WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 50 43 86% 50 0 0%
Current Year Financials 7 0 0% 0 (7) -100%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-24
2
Project Life Financials 30 5 16% 30 0 0%
Current Year Financials 25 0 0% 0 (25) -100%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 30-Sep-23 30-Nov-23
3
Project Life Financials 30 65 218% 65 35 117%
Current Year Financials 23 21 92% 58 35 157%
Project Description
Project Manager Adrian Gray
Chief Officer Laurence Slavin
Project Lifecycle 30-Apr-24 30-Apr-24
4 IFRS 16 Database
Project Life Financials 5 0 0% 5 0 0%
Current Year Financials 5 0 0% 0 (5) -100%
Project Description
Project Manager Jackie Nicol Thomson
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-24
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Mitigating Action
None required at this time.
Anticipated Outcome
Upgraded Electronic Insurance System.
Enhancements to Cash Receipting System
To enhance the cash receipting system in the way payments are made and allocated to back office by increasing the level
of security that is required for online payments made by customers
Electronic Insurance System
Acquisition of a claims/incident management system supported by an electronic document management system.
Planned End Date Forecast End Date
Main Issues / Reason for Variance 
Budget has been reprofiled to Financial Year 2024-2025.
Anticipated Outcome
Enhancements to the cash receipting system including PCI compliant telephone payment system.
Agresso development
The purpose of this project is to carry out an upgrade of the Agresso Finance System which was last upgraded in 2015. The
requirement to upgrade is to maintain a level of support available from Unit 4 who have advised that support for older
versions of the system is being reduced.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget has been reprofiled to Financial Year 2024-2025. Version 2 of the upgrade was completed Jan 2023.  Call Secure Module went Live in October 2023.
Mitigating Action
None required at this time.
This is a system which will ensure that WDC has the correct level of information and adheres to correct reporting of IFRS16 -
Leasing. 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
IFRS16 has been postponed and is due for implementation this financial year. It is anticipated that full spend will be incurred by 31 March 2024.
Main Issues / Reason for Variance
Work to significantly reduce the database size to facilitate a system upgrade has now been completed. Upgrade work can now commence, ICT currently building required
servers in preparation for new version to be installed, configured and tested.
Mitigating Action
None required
Anticipated Outcome
Anticipate completion of upgrade during 23-24 financial year.
Mitigating Action
None available at this time.
Anticipated Outcome
Completion of project by 31 March 2024

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Electronic Insurance System5
Project Life Financials 1,590 50 3% 1,590 0 0%
Current Year Financials 1,590 0 0% 50 (1,540) -97%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-24 31-Mar-25
6
Project Life Financials 1,150 1,150 100% 1,150 (0) 0%
Current Year Financials 5 2 33% 5 0 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-22 30-Apr-23
7
Project Life Financials 2,980 2,949 99% 2,980 0 0%
Current Year Financials 2,980 1,260 42% 2,970 (9) 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-24 31-Mar-24
8
Project Life Financials 349 9 3% 349 0 0%
Current Year Financials 340 0 0% 0 (340) -100%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-24 31-Mar-25
Main Issues / Reason for Variance
This project is linked to Glencairn House and Depot Rationalisation and will free up the current museum store and office space in Poplar Road. Opportunities exist to
attract external funding. Detailed design work ongoing for Glencairn House.
Mitigating Action
None available at this time
Project delivered on budget with required specifications
Strathleven Place
Re-development of Strathleven.
Planned End Date Forecast End Date
Mitigating Action
None required.
Anticipated Outcome
To create new community facilities with additional space for early years provisions.
Building Upgrades and H&S - lifecycle & reactive building upgrades
Lifecycle and reactive building upgrades.
Dalmonach CE Centre
To create new community facilities with additional space for early years provisions.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project complete and final account to be agreed.
Anticipated Outcome
Projects delivered to required specifications
New Sports Changing Facility Dumbarton West (Old OLSP site) 
New Sports Changing Facility Dumbarton West (Old OLSP site) 
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works progressing
Mitigating Action
None required at this time
Main Issues / Reason for Variance
No confirmation of start date can be confirmed until works commence on the wider housing site.
Mitigating Action
None available at this time
Anticipated Outcome
To deliver new sports changing facility.

