Page 1

Appendix 7
Recurring Budgets
Aids & Adaptations The provision of Aids and Adaptations links some of our main strategic priorities of Early
Intervention, Access and Resilience – which ties into the Scottish Government’s 2020 Vision of
“supporting people to live longer, healthier lives at home or in a homely setting” for as long as is
reasonably possible and also to support WD residents (mainly older people and physical
disabilities) to be discharged home from hospital as soon as possible – a key Strategic Priority as
set out in the HSCP Strategic Plan
Building Upgrades and H&S This links to key objectives within the Regeneration Delivery Plan, Asset Management Service Plan
and Property Asset Management Plan.  Contained within Asset Management Plan Property.
ICT Modernisation ICT Asset management plan commits to delivering ICT assets that are fit for purpose in terms of
ease of use, meeting business requirements and innovative
ICT Modernisation HSCP ICT Asset management plan commits to delivering ICT assets that are fit for purpose in terms of
ease of use, meeting business requirements and innovative
ICT Security & DR ICT Asset Management Plan commits to delivering a secure and resilient but cost effective
infrastructure to support service delivery and minimise disruption
Infrastructure - Roads This links to the Roads Asset Management Plan - to provide an improved Roads
Infrastructurewhich supports the Council's strategic aims & objectives with respect to connectivity
and access to employment, education, health, leisure  and transport opportunities.
Vehicle Replacement The Asset Management Plan - Vehicle Fleet establishes the replacement intervals for light
commercial vehicles (10 Years) and heavy vehicles (7 years) from the date of first registration. The
capital budget for replacement vehicles is aligned to replacement dates of the vehicles.
Flood Risk Management SEPA licensing & delays incurred by 3rd party utilities resulted in slippage of programme &
therefore budget Linking to AMP Flood protection of River Leven & surrounding water  courses &
critical drainage infrastructure.
Cycling, Walking and Safer Streets AMP states that we will undertake footway/cycleway Capital improvements.
Street Lighting and asssociated
electrical infrastructure
AMP states that we will continue with our ongoing programme of column and infrastructure
replacement.
Public non adopted paths and
roads
Upgrading paths is mentioned in the following sections of the Open Space Asset Management
Plan - Amenity Greenspace, Public parks, Green Corridors and Cemeteries.
Regeneration/Local Economic
Development
The LED budget contains numerous sub-projects.
Direct Project Support This is a general support budget that is not linked to a specific asset management plan
Legal Case Management System ICT Asset management plan commits to delivering ICT assets that are fit for purpose in terms of
ease of use, meeting business requirements and innovative
Solicitor Post Support for various capital projects.
Demolition 215 Main Street
Alexandria
This links to key objectives within the Asset Management Service Plan and Property Asset
Management Plan. 
Antonine Wall Heritage Lottery
Fund
This is a multi partner project and is a heritage site involving Historic Environment Scotland and
other Local Authorities. The aim is to carry out regeneration heritage projects and development. It
links in with Regeneration of West Dunbartonshire area.
Installation of Solar PV at
Clydebank Leisure Centre
This links to key objectives within the Regeneration Delivery Plan, Asset Management Service Plan
and Property Asset Management Plan. To continue to reduce energy consumption and deliver
savings through effective asset management.
Replace existing main hall Air
Handling unit at Clydebank Town
Hall
This links to key objectives within the Asset Management Service Plan and Property Asset
Management Plan. 
Replace failed heating
controls/valves & recommision
This links to key objectives within the Regeneration Delivery Plan, Asset Management Service Plan
and Property Asset Management Plan. To continue to reduce energy consumption and deliver
savings through effective asset management.
Leisure Energy projects This links to key objectives within the Regeneration Delivery Plan, Asset Management Service Plan
and Property Asset Management Plan. To continue to reduce energy consumption and deliver
savings through effective asset management.
Regeneration Fund This links in with plans to regenerate the West Dunbartonshire area and there are sub projects
within the plan to allow this to happen.
Place Based Investment This links in with plans to regenerate the West Dunbartonshire area and ensure plans are shaped
by the needs of the community
Clydebank Can on the Canal This project will provide a new community-run activities centre in Clydebank Town Centre which
assists with the regeneration nof the local area.
District Heating Network Expansion This links to key objectives within the Regeneration Delivery Plan, Asset Management Service Plan
and Property Asset Management Plan. Corporate Asset Management Strategy.
Level Up CapacityFunding Funding received from Scottish Government which has been targeted to support regeneration of
the lcoal area
Level Up Funding Funding received from Scottish Government which has been targeted to support regeneration of
the lcoal area
Transformation of Infrastructure
Libraries and Museums
Committee approved spend to invest in the improvement of the Libraries and Culture Service. This
fits in with efficient, effective, frontline services from the Strategic Plan.
Heritage Capital Fund Administration budget commitment
Invest in "Your Community
Initiative"
The H+E Delivery Plan clearly sets out the challenge of the competing demands of delivering
joined-up services to local areas, against a backdrop of financial and resourcing challenges. The
Delivery Plan confirms that the Your Community Inititative, which includes Community Budgeting
and the Improvement Fund, is the council's approach to delivering services to local areas and
involving local communities.  The Communities Team continue to work to embed this approach
across relevant council services and CPWD to improve ways of delivering the required services,
while improving community participation and engagement.
Valuation Joint Board This is linked to the VJB capital plan
General Services Capital Plan Linkage of Capital Projects to Asset Management Plans
Chief Officer - Regulatory and Regeneration
Chief Officer - Communications, Culture, Communities and Facilities
Chief Officer - Resources

