WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer (Regeneration and Regulatory)
Council: 27 March 2024
Subject: Glasgow City Region City Deal - Update
1. Purpose
1.1 To note the progress with the implementation of the Exxon Infrastructure
Project, and to provide an update on Glasgow City Region City Deal
Programme.
2. Recommendations
2.1 It is recommended that Council notes:
i) The progress of the Glasgow City Region programme
ii) The update on the Exxon Infrastructure Project
3. Background
3.1 The Glasgow City Region City Deal Infrastructure programme equates to
£1.13bn of investment during period 2015-2035. Projects are progressing
and have reached various stages from Strategic, Outline and Full Business
Case stages of approval.
4. Main Issues
4.1 This report provides information on City Region progress, and includes an
update on the Exxon site infrastructure project development.
Exxon Infrastructure Project
4.2 At its meeting in December 2023, Council noted progress made with the
Exxon Infrastructure Project and approved delegated authority to agree the
construction agreements required to deliver the project, subject to the
approval of Planning and the conclusion of land transfers. Planning
permission was granted in January 2024.
4.3 The main construction contract will be signed when all required land
acquisitions and temporary access agreements are concluded. Land
acquisitions are being progressed in line with the terms agreed with
landowners and are anticipated to be complete by the end of March 2024.
4.4 The Esso remediation work is delayed due to newly discovered heavy
contamination pockets on site at close proximity to the water edge. The latest
prediction to complete the work on site is end of April which will be followed
by a 4-6 weeks decommissioning phase. Parallel to this activity the
remediation report approval will be concluded. The estimated earliest land
ITEM 9

Page 2

transfer of the formal Esso site is mid-June 2024. 
4.5 The UK Government have recently confirmed to the  Glasgow Region City
Deal Programme Management Office that 50% of the £128m funding that was
to be released as a result of transferring the responsibility of delivery of
Glasgow Airport Rail Link from City Deal to Clyde Metro should be spent on
one new regional project. Prior to this announcement City Region Member
Authorities had anticipated that 100% of the reprogrammed monies would be
available to Member Authorities to meet the increased costs of their City Deal
Infrastructure projects, including Exxon. Consequently, only half of the
anticipated additional funding for the Exxon project will be now available. Each
Member Authority’s share of the funding will be confirmed later in 2024 in
tandem with the selection of the new regional project (refer to paragraph 4.9
for further information). Commencement of works at Exxon will not prejudice
the Council’s claim for additional funding. 
4.6 Decisions on Stage 2 Vacant and Derelict Land funding applications have
been delayed by Scottish Government in order to take stock of the impact of
recent reductions in their capital budget. The Council had submitted a £2m
application for greenspace and access improvements on the Exxon site and
was expected to hear the outcome in January of this year. 
City Region Update 
4.7 The last Glasgow City Region Cabinet Meeting was held on 13 February
2024.  Agenda items included: 
• proposed new Regional Spatial Planning Arrangements
• further information on the City Deal Reprogramming Exercise (referred to
in paragraph 4.5)
• an update on the City Region Investment Zone
• an update on Regional Electric Vehicle Charging. 
4.8 The report on Regional Spatial Planning outlined the proposed process for
agreeing the Regional Spatial Strategy which National Planning Framework 4
(NPF4)  has introduced, and which will replace Clydeplan. The report makes
the case for the Regional Spatial Strategy incorporating the various recent
economic ventures and initiatives, such as Investment Zone. 
4.9 Cabinet heard the process for Member Authorities to submit a proposal for
one new £64m project, or 2-3 smaller projects across Member Authorities
that would fulfil the expectations of UK Government and comply with the City
Deal’s own Assurance Framework. A call for bids with a 12 week turnaround
has been sent to Member Authorities to produce a Strategic Business Case
for eligible projects. Projects must have a regional impact and meet the
objectives of the Regional Economic Strategy. Member Authorities will be
responsible for delivery and managing risk. Programme Management Office
will revert to UK and Scottish Government for further advice if there are no
suitable bids identified following bid submission and assessment. At that
stage a regional programme might be considered but there is no guarantee
this will be acceptable to either or both governments.

Page 3

4.10 Stage 2 bids for the Investment Zone are to be submitted by the end of
March. It’s been confirmed that the funding available, and the timescale for
expenditure, of Investment Zone benefits has doubled to £160m, over 10
years.  The Stage 2 bids are expected to be led by business and/or
universities. The Regeneration and Business Support teams are currently
supporting one bid, and following a call to business via social media, have
responded to other enquiries.   
4.11 The Clyde Bridge contractor maintains a website with regular updates on the
project. A viewer at the top of the website home page shows a video of
progress which is updated monthly. This can be accessed at:
www.graham.co.uk/clyde-waterfront 
5 People Implications 
5.1 There are a number of senior officers involved in the Glasgow City
Region wider programme as identified at City Region Update paper at
Council on 26 August 2021. 
6. Financial Implications 
6.1  Spend this financial year to date on the Exxon project is £2,546,742.  
Overall spend is £6,483,747 
7. Risk Analysis 
7.1 There are a number of project risks associated with the development at
the Exxon project site and these are contained within the project risk
register and updated by the Project Board on a regular basis. The Project
Board is made up of senior officers from all key services. 
8. Equalities Impact Assessment 
8.1 Not relevant for this report 
9. Consultation 
9.1 Consultation with all key stakeholders is progressing as we continue
to work as part of the Glasgow City Region.
10 Strategic Assessment 
10.1 At its meeting on 26 October 2022, the Council agreed that one of its
main strategic priorities for the Strategic Plan 2022 - 2027 is ‘A Strong
local economy and improved employment opportunities’ 
10.2 The proposals within this report are specifically designed to deliver on
this priority.

Page 4

Alan Douglas
Chief Officer: Regulation and Regeneration
Date: 13 March 2024 
Person to Contact: Gillian McNamara 
gillian.mcnamara@west-dunbarton.gov.uk 
Appendix: None   
Background Papers: UK Shared Prosperity Fund Report to Housing and
Communities Committee 22 August 2022                                          
Glasgow City Region City Deal- Council 13 August 2014.                                          
“City Deal Initiative” Clyde Valley Investment Fund-
Council 30 April 2014 (Memorandum of Understanding).                                          
Clyde Valley Community Planning Partnership – City Deal
Initiative – Council 28 August 2013.   
Wards Affected: All