ARGYLL AND BUTE COUNCIL  COUNCIL  
FINANCIAL SERVICES 27 JUNE 2024 
CAPITAL BUDGET MONITORING REPORT – 31 MARCH 2024 
1.0 EXECUTIVE SUMMARY 
1.1 This report provides an update on the position of the capital budget as at 31 March
2024. The report provides information on the financial position in respect of the
capital plan and the performance in terms of delivery of capital plan projects. 
1.2  Financial Position: 
 Outturn for 2023-24 – actual net expenditure for the full financial year is
£37,860k compared to an annual budget of £33,166k giving rise to an
overspend for the year of £4,694k (14.15%). This variance is after previously
agreed slippage of £27,837k that has been approved throughout 2023-24
therefore budgets will be re-profiled accordingly.   
 Total Capital Plan – forecast total net project costs on the total capital plan
are £219,771k compared to a total budget for all projects of £219,771k. No
variance is projected.  
1.3 Project Delivery: 
 Asset Sustainability – Out of 96 projects there are 84 projects (87%) on track
and 12 projects (13%) off track but recoverable.
 Service Development - Out of 44 projects there are 40 projects (91%) on
track and 4 projects (9%) off track but recoverable.
 Strategic Change – Out of 29 projects there are 19 projects (66%) on track
and 10 projects (34%) off track but recoverable.  
1.4 
1.5 
The Capital Programme is funded by various income streams as detailed in
Appendix 3. Additional funding has been added for 2023-24 CFCR, STTS Income
for Roads, Scottish Government Grants for Bus Partnership Fund and Road Safety
Improvement Fund, third party contributions from Live Argyll and HSCP, Crown
Estates Allocation, Strategic Housing Fund contribution and additional allocation of
Rural Growth Deal funding. 
Originally the Council was projecting £1,195k of capital receipts this financial year
which was then revised to £484k. Actual receipts of £622k have been received
which will reduce the income target for 2024-25. The estimated level of receipts for
future years will be kept under review as market conditions change; as will values
following due diligence undertaken by prospective purchasers on the condition of
asset.

Page 2

ARGYLL AND BUTE COUNCIL  COUNCIL  
FINANCIAL SERVICES  27 JUNE 2024 
CAPITAL BUDGET MONITORING REPORT – 31 MARCH 2024 
2.0  INTRODUCTION 
2.1 
2.2 
2.3 
2.4 
2.5 
This report provides an update on the position of the capital budget as at 31 March
2024. The report provides information on the financial position in respect of the capital
plan and the performance in terms of delivery of capital plan projects. 
Following the decision at Policy and Resources Committee on 9 December 2021, the
Rothesay Pavilion project was put on pause whilst potential funding options were
being considered. At the budget meeting in February 2023 additional funding was
allocated to this project which will allow the project to progress towards success by
supporting completion of certain work stages. Further information regarding the
progress of this project will be reported during 2024-25 once tenders have been
received and finalised. The financial information included within this report includes
amounts relating to Phase 1 only of the Rothesay Pavilion project. 
Surveys have been completed in the Councils Learning Estates in relation to
RAAC with only 1 building confirmed as having it present with steps underway for its
removal. This will include a decant of the students for approximately 9 months plus
total removal and replacement of the roof during 2024-25. Funding of £3m was
considered as part of the 2024-25 budget setting process and additional funding was
allocated as agreed at the Council meeting on 22nd February 2024. 
The Councils bid to the Scottish Governments Learning Estate Investment Programme
(LEIP) for funding for a new school campus on Mull was successful. While this is good
news and will provide welcome investment in the school estate it does come with a
financial pressure that is required to be funded if the project is to proceed. The
Scottish Government will fund up to 50% of eligible costs therefore the Council will be
required to fund circa £20m prior to any associated borrowing costs. A Members
seminar was held on the 12th April 2024 and a report subsequently presented to
Council on 25th April outlining the financial, economic, community and educational
implications of the proposed campus. Members agreed that up to £5m from the
previously agreed earmarked LEIP funding could be used to commence the Business
Case, undertake engagement exercises, commence the site selection process and
establish governance arrangements. To progress with the project beyond this point
Members will consider the capital and revenue budget provision required as part of the
budget setting process. 
As a result of significant rainfall Argyll and Bute Council activated the Bellwin scheme
in relation to the recovery costs associated with the incident. The funding from this
scheme is welcomed however eligibility criteria of costs are restrictive. Capital
expenditure does not qualify therefore any long term replacements to infrastructure
such as bridges cannot be claimed through the scheme therefore if not already part of
the capital programme required to be funded. Works to the value of £1.8m have been
carried out already with future anticipated works costing circa £2.5m being identified,
both which will require capital funding. As a result of this borrowing of £4.3m to fund
the capital costs not eligible through the Bellwin Scheme was considered as part of the
2024-25 budget setting process and agreed at the Council meeting on 22nd February
2024.

