WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
PERIOD END DATE
PERIOD 3
Spend to Date Spend to
Date
£000 £000
Red
36 39.1% 58,260 29.7% 36 39.1% 368 26.0%
Amber
0 0.0% 0 0.0% 0 0.0% 0 0.0%
Green
56 60.9% 138,163 70.3% 56 60.9% 1,046 74.0%
92 100% 196,423 100% 92 100% 1,415 100%
Budget Spend to
Date
Forecast
Spend
Forecast
Variance Budget Spend to
Date
Forecast
Spend
Actual
Variance Re-profiling Over/ (Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
60,618 58,260 63,107 2,489 13,152 368 13,163 11 0 11
0 0 0 0 0 0 0 0 0 0
300,265 138,163 299,522 (743) 79,661 1,046 79,661 0 0 0
360,883 196,423 362,629 1,746 92,814 1,415 92,825 11 0 11
(360,883) (196,423) (362,629) (1,746) (92,814) (1,415) (92,825) (11)
0 0 (0) (0) (0) (0) (0) (0)
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
30 June 2023
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of Projects
at RAG Status
% Projects at
RAG Status
% Project
Spend at
RAG Status
Number of
Projects at RAG
Status
% Projects at
RAG Status
% Project
Spend at
RAG Status
Red
Projects are forecast to be overspent and/or experience material delay
to completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green
TOTAL EXPENDITURE
Project Status Analysis
Project Life Financials Current Year Financials
Red
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
TOTAL EXPENDITURE
TOTAL RESOURCES
NET EXPENDITURE
Projects are forecast to be overspent and/or significant delay to
completion
Amber

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 15 6 38% 16 1 4%
Current Year Financials 2 2 119% 2 0 19%
Project Description
Project Manager Russell Hewton
Chief Officer Russell Hewton
Project Lifecycle 31-Mar-23 31-Mar-24
2
Project Life Financials 10 20 199% 20 10 99%
Current Year Financials 0 0 0% 10 10 13594%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-24 31-Mar-24
3
Project Life Financials 50 51 101% 51 1 1%
Current Year Financials 7 0 0% 8 1 10%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-24
4
Project Life Financials 40 40 100% 40 (0) 0%
Current Year Financials 35 0 0% 35 0 0%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 30-Sep-23 30-Nov-23
Anticipated Outcome
Enhancements to the cash receipting system including PCI compliant telephone payment system.
Planned End Date Forecast End Date
Main Issues / Reason for Variance 
Budget has been reprofiled to Financial Year 2023-2024. Version 2 of the upgrade was completed Jan 2023. Currently working on Call Secure Module with an
anticipated go live late Autumn 2023.
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Upgraded Electronic Insurance System.
Enhancements to Cash Receipting System
To enhance the cash receipting system in the way payments are made and allocated to back office by increasing the level
of security that is required for online payments made by customers
Electronic Insurance System
Acquisition of a claims/incident management system supported by an electronic document management system.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The various claim forms and departmental reports have been reviewed and updated and the relevant online request forms were submitted to the Digital Sub-Group to be
converted to Online Achieve Forms.  The various claim forms and departmental reports have now been converted to Online Achieve Forms and are in the process of
being tested. Once complete, the supplier will take matters forward with their design team. An anticipated timeline for completion of the project, taking into account the
various stages i.e. development, testing, going live etc. will be drawn up in conjunction with the supplier at that time.  Budget spend anticipated in 2023/2024.
Main Issues / Reason for Variance
Budget was rephased to 2022-2023 as version upgrade of the Council's cash receipting system is required beforehand and is currently underway. The Module for this
has been secured and anticipated timescales for Go Live is May 2023.
Mitigating Action
None required at this time.
Anticipated Outcome
Upgraded version with PCI compliant telephone payment system.
None required at this time.
Anticipated Outcome
Requisition of ICT Equipment.
Payment Card Industry Data Security Standard (PCIDSS)
Module would ensure that WDC were compliant with the current requirements of PCIDSS for card payments without the
need for numerous costly workarounds
Planned End Date Forecast End Date
Requisition ICT Equipment.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Replacement of laptops, monitors and other ICT equipment. No further spend anticipated.
Mitigating Action
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment5
Project Life Financials 30 30 100% 30 0 0%
Current Year Financials 23 0 0% 23 0 0%
Project Description
Project Manager Adrian Gray
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-27 31-Mar-27
6
Project Life Financials 5 5 100% 5 0 0%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Jackie Nicol Thomson
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-23 31-Mar-24
7
Project Life Financials 1,000 250 25% 1,000 0 0%
Current Year Financials 250 0 0% 250 0 0%
Project Description
Project Manager Adrian Gray
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-26 31-Mar-26
8
Project Life Financials 33 33 100% 33 0 0%
Current Year Financials 33 0 0% 33 0 0%
Project Description
Project Manager Alan Douglas
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Budget has been repahsed from 2022/23. Project was originally delyaed due to COVID19 restrictions and a decision was made to resume project once mocrosoft 365
was implemeted. It is anticipated that the project will complete by 31 March 2024
Mitigating Action
None available  at this time.
Anticipated Outcome
Project will be delivered on budget
Anticipated Outcome
Project will be delivered on time and on budget
Legal Case Management System
Legal Case Management System
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
No variances currently anticiapted.
Mitigating Action
None required at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
Completion of project by 31 Macrh 2024
Cost of Living
To support Council and community organisations with capital costs for cost of living initiatives.
IFRS 16 Database
This is a system which will ensure that WDC has the correct level of information and adheres to correct reporting of IFRS16
- Leasing. 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
IFRS16 has been postponed and is due for implementation this financial year. It is anticipated that full spend will be incurred by 31 March 2024
Main Issues / Reason for Variance
Work done during May and June, plus ongoing. Not invoiced until July.
Mitigating Action
None required
Anticipated Outcome
Anticipate completion of upgrade during 23-24 financial year.
Agresso development
The purpose of this project is to carry out an upgrade of the Agresso Finance System which was last upgraded in 2015. The
requirement to upgrade is to maintain a level of support available from Unit 4 who have advised that support for older
versions of the system is being reduced.
Planned End Date Forecast End Date

