WEST DUNBARTONSHIRE COUNCIL APPENDIX 9
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
PERIOD END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials (2,169) (2,070) 95% (2,169) (0) 0%
Current Year Financials (2,070) 0 0% (2,070) 0 0%
Project Description
Project Lifecycle 31-Mar-24 31-Mar-24
2
Project Life Financials (92,560) (41,875) 45% (93,795) (1,236) 1%
Current Year Financials (7,453) (7,453) 100% (7,453) 0 0%
Project Description
Project Lifecycle 31-Mar-30 31-Mar-30
3
Project Life Financials (38,717) (20,133) 52% (40,756) (2,039) 5%
Current Year Financials (15,743) (2,659) 17% (15,743) 0 0%
Project Description
Project Lifecycle 31-Mar-26 31-Mar-26
4
Project Life Financials (6,783) (5,739) 85% (6,325) 458 -7%
Current Year Financials (2,933) (117) 4% (2,933) 0 0%
Project Description
Project Lifecycle 31-Mar-24 31-Mar-24
31 October 2023
Budget Details
Project Life Financials
Application of resources is dependent on capital project progressing in year as planned.
Spend to Date Forecast Variance
Resources Carried Forward
These are resources that have been received in previous years relating to Turnberry Homes, Town Centre Fund
Grant, Digital Inclusion, Clydebank Can on the Canal, Internet of Things Asset Tracking, Renew Playparks,
Knowes Nature Reserve, Flood Prevention, District Heating Electric Vehicle Infrastructure and Auld Street Bond.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Application of resources held on balance sheet as at 31 March 2023 as appropriate.
General Services Capital Grant
This is a general grant received from the Scottish Government in relation to General Services capital spend
Application of resources is dependent on capital project progressing in year as planned.
Main Issues / Reason for Variance
General services capital grant is anticipated to be received as forecast.
Mitigating Action
None required at this time
Anticipated Outcome
General services capital grant is anticipated to be received as forecast.
Ring Fenced Government Grant Funding
This is ring fenced grant funding which is primarily anticipated to be received from the Scottish Government and
relates to Cycling, Walking, Safer Streets, Regeneration Placed Based Investment Programme, Early Years,
Gruggies Burn Flood works, Early Years funding, City Deal and Town Centre Fund.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
None required.
Mitigating Action
Mitigating actions are detailed within the appropriate status updates.
Anticipated Outcome
Application of resources as appropriate.
Match Funding / Other Grants and Contributions
Match Funding / Other Grants and Contributions
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Application of resources is dependent on capital project progressing in year as planned.
Mitigating Action
Anticipated Outcome
Match funding received.

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 9
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
PERIOD END DATE
PERIOD 7
Budget Forecast Spend
£000 £000 % £000 £000 %
31 October 2023
Budget Details
Project Life Financials
Spend to Date Forecast Variance
Resources Carried Forward
5
Project Life Financials (146,754) (71,953) 49% (143,392) 3,362 -2%
Current Year Financials (63,067) 2,532 -4% (26,702) 36,365 -58%
Project Description
Project Lifecycle 31-Mar-26 31-Mar-26
Prudential Borrowing
Prudential borrowing is long term borrowing from financial institutions that has been approved for the purposes of
funding capital expenditure
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Prudential borrowing is impacted by programme delivery therefore mitigating action is detailed in the red and amber analysis.
Mitigating Action
None available at this time.
Anticipated Outcome
While prudential borrowing requirement is likely to be less than budgeted in the current financial year this is anticipated to catch up over the
programme life.