Page 2

Payment Card Industry Data
Security Standard (PCIDSS)
Development work required for Legislative purposes and to provide adequate security for citizens
making payment to the Council
Development of Agresso Development work required to ensure our computer systems remain robust and fit for purpose
Cash Receipting system
enhancements
Development work required to ensure our computer systems remain robust and fit for purpose
Electronic Insurance System Although not linked to a specific AMP this system will improve the working processes within the
insurance team, streamlining reporting and claims handling processes being dealt with. It will
improve the digitalisation of the work within the team.
Cost of Living Required to assist with cost of living projects.
IFRS 16 Database To ensure compliance with new accounting standard for leasing
Strathleven Place This links to key objectives within the Regeneration Delivery Plan, Asset Management Service Plan
and Property Asset Management Plan and Corporate Asset Management Strategy.
Dalmonach CE Centre This links to key objectives contained within Asset Management Plan Property & Corporate Asset
Management Strategy.
New Sports Changing Facility (Old
OLSP site)
This links to key objectives within the Regeneration Delivery Plan, Asset Management Service Plan
and Property Asset Management Plan. Contained within Asset Management Plan Property &
Corporate Asset Management Strategy.
New Sports Changing Facility at
Lusset Glen in Old Kilpatrick
This links to key objectives within the Regeneration Delivery Plan, Asset Management Service Plan
and Property Asset Management Plan. Contained within Asset Management Plan Property &
Corporate Asset Management Strategy.
Depot Rationalisation This links to key objectives within the Regeneration Delivery Plan, Asset Management Service Plan
and Property Asset Management Plan. Contained within Asset Management Plan Property &
Corporate Asset Management Strategy.
Dalmonach Steps Upgrade Funding received to make steps more accessible,
Pappert 2G Pitch This project links to the Open Space Asset Management Plan Action Plan.
Exxon City Deal This links to key objectives within the Regeneration Delivery Plan, Asset Management Service Plan
and Property Asset Management Plan. Corporate Asset Management Strategy.
Allotment Development There is a section within the Open Space Asset Management Plan Action Plan on Allotments. This
states that in line with the Councils obligations under the Community Empowerment Act we will
provide three new allotment sites of at least 0.66 hectares.
Kilmaronock Cemetery Extension The Open Space Asset Management Plan states that we will construct an extension to
Kilmaronock Cemetery.
Posties Park Sports Hub Within the Open Space Asset Management Plan it states that the provision of new 3G pitches and
new pavillions has improved the overall sports pitch asset, however there are some facilities still
classed as poor which require addressing.
Sports Facilities Upgrades - Argyll
Park - Construction of 3 All Weather
Tennis Courts
Within the Open Space Asset Management Plan it states that the provision of new 3G pitches and
new pavillions has improved the overall sports pitch asset, however there are some facilities still
classed as poor which require addressing.  Contained within Asset Management Plan Property &
Corporate Asset Management Strategy
Vale of Leven Cemetery Extension The Open Space Asset Management Plan states that we will identify a new Cemetery site in the
Vale of Leven.
Play Area Upgrade Programme This project links to the Open Space Asset Management Plan Action Plan where there is a section
on Playspace for children and teenagers
Nature Restoration Fund Funding has been received from Nature Restoration Fund to build nature resource for Faifley
community.
Pavement Improvements AMP states that we will undertake footway improvements as part of the Capital Programme.
Auld Street Clydebank - Bond Works to be carried out from recovered Road Bond include C/way, F/Way resurfacing, roundal &
street lighting.
A813 Road Improvement Phase 1 A813 forms a strategic link from the settlements witing WDC both Carriageway and geometery
require upgrading to current specifications and is named in current AMP.
Roads Safety Funding for speed bumps to ensure safer roads
Clydebank Charrette, A814 This will enhance the A814 through Clydebanl and links to the current AMP
Strathclyde Partnership for
Transport - Bus, cycling and
walking infrastructure
improvements & Park and Rides
These projects improve & support connectivity and equal access to Public transport and
infrastrutures for cycling.
Purchase of Gritters Allows the Counci to continue to deliver savings through effective asset management.
Turnberry Homes Final tranche of these works to be completed in conjuction with Dumbarton East footway
improvements. As previously noted AMP states we will deliver capital footway improvements to
facilitate safe pedestrian routes and encourage active travel.
Electrical Vehicle Charging AMP states that we will continue to work with other service deprtments and organisations to install
Electric Vehicle Charging points.
River Leven Flood Prevention
Scheme
AMP states that we will develop and produce a Flood Protection Study of the River Leven.
Continued  participation in CaLL - Clyde & Loch Lomond Flood Prevention Management Group.
Flood Prevention Development of flood prevention plans
Gruggies Burn Flood Prevention
Scheme
Project design is ongoing as optioneering has produced alternative design solutions ongoing
discussions with Consultants, Contractors & SEPA have permitted us to appoint a Specialist
Contractor via Scape framework to produce a "Buildabilit"y statement. Ground investigation works
instructed under Scape framework. Specialist Consultant appointed via SLC Professional Services
Framework.  AMP - continuation of the developement of Gruggies Burn and subsequent
implementation of Gruggies Burn Flood Prevention Scheme.
Bus rapid development fund Funding has been awarded from Sustrans to assist with social distancing measures required as a
result of the COVID-19 pandemic.
Waste Transfer Station The design, development and construction of a recycling and bulk waste transfer facility that will
ensure all recycling material can be sorted and disposed off appropriately to ensure compliance
with landfill ban in 2025.
Replacement of compactors at
Dalmoak civic amenity site
The purchase of 2 compactors for the Council civic amenity site at Dalmoak.
Depot Improvement Works Improvement of WDC Roads Depot to ensure fit for purpose
Large Bins for High Traffic Areas
(pilot)
Purchase of larger bins for high traffic areas to assess
Electric Vehicle Infrastructure AMP states that we will continue to work with other service deprtments and organisations to install
Electric Vehicle Charging points.
Chief Officer - Environment and Neighbourhood