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment9
Project Life Financials 61 61 100% 61 (0) 0%
Current Year Financials 58 0 0% 58 0 0%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
10
Project Life Financials 20 20 100% 20 0 0%
Current Year Financials 7 0 0% 7 0 0%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
11
Project Life Financials 290 290 100% 290 0 0%
Current Year Financials 227 0 0% 227 0 0%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
Mitigating Action
Liasing with Leisure to see if opportunity to carry works between Dec and March . Appoint new external structural engineer to provide SER.
Anticipated Outcome
It is anticipated that Tender will go out this financial year. Depending on feedback from leisure re opportunity to close centre for AHU works,  it is hoped Civil works will at
least be intiated this financial year with AHU works completed next financial year.
Leisure Energy projects - air handling units, upgrade lighting, circulating pumps, and draught proofing
Measures to be installed at both Meadow Centre & Vale of Leven Swimming Pool; new pool hall Air Handling Units,
upgrade lighting, circulating pumps Vale of Leven Swimming Pool, internal and external lighting and draught proofing.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Expecting full spend prior to 31 March 2024.  Other priorty projects have cintributed to delay. Also require to appoint structural engineer to progress report amd it is
anticipated that this will be undertaken in the near future.
Main Issues / Reason for Variance
Expect full spend before 31 March 2024.
Mitigating Action
None required.
Anticipated Outcome
Delivery of project with full budget spend.
Replace failed heating controls/valves & recommission
Replace failed heating controls/valves & recommission.
Planned End Date Forecast End Date
Mitigating Action
None Required.
Anticipated Outcome
Works to be undertaken in 24/25
Installation of Solar PV at Clydebank Leisure Centre
Installation of Solar PV at Clydebank Leisure Centre.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Tender works delayed due to Energy Officer being involved in other priority work. Aim to be tendered within this  financial year but  works will not be  completed.

Page 5

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment12
Project Life Financials 1,456 1,456 100% 1,456 0 0%
Current Year Financials 676 0 0% 676 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-24
13
Project Life Financials 747 747 100% 747 0 0%
Current Year Financials 707 0 0% 707 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Dec-22 30-Jun-24
14
Project Life Financials 125 125 100% 125 0 0%
Current Year Financials 26 0 0% 26 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 30-Jun-24
15
Project Life Financials 2,749 2,762 100% 2,762 13 0%
Current Year Financials 814 (248) -30% 814 0 0%
Project Description
Project Manager Sarah Christie/Michelle Lynn
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-23 31-Mar-24
Anticipated Outcome
Projects delivered on budget
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The original projected spend has been affected by internal and external delays due to the Covid 19 recovery, a reduction in the scope of the Clydebank Town Hall project,
a change in the delivery date for the Clydebank Museum at Clydebank Library during the contract award stage, while the new Dalmuir Library and Gallery had to be
rescheduled for approval in August 2021. Officers are now making progress to get projects back on track, projects will still be delivered in full.
Mitigating Action
None avaialble at this time
Heritage Capital Fund
Heritage Capital Fund.
Main Issues / Reason for Variance
This capacity funding was awarded by UK Government to assist with development of LUF bids. WDC has been awarded a grant from LUF Round 1 and the capacity
funding will be used in part to produce Artizan Centre redevelopment options. The balance will be used for Roads/Transportation to develop a major transportation bid for
LUF2.
Mitigating Action
None available at this time
Anticipated Outcome
Projects delivered on budget
Anticipated Outcome
Projects delivered on budget
Levelling Up
Successful LUF applications that meet UK Government's over-riding objective of Levelling Up and transformational
regeneration.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Kier is appointed to design and deliver the Activities Centre at Clydebank Town Centre. Design of the project is underway.
Mitigating Action
None available at this time
Mitigating Action
None required at this tinme
Anticipated Outcome
Projects delivered on budget
Clydebank Can On The Canal
New activities centre in Clydebank Town Centre.
Place Based Investment Programme
Scottish Government Funding to establish a Place-Based Investment Programme to ensure that all place based
investments are shaped by the needs and aspirations of local communities.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects contiue to be progressed and expected to complete this fiancnial year

Page 6

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment16
Project Life Financials 150 150 100% 150 0 0%
Current Year Financials 134 0 0% 134 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-21 31-Mar-24
17
Project Life Financials 2,375 1,175 49% 2,375 (0) 0%
Current Year Financials 1,085 6 1% 1,085 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 31-Mar-25
18
Project Life Financials 50 50 100% 50 (0) 0%
Current Year Financials 13 0 0% 13 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
19
Project Life Financials 2,712 5,305 196% 5,305 2,593 96%
Current Year Financials 864 421 49% 864 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 30-Nov-23
Main Issues / Reason for Variance
Project start was delayed due to planning issues and COVID-19 restrictions. Work commenced January 2021 with a proposed completion date of March 2022 which was 
extended to May 2023 due to design changes required by Planning. There is still a significant amount of work to be undertaken to complete the project and the cost of
this work has been affected by Covid, Brexit and supply chain issues. The project overspent on budget last year and the project will  overspend  overall. Ongoing
connection issues with Scottish Water. Delay issues have been highlighted at a senior level within Scottish Water and communication seems to be improving. Expected
completion date is estimated to be November 2023. However, this is dependent on when water connection is made.
Mitigating Action
None available at this time
Anticipated Outcome
New sports Hub delivered
Posties Park Sports Hub - New sports hub to include gym & running track
Creation of a sports hub at Posties/Marinecraft to include a new changing pavilion/Gym, new all-weather 6 lane running
track, conversion of blaze sports pitch to grass, new fencing, upgrade of existing floodlights and additional car parking.  This
combines the budget approved by the Council in February 2015 for Community Sports Facilities at Posties Park, draw down
Planned End Date Forecast End Date
Mitigating Action
None available at this time
Anticipated Outcome
Sustainable burial environment for local residents.
Kilmaronock Cemetery Extension
Extension of existing cemetery at Kilmaronock. 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget will be used to develop an area of the existing Cemetery for additional burials.  Project scope has now been developed and will be tendered under the minor
civils framework.  Budget spend anticipated in 2023/2024.
Main Issues / Reason for Variance
Various delays due to Covid and other utility issues. Planning was previously delayed but now resolved. Building warrant applications submitted and tender to be issued.
Mitigating Action
None available at this time.
Anticipated Outcome
New build community facility.
Anticipated Outcome
To deliver new sports changing facility.
New Westbridgend Community Centre
New Westbridgend Community Centre
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project was delayed due to a number of COVID-19 related issues and utilities issues.  Unit is now in production but delay to site due to the utility disconnection and
demolition works. Demolition works complete and waiting for a date for installation.
Mitigating Action
None available at this time.
New Sports Changing Facility at Lusset Glen in Old Kilpatrick
New Sports Changing Facility at Lusset Glen in Old Kilpatrick