Page 3

2.6 
2.7 
2.8 
2.9 
A £1m cost pressure was identified during 2021-22 in relation to repairs to the A884
Ardbeg Sea Wall, where severe storm damage resulted in failure of the sea wall on
Bute. Emergency works were carried out and a permanent solution is currently being
developed. Additional funding of £1m was allocated for this purpose at the Council
meeting on 24 February 2022 however there remains a risk that costs will exceed this.
The tender for this project is being developed with the current aim to have a contractor
on site by Spring/Summer 2025, final costs will be known once tenders are returned
early in 2024-25. 
The impact of the pandemic along with the UK exit from the European Union, the
Russian invasion of Ukraine and sanctions on Russian owned entities continues to
result in significant price increases as well as disruptions to the supply chain and
longer lead in times. The increased rate of inflation impacts costs such as energy
prices, labour, packaging and transport. These all have an effect on the overall
contract price and make it extremely challenging to manage expenditure and the
availability of supply. 
As a result of this it should be noted that there are likely to be other significant financial
impacts which are not quantifiable at this stage, as follows: 
 Rothesay Pavilion – despite additional funding being awarded there remains a
funding gap to allow full completion of the original intended works. 
 Harbour Investment Programme – likely to be contractual cost increases in
future years (expected to be funded from increased fees and charges).
 Universal Free School Meals – roll out to P6 and P7 has been confirmed but
capital funding levels available from the Scottish Government are still unknown. 
 Bridges Fund - A scheme of bridge capital works was developed and 80%
funded through the Local Bridge Maintenance Fund with £5.450m of funding
approved. Increased capital contract costs from when the scheme was
developed to now, has the schemes costing approximately £12m. A request for
the original funding to be approved to cover a smaller scheme with less bridges
has been sent to Scottish Government and awaits a response. 
 In general, capital contracts across the programme are seeing significant price
increases. 
Although the direct impact of COVID on most local services has reduced or even
ceased altogether over the last 12 months, COVID-19 in conjunction with the UK exit
from the European Union and the Russian invasion of Ukraine, continues to affect
worldwide supply chains. 
In recent years additional funding of £10.803m has been allocated to the capital
programme for this purpose which has mitigated the impact to date however, as
detailed in the table below. An additional £0.297m was considered as part of the 2024-
25 budget setting process and this additional funding was allocated as agreed at the
Council meeting on 22nd February 2024. With £8.834m already allocated or
committed this results in £2.266m of the fund remaining unallocated to projects facing
inflationary pressures. 
Funding for Capital Inflationary Pressures £m
COVID-19 Funding 0.257
February 2021 Budget Meeting - Capital Cost Pressures 4.646
February 2022 Budget Meeting - Capital Cost Pressures 3.900
February 2023 Budget Meeting - Capital Cost Pressures 2.000
February 2024 Budget Meeting - Capital Cost Pressures 0.297
Total Additional Funding Allocated to Capital 11.100
Allocated to Projects within Capital Programme (5.779)
Committed for future years (3.055)
Balance Remaining 2.266