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Electronic Insurance System9
Project Life Financials 150 296 197% 296 146 97%
Current Year Financials 134 227 170% 280 146 109%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-21 31-Mar-24
10
Project Life Financials 2,375 122 5% 2,375 0 0%
Current Year Financials 1,085 18 2% 31 (1,053) -97%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-22 31-Mar-25
11
Project Life Financials 33 33 100% 33 0 0%
Current Year Financials 33 0 0% 33 0 0%
Project Description
Project Manager Alan Douglas
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
12
Project Life Financials 155 145 93% 155 0 0%
Current Year Financials 10 0 0% 0 (10) -100%
Project Description
Project Manager Pamela Clifford
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project had been delayed due to a number of COVID-19 related issues and utilities issues. Unit is now in production but delay to site due to the utility disconnection and
demolition works. Demolition works complete and waiting for a date for installation due to be complete by 31st March 2024.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Various delays due to Covid and other utility issues. Planning was previously delayed but now resolved. Building warrant applications submitted and tender to be issued. 
Anticipate going to tender at end February with a site start in spring 2024. Also awaiting confirmation of RCGF funding.
Mitigating Action
None available at this time
Mitigating Action
None available at this time
Anticipated Outcome
To deliver new sports changing facility.
New Westbridgend Community Centre
New Westbridgend Community Centre
Main Issues / Reason for Variance
Budget has been rephased from 2022/23. Project was originally delayed due to COVID19 restrictions and a decision was made to resume project once Microsoft 365 was
implemented. It is anticipated that the project will complete by 31 March 2024.
Mitigating Action
None available at this time.
Anticipated Outcome
Project will be delivered on budget
Anticipated Outcome
To deliver new community centre.
Legal Case Management System
Legal Case Management System
Planned End Date Forecast End Date
Demolition 215 Main Street Alexandria
Demolition of 215 Main Street Alexandria.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This outstanding money is being sought through the recharging order and through debtors.
Mitigating Action
No action required at this time in the hands of Legal
Anticipated Outcome
Continue to pursue repayment

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Electronic Insurance System13
Project Life Financials 61 61 100% 61 (0) 0%
Current Year Financials 58 1 1% 58 0 0%
Project Description
Project Manager Rachel Moir
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-25
14
Project Life Financials 87 85 97% 87 0 0%
Current Year Financials 79 85 107% 85 5 7%
Project Description
Project Manager Rachel Moir
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
15
Project Life Financials 20 20 100% 20 0 0%
Current Year Financials 7 1 19% 7 0 0%
Project Description
Project Manager Rachel Moir
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
16
Project Life Financials 290 64 22% 290 0 0%
Current Year Financials 227 1 0% 1 (226) -100%
Project Description
Project Manager Rachel Moir
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
17
Project Life Financials 16,154 1,105 7% 16,154 0 0%
Current Year Financials 2,933 224 8% 511 (2,422) -83%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-25
Installation of Solar PV at Clydebank Leisure Centre
Installation of Solar PV at Clydebank Leisure Centre.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Tender works delayed due to Energy Officer being off sick. Work underway and will be undertaken in 24/25.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works are currently being undertaken to upgrade controls in Clydebank Town Hall.
Mitigating Action
None Required.
Mitigating Action
None required
Anticipated Outcome
Works to be undertaken in 24/25
Replace existing main hall Air Handling unit at Clydebank Town Hall
Replace existing main hall Air Handling unit at Clydebank Town Hall.
Main Issues / Reason for Variance
Expected completion in 24/25
Mitigating Action
None required.
Anticipated Outcome
Delivery of project with full budget spend.
Anticipated Outcome
Replace existing main hall Air Handling unit at Clydebank Town Hall.
Replace failed heating controls/valves & recommission
Replace failed heating controls/valves & recommission.
Planned End Date Forecast End Date
Mitigating Action
Energy team to remain involved for update and communicate any potential additional costs.
Anticipated Outcome
Delivery of project with full budget spend.
Leisure Energy projects - air handling units, upgrade lighting, circulating pumps, and draught proofing
Measures to be installed at both Meadow Centre & Vale of Leven Swimming Pool; new pool hall Air Handling Units, upgrade
lighting, circulating pumps Vale of Leven Swimming Pool, internal and external lighting and draught proofing.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works have been delayed due to flooding issues. Tender process due to be undertaken shortly; however, due to additional issues identified, the current budget may
require review.
Regeneration/Local Economic Development
Budget to facilitate the delivery of Regeneration throughout West Dunbartonshire, aligned to the Economic Strategy.
External funding will be sought to maximise opportunities for redevelopment of these sites.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
LED budget is invested across our town centres and strategic sites and is used to develop and implement projects as well as providing match funding to lever in external
funding. During 2023/2024 the key projects to be developed and delivered include a Alexandria Town Centre Masterplan projects (Smollet Fountain, Green heritage
Corridors), and in Clydebank implementation of the Development Framework. Many regeneration projects are subject to factors outwith Council control and close
monitoring of the programming is required. Enabling works at Mitchell Way  have been delayed as they are subject to the timescale of the developer. Activity Centre in
Clydebank is delayed and now planned to be delivered in 2024/2025. A contingency is included for increasing costs and new funding opportunities.
Mitigating Action
none required
Anticipated Outcome
projects delivered on time and on budget