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment20
Project Life Financials 25 25 100% 25 0 0%
Current Year Financials 6 0 0% 6 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
21
Project Life Financials 217 217 100% 217 0 0%
Current Year Financials 214 0 0% 214 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
22
Project Life Financials 400 400 100% 400 0 0%
Current Year Financials 42 0 0% 42 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
23
Project Life Financials 314 314 100% 314 (0) 0%
Current Year Financials 56 0 0% 56 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
Main Issues / Reason for Variance
Charging points to be installed at Moss O' Balloch park - project carried forward from 2022/23
Mitigating Action
None required at this time.
Anticipated Outcome
To provide Electric Vehicle Charging points within West Dunbartonshire.
Electrical Charging Points - Rapid Charge
Funding has been awarded from Transport Scotland for the Installation of electrical charging points
Planned End Date Forecast End Date
Mitigating Action
None available at this time.
Anticipated Outcome
To complete remaining civil works required.
Auld Street Clydebank - Bond
Completion of roadworks associated with Auld Street housing development. Creation of a footpath to Golden Jubilee
Hospital.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Road construction works completed in previous years. Remaining funds are insufficient to complete footpath construction. Works on hold until such time as additional
funds can be secured.
Anticipated Outcome
To improve journey times and reliability of bus services.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Officers working with external partners to identify projects to support funding. Project carried frowrd from 2022/23
Mitigating Action
None available at this time.
Bus Rapid Deployment Fund
Funding has been awarded from Sustrans to assist with social distancing measures required as a result of the COVID-19
pandemic.
Main Issues / Reason for Variance
Supply and install extra large litter bins as a pilot project within hotspot problem areas. Project has commenced.
Mitigating Action
None required at this time.
Anticipated Outcome
Large bins provided for high traffic areas
Large bins for high traffic areas (pilot)
Supply and install extra large litter bins as a pilot project within hotspot problem areas.
Planned End Date Forecast End Date

Page 8

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment24
Project Life Financials 2,485 350 14% 2,485 0 0%
Current Year Financials 237 16 7% 237 0 0%
Project Description
Project Manager Raymond Walsh/ Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
25
Project Life Financials 500 500 100% 500 0 0%
Current Year Financials 500 0 0% 500 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
26
Project Life Financials 4,300 4,300 100% 4,300 (0) 0%
Current Year Financials 138 0 0% 138 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-22 31-Mar-24
27
Project Life Financials 400 400 100% 400 0 0%
Current Year Financials 400 0 0% 400 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
Anticipated Outcome
Project delivered within  budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Delivery delayed by the supplier. Full budget spend expected before the end of the financial year.
Mitigating Action
None available at this time.
Purchase of gritters
Purchase of gritters.
Anticipated Outcome
Projectwill enhance the A814 through Clydebank.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works substantially complete. Additional works as a compensation event started on Wallace street in July 2022.
Mitigating Action
None available at this time.
Clydebank Charrette, A814
Clydebank Charrette, A814
Anticipated Outcome
Projects should be complete within budget.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Plans are under consideration by officers and will be submitted to Elected Members for approval. Project has been carried forward from 2022/23
Mitigating Action
None required at this time.
Mitigating Action
None required at this time.
Anticipated Outcome
Project should be complete within budget.
Flood Prevention
Various flood prevention projects.
Flood Risk Management
Enhancement of drainage infrastructure to ensure compliance with Flood Risk Management Act 2009.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
A detailed design for Gruggies Burn will be undertaken. Project has been carried forward from 2022/23

Page 9

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment28
Project Life Financials 869 659 76% 869 (0) 0%
Current Year Financials 397 0 0% 397 0 0%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-29 31-Mar-29
29
Project Life Financials 376 376 100% 376 (0) 0%
Current Year Financials 41 0 0% 41 0 0%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
30
Project Life Financials 20,621 19,766 96% 20,308 (313) -2%
Current Year Financials 4,222 169 4% 4,222 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
31
Project Life Financials 2,011 2,011 100% 2,011 0 0%
Current Year Financials 1,439 12 1% 1,439 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within amended timescales.
Free School Meals
Provision of Capital Funding from Scottish Government to implement free school meal initiative.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project is complete other than snagging works which can only be completed when school is closed however project end date is still on target. Additional budget required
in relation to electrical phasing which was unknown at the time of project inception.
Anticipated Outcome
Project delivered within budget and to the revised programme, following COVID-19.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Phase 1 of the project was handed over on Monday 18 October 2021, with pupils returning to the new school campus on Wednesday 20 October 2021.  Phase 2 
handed over on 25th July 2022.  Ongoing work to conclude Final Defects and release final retention  Note to Sarah.  Forecast is required for retention plus any other
money to be spent.  Also Financial End date needs to be amended to the rention payment date.  Thereafter no further payments will be made.
Mitigating Action
None Required
Mitigating Action
None required at this time.
Anticipated Outcome
Increase the Chromebook ratio for most disadvantaged children.
Schools Estate Improvement Plan
Improvement of Schools Estate.
Digital Inclusion
Increase the ratio of chrome book devices for most disadvantaged children and families and support for families with
remote access.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Although there is slippage caused mainly by the academic year starting several months after the financial year the project is still on track to be completed by the planned
end date.
Main Issues / Reason for Variance
Although there is slippage caused mainly by the academic year starting several months after the financial year the project is still on track to be completed by the planned
end date.
Mitigating Action
None required at this time.
Anticipated Outcome
Purchase of AV Equipment for Education.
AV Equipment - Education
Purchase of AV Equipment for Education.
Planned End Date Forecast End Date

Page 10

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment32
Project Life Financials 750 750 100% 750 0 0%
Current Year Financials 112 0 0% 112 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-24
33
Project Life Financials 5,508 5,508 100% 5,508 (0) 0%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-22 30-Apr-23
34
Project Life Financials 8,628 8,820 102% 8,820 192 2%
Current Year Financials 287 (11) -4% 287 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
35
Project Life Financials 1,150 1,150 100% 1,150 (0) 0%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-22 30-Apr-23
Anticipated Outcome
To create new community facilities with additional space for early years provisions.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project complete and final account to be agreed.
Mitigating Action
None required.
Mitigating Action
None required.
Anticipated Outcome
The project will be completed to deliver the requirements of the Early Years expansion plans.
Dalmonach CE Centre
To create new community facilities with additional space for early years provisions.
Early Years Early Learning and Childcare Funding
Early learning and childcare funding awarded to West Dunbartonshire Council to facilitate the expansion in entitlement to
funded ELCC to 1140 hours from August 2020.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works progressing and budget spend anticipated in 2023/24
Main Issues / Reason for Variance
Works progressing and budget spend anticipated in 2023/24
Mitigating Action
None required.
Anticipated Outcome
Project delivered on time and within budget
Anticipated Outcome
Project delivered on budget.
Schools Estate Refurbishment Plan
Completion of condition surveys has been carried out to identify works required to bring various schools from Condition C to
Condition B.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works progressing and budget spend anticipated in 2023/24
Mitigating Action
None available at this time.
Choices Programme - to assist young people who require additional support
Bringing together Central Support Services which will include relocation of Choices Programme.

