Page 1

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer - Resources
Council: 30 August 2023
Subject: Unaudited 2022/23 Annual Accounts
1. PURPOSE
1.1 The purpose of this report is to provide Council with a copy of the unaudited
2022/23 Annual Accounts and information regarding the 2022/23 outturn as
set out in the draft accounts.
2. RECOMMENDATIONS
2.1 Members are asked to:
a) note the unaudited 2022/23 Annual Accounts
b) note the information provided in relation to the financial
performance of the Council’s services and capital plan for
2022/23
c) note the current position regarding the Council’s reserves
d) note that a report on the audited accounts will be submitted to
either Council or Audit Committee by 31 October 2023 for
approval
e) agree to delegate authority to the Audit Committee to formally
approve the audited accounts at a special meeting of the Audit
Committee scheduled for 2 November 2023, prior to submission to
the Accounts Commission.
3. BACKGROUND
3.1 The annual accounts set out the financial statements of the Council and its
group for the year ended 31 March 2023. Its main purpose is to demonstrate
the stewardship of public funds entrusted to the Council. The requirements
governing the format and content of local authorities’ annual accounts are
contained in the Code of Practice on Local Authority Accounting in the
United Kingdom (the Code). The 2022/23 accounts have been prepared in
accordance with this Code.
3.2 There is a statutory requirement to prepare a set of accounts and submit
them to the Controller of Audit. The date set by the Scottish Government for
the submission of the unaudited annual accounts is 30 June each year.
4. MAIN ISSUES
4.1 The Council’s draft 2022/23 annual accounts, including the group accounts,
were submitted to the Controller of Audit on 3 July 2023. This is marginally
after the 30 June deadline (one working day late) however this is not a
ITEM 10

Page 2

material concern. Our external auditors (Mazars) have commenced their
audit. 
4.2 The unaudited accounts show that the outturn on the general fund is an
overspend of £6.607m after the budgeted use of additional resources of
£9.068m.  This represents an overspend of 2.56% against 2022/23 revised
budget of £258.297m.  The £6.607m overspend breaks down as: 
£000
Service overspend including loan charges 1,311
Under recovery of capital receipts (used to fund repayment
of loan principle and any premiums incurred when
restructuring loans) 2,800
Voluntary redundancy/severance provision 3,400
Over recovery of Council Tax Income (904)
Total  6,607 
The Housing Revenue Account (HRA) is reporting an in-year deficit of
£0.099m. 
4.3 Since 2010/11, local authorities have been required to prepare financial
statements following International Financial Reporting Standards (IFRS).
Under the Local Authority Accounts (Scotland) Regulations 2014 there is a
requirement to include a management commentary in the accounts. The
contents of the annual accounts are summarised in the paragraphs that
follow. 
4.4 Management Commentary: outlines the key messages regarding the
objectives and strategy of the Council and its financial performance for the
year. It also looks forward, outlining the future financial plans for the
organisation and the challenges and risks which are faced by the Council. 
4.5 Statement of Responsibilities for the annual accounts: outlines the
Council’s responsibilities and also the responsibilities of the Council’s
Section 95 Officer. 
4.6 Annual Governance Statement: this details the view on the adequacy of its
governance and internal control system. It is the Council’s view that the
systems for governance and internal control are operating effectively within
the Council during 2022/23 and that there are no significant weaknesses. 
4.7 Remuneration Report: provides details of the remuneration policy,
remuneration and pension benefits of senior councillors and senior officers
in addition to detail on employee exit packages. 
Comprehensive Income and Expenditure Statement (CIES): 
4.8 This statement shows the accounting cost of providing services rather than
the amount to be funded from taxation, in order to comply with the
requirements of the Code. This means that the net cost of service includes

