WEST DUNBARTONSHIRE COUNCIL APPENDIX 1
HRA CAPITAL INVESTMENT PROGRAMME
CAPITAL PROJECTS FORECAST OUTTURN AND REPROFILING REQUIRED
RESOURCES
2023/24
Forecast
Outturn
£000
2023/24
Budget
Inc B/F
£000
Reprofiling
required
£000
Over / 
(Under)
Recovery
£000
New Build Grant 6,885 28,055 0 21,170
Buy Back Grant 3,000 0.00 0 (3,000)
Prudential Borrowing / CFCR 45,795 96,788 0 50,993
Total Resources 55,680 124,843 0 69,163
CAPITAL EXPENDITURE
2023/24
Forecast
Outturn
£000
2023/24
Budget
Inc B/F
£000
Reprofiling
required
£000
Over / 
(Under)
Recovery
£000
OTHER CAPITAL EXPENDITURE 4,528 4,240 2,238 (2,526)
Special Need Adaptations 585 600 0 15
Capitalised Minor Works 3,200 525 0 (2,675)
Better Homes Priority Budget 154 529 375 0
Environmental Sensors Programme 500 2,000 1,500 0
Housing CCTV Installation Programme 0 250 250 0
Housing Management System Development 16 116 0 100
Gypsy Travellers Site Upgrades 37 71 0 34
Community Safety Projects 0 17 17 0
Airport Noise 0 96 96 0
Redeployable CCTV Cameras 36 36 0 0
MAJOR COMPONENT REPLACEMENTS 17,902 21,810 1,538 2,370
Targeted EESSH compliance works 4,400 6,146 1,746 0
Building external component renewals 3,150 5,679 0 2,529
Doors/window component renewals 4,580 4,547 (33) 0
External stores/garages/bin stores 80 45 0 (35)
Secure entry component renewals 22 45 0 23
Statutory/regulatory compliance works 50 113 0 63
Heating improvement works 2,200 1,840 0 (360)
Energy improvements/energy efficiency works 10 57 0 47
Modern facilities and services 3,410 3,235 (175) 0
Non Traditional/Traditional Improvement Works 0 103 0 103
VOID CAPITAL 6,735 3,000 0 (3,735)
Void house strategy programme 6,735 3,000 0 (3,735)
CONTINGENCIES 0 100 0 100
Contingencies 0 100 0 100
STRUCTURAL & ENVIRONMENTAL 2,162 3,420 1,200 58
Defective structures/component renewals 422 877 0 455
Environmental renewal 1,540 1,017 0 (523)
Asbestos management works 100 226 0 126
Multi-Storey Flat Strategy 100 1,300 1,200 0
SUPPORT COSTS 2,629 2,629 0 0
Direct Project Support 2,629 2,629 0 0
AFFORDABLE SUPPLY PROGRAMME 21,724 89,644 (65) 67,985
Buy Backs 4,500 4,435 (65) 0
New Builds 17,224 85,209 0 67,985
TOTAL 55,680         124,843           4,911              64,252