Page 11

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment36
Project Life Financials 60 60 100% 60 0 0%
Current Year Financials 10 0 0% 10 0 0%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 31-Oct-22 31-Mar-24
Main Issues / Reason for Variance
Technical aspect of the project is complete and WDC are assisting with user testing. Delayed but on budget. This is funded by Scottish Government budget.
Mitigating Action
None available at this time.
Anticipated Outcome
Technical aspect of the project is complete and WDC assisting with user testing. Delayed but on budget.
Internet of Things Asset Tracking
Asset Tracking.
Planned End Date Forecast End Date

Page 12

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 53 48 90% 48 (5) -10%
Current Year Financials 7 0 0% 7 0 0%
Project Description
Project Manager Alan Douglas
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
2
Project Life Financials 30 20 67% 30 0 0%
Current Year Financials 10 0 0% 10 0 0%
Project Description
Project Manager Pamela Clifford
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
3
Project Life Financials 155 155 100% 155 0 0%
Current Year Financials 10 0 0% 10 0 0%
Project Description
Project Manager Pamela Clifford
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
4
Project Life Financials 450 193 43% 193 (258) -57%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Steven Milne
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
None required at this time.
No action required at this time in the hands of Legal
Zero Carbon
Planned End Date Forecast End Date
Anticipated Outcome
Aniticpate full budget spend.
Demolition 215 Main Street Alexandria
Demolition of 215 Main Street Alexandria.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Trainee solicitor in place. Budget will be fully spent.
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Main Issues / Reason for Variance
Mitigating Action
Officers will continmue to persue the credit note
Anticipated Outcome
Main Issues / Reason for Variance
This outstanding money is being sought through the recharging order and through debtors.
Anticipated Outcome
Mitigating Action
Continue to pursue repayment
Mitigating Action
Solicitor Project Support for Capital Projects
Solicitor costs to directly support capital projects
Planned End Date
This project has been completed. However a credit is outstanding and should be received this financial year.
ZeroCarbon
No action required
Main Issues / Reason for Variance
This goes into the overall Antonine Project budget.
Forecast End Date
Mitigating Action
Anticipated Outcome
Solicitor support for Capital Projects, with full budget spend anticipated.
Re -imagine Antonine Wall  
Council's capital contribution towards the multi-partner (five local authorities and Historic Environment Scotland)
Rediscovering the Antonine Wall project which is also funded by the Heritage Lottery Fund.
Planned End Date Forecast End Date
Credut note received and project closed

Page 13

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Solicitor Project Support for Capital Projects5
Project Life Financials 5,064 3,527 70% 4,527 (538) -11%
Current Year Financials 2,933 50 0% 2,933 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-23 31-Mar-25
6
Project Life Financials 16,155 8,997 56% 13,997 (2,158) -13%
Current Year Financials 4,098 0 0% 4,098 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-25
7
Project Life Financials 22,213 22,100 99% 22,100 (113) -1%
Current Year Financials 19,984 120 1% 19,984 0 0%
Project Description
Project Manager Gillian McNamara
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-25 31-Mar-25
8
Project Life Financials 11,220 7,365 66% 11,220 0 0%
Current Year Financials 7,209 150 2% 7,209 0 0%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
LUF
Year one LUF spend includes acquisition cost of Artizan Centre, and design development for Glencairn House and
Connecting Dumbarton
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Following completion of the Developments Strategy the delivery plan has been revised and updated.
District Heating Network Expansion
Network expansion to Golden Jubilee is discussed at every District Heating Project Board
Anticipated Outcome
Main Issues / Reason for Variance
Funding to implement major regeneration projects linked to community charrettes. 
Planned End Date Forecast End Date
Projects ongoing and expected be delivered on time and on budget
Mitigating Action
None required
Anticipated Outcome
Projects delivered on time and on budget
Regeneration Fund
Budget to facilitate the delivery of Regeneration throughout West Dunbartonshire, aligned to the Economic Strategy.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects in progress and anticipate to complete on time
Mitigating Action
none required
Anticipated Outcome
Regeneration/Local Economic Development
Mitigating Action
None available at this time
Anticipated Outcome
District Heating Network Expansion.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Network expansion to GJNH (Golden Jubilee National Hospital) will commence pending approval to proceed by the GJNH Board including agreeing tariff rates .  Unable
to confirm exact programme until approval has been given.
Mitigating Action
Projects delivered on budget
Project to be delivered on programme and within budget once it has been fully set.
projects delivered on time and on budget

Page 14

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Solicitor Project Support for Capital Projects9
Project Life Financials 33,491 15,790 47% 34,049 558 2%
Current Year Financials 11,845 352 3% 11,845 0 0%
Project Description
Project Manager Patricia Rowley/ Craig Jardine
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-27 31-Mar-27
10
Project Life Financials 421 421 100% 421 (0) 0%
Current Year Financials 116 0 0% 116 0 0%
Project Description
Project Manager David Main
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-24 31-Mar-24
11
Project Life Financials 1,590 1,590 100% 1,590 0 0%
Current Year Financials 1,590 0 0% 1,590 0 0%
Project Description
Project Manager Michelle Lynn/ Sarah Christie
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-24 31-Mar-25
12
Project Life Financials 8,535 2,583 30% 8,535 (0) 0%
Current Year Financials 2,238 10 0% 2,238 0 0%
Project Description
Project Manager Sharon Jump/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-25 31-Mar-25
Transformation of Infrastructure Libraries and Museums
Delivery of the project on time and within the increased budget
Exxon City Deal
Main Issues / Reason for Variance
Strathleven Place
Project delivered on budget
None avalable at this time
Anticipated Outcome
Main Issues / Reason for Variance 
Budget has been rephased to this financial year for Dalmuir library as work was scheduled for 2023/2024.
Mitigating Action
As part of the City Deal project the WDC Exxon site at Bowling regeneration with alternative A82 route included.
Planned End Date
A number of H&S works have been carried out in depots with other works planned in the coming months.  Scope and design of future works are currently being
developed. 
Mitigating Action
None available at this time
Anticipated Outcome
Deliver project outcomes within agreed budget
Forecast End Date
Main Issues / Reason for Variance
Regular updates are provided at every Council meeting and monthly Project Board meetings and to City Deal.  The main issues contained within the new Council's
approved Outline Business Case are still valid, which include Exxon's remediation strategy, land transfer arrangements and issues relating to adjoining owners.  WDC
Consultants are monitoring the remediation process to ensure compliance with specification, also Esso are independently monitoring the remediation works.  Final
Business Case submission was June 2023. Through the Scape framework we are working closely with Balfour Beatty to achieve a formal pre construction agreement to
allow the detailed design works to commence and the full construction programme to be developed. Agreements in principle are progressing with third party land owners. 
Note for Patricia - needs narrative on underbridge not happening this financial year and impact on budget spend for 23/24. Forecast will need to be amended.
Mitigating Action
None Required
Anticipated Outcome
To improve performance and efficiency of Council's Libraries and Cultural Services.
Planned End Date Forecast End Date
Depot Rationalisation
None required.
Anticipated Outcome
Projects delivered on budget
Depot Rationalisation.
Planned End Date Forecast End Date
Re-development of Strathleven.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This project is linked to Glencairn House and Depot Rationalisation and will free up the current museum store and office space in Poplar Road. Opportunities exist to
attract external funding.
Mitigating Action