Page 3

Roads Plant The Asset Management Plan - Vehicle Fleet establishes the replacement intervals for light
commercial vehicles (10 Years) and heavy vehicles (7 years) from the date of first registration. The
capital budget for replacement vehicles is aligned to replacement dates of the vehicles.
East End Park Resurfacing AMP states that we will undertake footway improvements as part of the Capital Programme.
Cemetery Extension, North
Dalnotter
Links to the Asset Management Plan.
Balloch Mountain Bike Track AMP states that we will undertake footway improvements as part of the Capital Programme.
Traffic Signal Upgrades Upgarde required due to repeated failure of current signlas
Vehicle Replacement Strategy The Asset Management Plan - Vehicle Fleet establishes the replacement intervals for light
commercial vehicles (10 Years) and heavy vehicles (7 years) from the date of first registration. The
capital budget for replacement vehicles is aligned to replacement dates of the vehicles.
River bank erosion repair -
Levenhowe
Assist with flood prevention
Park Improvements and Mulit
Games Area - Goldenhill Park
This project links to the Open Space Asset Management Plan Action Plan
Whitecrook Tennis Court Upgrade This project links to the Open Space Asset Management Plan Action Plan
AV Equipment - Education The current Education audio visual estate numbers ~650 teaching boards. ~200 boards are
currenty aged 7+ years old and/or faulty. The project aims to create and maintain a 'fit for purpose'
learning enviroment to ensure compatability with emerging and futre technology by replacing
ageing and faulty audio visual teaching boards.
Digital Inclusion Increase the ratio of chrome book devices for most disadvantaged children and families and
support for families with remote access. Particular requirement during recent pandemic
Schools Estate Improvement Plan -
next Phase Faifley
This links to key objectives within the Regeneration Delivery Plan, Asset Management Service Plan
and Property Asset Management Plan. Contained within Asset Management Plan Property &
Corporate Asset Management Strategy
Schools Estate Improvement Plan This links to key objectives within the Regeneration Delivery Plan, Asset Management Service Plan
and Property Asset Management Plan. Contained within Asset Management Plan Property &
Corporate Asset Management Strategy
Free School Meals This links to key objectives within the Regeneration Delivery Plan, Asset Management Service Plan
and Property Asset Management Plan.
Early Years Early Learning and
Childcare Funding
This is linked to the Early Year Strategy
Criminal Justice Adaptations Renovation of Unit 11 Levenside Business Court which is funded from revenue.
Community Alarm upgrade Development work required to ensure our computer systems remain robust and fit for purpose
Internet of Things Asset Tracking ICT Asset management plan commits to delivering ICT assets that are fit for purpose in terms of
ease of use, meeting business requirements and innovative
365 Implementation ICT Asset management plan commits to delivering ICT assets that are fit for purpose in terms of
ease of use, meeting business requirements and innovative
Development of Workforce
Management System
ICT Asset management plan commits to delivering ICT assets that are fit for purpose in terms of
ease of use, meeting business requirements and innovative
Chief Officer - Health and Social Care Partnership
Chief Officer - People and Technology
Chief Officer - Education, Learning and Attainment