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Electronic Insurance System18
Project Life Financials 5,064 4,898 97% 5,064 0 0%
Current Year Financials 4,098 0 0% 274 (3,824) -93%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-25
19
Project Life Financials 2,869 1,617 56% 2,869 0 0%
Current Year Financials 1,147 0 0% 837 (310) -27%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
20
Project Life Financials 747 40 5% 747 0 0%
Current Year Financials 707 0 0% 0 (707) -100%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Dec-22 30-Jun-24
21
Project Life Financials 320 159 50% 320 0 0%
Current Year Financials 221 60 27% 60 (161) -73%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 30-Jun-24
22
Project Life Financials 22,100 7,229 33% 22,100 0 0%
Current Year Financials 19,984 3,257 16% 5,113 (14,871) -74%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-25 31-Mar-25
Funding to implement major regeneration projects linked to community charrettes. 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Progress being made by Malin Group with expenditure of Clyde Mission funding at the Scottish Marine Technology Park. Remaining projects are multi-year.
Regeneration Fund
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects continue to be progressed. 23/24 allocation will be distributed as capital grants.
Mitigating Action
None required at this time
Mitigating Action
Anticipated Outcome
Projects delivered on time and on budget
Place Based Investment Programme
Scottish Government Funding to establish a Place-Based Investment Programme to ensure that all place based
investments are shaped by the needs and aspirations of local communities.
Main Issues / Reason for Variance
Kier is appointed to design and deliver the Activities Centre at Clydebank Town Centre. Design of the project is underway and a commencement date for construction will
be later in 2024.
Mitigating Action
None available at this time
Anticipated Outcome
Projects delivered on budget
Anticipated Outcome
Projects delivered on budget
Clydebank Can On The Canal
New activities centre in Clydebank Town Centre.
Planned End Date Forecast End Date
Mitigating Action
None available at this time
Anticipated Outcome
Projects delivered on budget
LUF
Year one LUF spend includes acquisition cost of Artizan Centre, and design development for Glencairn House and
Connecting Dumbarton
Levelling Up Capacity
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and transformational
regeneration.
Planned End Date Forecast End Date
Main Issues / Reason for Variance 
This capacity funding is used to fund consultancy work associated with current and future LUF projects development.
Anticipated Outcome
Projects delivered on budget
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Artizan Masterplan approved by IRED in Nov 2023, deigns progressing as planned but some delay to early enabling works (demolition) and commencement of the
delivery phase (Glencairn House).
Mitigating Action
None available at this time

