WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer (Regeneration and Regulatory)
Council: 20 December 2023
Subject: Glasgow City Region City Deal and Exxon Site Project
1. Purpose
1.1 To approve the construction agreements with Balfour Beatty Civil
Engineering Ltd and Network Rail for the Exxon site infrastructure project
to note the progress being made on delivering the projects, and to note
the progress with the implementation of the Glasgow City Region
programme.
2. Recommendations
2.1 It is recommended that Council
i) Delegate authority to the Chief Officer of Regulatory and Regeneration to
agree the construction agreements with Balfour Beatty Civil Engineering
Ltd  and Network Rail and such ancillary agreements as may be required
to deliver the works, all in line with approved budget
ii) note the progress made on site remediation made by ExxonMobil, and
the new target completion date of end February 2024
iii) note the progress made with Network Rail on possession of the site for
construction of the western underpass
iv) note that the outcome of the Council’s additional funding request to
Glasgow City Region is not yet known
v) note the progress of the Glasgow City Region programme.
3. Background
3.1 The Glasgow City Region City Deal Infrastructure programme equates to
£1.13bn of investment during period 2015-2035. Projects are progressing
and have reached various stages from Strategic, Outline and Full Business
Case stages of approval. The Exxon Site Infrastructure project is West
Dunbartonshire’s City Deal funded project.
4. Main Issues
4.1 This report seeks approval to conclude the construction agreement with
Balfour Beatty, Network Rail and such other parties (e.g. Scottish Gas
Networks, Scottish Power Energy Networks etc.) for the Exxon infrastructure
project, conditional upon approval of planning permission, which is anticipated
ITEM 10

Page 2

in January 2024, and conclusion of acquisition of third party land, anticipated
by end of January 2024. The report also provides an update on City Region
progress. 
Exxon Infrastructure Project 
4.2 Following the approval of the Full Business Case by Council in June and by
Glasgow City Region Cabinet in August of this year, Balfour Beatty have
been engaged in producing final costs and contractual documentation for the
construction of the Exxon transport infrastructure project. 
4.3 The current estimated cost based on the Final Business Case remains at
£44.325m, as reported to Council in June 2023.  The transport infrastructure
design is completed and has been consulted with relevant statutory bodies.
Planning determination is in progress and will be reported to Planning
Committee in January 2024. The construction contracts with Balfour Beatty
are expected to be finalised by February 2024, and some early works
activities might be considered to accelerate the programme prior to the Exxon
Site land transfer. The wider landscape and path development design is also
progressing.   
4.4 The remediation work undertaken by Esso Petroleum is ongoing. Site
excavation has slowed down due to a significant wet period during
September and October. The estimated completion date for remediation is
the end of February 2024, however this will not automatically trigger land
transfer. Additional time is required for a report by Esso`s environmental
contractor, WSP and the Regulators. A phased approach has been agreed
for report submissions to speed up and review times, and a final report
review is expected in April 2024 at the earliest. This will trigger the land
transfer from Esso to the Council. 
4.5 Network Rail confirmed that our request for the 5 days possession between
the 24th and 30th December 2024 was approved to allow the construction of
the western underpass. The construction contract is programmed to be
finalised by the 29th March 2024 and pre-construction start is expected on the
20th May 2024 for the western underpass. 
4.6 In relation to land acquisitions there are a number of Temporary Access
Agreements required to be completed and these have been agreed in
principal pending confirmation of dates and scope of works. All land
acquisitions are being progressed and are anticipating completing these in
January 2024.   
4.7 The Council has requested that further funding be made available from
Glasgow City Region to offset some of the Council’s contribution to the
£44.325m project cost. It had been hoped that the outcome of that request
would have known by now, but due to delays in City Region gaining both
Governments’ agreement to the proposed method of project prioritisation and
fund redistribution, we are advised that the outcome won’t be known until
early 2024 though no further details are available at present.

