WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Council: 29 October 2025
_________________________________________________________________
Subject: General Services Capital Budgetary Control Report 2025/26 to
31 August 2025 (Period 5)
1. Purpose
1.1 This report provides an update on the General Services capital financial
performance to 31 August 2025.
2. Recommendations
2.1 Members are asked to:
a) Note the current position of the 2025/26 General Services capital budget.
b) Approve the revised completion dates in respect of 5 projects detailed in
Appendix 2 (Para 4.4).
c) Note the reprofiling of 6 projects in Appendix 3 of (£4.237m) over the
project life.
d) Approve £0.027m of additional capital budget for data strategy (Para 4.9)
e) Approve £1.316m of additional capital budget for plant and machinery
replacement strategy (Para 4.10).
f) Approve £0.352m of additional capital budget for vehicle replacement
strategy (Para 4.11).
3. Background
3.1 On 5 March 2025 the Council approved the updated General Services Capital
Plan for 2025/2026 to 2034/35. The three years from 2025/26 to 2026/28
were approved in detail with the remaining years being indicative. The budget
agreed was £73.780m for 2025/26 and £307.818m for the project life budget.
4. Main Issues
4.1 Exhibit 1 sets out the revised capital budget at period 3 as reported to Council
on 27 August 2025.
Exhibit 1: Revised Capital Budget as at 30 June 2025.
2025/26
(£m)
Project Life
(£m)
Capital Budget Agreed 5 March 2025 73.780 307.818
ITEM 17

Page 2

Updates reported to Council on 27 August plus
adjustments for year-end carried forward balances
5.150 5.536
Reprofiling reported to Council on 27 August (7.118) 0
Revised Capital Budget as at Period 3 71.812 313.354
4.2 Progress against the 2025/26 capital plan is detailed in:
Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Off Track Projects
Appendix 3 – Changes to Capital Plan for Noting
Appendix 4 – All Approved Projects
4.3 The overall programme summary report at Appendix 1 shows that planned
expenditure against the budget is currently on track. Note Appendix 1 is
constructed assuming all changes in this report are approved.
4.4 Appendix 2 highlights 5 projects currently showing as off-track, all of which
are due to revised completion dates.
 Project RR 5 (Regeneration Fund) is off track due to the Waterfront
Walkway progress being dependent on external factors, with an
anticipated completion date of 31 March 2029.
 Project RR 7 (Level Up Funding) is off track due to the project delivery
taking longer than initially expected. Resulting in an updated
completion date of 31 December 2027.
 Project RN 16 (Allotment Development) is off track due to a delay in the
tender process as a result of a service restructure and allocation of new
resources. The project completion date has been extended to 31 March
2027.
 Project RN 17 (Waste Transfer Station) has currently been paused as
the construction cost is significantly higher than the available budget. In
addition following the implementation of the Net Zero Cooperation
Agreement the Council now has resilience and this will be monitored
and reported to Council to consider whether the project is still required.
The completion date for the project has therefore been extended to 31
March 2029 while this monitoring and discussions are taking place.
 Project RN 23 (Creation of 3 new all weather pitches at Argyll Park,
Posties Park and Mountblow playing fields) is off track due to a delay in
the tender process because of Council service restructure and the
allocation of new resources. Posties Park (to be renamed to
commemorate Lachie Stewart) is now not expected to progress as
anticipated, the balance of the budget is being rephased to 2026/27
pending an appropriate site being identified.
4.5 Appendix 3 highlights 6 projects where the expenditure requires to be
reprofiled but there is no need for additional budget.

Page 3

4.6 Exhibit 2 sets out the revised capital budget at period 5 assuming approval by
Council of all recommendations contained within this report.
Exhibit 2: Revised Capital Budget
2025/26
(£m)
Project Life
(£m)
Capital Budget as at 30 June 2025 71.812 313.354
New Funding – RN 31 Bus Infrastructure Fund
(Para 4.8)
0.050 0.050
New Funding – RN 32 People and Places –
Transport Scotland (Para 4.8)
0.035 0.035
New Funding – RN 34 Nature Restoration Fund
(Para 4.8)
0.185 0.185
New Funding – RN 35 Road Safety Improvement
Fund (Para 4.8)
0.185 0.185
New Funding – RES 15 Design, Creation,
Installation of Digital Content for Glencairn House
(Para 4.8)
0.187 0.187
Additional Funding – RN 25 Active Travel (Para
4.8)
0.306 0.306
Additional Funding – RN 27 Implementation
20mph Speed Limits (Para 4.8)
0.458 0.458
Added RN 33 Shared Prosperity Funding – Open
Places (Para 4.8)
0.396 0.396
Added RR 12 Hybrid Meetings Equipment (Para
4.8)
0.053 0.053
Approved P&T 5 Capital Bid – Data Strategy
(Para 4.9)
0.027 0.027
Approved RN 30 Capital Bid – Plant and
Machinery Replacement (Para 4.10)
0.516 1.316
Approved Capital Bid – Vehicle Replacement
Strategy (Para 4.11) (added to RN 5)
0.352 0.352
Proposed revised Capital Budget as at Period
5
74.562 316.904
Reprofiling over project life (Appendix 3) (4.237) 0
Proposed revised Capital Budget as at Period
5 subject to Council Approval
70.325 316.904
4.7 Appendix 4 shows all projects with approved in year and project life budgets
as well as anticipated expenditure. It highlights that the 2025/26 budget is
£74.562m. Spend as at period 5 is £14.975m (21.29%) of the current forecast
spend of £70.325m.
4.8 Other minor changes to the capital plan included in the summarised plan in
appendix 4 are:
 New funding has been received from Scottish Government of £0.050m for
Bus Infrastructure Fund (RN 31) to support improvements to bus
infrastructure and accessibility.