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Electronic Insurance System23
Project Life Financials 11,064 100 1% 11,064 0 0%
Current Year Financials 7,209 3 0% 100 (7,109) -99%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
24
Project Life Financials 2,749 2,373 86% 2,749 0 0%
Current Year Financials 814 420 52% 425 (389) -48%
Project Description
Project Manager Michelle Lynn
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-23 30-Sep-24
25
Project Life Financials 449 319 71% 449 0 0%
Current Year Financials 446 13 3% 260 (186) -42%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 30-Sep-24
26
Project Life Financials 58 45 77% 58 0 0%
Current Year Financials 13 0 0% 13 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
27
Project Life Financials 250 14 6% 250 0 0%
Current Year Financials 250 0 0% 0 (250) -100%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
District Heating Network Expansion
District Heating Network Expansion.
Planned End Date Forecast End Date
Main Issues / Reason for Variance  
Network expansion to GJNH (Golden Jubilee National Hospital) will commence pending approval to proceed by the GJNH Board including agreeing tariff rates .  Unable
to confirm exact programme until approval has been given.
Mitigating Action
Network expansion to Golden Jubilee is discussed at every District Heating Project Board
Anticipated Outcome
Project to be delivered on programme and within budget once it has been fully set.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Administration budget commitment.  All projects progressing.
Mitigating Action
Unallocated budget to be taken per Council savings option 
Heritage Capital Fund
Heritage Capital Fund.
Anticipated Outcome
Budget to be taken per Council savings option 
Allotment Development
To develop an allotment site.
Anticipated Outcome
Additional allotments delivered within budget
Kilmaronock Cemetery Expansion
Expansion of existing cemetery at Kilmaronock. 
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works Progressing
Mitigating Action
None required at this time.
Cemetery Extension, North Dalnotter
Cemetery Extension, North Dalnotter
Planned End Date Forecast End Date
Main Issues / Reason for Variance
North Dalnotter will now be delivered in financial year 24/25
Main Issues / Reason for Variance
Project Underway
Mitigating Action
None available at this time
Anticipated Outcome
Sustainable burial environment for local residents.
Mitigating Action
None required at this time.
Anticipated Outcome
Sustainable burial environment for local residents.

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Electronic Insurance System28
Project Life Financials 3,576 5,305 148% 5,305 1,729 48%
Current Year Financials 864 1,223 142% 1,260 396 46%
Project Description
Project Manager Craig Jardine
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-24
29
Project Life Financials 817 817 100% 817 (0) 0%
Current Year Financials 529 401 76% 529 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
30
Project Life Financials 395 0 0% 395 0 0%
Current Year Financials 385 0 0% 0 (385) -100%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
31
Project Life Financials 739 90 12% 739 0 0%
Current Year Financials 380 32 8% 32 (349) -92%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-28 31-Mar-28
32
Project Life Financials 600 10 2% 600 0 0%
Current Year Financials 200 0 0% 10 (190) -95%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 30-Nov-23 31-Mar-25
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Scottish Water connection now complete.  Programme to completion being finalised by Contractor, anticipated completion date is now 15 March 24.
Mitigating Action
None available at this time
Posties Park Sports Hub - New sports hub to include gym & running track
Creation of a sports hub at Posties/Marinecraft to include a new changing pavilion/Gym, new all-weather 6 lane running
track, conversion of blaze sports pitch to grass, new fencing, upgrade of existing floodlights and additional car parking.  This
combines the budget approved by the Council in February 2015 for Community Sports Facilities at Posties Park, draw down
of budget from the generic sports facilities budget line.
Anticipated Outcome
New sports Hub delivered
Mitigating Action
None available at this time.
Anticipated Outcome
Extension to existing cemetery providing a sustainable burial environment.
East End Park Resurfacing
Resurfacing of 3G pitch at East End Park.
Vale of Leven Cemetery Extension
Extension of existing cemetery in Vale of Leven.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project will be completed Summer 2024
Anticipated Outcome
Resurfacing of 3G pitch at East End Park.
Play Parks Grant Funding
Renew and replace play park equipment
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
External funding confirmed and design commencing.
Mitigating Action
None required.
Balloch Mountain Bike Track
Develop a mountain bike skills trail at Balloch Castle Country Park.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Design undertaken this financial year.
Main Issues / Reason for Variance
Tender documentation complete, commencement programmed February 24.
Mitigating Action
None required at this time.
Anticipated Outcome
Renewal of play parks
Mitigating Action
None required at this time.
Anticipated Outcome
Develop a mountain bike skills trail at Balloch Castle Country Park.