Page 15

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Solicitor Project Support for Capital Projects13
Project Life Financials 25,439 2,030 8% 24,278 (1,161) -5%
Current Year Financials 2,030 (59) -3% 2,030 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-24 31-Mar-24
14
Project Life Financials 349 349 100% 349 0 0%
Current Year Financials 340 0 0% 340 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Angela Wilson
Project Lifecycle 31-Mar-24 31-Mar-24
15
Project Life Financials 912 912 100% 912 0 0%
Current Year Financials 6 (0) 0% 6 0 0%
Project Description
Project Manager Elaine Troup
Chief Officer Peter Barry
Project Lifecycle 31-Mar-24 31-Mar-24
16
Project Life Financials 2,430 630 26% 2,430 0 0%
Current Year Financials 478 0 0% 478 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
The budget for this project was been rephased to FY 2023/2024.
Mitigating Action
None available at this time.
Anticipated Outcome
To deliver new sports changing facility.
Works progressing.
Mitigating Action
None required at this time
Anticipated Outcome
Full budget spend anticipated.
Mitigating Action
None required
Full spend is anticipated on this year's budget.
Main Issues / Reason for Variance
The budget will continue to support and contribute to building capacity in communities.
Planned End Date Forecast End Date
Mitigating Action
Anticipated Outcome
Better access with parks, cemeteries and open spaces.
Building Upgrades and H&S - lifecycle & reactive building upgrades
Lifecycle and reactive building upgrades.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
New Sports Changing Facility Dumbarton West (Old OLSP site) 
New Sports Changing Facility Dumbarton West (Old OLSP site) 
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Invest in "Your Community Initiative"
Capital budget to support the roll out of Your Community,  an initiative designed to achieve coordinated service delivery in
response to community need. This is complimented by community capacity building, empowering WD citizens to do more
for their own communities (leading to less reliance on council).  Also included is the implementation of participatory
Planned End Date Forecast End Date
Anticipated Outcome
Public non-adopted paths and roads
Upgrades to drainage and lighting to enhance the lifespan of paths and roads within  facilities in public parks, cemeteries
and civic spaces.
None required at this time.
Main Issues / Reason for Variance
Projects are currently being developed to deliver better access in our parks, cemeteries and open spaces. Full budget spend anticipated in 2023/2024.

Page 16

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Solicitor Project Support for Capital Projects17
Project Life Financials 449 492 110% 492 44 10%
Current Year Financials 446 0 0% 446 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
18
Project Life Financials 250 250 100% 250 0 0%
Current Year Financials 250 0 0% 250 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
19
Project Life Financials 221 221 100% 221 0 0%
Current Year Financials 8 0 0% 8 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 03-Apr-21 31-Mar-23
20
Project Life Financials 817 817 100% 817 (0) 0%
Current Year Financials 529 0 0% 529 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Works progressing
None required at this time.
Allotment Development
To develop an allotment site.
Planned End Date Forecast End Date
Mitigating Action
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Sustainable burial environment for local residents.
Project is now being developed for tendering, with project commencing May 2023 and completion expected by 31 March 2024. 
Anticipated Outcome
Extension to existing cemetery providing a sustainable burial environment.
None required at this time.
Main Issues / Reason for Variance
New all weather tennis courts.
Vale of Leven Cemetery Extension
Extension of existing cemetery in Vale of Leven.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
None available at this time.
Mitigating Action
Anticipated Outcome
Additioanl allotments delivered within budget
Cemetery Extension, North Dalnotter
00 January 1900
Planned End Date Forecast End Date
Works progressomg
Sports Facilities Upgrades - Argyll Park - Construction of 3 All Weather Tennis Courts
Project is part of wider investment in sporting facilities and is dependent on match funding from Sports Scotland. Agreement
in principle to wider WDC strategic priorities.
Planned End Date Forecast End Date
Project works complete.  Retentions to be paid
None required at this time.
Anticipated Outcome

Page 17

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Solicitor Project Support for Capital Projects21
Project Life Financials 200 200 100% 200 0 0%
Current Year Financials 200 0 0% 200 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
22
Project Life Financials 739 439 59% 739 (0) 0%
Current Year Financials 380 33 9% 380 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-28 31-Mar-28
23
Project Life Financials 210 210 100% 210 0 0%
Current Year Financials 210 0 0% 210 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 30-Nov-23 31-Mar-24
24
Project Life Financials 485 485 100% 485 0 0%
Current Year Financials 430 0 0% 430 0 0%
Project Description
Project Manager Ian Bain
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Mitigating Action
None required.
Anticipated Outcome
Consultant and design team fees for resurfacing of 3G pitch at East End Park.
East End Park Resurfacing
Resurfacing of 3G pitch at East End Park.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Additional fudning received and projects will be allocated.
Design fees to develop Mountain bike skills trail in Balloch country park. Invoice for project received
Anticipated Outcome
Mountain bike track
Resurfacing of 3G pitch at East End Park.
Play Parks Grant Funding
Renew and replace play park equipment
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
None required at this time.
Anticipated Outcome
Renewal of play parks
Balloch Mountain Bike Track
Develop a mountain bike skills trail at Balloch Castle Country Park.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
None required at this time.
Development of play areas to improve accessibility and inclusiveness of play areas throughout West Dunbartonshire. Projects are being developed for implementation
over the next five years.
Nature Restoration Fund
Nature resource for Faifley Community
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
None required at this time.
Anticipated Outcome
complettion of project on time and on budget