Page 4

4.0 OUTTURN FINANCIAL POSITION 2023-24 
4.1 
4.2
Overall Position 
Actual net expenditure for the full financial year is £37,860k compared to a budget for
the year to date of £35,175k giving rise to an overspend for the year of £4,694k
(14.15%). This variance is after previously agreed slippage of £27,837k that has been
approved throughout 2023-24 therefore budgets will be re-profiled accordingly. 
Project/Department Position 
The table below shows the actual expenditure and budget for the year by project type
and service: 
Project Type:
Annual
Budget            
£'000
Forecast
Outturn        
£'000 
Forecast
Variance         
£'000
Asset Sustainability 19,680 18,343 1,337
Service Development 322 3,220 (2,898)
Strategic Change 13,164 16,297 (3,133)
Total  33,166 37,860 (4,694)
Service:      
ICT 1,457 1,410 47
Education 7,208 5,748 1,460
Live Argyll 1,175 1,034 141
Health & Social Care Partnership 957 748 209
Shared Offices 1,660 1,162 498
Roads & Infrastructure 19,522 19,835 (313)
Development & Economic Growth (2,143) 990 (3,133)
CHORD 3,330 6,933 (3,603)
Total 33,166 37,860 (4,694) 
Material variances are explained in Appendix 1 and there are a number of small
variances contributing to the overspend. 
3.0  RECOMMENDATIONS 
3.1 Note the contents of this report and the financial summaries as detailed in Appendix 6
and approve the proposed changes to the capital plan detailed in Appendix 2.

Page 5

5.0 TOTAL PROJECT COSTS 
5.1 Overall Position 
Forecast total net project costs on the total capital plan are £228,625k compared to a total
budget for all projects of £228,625k. No variance is projected. 
5.2  Project/Department Position 
The table below shows the forecast expenditure and budget for the total capital plan by
project type and service. 
Project Type:
Capital Plan
Budget           
£'000
Forecast
Project
Costs        
£'000 
Total
Capital
Plan
Variance         
£'000
Asset Sustainability 69,755 69,755 0
Service Development 23,749 23,749 0
Strategic Change 126,267 126,267 0
Total  219,771 219,771 0
Service:      
ICT 7,068 7,068 0
Education 49,755 49,755 0
Live Argyll 4,070 4,070 0
Health & Social Care Partnership 4,684 4,684 0
Shared Offices 23,974 23,974 0
Roads & Infrastructure 64,490 64,490 0
Development & Economic Growth 6,385 6,385 0
CHORD 59,345 59,345 0
Total 219,771 219,771 0 
There are no variances to report.

Page 6

6.0  TOTAL PROJECT PERFORMANCE 
6.1  Overall Position 
There are 169 projects within the Capital Plan, 143 are Complete or On Target, 26 are
Off Target and Recoverable and none are Off Track.
6.2  Project Position 
The table below shows the Performance Status of the Projects in the Capital Plan. 
Project Type:
Complete
/ On
Target
Off Target/
Recoverable
Off
Target/
Problem Total
Asset Sustainability 84 12 0 96
Service Development 40 4 0 44
Strategic Change 19 10 0 29
Total 143 26 0 169
Service:        
ICT 7 0 0 7
Education 27 6 0 33
Live Argyll 22 0 0 22
Health & Social Care
Partnership 16 3 0 19
Shared Offices 23 2 0 25
Roads & Infrastructure 31 9 0 40
Development &
Economic Growth 14 3 0 17
CHORD 3 3 0 6
Total 143 26 0 169 
6.3  Chart of Performance Status 
The graph provides a view of the Performance Status of the Projects included in the
Capital Plan:

Page 7

7.0 OFF TRACK PROJECTS 
7.1  There are no Off Track projects for this report.  
8.0  STRATEGIC CHANGE PROJECTS 
8.1 Appendix 5 gives detailed information in respect of the Strategic Change Projects within
the Capital Plan. The appendix gives details of the forecast cost of each project against
the approved budget, the start and anticipated completion date of the project and an
assessment of the risks of the project and, if these are not green, gives an explanation of
the problem. 
9.0 
9.1 
CHANGES TO CAPITAL PLAN 
The table below shows previous changes to expenditure budgets within the Capital
Plan at summary level, including slippages and accelerations offset by any budget
adjustments. There are no proposed changes in terms of slippages or accelerations in
the current month as any over or under spends are rolled forward into future years as
part of the year end process. 
Projects with slippages greater than £500k are detailed in Appendix 4.