Page 8

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Electronic Insurance System33
Project Life Financials 217 3 1% 3 (214) -99%
Current Year Financials 214 0 0% 0 (214) -100%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
34
Project Life Financials 561 0 0% 561 0 0%
Current Year Financials 561 204 36% 361 (200) -36%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
35
Project Life Financials 400 400 100% 400 0 0%
Current Year Financials 42 0 0% 42 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
36
Project Life Financials 315 315 100% 315 0 0%
Current Year Financials 56 0 0% 56 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
37
Project Life Financials 500 32 6% 500 0 0%
Current Year Financials 500 32 6% 350 (150) -30%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Mitigating Action
None available at this time.
Anticipated Outcome
To improve journey times and reliability of bus services.
Cycling, Walking and Safer Streets
Introduction of enhanced walking routes and traffic calming schemes to introduce safer streets within West Dunbartonshire.
Bus Rapid Deployment Fund
Funding has been awarded from Sustrans to assist with social distancing measures required as a result of the COVID-19
pandemic.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Funding no longer available
Anticipated Outcome
To improve connectivity and enhanced Cycling routes within West Dunbartonshire.
Auld Street Clydebank - Bond
Footpath still to be done after xmas spend.  Part funded by Golden jubie £20k.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works for a footway/cycleway improvement at Bellsmyre Avenue are now complete. Dropped kerbs at various locations are underway. Proposed further works to
cycleways due to commence late 2023.
Mitigating Action
None required at this time.
Main Issues / Reason for Variance
Works instructed for link path to be combined with Golden Jubilee Active travel contributions
Mitigating Action
None available at this time.
Anticipated Outcome
To complete remaining civil works required.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Balloch Park 50kw EVC to be upgraded.
Mitigating Action
None required at this time.
Electrical Charging Points - Rapid Charge
Funding has been awarded from Transport Scotland for the Installation of electrical charging points
Anticipated Outcome
To provide Electric Vehicle Charging points within West Dunbartonshire.
Mitigating Action
None required at this time.
Anticipated Outcome
Projects should be complete within budget.
Flood Prevention
Various flood prevention projects.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Limited uptake om property level protection

Page 9

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Electronic Insurance System38
Project Life Financials 800 181 23% 800 0 0%
Current Year Financials 620 0 0% 0 (620) -100%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-26
39
Project Life Financials 2,277 1,247 55% 2,277 0 0%
Current Year Financials 650 80 12% 450 (200) -31%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
40
Project Life Financials 97 97 100% 97 (0) 0%
Current Year Financials 29 29 99% 29 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
41
Project Life Financials 15,053 1,054 7% 15,053 0 0%
Current Year Financials 1,530 0 0% 600 (930) -61%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-27
42
Project Life Financials 1,700 1,207 71% 1,700 0 0%
Current Year Financials 693 0 0% 200 (493) -71%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-26 31-Mar-27
River Leven Flood Prevention Scheme
River Leven Flood Prevention Scheme.
Anticipated Outcome
Project should be completed within budget.
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements & Park and Rides
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Awaiting outcome of Scottish Government & SEPA consideration of submitted study .
Mitigating Action
None required at this time.
Main Issues / Reason for Variance
For Bus Infrastructure a program of works Is being developed. For A8014 Kilbowie Rd works are being planned awaiting further feedback from Utilities, For A814
Congestion measures further development & expansion of vehicle detection systems and for Balloch P & R Consultants are appointed, agreement in principal with
Network Rail & further investigatory works are planned.
Mitigating Action
None required at this time.
Anticipated Outcome
Improve accessibility to Public Transport and improve journey time reliability.
Main Issues / Reason for Variance
Detailed design underway. Design will be completed 24/25
Mitigating Action
None available at this time.
Anticipated Outcome
Intention is to complete works within budget.
Depot Improvement Works
Improvement of WDC Roads Depot.
Planned End Date Forecast End Date
Mitigating Action
None available at this time.
Anticipated Outcome
Project should be completed within budget.
A813 Road Improvement Phase 1
A813 Road Improvement Phase 1.
Gruggies Burn Flood Prevention
Commission of Gruggies Flood Prevention Scheme.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Detailed design underway. Design will be completed 24/25
Anticipated Outcome
To provide an improved A813.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Initial works commencing March 23 with majority of works to be delivered 24/25
Mitigating Action
None required at this time.

