WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Council – 29 October 2025
___________________________________________________________________
Subject: Housing Revenue Account (HRA) Capital 
Budgetary Control Report to 31 August 2025 (Period 5)
1. Purpose
1.1 This report provides an update on the HRA capital programme to 31 August
2025.
2. Recommendations
2.1 Council is asked to:
i) Note the position of the 2025/26 HRA capital budget and the HRA capital plan
as 31 August 2025.
ii) Note project life performance is monitored against a £345.311m project life
expenditure estimate, a £80.379m project life income estimate and a
£264.932m five-year borrowing requirement.
iii) Note all projects are currently on track to achieve their planned completion
dates and that eleven projects are forecast to deliver a total underspend of
£6.481m against their five-year project life budgets.
iv) Note in year financial performance is monitored against a 2025/26 capital
expenditure budget of £55.547m, 2025/26 capital income budget of £6.290m
and a one-year borrowing requirement of £49.257m.
v) Note thirty-two projects are reporting as off track in 2025/26 with an
anticipated under spend of £9.812m against their 2025/26 budgets reducing
the forecast one-year borrowing requirement to £39.445m.
3. Background
3.1 The Council approved the HRA Capital Plan for 2025/26 to 2029/30 on 5
March 2025. The HRA capital plan approved £70.590m of capital expenditure
and £15.324m of capital income in 2025/26, creating a borrowing requirement
of £55.266m.
3.2 At its meeting on the 27 August 2025, the Housing and Communities
Committee agreed budget adjustments that revised the 2025/26 capital
expenditure budget to £55.547m and the capital income budget to £6.290m,
an updated one-year borrowing requirement of £49.257m. Committee also
approved a revised project life budget of £264.932m. A summary of the
revised capital budgets is set out in Exhibit 1.
ITEM 19

Page 2

Exhibit 1: HRA Capital Estimates 2025/26 – 2029/30
Project Life
Budget
(£m)
2025/26
Budget
(£m)
Project Life
Forecast
BCR05
(£m)
2025/26
Forecast
BCR05
(£m)
Other Capital Expenditure 26.267 7.433 26.052 6.738
Component Replacement 93.567 20.881 89.226 14.468
Void Capital 19.873 5.258 19.873 5.700
Structural & Environmental 17.320 3.762 16.653 1.875
Support Costs 17.155 3.100 17.155 3.100
More Homes Programme  171.129 15.113 171.129 17.962
Total Expenditure 345.311 55.547 340.088 49.843
Total Income -80.379 -6.290 -81.636 -10.398
Prudential Borrowing 264.932 49.257 258.452 39.445
4. Main Issues
4.1 Progress against the 2025/26 capital plan is detailed in:
Appendix 1 – HRA Capital Summary BCR05
Appendix 2 – HRA Capital Detail BCR05
4.2 The HRA capital summary report at Appendix 1 reports that:
 project life expenditure is forecast to be less than budget by £5.223m over
the 5-year period of the capital plan.
 one project has forecast project life income of £1.258m more than the
project budget
 consequently, prudential borrowing will be £6.481m less than the approved
project life budget over the 5-year period of the capital plan.
4.3 Appendix 2 reports all projects with their approved in year and project life
estimates as well as their 2025/2026 expenditure and income forecasts. The
appendix reports:
 2025/2026 forecast spend of £49.843m, a £5.704m underspend against
the 2025/2026 budget.
 2025/2026 forecast income of £10.398m, a £4.108m over-recovery against
the 2025/2026 budget
 2025/2026 prudential borrowing will be £39.445m, £9.812m less than the
approved plan for 2025/2026.
4.4 Commentary on the 2025/2026 variances are set out in Exhibit 2 below.
Exhibit 2: Project Over / Underspends 2025/2026 as at BCR05
Project 25/26
Forecast
(£m)
25/26
Budget
(£m)
25/26
Variance
(£m) Commentary
1 Special Need
Adaptations
0.668 0.688 0.020 Small overspend to be re-
profiled across future years.

Page 3

Project 25/26
Forecast
(£m)
25/26
Budget
(£m)
25/26
Variance
(£m) Commentary
2 Capitalised
Minor Works
3.500 3.715 -0.215 Reduced contractors spend.
Underspend will reduce
borrowing requirement
3 Environmental
Sensors
1.500 2.000 -0.500 Underspend due to
challenges getting access to
properties.
Underspend will be re-
profiled across future years.
4 Targeted
SHQS /EESSH
compliance
works
5.000 6.628 -1.628 Underspend reflects the
changing mix of the capital
programme with an
increased number of mixed
tenure blocks that require
owner consent before work
can start. This necessary
process delays project start.
Underspend to be re-profiled
across future years.
5 External
Component
Renewal -
Roofs
1.250 2.500 -1.250 Underspend reflects the
changing mix of the capital
programme with an
increased number of mixed
tenure blocks that require
owner consent before work
can start. This necessary
process delays project start.
Underspend will reduce
borrowing requirement.
6 Doors/Windows
Component
Renewals
3.600 4.985 -1.385 Underspend due to
challenges getting access to
properties. Install team to
continue programmed
addresses and revisit no
accesses to use materials
already supplied.
Underspend will reduce
borrowing requirement.
7 External Stores
/ Garages / Bin
Stores
0.000 0.048 -0.048 Works are being funded from
the capitalised minor works
budget.
Underspend will reduce
borrowing requirement