Page 18

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Solicitor Project Support for Capital Projects25
Project Life Financials 1,244 1,051 84% 1,051 (193) -16%
Current Year Financials 905 0 0% 905 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
26
Project Life Financials 60 60 100% 60 0 0%
Current Year Financials 5 0 0% 5 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
27
Project Life Financials 800 800 100% 800 0 0%
Current Year Financials 620 0 0% 620 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-24
28
Project Life Financials 2,277 2,277 100% 2,277 0 0%
Current Year Financials 1,480 0 0% 1,480 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Cycling, Walking and Safer Streets
Introduction of enhanced walking routes and traffic calming schemes to introduce safer streets within West Dunbartonshire.
Planned End Date Forecast End Date
Turnberry Homes - traffic calming/ management at Turnberry housing development off Castle Road
To develop projects including Balloch Cycle Way (Pier Road to Mollanbowie/Boturich Road), and other projects principally around National Cycle Network 7 including
Angus Street/Bonhill Bridge and Atlus Street/Cart Street, Clydebank and pedestrian dropped kerbs. Additional funding has been received and will be allocted to
appropriate projects.
Funding has been received from Turnberry Homes and will be used to introduce traffic calming and traffic management
measures to mitigate the impact of additional traffic accessing the housing development off Castle Road, Dumbarton.
Planned End Date Forecast End Date
Consultation completed 2021/2022 and speed humps  installed prior to 31 March 2023.
Main Issues / Reason for Variance
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements & Park and Rides
River Leven Flood Prevention Scheme
Main Issues / Reason for Variance
Mitigating Action
None required at this time.
Anticipated Outcome
Traffic calming to be installed in Dumbarton East.
Main Issues / Reason for Variance
Mitigating Action
None required at this time.
Anticipated Outcome
To improve connectivity and enhanced Cycling routes within West Dunbartonshire.
River Leven Flood Prevention Scheme.
Main Issues / Reason for Variance
Planned End Date Forecast End Date
Awaiting outcome of Scottish Government & SEPA deliberations - project has been carried forward from 2022/23
Mitigating Action
None required at this time.
Anticipated Outcome
Project should be completed within budget.
Strathclyde Partnership for Transport - Bus, cycling and walking infrastructure improvements.
Planned End Date Forecast End Date
Work will be undertaken during this financial year for A8014 Kilbowie Road, Balloch Station Park and Ride and Bus Infrastructure Improvements. A814 Congestion
measures contractor arrived on site mid-August. Works are progressing well. The budget for Balloch Station will be used for consultancy works and planning application
fees. Additional funding has been received and approriate projects will be identified.
Mitigating Action
None required at this time.
Anticipated Outcome
Improve accessibility to Public Transport and improve journey time reliability.

Page 19

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Solicitor Project Support for Capital Projects29
Project Life Financials 24,658 6,872 28% 27,224 2,565 10%
Current Year Financials 2,195 (64) -3% 2,195 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
30
Project Life Financials 881 112 13% 912 32 4%
Current Year Financials 84 4 5% 84 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
31
Project Life Financials 97 97 100% 97 (0) 0%
Current Year Financials 29 2 7% 29 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
32
Project Life Financials 15,053 1,984 13% 15,053 (0) 0%
Current Year Financials 1,530 0 0% 1,530 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-25
Infrastructure - Roads
Gruggies Burn Flood Prevention
Street lighting and associated electrical infrastructure
Main Issues / Reason for Variance
Roads Operations are progressing an extensive surfacing program and have a number of schemes to be completed by the end of the financial year.
Mitigating Action
Planned End Date Forecast End Date
Anticipated Outcome
Intention is to complete works within budget.
Improvement of WDC Roads Depot.
Depot Improvement Works
None available at this time.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget will be allocated to ensure mainteance of street lighting.
Mitigating Action
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This budget will be utilised for depot rationalisation works during the financial year.
Infrastructure - Roads.
None required at this time.
Anticipated Outcome
Intention is to complete various surfacing works by the end of March 2024.
WDC is responsible for the maintenance of 18,000 street lighting columns and associated illuminated signs and bollards. 
This budget is required for this infrastructure.
Mitigating Action
None available at this time.
Anticipated Outcome
Intention is to complete works within budget.
Commission of Gruggies Flood Prevention Scheme.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Budget to be used for a detailed design for Gruggies Burn.
Mitigating Action
None available at this time.
Anticipated Outcome
Project should be completed within budget.

Page 20

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Solicitor Project Support for Capital Projects33
Project Life Financials 1,700 1,700 100% 1,700 0 0%
Current Year Financials 693 0 0% 693 0 0%
Project Description
Project Manager Derek Barr
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
34
Project Life Financials 134 134 100% 134 0 0%
Current Year Financials 134 0 0% 134 0 0%
Project Description
Project Manager Sharron Worthington
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
35
Project Life Financials 80 80 100% 80 0 0%
Current Year Financials 75 0 0% 75 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
36
Project Life Financials 300 300 100% 300 0 0%
Current Year Financials 26 0 0% 26 0 0%
Project Description
Project Manager Raymond Walsh
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
Traffic Signal Upgrades
Roads Plant
To purchase equipment.
A813 Road Improvement Phase 1
Funding has been awarded from Sustrans to assist with social distancing measures required as a result of the COVID-19
pandemic.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Roads Safety
Main Issues / Reason for Variance
New Plant to be purchased
Mitigating Action
None required.
Anticipated Outcome
Upgrade Traffic Signals
Planned End Date Forecast End Date
Officers working with external partners to identify projects to support funding. Project carried frowrd from 2022/23
Mitigating Action
None available at this time.
Anticipated Outcome
To improve journey times and reliability of bus services.
Roads Safety
Planned End Date Forecast End Date
Main Issues / Reason for Variance
New funding which will be allocated to approiate projects.
Mitigating Action
None required at this time.
Anticipated Outcome
Projects delivered on time and on budget
Purchase of Roads plant and equipment.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
The signalisation design of Kilbowie roundabout is underway and ocne complete construction will be programmed.
Mitigating Action
None required.
To upgrade traffic signals.
Anticipated Outcome

Page 21

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Solicitor Project Support for Capital Projects37
Project Life Financials 1,000 1,000 100% 1,000 0 0%
Current Year Financials 878 185 21% 878 0 0%
Project Description
Project Manager Hugh Campbell
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
38
Project Life Financials 1,000 1,000 100% 1,000 0 0%
Current Year Financials 1,000 0 0% 1,000 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-25 31-Mar-25
39
Project Life Financials 12,177 3,857 32% 12,177 0 0%
Current Year Financials 3,314 29 1% 3,314 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
40
Project Life Financials 1,980 1,980 100% 1,980 0 0%
Current Year Financials 1,980 0 0% 1,980 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
Waste Transfer Station
Mitigating Action
None available.
None required.
Anticipated Outcome
Improvement to pavements.
Vehicle Replacement Strategy
Anticipated Outcome
Replacement of refuse collection vehicles.
Vehicle Replacement
Mitigating Action
Replacement of refuse collection vehicles.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Full budget allocated for this year including the procurement of large vehicles for waste collection.
Replacement of vehicles which have reached end of programmed lifespan (7 year heavy vehicles, 10 year light vehicles).
Planned End Date Forecast End Date
Various pavement improvement projects.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Projects and locations to be decided.
Pavement improvements
Main Issues / Reason for Variance
Vehicles are being ordered for delivery in this financial year but larger vehicles have been delayed into financial year 2023/2024.
The design, development and construction of a recycling and bulk waste transfer facility that will ensure all recycling
material can be sorted and disposed off appropriately to ensure compliance with landfill ban in 2025.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Consultant project nearing completion and spend will be made thereafter.
Mitigating Action
None Required.
Anticipated Outcome
Replacement of fleet within budget.
Anticipated Outcome
Mitigating Action
None Required.
Project delivered within budget.