Page 10

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Electronic Insurance System43
Project Life Financials 134 65 49% 134 0 0%
Current Year Financials 134 0 0% 65 (69) -51%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
44
Project Life Financials 4,300 4,211 98% 4,300 0 0%
Current Year Financials 138 5 4% 50 (88) -64%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-24
45
Project Life Financials 1,400 500 36% 1,400 0 0%
Current Year Financials 1,400 0 0% 500 (900) -64%
Project Description
Project Manager Craig Jardine
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
46
Project Life Financials 3,314 455 14% 3,314 0 0%
Current Year Financials 3,314 455 14% 455 (2,859) -86%
Project Description
Project Manager Craig Jardine
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 30-May-24
47
Project Life Financials 1,980 200 10% 1,980 0 0%
Current Year Financials 1,980 0 0% 200 (1,780) -90%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Dec-25
Roads Safety
Roads Safety
Planned End Date Forecast End Date
Clydebank Charrette, A814
Clydebank Charrette, A814
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works complete and on maintenance period - retention payment due prior to March 2024.
Main Issues / Reason for Variance
New funding which will be allocated to appropriate projects.
Mitigating Action
None required at this time.
Anticipated Outcome
Projects will be delivered on time.
Mitigating Action
None available at this time.
Anticipated Outcome
Project will enhance the A814 through Clydebank.
Vehicle Replacement Strategy
Replacement of refuse collection vehicles.
Anticipated Outcome
Replacement of refuse collection vehicles.
Vehicle Replacement
Replacement of vehicles which have reached end of programmed lifespan (7 year heavy vehicles, 10 year light vehicles).
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Bin lorries ordered and build slot allocated this financial year.
Mitigating Action
None available.
Waste Transfer Station
The design, development and construction of a recycling and bulk waste transfer facility that will ensure all recycling
material can be sorted and disposed off appropriately to ensure compliance with landfill ban in 2025.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Detailed design ongoing
Main Issues / Reason for Variance
Vehicles have been ordered including bin lorries, sweepers and tractors.  Expected delivery of bin lorries between April and July 2024.
Mitigating Action
None Required.
Anticipated Outcome
Replacement of fleet within budget.
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within budget.

