WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
PERIOD END DATE
PERIOD 5
Spend to Date Spend to
Date
£000 £000
Red
33 35.1% 44,266 51.5% 33 35.1% 1,155 22.9%
Amber
0 0.0% 0 0.0% 0 0.0% 0 0.0%
Green
61 64.9% 41,648 48.5% 61 64.9% 3,897 77.1%
94 100% 85,914 100% 94 100% 5,052 100%
Budget Spend to
Date
Forecast
Spend
Forecast
Variance Budget Spend to
Date
Forecast
Spend
Actual
Variance Re-profiling Over/ (Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
57,482 44,266 58,899 1,417 12,801 1,155 12,689 (112) (122) 11
0 0 0 0 0 0 0 0 0 0
192,693 41,648 192,892 199 80,632 3,897 71,887 (8,746) (8,746) 0
250,175 85,914 251,791 1,616 93,433 5,052 84,576 (8,857) (8,868) 11
(250,175) (85,914) (251,791) (1,616) (93,433) (5,052) (84,576) 8,857
0 (0) 0 (0) 0 0 0 0
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
TOTAL EXPENDITURE
TOTAL RESOURCES
NET EXPENDITURE
Projects are forecast to be overspent and/or significant delay to
completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green
TOTAL EXPENDITURE
Project Status Analysis
Project Life Financials Current Year Financials
Red
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
31 August 2023
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of Projects
at RAG Status
% Projects at
RAG Status
% Project
Spend at
RAG Status
Number of
Projects at RAG
Status
% Projects at
RAG Status
% Project
Spend at
RAG Status
Red
Projects are forecast to be overspent and/or experience material delay
to completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green