Page 22

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Solicitor Project Support for Capital Projects41
Project Life Financials 179 80 45% 160 (19) -10%
Current Year Financials 9 0 0% 9 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
42
Project Life Financials 60 60 100% 60 0 0%
Current Year Financials 16 0 0% 16 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-23 31-Mar-23
43
Project Life Financials 79 79 100% 79 0 0%
Current Year Financials 79 0 0% 79 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
44
Project Life Financials 20 20 100% 20 0 0%
Current Year Financials 20 0 0% 20 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
None Required.
Anticipated Outcome
Project delivered within  budget.
None Required.
Anticipated Outcome
Project delivered within  budget.
2022/23 GRANT OFFER FOR ELECTRIC VEHICLE INFRASTRUCTURE
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project in progress
2022/23 GRANT OFFER FOR ELECTRIC VEHICLE INFRASTRUCTURE
Smarter Choices, Smarter Places
Planned End Date Forecast End Date
Main Issues / Reason for Variance
River bank erosion repair - Levenhowe
Project in progress
Mitigating Action
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within  budget.
2022/23 GRANT OFFER FOR ELECTRIC VEHICLE INFRASTRUCTURE
New Funding - Project in progress
Mitigating Action
None Required.
Anticipated Outcome
Project delivered within  budget.
River bank erosion repair in the Levenhowe area
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
The purchase of 2 compactors for the Council civic amenity site at Dalmoak.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Compactors have now been delivered.
Replacement of compactors at Dalmoak civic amenity site

Page 23

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Solicitor Project Support for Capital Projects45
Project Life Financials 150 150 100% 150 0 0%
Current Year Financials 150 0 0% 150 0 0%
Project Description
Project Manager Gail MacFarlane
Chief Officer Gail MacFarlane
Project Lifecycle 31-Mar-24 31-Mar-24
46
Project Life Financials 35,714 4,395 12% 35,714 (0) 0%
Current Year Financials 3,495 81 2% 3,495 0 0%
Project Description
Project Manager Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-26 31-Jul-27
47
Project Life Financials 7,886 1,773 22% 7,886 0 0%
Current Year Financials 845 1 0% 845 0 0%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-23 31-Mar-23
48
Project Life Financials 214 125 58% 214 0 0%
Current Year Financials 125 3 3% 125 0 0%
Project Description
Project Manager Alastair Handley
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-24 31-Mar-24
Project delivered within  budget.
Project in progress
None Required.
Anticipated Outcome
Main Issues / Reason for Variance
The next phase of the Schools Estate Improvement Plan involves the development of a new Campus provision in the Faifley area. WDC has been successful in securing
funding from the Scottish Government Learning Estate Improvement Programme. SFT confirmed the indicative funding allocation for this project at £18.416m on the 4
May 2021, this will be received as a revenue stream over the 25 years of the Scottish Government financial support (subject to the Council adhering to the funding
criteria). Site Options Appraisal has taken place and Members approved the recommendation to proceed with the new Faifley Campus on the St Joseph's site at
Education Committee on 9th June 2021.  The design team and main contractor have been appointed and the next phase will see the design development for the new
Campus taking place. The statutory consultation process was launched in September 2021 and a report was brought back to the Educational Services committee in
March 2022 concluding the process. RIBA Stage 4 is now complete with an expected Planning Committee date of September/October 2023. 
Mitigating Action
None required at this time
Schools Estate Improvement Plan - next Phase - Faifley Campus
Improvement of Schools Estate.
Planned End Date Forecast End Date
Delivery of the project within budget and on time.
Forecast End Date
None available at this time
Main Issues / Reason for Variance
Anticipate the budget to be fully spent in 2023/24
Anticipated Outcome
Main Issues / Reason for Variance
Anticipate the budget to be fully spent in 2023/24
Mitigating Action
Anticipated Outcome
Aids & Adaptations - Special Needs Adaptations & Equipment
Reactive budget to provide adaptations and equipment for HSCP clients.
Planned End Date
Park Improvements and Mulit Games Area - Goldenhill Park
River bank erosion repair in the Levenhowe area
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Provision of adaptations and equipment to HSCP clients as anticipated.
HSCP ICT Upgrade of systems
Review/replace the current case management systems.
Planned End Date Forecast End Date
None available at this time
Review/replace the current case management systems.
Mitigating Action

Page 24

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Solicitor Project Support for Capital Projects49
Project Life Financials 924 308 33% 924 0 0%
Current Year Financials 308 0 0% 308 0 0%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-23 31-Mar-23
50
Project Life Financials 73 73 100% 73 0 0%
Current Year Financials 19 0 0% 19 0 0%
Project Description
Project Manager Julie Slavin
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-23 31-Mar-23
51
Project Life Financials 27,550 27,550 100% 27,550 0 0%
Current Year Financials 277 0 0% 277 0 0%
Project Description
Project Manager Craig Jardine
Chief Officer Beth Culshaw
Project Lifecycle 31-Mar-22 31-Mar-23
52
Project Life Financials 11,413 2,127 19% 11,325 (87) -1%
Current Year Financials 1,332 13 1% 1,332 0 0%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-24 31-Mar-24
Main Issues / Reason for Variance
Anticipate the budget to be fully spent in 2023/24
Mitigating Action
Main Issues / Reason for Variance
Project complete with a slight overspend due to additional works required in relation to roof vents which required to be installed. Acceleration of budget has been
requested in relation to an overspend in the current year.
Mitigating Action
Anticipated Outcome
Main Issues / Reason for Variance
Anticipate the budget to be fully spent in 2023/24
Mitigating Action
Anticipated Outcome
Planned End Date Forecast End Date
Community Alarm upgrade
To upgrade Community Alarm
None available at this time
Community Alarm Upgrade
Criminal Justice Adaptations
Renovation of Unit 11 Levenside Business Court.
Planned End Date Forecast End Date
Mitigating Action
Anticipated Outcome
Main Issues / Reason for Variance
None available at this time
Renovation of Unit 11 Levenside Business Court
Replace Elderly Care Homes and Day Care Centres
Design and construction of replacement elderly care homes and day care centres in Dumbarton and Clydebank areas.
Planned End Date Forecast End Date
The statement of final account has been signed and financial risk exposure should be reduced through efforts to dispose of the existing properties at the earliest
opportunity.
Dumbarton Care Home opened 2017.  Clydebank Care Home was certified complete on 9 November 2020.
ICT Modernisation
This budget is to facilitate ICT infrastructure and modernise working practices.
Planned End Date Forecast End Date
This budget will be utilised facilitate ICT infrastructure and modernise working practices.
none required
Anticipated Outcome
projects delivered on time and on budget