Page 11

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Electronic Insurance System48
Project Life Financials 33,491 7,946 24% 33,491 0 0%
Current Year Financials 11,845 1,917 16% 4,000 (7,845) -66%
Project Description
Project Manager Patricia Rowley
Chief Officer Gail McFarlane
Project Lifecycle 31-Mar-27 31-Mar-27
49
Project Life Financials 8,535 445 5% 8,535 0 0%
Current Year Financials 2,238 94 4% 100 (2,138) -96%
Project Description
Project Manager Craig Jardine
Chief Officer Gail McFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
50
Project Life Financials 250 20 8% 250 0 0%
Current Year Financials 250 0 0% 20 (230) -92%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
51
Project Life Financials 868 301 35% 868 0 0%
Current Year Financials 397 18 5% 40 (357) -90%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-29 31-Mar-29
52
Project Life Financials 376 355 94% 376 0 0%
Current Year Financials 41 0 0% 20 (21) -51%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-24
Exxon City Deal
As part of the City Deal project the WDC Exxon site at Bowling regeneration with alternative A82 route included.
Planned End Date Forecast End Date
Main Issues / Reason for Variance 
Regular updates are provided at every Council meeting and monthly Project Board meetings and to City Deal.  The main issues contained within the new Council's
approved Outline Business Case are still valid, which include Exxon's remediation strategy, land transfer arrangements and issues relating to adjoining owners.  WDC
Consultants are monitoring the remediation process to ensure compliance with specification, also Esso are independently monitoring the remediation works.  Final
Business Case submission was June 2023. Through the Scape framework we are working closely with Balfour Beatty to achieve a formal pre construction agreement to
allow the detailed design works to commence and the full construction programme to be developed. Agreements in principle are progressing with third party land owners.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Committee approval given to upgrade and improve depots.  Project delivery will be phased, work underway to determine phasing of spend and scope.  Garage facilities
will be treated as a priority
Mitigating Action
None available at this time
Mitigating Action
None Required
Anticipated Outcome
Delivery of the project on time and within the increased budget
Depot Rationalisation
Depot Rationalisation.
Anticipated Outcome
Deliver project outcomes within agreed budget
Mitigating Action
None Required.
Anticipated Outcome
Resurfacing of blaze pitch to 3G all weather surface
AV Equipment - Education
Purchase of AV Equipment for Education.
Pappert 2G pitch
Resurfacing of blaze pitch to 3G all weather surface
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Expecting work to commence in financial year 2024/25.
Anticipated Outcome
Purchase of AV Equipment for Education.
Digital Inclusion
Increase the ratio of chrome book devices for most disadvantaged children and families and support for families with remote
access.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Progressing as expected. Spend is not linear AV boards replaced as a when they fail.
Mitigating Action
None required at this time.
Main Issues / Reason for Variance
Delay in identifying appropriate cohort for project delivery. Current challenge is finding a suitable and available location.
Mitigating Action
None required at this time.
Anticipated Outcome
Increase the Chromebook ratio for most disadvantaged children.

Page 12

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Electronic Insurance System53
Project Life Financials 20,621 16,090 78% 20,621 0 0%
Current Year Financials 4,222 489 12% 522 (3,700) -88%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
54
Project Life Financials 34,204 2,384 7% 34,204 0 0%
Current Year Financials 3,495 891 26% 1,579 (1,916) -55%
Project Description
Project Manager Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-26 31-Jul-27
55
Project Life Financials 694 762 110% 694 0 0%
Current Year Financials 122 190 156% 190 68 56%
Project Description
Project Manager Michelle Lynn
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
56
Project Life Financials 8,628 8,723 101% 8,628 0 0%
Current Year Financials 287 110 38% 214 (72) -25%
Project Description
Project Manager Michelle Lynn
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
57
Project Life Financials 845 10 1% 845 0 0%
Current Year Financials 845 10 1% 766 (79) -9%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-24 31-Mar-24
Schools Estate Improvement Plan
Improvement of Schools Estate.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works progressing in line with programme.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The next phase of the Schools Estate Improvement Plan involves the development of a new Campus provision in the Faifley area. WDC has been successful in securing
funding from the Scottish Government Learning Estate Improvement Programme. SFT confirmed the indicative funding allocation for this project at £18.416m on the 4
May 2021, this will be received as a revenue stream over the 25 years of the Scottish Government financial support (subject to the Council adhering to the funding
criteria). Site Options Appraisal has taken place and Members approved the recommendation to proceed with the new Faifley Campus on the St Joseph's site at
Education Committee on 9th June 2021.  Work is progressing well to reach Financial Close by 19 February.  Planning permission has been agreed and Stage 1 Building
Warrant approved. 
Mitigating Action
None required at this time
Mitigating Action
None at this time
Anticipated Outcome
Project delivered within budget and to required specification
Schools Estate Improvement Plan - next Phase - Faifley Campus
Improvement of Schools Estate.
Main Issues / Reason for Variance
Provision of Capital Funding from Scottish Government to implement free school meal initiative.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within amended timescales.
Anticipated Outcome
Delivery of the project within budget and on time.
Free School Meals
Provision of Capital Funding from Scottish Government to implement free school meal initiative.
Planned End Date Forecast End Date
Mitigating Action
None at this time
Anticipated Outcome
The project will be completed to deliver the requirements of the Early Years expansion plans.
Aids & Adaptations - Special Needs Adaptations & Equipment
Reactive budget to provide adaptations and equipment for HSCP clients.
Early Years Early Learning and Childcare Funding
Early learning and childcare funding awarded to West Dunbartonshire Council to facilitate the expansion in entitlement to
funded ELCC to 1140 hours from August 2020.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works progressing in 2023/24.
Anticipated Outcome
Provision of adaptations and equipment to HSCP clients as anticipated.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
There is likely to be a small underspend in the current year due to the implementation of the new system, however this will require to be carried forward to 2024/25 in light
of anticipated equip cost increases and as activity levels increase back to normal levels.
Mitigating Action
None available at this time