Page 8

Department Prev. Agreed Changes 
2023-24
Asset Sustainability (10,861)
Service Development (3,141)
Strategic Change (13,835)
Total (27,837)   
Service: 0
ICT 136
Education (3,542)
Live Argyll (448)
Health & Social Care Partnership (2,047)
Shared Offices (1,166)
Roads & Infrastructure (15,518)
Development & Economic Growth (2,674)
Major Projects (2,578)
Total (27,837) 
10.0 
10.1 
FUNDING 
The Capital Programme is funded by various income streams as detailed in Appendix 3.
Additional funding has been added for 2023-24 CFCR, STTS Income for Roads, Scottish
Government Grants for Bus Partnership Fund and Road Safety Improvement Fund, third
party contributions from Live Argyll and HSCP, Crown Estates Allocation, Strategic
Housing Fund contribution and additional allocation of Rural Growth Deal funding.
11.0 
11.1 
11.2 
11.3 
11.4 
11.5 
11.6 
11.7 
11.8 
11.9
IMPLICATIONS 
Policy – Monitors progress against the capital plan. 
Financial – Monitors funding and commitments of the capital plan. 
Legal – Available funding may not address all Statutory and Regulatory requirements in
relation to Health and Safety. 
HR – Available funding may have an impact on the sustainability of the Property Design
Team and Infrastructure Design Team. 
Fairer Scotland Duty – None. 
12.5.1     Equalities – protected characteristics – None. 
12.5.2     Socio-economic Duty – None. 
12.5.3     Islands – None. 
Climate Change – The Council is committed to addressing climate change via projects
within the capital plan. 
Risk – There are risks around increasing capital contract costs and the level and timing of
capital receipts. 
Customer Service – None. 
The Rights of the Child (UNCRC) - None.

Page 9

Kirsty Flanagan 
Executive Director / Section 95 Officer 
13 June 2024                                                  
Policy Lead for Finance and Commercial Services – Councillor Ross Moreland 
APPENDICES
- Appendix 1 – Forecast Outturn variance explanations
- Appendix 2 – Changes to Capital Plan and Financial Impact
- Appendix 3 – Capital Funding
- Appendix 4 – Over £500k Variance Reports
- Appendix 5 - Cumulative spend, completion dates and risks relating                         
to significant capital projects. 
- Appendix 6 - Financial Summary – Overall
- Financial Summary – Executive Director Kirsty Flanagan
- Financial Summary – Executive Director Douglas Hendry
- Appendix 7 - Updated/Revised Capital Plan
For further information contact: Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 10

APPENDIX 1 – Outturn Variance Explanations
Listed below are the projects where the current year variance is +/- £50k. 
Project 
Annual
Budget
£’000
Outturn
£’000
Total
(Over)/
Under
Forecast
Variance         
£’000
Explanation
Server Sustainability 352 289 63
Minor delay in receiving order at end of year.
Primary Schools 3,370 3,195 175 Continued issues with availability of skilled labour and spiralling material
costs resulting in delays to projects
Secondary Schools 852 709 143 Continued issues with availability of skilled labour and spiralling material
costs resulting in delays to projects
Free School Meals 379 213 166
Retention values slipped into future year.
Block Allocation - Education 243 0 243 Continued issues with availability of skilled labour and spiralling material
costs resulting in delays to projects
Dunoon Primary School 234 2 232 Ongoing negotiations with contractor have delayed final payments and
retention invoices.
Replacement of Oban High
School
406 0 406 Ongoing negotiations with contractor have delayed final payments and
retention invoices.
Glencruitten Hostel 81 9 72
Minor works carried out in 23-24, project will commence 24-25.
Capital Property Works -
HSCP
167 0 167
Delays in agreeing the programme priorities with HSCP 
Dunclutha Childrens Home 54 0 54
Retention remains held due to dispute over defects.