Page 3

statutory accounting adjustments for depreciation, loans fund principal
repayment, the net change for the pension adjustment and accrued holiday
leave not taken by 31 March 2023; adding a total of £34.907m onto the cost
of service provision.  This is one of the main reasons why the actual outturn
shown within the Comprehensive Income and Expenditure account differs
from the actual outturn shown within the management commentary (page 8),
as these costs are not included as part of the service budgets.  A
reconciliation between the two outturns is shown at paragraph 4.10. 
4.9 The Council ended the year with a surplus of £289.332m for 2022/23.  This
is the accounting surplus based on the IFRS compliant accounts rather than
the movement in the General Fund Balance, which comprises of the
following: 
£000
Deficit on Provision of Services 51,881
Deficit on the revaluation of long term assets 1,554
Actuarial gain on the pension fund asset (342,767)
Total Surplus (289,332)  
4.10 The table below, sets out a reconciliation of the deficit on the provision of
services of £51.881m as noted in the Statement of Comprehensive Income
and Expenditure under IFRS requirements and the in-year revenue
overspend of £6.607m against budget (paragraph 4.2): 
£000
Deficit on Provision of Services per the Comprehensive
Income and Expenditure Statement
51,881
Less: statutory adjustments required by the Code (paragraph
4.8)
(34,907)
Deficit on Provision of Services per Note 15 – Expenditure
and Funding Analysis
16,974
Adjust for movements to/from statutory reserves: 
HRA reserve 0,170
Other reserves (1,469)
Movement in General Fund Balance 15,675
Use of Earmarked Reserves (9,068)
Net General Fund budgetary control position 2022/23 6.607 
4.11 Balance Sheet: The Balance Sheet shows that the net worth of the Council
has increased by £289.333m from £327.122m as at 31 March 2022 to
£616.455m as at 31 March 2023. The major changes are set out in the table
below.

Page 4

Movement in Reserves Statement 
4.12 This shows the movement on the different reserves held by the Council,
analysed into usable reserves (resource backed reserves which can be
used to fund expenditure) and unusable reserves (required purely for
accounting purposes and are not backed by resources). 
4.13 The total Council reserves have increased from £327.122m at 31 March
2022 to £616.455m at 31 March 2023, an increase of £289.333m, due
predominantly in the material change in the pension reserve. 
4.14 The balance of unusable reserves has increased by £276.337m from
£308.070m as at 31 March 2022 to £584.407m as at 31 March 2023. This is
predominantly due to the material change in the pension reserve from a
liability of £55.690m in 2021/22 to an asset of £260.242m in 2022/23 (an
increase of £315.932m).   
4.15 In respect of the General Fund Balance movement, during 2022/23, the
Scottish Government issued Finance Circular 10/2022, which permits the
authority to apply an accounting flexibility for service concession
arrangements entered into prior to April 2022. The application of this
flexibility has resulted in the repayment of the liability being reprofiled over
the asset life, therefore extending the repayment period. The unitary charge
will continue to be paid to the contractor over the original contract period. 
This resulted in a revision to the opening balance in the General Fund which
increased it by £29.734m from £15.020m to £44.754m. There was a
corresponding decrease to the Capital Adjustment Account. 
In 2022/23 there has been a decrease of in the general fund of £15.675m
from that revised opening balance of £44.754m to £29.079m.  Of that total
£24.590m is earmarked for specific purposes.  The Council has agreed to
hold a contingency balance (prudential target) equivalent to 2% net
expenditure (excluding requisitions) and this amounts to £3.438m. The
remaining General Fund balance (unearmarked balance) amounts to
£1.051m.