Page 13

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Electronic Insurance System58
Project Life Financials 584 50 9% 584 0 0%
Current Year Financials 584 47 8% 50 (534) -91%
Project Description
Project Manager Alastair Handley
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-24 31-Mar-24
59
Project Life Financials 388 50 13% 388 0 0%
Current Year Financials 308 12 4% 50 (258) -84%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-24 31-Mar-24
60
Project Life Financials 19 3 14% 3 (16) -84%
Current Year Financials 19 3 14% 3 (17) -86%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-24 31-Mar-24
61
Project Life Financials 60 50 83% 50 (10) -17%
Current Year Financials 10 0 0% 0 (10) -100%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 31-Oct-22 31-Mar-24
HSCP ICT Upgrade of systems
Review/replace the current case management systems.
Planned End Date Forecast End Date
Community Alarm upgrade
To upgrade Community Alarm
Planned End Date Forecast End Date
Main Issues / Reason for Variance
While there has been some movement on the project to date, progress is slow.  Procuring equipment that is fully compatible with the platform is the priority to enable
WDHSCP to best support the digital rollout, however delays from Scotland Excel has required an alternative procurement solution to be identified for a smaller scale
initial purchase.  The contract for the Digital ARC has been awarded and a test unit and access to the demo platform has been received with a plan to on-board
partnerships to the live platform in Spring 2024, while the process to formalise arrangements with East Dunbartonshire Council for the ARC cover for the calls is ongoing
with the cost for the call handling service still to be confirmed.
Main Issues / Reason for Variance
A HSCP Digital Strategy 2024-2027 is in development. The strategy will have an internal focus, identifying areas where the HSCP would need to progress to support
digital transformation and improve the digital maturity of the partnership. The strategy will focus on areas where structures are in place to support change, where focus
will be required and setting the stage for opportunities to move forward. As well as digital technologies, the strategy will focus on staff skills and digital inclusion within our
communities, and support digital change projects over the duration of the strategy. A draft version of the strategy is out for comment, and has been submitted to the
Senior Management Team, with a view to a final version being submitted to HSCP Board for approval on 25th June.  It is unlikely that the budget will be fully spent by
March 2024, however the budget will be required to be carried forward to next financial year to progress planned works
Mitigating Action
None available at this time as project spend will be dependent upon the digital strategy being approved by the HSCP Board
Anticipated Outcome
Upgrade and enhance digital systems within HSCP
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works Complete
Mitigating Action
None available at this time
Mitigating Action
Officers will continue to progress the project as quickly as possible but is complex and dependent on 3rd parties and equipment being compliant with the platform
Anticipated Outcome
Community Alarm Upgrade
Criminal Justice Adaptations
Renovation of Unit 11 Levenside Business Court.
Anticipated Outcome
Renovation of Unit 11 Levenside Business Court
Mitigating Action
None available at this time.
Anticipated Outcome
projects delivered on time.
Internet of Things Asset Tracking
Asset Tracking.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project Complete