Page 11

Block Allocation - Shared
Offices
372 0 372
Minor works carried out to Offices during 23-24 due to office rationalisation.
Roads Reconstruction 7,766 7,259 507
Additional funding received late in year.
Lighting 440 246 194
Delays due to other commitments
Environmental Projects (200) 300 (500)
External funding won’t be received until works are complete.
Public Conveniences (200) 0 (200) External funding won’t be received until works are complete – project slipped
earlier in the year so income should have been re-profiled at the same time.
Fleet Management 1,664 1,469 195
Late delivery of vehicles
Footway Improvements 450 531 (81)
Reversal of previous slippage as value too much
EV Quick Chargers 62 10 52
No new installations, should have been re-profiled earlier in year
Block Allocation - RIS -100 0 (100)
Acceleration of block allocation to fund Depot project
Campbeltown Flood Scheme 8,625 8,756 (131) Reversal of previous slippage as value too much – continual changes to
programme by contractor and high value of project make projections difficult
at year end.
Harbour Investment
Programme PB
1,490 1,898 (408)
Reversal of previous slippage as value too much
Safe Streets, Walking and
Cycling (CWSS)
(6) 130 (136)
Project spans into 24-25 when external grant income will be received
Cycleways - H&L (FSPT) (290) 93 (293)
Project spans into 24-25 when external grant income will be received

Page 12

CHORD - Oban 626 47 579 Work ongoing to determine cause of defects.  Benefits realisation analysis
will commence once all CHOS projects are complete.
CHORD - Rothesay  4,735 6,170 (1,435)
External funding won’t be received until works are complete.
Town Centre Funds 34 384 (350)
External funding won’t be received until works are complete.
Dunoon STEM Hub (2,050) 0 (2,050) Project has been delayed due to location of the STEM Hub, income profile
should have been updated earlier in year when project expenditure was
slipped.
Dunoon Cycle Both (394) (96) (298)
External funding won’t be received until works are complete.
Rural Growth Deal (211) (81) (130) Delay in drawdown of earmarked reserves due to accounting practices, will
be drawn down in 24-25.
Tigh An Rudha HFE 116 201 (85)
Major works starting in 24-25, only minor works carried out in 23-24.
Clean Energy - NDEEF1 224 145 79
Delays due to VFM concerns
TIF - Halfway House
Roundabout 
56 0 56
Project still being developed
Tobermory Car Park  96 0 96
Decision still pending on car park works.
CO2 Monitoring - Covid
Mitigation in Schools
113 0 113
Scottish Government grant requires to be allocated to specific projects
Kilmory Business Park Phase
2AA
(419) 13 (432) Delays in invoicing due to legal requirements resulting in delays in receiving
external funding
Helensburgh Waterfront (1,673) 696 (2,369)
Timing of external funding, will be received in 24-25.

Page 13

Coastal Change Adaptation  126 48 78
Payment to Luing Community Council slipped to 24/25.
Clean Energy - NDEEF2 50 0 50
Delays due to VFM concerns
Other variances under £50k   212
Total value of non-material variances less than +/-£50k.
Total  (4,694)   
APPENDIX 2 – Changes to Capital Plan and Financial Impact
OVERALL COST CHANGES
Project
2023-
24
£’000
2024-
25
£’000
2025-
26
£’000
Future
Years
£’000
Total
Capital
Plan
£’000
Recommendation Explanation
Total Cost Changes 0 0 0 0 0   
SLIPPAGES AND ACCELERATIONS
Project 2023-24
£’000
2024-25
£’000
2025-26
£’000
2026-27
£’000
Total
Capital
Plan
£’000
Recommendation Explanation
None for this report       
Total Slippages and Accelerations 0 0 0 0 0  
Net Impact of Changes 0 0 0 0 0   
There are no proposed changes in the current month regarding slippages or accelerations as any over or underspends are rolled forward into future years as part of the
year end process. Income budgets will also be aligned accordingly as part of this process.