Page 5

Note that the Council has approved an increase in the prudential target from
2% to 3% and this will be reflected from 2023/24 onwards. 
4.16 Cash Flow Statement: The Cash Flow Statement shows the changes in
cash and cash equivalents of the Council during the financial year. The
Cash and Cash Equivalents increased by £0.410m to £2.550m. 
4.17 Notes to the Financial Statement: The notes section provides further
information and explanation on some of key figures included within the
Accounts. The notes conform to the guidance issued by CIPFA/LASAAC
within the Code of Practice on Local Authority Accounting. 
4.18 Council Tax Income Account: This account shows the gross income
raised from council tax levied and deductions made under the Local
Government Finance Act 1992. The resultant net income is transferred to
the CIES. Council Tax rate for Band D was £1,332.36 for 2022/23 compared
to £1,293.55 in 2021/22 (a £38.81 increase) reflecting the 3% increase
agreed by Council as part of the budget setting process. The income
transferred to the general fund for Council Tax in 2022/23 was £39.313m.
This compared to £38.207m in 2021/22. 
4.19 Non Domestic Rate Income Account: This account is an agent’s
statement that reflects the statutory obligation for billing authorities to
maintain a separate Non Domestic Rate Account. Net Non-Domestic Rate
Income to the Consolidated Income and Expenditure Account amounted to
£107.740m for 2022/23. This compares to £81.408mm in 2021/22. This is
WDC’s share of the estimated NDR income which has been distributed
proportionately on the basis of the Council’s 2021/22 mid-year income.  It
does not represent additional income to the Council, just a distribution of the
national pool to reflect what is due to the Council as agreed as part of the
2022/23 settlement figure (already accounted for) and what the Council
collected. 
4.20 Housing Revenue Account 
In relation to the HRA, the draft accounts show a balance of £2.635m as at
31 March 2023. Of this balance £1.650m is earmarked for service
improvements/welfare reform resilience, leaving an un-earmarked balance
of £0.985m, which is in line with the prudential reserve target. 
4.21 Capital Programmes 
Details of the capital programmes are shown in Appendix 4 (General Fund)
and Appendix 5 (HRA) and are summarised below. The appendices detail
the outturn of the projects within 2022/23 and provide further information on
the projects which have been identified as red status (i.e. those projects
which are likely to be significantly overspent and/or to have significant
delays in completion). A list of the main capital projects progressed during

Page 6

2022/23 is provided on page 12 of the Annual Accounts. The year end
position is summarised as follows: 
Budget Spend Variance Overspend Underspend Reprofiling  
£,000 £,000 £,000 £,000 £,000 £,000
General Services 66,686 27,297 -39,389 2,079 -1,568 -38,878
HRA 65,604 34,930 -30,674 9,467 -1,176 -38,965
Total 132,290 62,227 -70,063 11,546 -2,744 -77,843 
4.22 The main areas of reprofiling in the year were: 
General Services
District Heating
Expansion
Network expansion to Golden Jubilee National Hospital will
commence pending positive commercial discussions.  
Heritage Capital
Fund
Original plans were affected by COVID. Officers are now
progressing the projects with an aim to bring them back on
track. 
Vehicle
Replacement
Delay due to the vehicle build time associated with the
specialist vehicles and the delivery lead time from the date of
supply order placement.
Levelling Up Fund Artizan Development will progress following completion of
the development plan.
HRA
New house build While the programme has progressed with a new site
completed and handed over in 2022/23, due to a number of
different complexities there were delays in progress to newer
new build sites.
Projects to deliver
housing strategies
(Buy Backs)
These are subject to stringent criteria to ensure
accountability and value for money for tenants and involves
several key stakeholders which resulted in time delays
Doors/Windows  Installations are behind original planned targets due to
internal and external contractor resource issues
Building external
components
Many tiled roof blocks require owner involvement and under
the current financial climate, it has been more difficult to
progress works with owners. 
4.23 Group Accounts: The Council is required to prepare Group Accounts in

Page 7

addition to its own Annual Accounts. Group Accounts are prepared when a
Council has a material interest in other organisations. The purpose of the
accounts is to combine its financial information with other organisations
within its group. For 2022/23 the Council’s group consists of 
(a) West Dunbartonshire Leisure Trust
(b) Dunbartonshire and Argyll and Bute Valuation Joint Board
(c) Strathclyde Partnership for Transport
(d) Strathclyde Concessionary Travel Joint Board
(e) Clydebank Property Company
(f) West Dunbartonshire Energy Company
(g) Health and Social Care Integrated Joint Board
(h) Dumbarton Common Good and Trust Funds. 
4.24 The effect of combining these entities on the Group Balance Sheet is to
increase reserves and net assets by £56.287m creating an overall net asset
of £673.005m. 
4.25  Update on Transformational Projects 
Following recent (but temporary) Scottish Government legislation, the
Council agreed as part of its budget for 2022/23 to use capital receipts to
fund some transformational spend. The budgeted spend approved by
Council was £0.700m, the actual spend as at 31 March 2023 was £0.700m.
Appendix 6 provides further details of these transformational projects and
the position regarding these as at 31 March 2023. 
Next Steps 
4.26 To enable the Council to meet its legislative requirements, Members require
to approve the audited Annual Accounts for signature no later than 30
September  2023. The Council’s external auditors have advised that they
are unlikely to have their audit fully completed by this deadline. As there is a
Council meeting scheduled for 25 October 2023, and the next Council
meeting scheduled after that is 20 December 2023, a special meeting of the
Audit Committee has been arranged for 2 November 2023 to allow the
audited accounts to be approved.   Council is therefore asked to agree to
delegate authority to the Audit Committee to formally approve the audited
accounts at this special meeting which will allow the audited accounts to be
submitted to the Accounts Commission. 
Charity Accounts 
4.27 Appendix 7 provides Members with the accounts of the Trust Funds which
are administered by the Council. These Financial Statements are also
audited by our external auditors prior to submission to the Office of the
Scottish Charity Regulator (OSCR). The draft Financial Statements 2022/23
have been presented to the external auditors. As noted at 4.23 above these
are also included within the Council’s Group position. 
The summary position of the Trusts are noted below – interest gained was

