Implications 
5.1 There are no people implications. 
6. Financial and Procurement Implications 
6.1 Other than the financial position noted above, there are no financial
implications of the budgetary control report. There are no procurement
implications arising from this report. 
7. Risk Analysis 
7.1 The main financial risks to the ongoing financial position relate to the
identification of unforeseen cost between now and the end of the financial
year. This can affect all service areas. 
8. Equalities Impact Assessment (EIA) 
8.1 The report is for noting and therefore there is no Equalities Impact Assessment
for this report. 
9. Consultation 
9.1 Housing management and Legal services have advised there are neither any
issues nor concern with the report. 
10. Strategic Assessment 
10.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the five strategic
priorities of the Council’s Strategic Plan. This report forms part of the financial
governance of the Council. This report is for noting and, therefore, does not
directly affect any of the strategic priorities. 
Laurence Slavin
Chief Officer – Resources
Date: 22 February 2024
___________________________________________________________________
Page 4

Page 5

Person to Contact:  Jim McCarron - Business Unit Finance Partner  
16 Church Street, Dumbarton, G82 1QL,    
e-mail james.mccarron@west-dunbarton.gov.uk 
Appendices:  Appendix 1 - Budgetary Position (Revenue)    
Appendix 2 - Variance analysis (Revenue)                                           
Appendix 3 - Budgetary Position (Capital)    
Appendix 4 - Variance analysis Red (Capital)    
Appendix 5 - Variance analysis Green Projects (Capital)
Appendix 6 - Resources (Capital)
Appendix 7 - Analysis of Affordable Housing Supply 
Programme (Capital)     
Background Papers: None    
Wards Affected:  All 
Page 5