Page 14

CAPITAL PROGRAMME FUNDING Appendix 3
Estimated
Capital
Funding
Carry
Forwards
from 23-24
Slippage /
Acceleration
Additional
Funding
Updated
Capital
Funding
Available
Estimated
Capital
Funding
Carry
Forwards
from 22-23
Slippage /
Acceleration
Additional
Funding
Updated
Capital
Funding
Available
Estimated
Capital
Funding
Carry
Forwards
from 22-23
Slippage /
Acceleration
Additional
Funding
Updated
Capital
Funding
Available
Estimated
Capital
Funding
Carry
Forwards
from 22-23
Slippage /
Acceleration
Additional
Funding
Updated
Capital
Funding
Available
General Capital Grant 17,626 0 0 0 17,626 9,042 0 0 0 9,042 9,069 0 0 0 9,069 8,834 0 0 0 8,834
Capital Grant - Area Control Accounts 51 0 0 3 54 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Transfer to Revenue for Private Sector Housing Grant (PSHG) -1,033 0 0 0 -1,033 -1,033 0 0 0 -1,033 -1,033 0 0 0 -1,033 -1,033 0 0 0 -1,033
Capital Receipts 511 0 138 0 649 750 0 -138 0 612 750 0 0 0 750 400 0 0 0 400
Flooding Allocation 155 0 0 0 155 156 0 0 0 156 156 0 0 0 156 0 0 0 0 0
Ring Fenced Capital Grant 5,800 0 0 0 5,800 379 0 0 0 379 618 0 0 650 1,268 0 0 0 0 0
Restricted Funding 2,485 0 -473 793 2,805 2,553 0 9,488 2,031 14,072 84 0 0 0 84 0 0 0 0 0
Funded by Reserves 13,632 691 -10,615 0 3,708 10,061 0 783 1,559 12,403 1,412 0 -692 600 1,320 -38 0 0 0 -38
Additional Funding from Revenue 142 0 0 1,616 1,758 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Insurance 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Harbour Investment Programme 3,200 0 -1,302 0 1,898 24,110 0 1,302 0 25,412 39,000 0 0 0 39,000 17,585 0 0 0 17,585
Prudential Borrowing 3,413 3 1,137 0 4,553 17,567 0 -1,047 0 16,520 166 0 1,313 0 1,479 376 0 -609 0 -233
Loans Fund Review 2,690 0 0 0 2,690 431 0 0 0 431 0 0 0 0 0 0 0 0 0 0
COVID Funding 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
48,672 694 -11,115 2,412 40,663 64,016 0 10,388 3,590 77,994 50,222 0 621 1,250 52,093 26,124 0 -609 0 25,515
BREAKDOWN OF ADDITIONAL FUNDING
Additional Funding 2023-24 2024-25 2025-26 2026-27 Reported Source
Fleet Management 159 Jan-24
Area Control Accounts 3 Jan-24 Control Accounts
Rural Growth Deal 9 Feb-24
Coastal Adaptation Change 65 Feb-24
Bus Partnership Fund 18 Feb-24
CFCR 2023-24 1,616 Mar-24
East Clyde Street 1 Mar-24 Crown Estates Fund
RAAC 10 2,390 600 Mar-24
Roads Reconstruction 347 Mar-24
Bus Partnership Fund 32 Mar-24
Rural Growth Deal 20 Mar-24
Road Safety Imp Fund 191 Mar-24
Aqualibrium - Health Suite Upgrade 20 Mar-24
Riverside Leisure Centre - Health Suite Upgrade 80 Mar-24
Tigh An Rudha HFE 731 Mar-24 HSCP
Tigh An Rudha HFE 160 Mar-24 Strategic Housing Fund
Kintyre Care Home 150 650 Mar-24 HSCP
Scottish Government
Scottish Government
Third Party Contribution
Third Party Contribution
Scottish Government
2023-24 2024-25
Earmarked Reserves
Scottish Government
Scottish Government
Scottish Government
2025-26 2026-27
Revenue
Council Reserves
STTS