Page 4

Project 25/26
Forecast
(£m)
25/26
Budget
(£m)
25/26
Variance
(£m) Commentary
8 Secure entry
component
renewals
0.000 0.100 -0.100 Works are being funded from
the capitalised minor works
budget.
Underspend will reduce
borrowing requirement.
9 Statutory /
Regulatory
Compliance
Works
0.150 0.594 -0.444 Health and safety works are
now being delivered across
two years.
Underspend will be re-
profiled across future years.
10 Energy
Improvements /
Energy
Efficiency
Works
0.000 0.058 -0.058 Works are being funded from
the capitalised minor works
budget.
Underspend will reduce
borrowing requirement.
11 Kitchen
Upgrade
1.600 2.850 -1.250 Underspend projected as
team re-assess and pre-
inspect to ensure a focus on
necessary renewals led by
condition.
Underspend will reduce
borrowing requirement.
12 Bathroom &
Shower
Replacement
0.600 0.800 -0.200 Underspend projected as
team re-assess and pre-
inspect to ensure a focus on
necessary renewals led by
condition.
Underspend will reduce
borrowing requirement.
13 Void House
Strategy
Programme
5.700 5.258 0.442 Contractor voids spend
greater than budgeted.
Overspend will be re-profiled
across future years.
14 Defective
structures
/component
renewals
0.175 0.800 -0.625 Underspend projected as
future blocks are pre-
inspected for condition and
re-prioritisation for
completion if necessary.
Building Services resources
are assisting in the void
house programme of work.
Underspend will reduce
borrowing requirement.

Page 5

Project 25/26
Forecast
(£m)
25/26
Budget
(£m)
25/26
Variance
(£m) Commentary
15 Environmental
Renewal -
Paths &
Environment
1.100 1.000 0.100 Overspend due to mix of
work requiring contactors in
addition to in-house team.
Overspend will be re-profiled
across future years.
16 Asbestos
Management
Works
0.200 0.242 -0.042 Demand lower than
anticipated.
Underspend will reduce
borrowing requirement
17 Multi Storey
Flat Strategy
0.400 1.720 -1.320 Revised projection based on
timing of programme.
Underspend will be re-
profiled across future years.
18 Buy Backs 4.000 4.380 -0.380 Revised projection based on
the anticipated programme of
thirty-five acquisitions to be
completed in 25/26.
Underspend will be re-
profiled across future years.
19 Demolition
Programme
0.206 0.140 0.066 Revised projection based on
timing of programme.
In year overspend will be re-
profiled across future years
20 Clydebank East 0.365 0.250 0.115 Revised projection based on
development project plan.
In year overspend will be re-
profiled across future years.
21 Pappert 0.872 0.730 0.142 Revised projection based on
development project plan.
In year overspend will be re-
profiled across future years.
22 Willox Park
Phase1
3.398 2.980 0.418 Revised projection based on
development project plan.
In year overspend will be re-
profiled across future years.
23 Bank Street 0.839 1.500 -0.661 Revised projection based on
development project plan.
In year underspend will be
re-profiled across future
years.

Page 6

Project 25/26
Forecast
(£m)
25/26
Budget
(£m)
25/26
Variance
(£m) Commentary
24 Bonhill Gap
Sites
5.145 1.600 3.545 Revised projection based on
development project plan.
Overspend will be re-profiled
across future years.
25 Silverton 0.050 0.100 -0.050 Revised projection based on
development project plan.
In year underspend will be
re-profiled across future
years.
26 Queen Mary
Avenue
1.000 0.800 0.200 Revised projection based on
development project plan.
In year overspend will be re-
profiled across future years.
27 Future New
Build & Related
Regeneration
Projects
0.000 0.550 -0.550 Revised projection based on
development project plan.
In year underspend will be
re-profiled across future
years.
28 Scottish Govt
Buyback Grant
-2.378 -0.550 -1.828 Revised projection based on
the distribution of Scottish
Government acquisition
funding
29 Bank Street -0.839 -1.500 0.661 Revised projection based on
the application of the
Strategic Local Programme
30 Bonhill Gap
Sites
-3.360 -1.600 -1.760 Revised projection based on
the application of the
Strategic Local Programme
31 Clydebank
Health Centre
-0.350 -0.375 0.025 Revised projection based on
the application of the
Strategic Local Programme
32 Other Grant -1.612 -0.406 -1.206 Additional Scottish
Government Net Zero
Funding awarded to fabric
first energy efficiency works
4.5 Budget assumptions are required to forecast costs / income, especially where
projects span multi-year and project finances have yet to be finalised. It is
therefore likely that the projected year end position will change during the
year.

Page 7

5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital estimates.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
several variable factors which could arise between now and 31 March
which could affect the year end results for capital budgets.
(b) To forecast for the full year costs budget assumptions have been
required. These assumptions continue to change regularly and therefore
it is likely the projected year end position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital estimates have been consulted
during the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.

Page 8

________________
Laurence Slavin
Chief Officer – Resources
Date: 29 October 2025
Person to Contact: Jim McCarron
Business Partner, Finance 07772 322055
E-mail: james.mccarron@west-dunbarton.gov.uk
Appendices: Appendix 1 - HRA Capital Summary BCR05
Appendix 2- HRA Capital Details BCR05
Background Papers:
Housing Revenue Account (HRA) Capital Investment Programme, Revenue
Budget, and Rent Levels for 2025/26 - Council 5 March 2025.
Wards Affected           All Wards