Page 25

WEST DUNBARTONSHIRE COUNCIL APPENDIX 8
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Variance
Solicitor Project Support for Capital Projects53
Project Life Financials 2,026 2,026 100% 2,026 0 0%
Current Year Financials 873 112 13% 873 0 0%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-24 31-Mar-24
54
Project Life Financials 503 503 100% 503 0 0%
Current Year Financials 185 (7) -4% 185 0 0%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 30-Sep-23 30-Sep-23
55
Project Life Financials 379 88 23% 379 (0) 0%
Current Year Financials 46 0 0% 46 0 0%
Project Description
Project Manager Arun Menon
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-30 31-Mar-30
56
Project Life Financials 17,776 5,678 32% 18,366 590 3%
Current Year Financials 1,586 31 2% 1,586 0 0%
Project Description
Project Manager N/A
Chief Officer N/A
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
Mitigating Action
Main Issues / Reason for Variance
Main Issues / Reason for Variance
Mitigating Action
Main Issues / Reason for Variance
Planned End Date Forecast End Date
ICT Security & DR
The project is for the enhancement of security systems, server replacement and the update of corporate applications to
ensure compliance with 15/16 PSN requirements, to enhance the disaster recovery capabilities of WDC.
Direct Project Support
The project is for the enhancement of security systems, server replacement and the update of corporate applications to ensure compliance with 15/16 PSN requirements,
to enhance the disaster recovery capabilities of WDC.  Projects will be undertaken throughout bthe year to support this
none required
Anticipated Outcome
projects delivered on time and on budget
365 Implementation
Project services to delivery Microsoft 365 Implementation including 3rd party supplier, training, technical consultancy etc.
Salary Capitalisation in 2023/2024.
Mitigating Action
None required.
Anticipated Outcome
Direct project support costs allocated as appropriate.
Planned End Date Forecast End Date
Project spend relates to internal and external resources to implement new systems, processes and user training skills. Mailbox migration aspect of the project now being
resumed as cloud backup solution is in place. Implementation of device management functionality in 365 is live for corporate devices but full rollout is linked to mailbox
migrations. Information governance work stream in progress. Project resourcing issues continue due to competing demands and competitive environment for recruitment.
none required
Anticipated Outcome
projects delivered on time and on budget
Development of Workforce Management System
Project to develop the Workforce Management System.
Planned End Date Forecast End Date
Work continues on developments resulting in some spend in the current year.
none required
Anticipated Outcome
Work continues on developments resulting in some spend in the current year.
Business support cost such as reallocation of architects and project support at year end.
Planned End Date Forecast End Date
Mitigating Action

Page 26

WEST DUNBARTONSHIRE COUNCIL APPENDIX 9
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
PERIOD END DATE
PERIOD 3
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials (2,169) (2,070) 95% (2,169) (0) 0%
Current Year Financials (2,070) 0 0% (2,070) 0 0%
Project Description
Project Lifecycle 31-Mar-24 31-Mar-24
2
Project Life Financials (92,560) (41,875) 45% (93,795) (1,236) 1%
Current Year Financials (7,453) (2,416) 32% (7,453) 0 0%
Project Description
Project Lifecycle 31-Mar-30 31-Mar-30
3
Project Life Financials (41,410) (22,826) 55% (43,449) (2,039) 5%
Current Year Financials (15,890) (123) 1% (15,890) 0 0%
Project Description
Project Lifecycle 31-Mar-26 31-Mar-26
4
Project Life Financials (11,176) (11,264) 101% (12,741) (1,565) 14%
Current Year Financials (3,824) 50 -1% (3,824) 0 0%
Project Description
Project Lifecycle 31-Mar-24 31-Mar-24
30 June 2023
Budget Details
Project Life Financials
Application of resources is dependent on capital project progressing in year as planned.
Spend to Date Forecast Variance
Resources Carried Forward
These are resources that have been received in previous years relating to Turnberry Homes, Town Centre Fund
Grant, Digital Inclusion, Clydebank Can on the Canal, Internet of Things Asset Tracking, Renew Playparks,
Knowes Nature Reserve,Flood Prevention, District Heating Electric Vehicle Infrastructure and Auld Street Bond.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Planned End Date Forecast End Date
Mitigating Action
None required at this time.
Anticipated Outcome
Application of resources held on balance sheet as at 31 March 2023 as appropriate.
General Services Capital Grant
This is a general grant received from the Scottish Government in relation to General Services capital spend
Application of resources is dependent on capital project progressing in year as planned.
Main Issues / Reason for Variance
General services capital grant is anticipated to be received as forecast.
Mitigating Action
None required at this time
Anticipated Outcome
General services capital grant is anticipated to be received as forecast.
Ring Fenced Government Grant Funding
This is ring fenced grant funding which is primarily anticipated to be received from the Scottish Government and
relates to Cycling, Walking, Safer Streets, Regeneration Placed Based Investment Programme, Early Years,
Gruggies Burn Flood works, Early Years funding, City Deal and Town Centre Fund.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
None required.
Mitigating Action
Mitigating actions are detailed within the appropriate status updates.
Anticipated Outcome
Application of resources as appropriate.
Match Funding / Other Grants and Contributions
Match Funding / Other Grants and Contributions
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Application of resources is dependent on capital project progressing in year as planned.
Mitigating Action
Anticipated Outcome
Match funding received.

Page 27

WEST DUNBARTONSHIRE COUNCIL APPENDIX 9
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
PERIOD END DATE
PERIOD 3
Budget Forecast Spend
£000 £000 % £000 £000 %
30 June 2023
Budget Details
Project Life Financials
Spend to Date Forecast Variance
Resources Carried Forward
5
Project Life Financials (213,569) (118,388) 55% (210,475) 3,094 -1%
Current Year Financials (63,578) 1,074 -2% (63,589) (11) 0%
Project Description
Project Lifecycle 31-Mar-26 31-Mar-26
Prudential Borrowing
Prudential borrowing is long term borrowing from financial institutions that has been approved for the purposes of
funding capital expenditure
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Prudential borrowing is impacted by programme delivery therefore mitigating action is detailed in the red and amber analysis.
Mitigating Action
None available at this time.
Anticipated Outcome
While prudential borrowing requirement is likely to be less than budgeted in the current financial year this is anticipated to catch up over the
programme life.