Page 8

received for all trusts, with six grant payments made, four from the
Alexander Cameron Bequest and two from Dr AK Glen Fund. As the AK
Glen Fund has bene fully distributed it has been wound up and removed
from the Scottish Charity Register. 
Opening Balance   
2022/23
Surplus /
(Deficit)   
2022/23
Closing
Balance   
2022/23
Dunbartonshire
Educational Trust
Scheme 1962
90,712 1,796 92,508
McAuley Prize for
Mathematics 21,898 435 22,333
Alexander
Cameron Bequest 120,269 (2,764) 117,505
Dr AK Glen 4,947 (4,947) 0
UIE Award 24,757 491 25,248
Totals 262,583 (4,989) 257,594 
4.28 The audited Trust Fund accounts will be approved by the Council, together
with the Council’s Financial Statements, but will be presented to the Trust
Committees separately. 
4.29 Common Good 
Appendix 8 provides Members with the accounts of the Dumbarton Common
Good which are administered by the Council, also audited by our external
auditors as part of the year end process. As noted at 4.23 above this is also
included within the Council’s Group position. 
The main movements within the common good are noted below: 
£
Opening Balance 581,313
Income 330,789
Expenditure (287,207)
Closing Balance 624,895 
CONCLUSION 
4.30 The Unaudited Annual Accounts have been prepared in accordance with
professional and statutory requirements. The General Fund Balance has 
decreased by £15.675m from a revised opening balance of £44.754m to
£29.079m, after taking into consideration the movement during the year, the
end of year outturn position and earmarkings. The Council’s net worth, per
the balance sheet, has increased from £327.122m at 31 March 2022 to
£616.455m at 31 March 2023, an increase of £289.333m, due
predominantly to a material change in the pension reserve which is an
unusable reserve.

Page 9

5. PEOPLE IMPLICATIONS 
5.1 There are no people implications as a consequence of this report. 
6. FINANCIAL AND PROCUREMENT IMPLICATIONS 
6.1 There are no direct financial or procurement implications arising from this
report. 
7. RISK ANALYSIS 
7.1 No risk analysis was required 
8. EQUALITIES IMPACT ASSESSMENT (EIA) 
8.1 No equalities impact was required in relation to the preparation of this report. 
9. CONSULTATION 
9.1 The views of Legal Services have been requested on this report and have
advised there are neither any issues nor concerns with the report. 
10. STRATEGIC ASSESSMENT 
10.1 Sound financial practices are cornerstones of good governance and support
Council and officers to pursue the Council’s strategic priorities. 
Laurence Slavin
Chief Officer - Resources
Date:   30 August 2023 
Person to Contact: Carol Alderson, Finance Manager, 16 Church Street, Dumbarton   
E-mail: carol.alderson@west-dunbarton.gov.uk
Appendices
1. Draft Annual Accounts to 31 March 2023 
2. General Services Budgetary Control Report to 31 March 2023 – Revenue
3. HRA Budgetary Control Report to 31 March 2023 – Revenue
4. General Services Budgetary Control Report to 31 March 2023 – Capital 
5. HRA Budgetary Control Report to 31 March 2023 - Capital
6. Update on transformational spend 2022/23 
7. Draft Annual Accounts to 31 March 2023 for Trust Funds 
8. Draft Position to 31 March 2023 for Dumbarton Common Good 
Background Papers
Budget Report to Council - 1 March 2023
Local Government Finance Circular 4/2019 – capital receipts to fund
transformational projects