Page 15

CAPITAL PROJECT SLIPPAGE OVER £0.500M – YEAR END EXPLANATION REPORT FOR SMT
Projects Names: Bridge Strengthening & Local
Bridge Maintenance Fund
Project Manager: E Simoes
Year 2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Anticipated Spend at start of 2023-24 2.336 4.350 0.203 0.000
Anticipated spend at end of 2023-24 0.515 6.171 0.203 0.000
(Slippage)/Acceleration (1.821) 1.821 0.000 0.000
In 2023-24 there has been £1.821m of slippage compared to the projections for this year at the
beginning of 2023-24. Please identify the reason for this slippage below by ticking (√) the
appropriate box:
Incorrect profiling at start of year Material delays
Changes to project plan Other (explain below) √
Detailed explanation for the above (if there is more than one reason ticked above please give
approximate values applicable to each cause):
Following a period of wet weather which left ground conditions very wet and in many cases
saturated, over a months’ worth of rain fell over a 36 hour period starting Friday 6 October
2023 and running into Saturday 7 October 2023 – Infrastructure Design were required to
attend the following sites and take over the major bridges replacements and landslides;
these are the major following protects still ongoing:
1. Kilmelford Bridge, replacement of the full bridge including scour protection along
upper and downstream and narrow footway on the upstream side of the bridge
2. Kilninver Bridge, rock amour protection to the south east banking which abuts the
bridge
3. Glen Lean B836, design and installation of a temporary bridge and diversion road.
Construction of permanent bridge and removal of temporary structure
4. Lochgoilhead Bridge, scour protection
5. Ri Cruin Bridge, scour and undermining works
6. Landslide at C30 Kilmaha Ford to Dalavich, slope stability and vehicle barrier
7. A816 Kintraw, landslide, catch pits at base of unstable slope  Catch pits and
bound to be completed following the completion of the last of the temporary works
land agreement. Design and construction of a Permanente road along with consents
and land agreements
8. A815 landslide and monitoring
9. U014 Scammadale, landslide
10. B828 Glenmore Road Stabilization
11. B836 - 090 Upper Stronafian Bridge
APPENDIX 4

Page 16

CAPITAL PROJECT SLIPPAGE OVER £0.500M – YEAR END EXPLANATION REPORT FOR SMT 
While it is appreciated figures will not be 100% accurate, are you content that the “Anticipated
Spend at end of 2023-24” noted in the table at the top of the page are a good estimate of what
will be spent in each of the years 2024-25, 2025-26 and 2026-27? 
Yes, however given the services that Infrastructure Design team are required to
undertake, provisional figures will be always provisional 
If not, have you advised Financial Services of the changes to these forecasts as this is what is
currently populated in the Capital Monitoring spreadsheets completed by Project Managers?

Page 17

CAPITAL PROJECT SLIPPAGE OVER £0.500M – YEAR END EXPLANATION REPORT FOR SMT 
Project Name: Campbeltown Flood Scheme Project Manager: J Salmon 
Year 2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Anticipated Spend at start of 2023-24 9.860 0.029 0.330 0.004
Anticipated spend at end of 2023-24 8.756 1.780 0.010 0.387
(Slippage)/Acceleration (1.104) 1.751 (0.320) 0.383
Note additional budget was allocated to this project during the year totalling £0.710m
In 2023-24 there has been £1.104m of slippage compared to the projections for this year at the
beginning of 2023-24. Please identify the reason for this slippage below by ticking (√) the
appropriate box:
Incorrect profiling at start of year  Material delays 
Changes to project plan  Other (explain below) √     
Detailed explanation for the above (if there is more than one reason ticked above please give
approximate values applicable to each cause): 
Profile provided by the contractor changed throughout 2023-24 due to extension of works
contract into 24-25 financial year, largely due to Scottish Water delaying contractors
progress 
While it is appreciated figures will not be 100% accurate, are you content that the “Anticipated
Spend at end of 2023-24” noted in the table at the top of the page are a good estimate of what
will be spent in each of the years 2024-25, 2025-26 and 2026-27?
Yes however figures are revised on a monthly basis in the Capital Monitoring report and
will change based on updated forecasts from Contractor
If not, have you advised Financial Services of the changes to these forecasts as this is what is
currently populated in the Capital Monitoring spreadsheets completed by Project Managers?