Page 4

 New funding has been received from Transport Scotland of £0.035m for
People and Place Local Authority Direct Award (RN 32) for active and
sustainable travel behaviour change programme.
 New funding has been received from Scottish Government of £0.185m for
Nature Restoration Fund (RN 34) to support approaches to restoring
biodiversity.
 New funding has been received from Transport Scotland of £0.185m for
Road Safety Improvement Fund (RN 35).
 New funding from Strathleven Foundation for Inspiring Change for the
Design, Creation, Installation, and ongoing Management of Digital Content
for Glencairn House (RES 15) of £0.187m.
 Additional funding from Scottish Government for Active Travel (RN 25) of
£0.306m to support and promote active travel within the authority and to
improve active travel links.
 Additional funding from Transport Scotland for Implementation of 20mph
Speed Limits (RN 27) of £0.458m.
 Shared Prosperity Funding (RN 33) of £0.396m for open places such as
West Bridgend Community Space and Allotments.
 Addition of Hybrid Meetings Equipment (RR 12) approved at Council on
the 27 August 2025 of £0.053m to replace conference units and
microphones to allow hybrid meetings to continue with improved sound
quality.
4.9 Members are asked to approve a capital budget of £0.027m to fund data
strategy.
This bid has been reviewed by the Strategic Asset Management Group who
recommend that £0.027m is added to the Capital plan to allow the People and
Technology team to provide a robust data strategy which would be the
cornerstone of creating a sustainable, modern data ecosystem capable of
meeting the council’s evolving needs while improving outcomes for its
residents. A data strategy provides a unified framework for aligning data
governance, technology, and processes with organisational goals. This
approach positions West Dunbartonshire Council to effectively transform its
data into a strategic asset that can be better utilised and controlled to achieve
financial efficiencies and benefits while addressing challenges and setting the
foundation of a clear path for long-term data-driven success.
The new data platform and modern ways of working will drive operational
efficiencies and bring time-saving benefits forecast from the outset. The
Council can also better understand the changing landscape of public sector
demand on services and keep pace with legislative demands on statutory
services, and privacy and security requirements.

Page 5

This project has been included in appendix 4 (P&T 5).
4.10 Members are asked to approve a capital budget of £1.316m for the plant and
machinery replacement program.
This bid has been reviewed by the Strategic Asset Management Group who
recommend that £1.316m is added to the Capital plan to allow the Roads and
Neighbourhood team to replace plant and machinery which is no longer fit for
purpose.
This project has been included in appendix 4 (RN 30).
4.11 Members are asked to approve a capital budget of £0.352m for the vehicle
replacement strategy.
This bid has been reviewed by the Strategic Asset Management Group who
recommend that £0.352m is added to the Capital plan to allow the Roads and
Neighbourhood team to replace vehicles which are no longer fit for purpose.
This project has been included in appendix 4 (included within RN 5).
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are a
number of variable factors which could arise between now and 31 March
which could affect the year end results for capital budgets.
(b) As a consequence of current market conditions, inflation is high and interest
rates continue to be volatile. To forecast for the full year costs budget
assumptions have been required. These assumptions continue to change
regularly and therefore it is likely the projected year end budgetary position
will change from that reported.
9. Equalities Impact Assessment (EIA)

Page 6

9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
______________
Laurence Slavin
Chief Officer – Resources
Date: 22 September 2025
Person to Contact: Lynsey Dickson
Council Offices, Church Street, Dumbarton
E-mail: lynsey.dickson@west-dunbarton.gov.uk
Appendices:
Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Off Track Projects
Appendix 3 – Changes to Capital Plan for Noting
Appendix 4 – All Approved Projects
Background Papers: 
General Services Capital Plan Update - Council 6 March 2024
General Services Capital Plan Update - Council 5 March 2025
Capital Budgetary Control Report (P3) – Council 27 August 2025
Review of Hybrid Meetings of Council and Committees – Council 27 August 2025
Wards Affected          
All Wards