Page 3

4.8 A Stage 2 Vacant and Derelict Land grant application for £1.9m to fund
greenspace and footpath improvements has been submitted to Scottish
Government, with the outcome expected in late January 2024. If the funding
application is successful, it is anticipated that the delivery of work will be
added as a variation to the main construction contract via the SCAPE
Framework. 
4.9 Residents, businesses and Elected Members will be kept well informed
throughout the project. In addition, the Council will work with partners
including Transport Scotland, to ensure all key messaging about the project
is distributed widely to maximise reach and engagement. 
4.10 A promotional brochure for the site is currently being designed and will be
produced before any works take place on site that can be distributed to
interested developers and other parties. 
City Region Update 
4.11 The last Glasgow City Region Cabinet Meeting was held on 7 November
2023. Agenda items included Clyde Climate Forest; Glasgow City Region
Education Improvement Plan; a presentation on the Regional Transport Plan
by SPT; Glasgow City Region Innovation Action Plan; Glasgow City Region
Investment Zone; an update on the Clyde Mission move to City Region from
Scottish Government; an update on Shared Prosperity Fund; a report on
Governance and a recommendation to approve the Outline Business Case
for A78 Inverkip Transport Improvements in Inverclyde Council. 
4.12 The City Region Update report to Council in October 2023 set out UK
Government’s intention to establish an Investment Zone of up to 600
hectares in Glasgow City Region to facilitate the expansion of industry,
commerce and research & development within key growth sectors. Following
a consultation process with our larger businesses that fall into the key
sectors, and in response to Glasgow City Region seeking suggestions on
where Investment Zones could be established, the Council submitted a
proposal identifying the proposed Scottish Marine Technology Park at the
former Carless site together with some adjacent underused land, and the
Exxon site together with the adjacent Scotts Yard as potential locations for an
Investment Zone in West Dunbartonshire. In consultation with Peelports,
Rothesay Dock in Clydebank was also identified as an area that could
contribute to a wider Investment Zone across multiple local authorities.
Glasgow City Region Programme  Management Office is now in discussion
with both Governments to undertake a sifting exercise that will determine the
industrial sector to be supported, and, as a second stage, the location(s) of
the Investment Zone 
4.13 The management and administration of Clyde Mission has now moved from
Scottish Government to the City Region, and the work will be overseen by
Regional Economic Strategy Group. A new Head of Place in the Programme
Management Office is to be appointed. Argyll and Bute Council will be part of

Page 4

a Heads of Planning group looking at a masterplan for the Clyde. More
information will follow on grants for the Clyde Missions Heat Decarbonisation
Fund. 
4.14 Glasgow City Region Programme Management Officer continues to monitor
UK Shared Prosperity Fund (SPF) expenditure against the agreed Local
Investment Plan. Council officers continue to promote grants funded by SPF
to our local businesses for Business Recovery & Growth, Early Stage
Growth, Towards Net Zero, Enhancing Tourism Events & Attractions,
Business Gateway Expert Help and Shopfront & Small Business
Improvement Grants. 
Clyde Bridge 
4.13  The Clyde Bridge contractor maintains a website with regular updates on the
project. A viewer at the top of the website home page shows a video of
progress which is updated monthly. This can be accessed at:
www.graham.co.uk/clyde-waterfront 
4.14    Newsletters are accessible to those who register for further updates. A link to
register for updates is contained within the project webpage noted above.   
5 People Implications 
5.1 There are a number of senior officers involved in the Glasgow City
Region wider programme as identified at City Region Update paper at
Council on 26 August 2021. 
6. Financial Implications 
6.1  £1,558,575 has been spent this year on the Exxon project. 
6.2 An overall budget of £44.325M was approved at Council on 28th June
2023.  Officers will continue to seek means of reducing the overall net
cost of the project as it moves into delivery phase. 
7. Risk Analysis 
7.1 There are a number of project risks associated with the development at
the Exxon project site and these are contained within the project risk
register and updated by the Project Board on a regular basis. The Project
Board is made up of senior officers from all key services.   
8. Equalities Impact Assessment 
8.1 An EIA was undertaken as part of the Outline Business Case, and there
have been no material changes since.

Page 5

9. Consultation 
9.1 Consultation with all key stakeholders is progressing as we continue
to work as part of the Glasgow City Region. 
10 Strategic Assessment 
10.1 At its meeting on 26 October 2022, the Council agreed that one of its
main strategic priorities for the Strategic Plan 2022 - 2027 is: 
• A Strong local economy and improved employment opportunities 
10.2 The proposals within this report are specifically designed to deliver on
this priority. 
Alan Douglas
Chief Officer: Regulation and Regeneration
Date: December 2023 
Person to Contact: Gillian McNamara 
gillian.mcnamara@west-dunbarton.gov.uk 
Appendix: None   
Background Papers: UK Shared Prosperity Fund Report to Housing and
Communities Committee 22 August 2022                                          
Glasgow City Region City Deal- Council 13 August 2014.                                          
“City Deal Initiative” Clyde Valley Investment Fund-
Council 30 April 2014 (Memorandum of Understanding).                                          
Clyde Valley Community Planning Partnership – City Deal
Initiative – Council 28 August 2013.   
Wards Affected: All