Page 18

CAPITAL PROJECT SLIPPAGE OVER £0.500M – YEAR END EXPLANATION REPORT FOR SMT 
Project Name: CHORD – Oban Project Manager: J Gordon 
Year 2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Anticipated Spend at start of 2023-24 0.626 0.000 0.000 0.000
Anticipated spend at end of 2023-24 0.047 0.579 0.000 0.000
(Slippage)/Acceleration (0.579) 0.579 0.000 0.000 
In 2023-24 there has been £0.579m of slippage compared to the projections for this year at the
beginning of 2023-24. Please identify the reason for this slippage below by ticking (√) the
appropriate box:
Incorrect profiling at start of year  Material delays 
Changes to project plan  Other (explain below) X     
Detailed explanation for the above (if there is more than one reason ticked above please give
approximate values applicable to each cause): 
All of the Projects within the CHORD_Oban programme of works have achieved practical
completion. There was a residual budget of £626k made up as follows: 
1. CHORD_Oban (General)     £115k
2. CHORD_Oban (Transit Berthing Facility)   £  85k
3. CHORD_Oban (Public Realm Phase 1 and Phase 2) £131k
4. CHORD_Oban (Maritime Visitor Facility)   £295k 
The budget allocations noted above were carried over from previous years, and we require to
carry them forward in FY24/25 as the expenditure has not been incurred as expected due to the
following reasons: 
1. This budget allocation is to (a) provide additional budget cover in respect of Item (2)
below should the Council be responsible for any additional costs, and (b) to enable us to complete
the full Benefits Realisation Analysis and Economic Evaluation for CHORD-Oban and the overall
CHORD Programme once all of the works are complete and the various contracts closed out,
including the settlement of all outstanding commercial issues.
2. This budget allocation is to enable the project team to address the root cause of Defect
55, the appearance of transverse cracks on two of the concrete pontoons. As there is a dispute
between the Contract and Employer as to the cause of this defect, budget is to cover any risk
arising to the Employer. We have commissioned Royal Haskoning DHV to undertake independent
structural analysis of the facility to determine the root cause and any subsequent remedial actions
to rectify. We have received the Phase 2 analysis report and met with RHDHV to discuss its
content and request certain revisions to make the conclusion and recommendations as specific
and unambiguous as possible. RHDHV will resubmit their report and in consultation with
colleagues in Procurement, Commercial and Contract Management, this will enable us to assess
the appropriate course of action in terms of remedial works and the cost thereof.
3. This budget allocation is to cover any potential risk arising to the Council as Employer
under the two works contracts whilst we await the end of the statutory prescription period for
potential claims arising from the Contractor (Ph1) or the Administrator (Ph2)
4. This budget allocation is to enable additional works with respect to air handling units for
the facility once the specification is confirmed.

Page 19

CAPITAL PROJECT SLIPPAGE OVER £0.500M – YEAR END EXPLANATION REPORT FOR SMT 
While it is appreciated figures will not be 100% accurate, are you content that the “Anticipated
Spend at end of 2023-24” noted in the table at the top of the page are a good estimate of what
will be spent in each of the years 2024-25, 2025-26 and 2026-27?
1. No – whilst we should be in a position to progress the Benefits Realisation Analysis for
CHORD-Oban in FY24/25. In terms of the CHORD Programme, and given the extended
delays to the Rothesay Pavilion Project, it would make sense to commence the
Programme Level analysis in FY24/25, and as necessary pick up on the RPN project as a
separate issue once it achieves practical completion. We would therefore recommend
that £79k is taken from the FY24/25 Forecast and reprofiled in FY25/26 as follows: 
Year 2023-24 £m 2024-25 £m 2025-26 £m 2026-27
£m
Anticipated Spend at start of 2023-24 0.626 0.000 0.000 0.000
Anticipated spend at end of 2023-24 0.047 0.579
0.500
0.000
0.079
0.000
(Slippage)/Acceleration (0.579) 0.579
0.500
0.000
0.079
0.000 
2. Yes – £47k has been expended in FY23/24 and the balance of £38k therefore carries
forward into FY24/25. The submission of the RHDHV Stage 2 analysis report should
facilitate the closure of the outstanding issues on the Transit Berthing Facility
3. Yes – Prescriptive period runs out in 2024
4. Yes – Marine Operations to confirm specification of requirements 
If not, have you advised Financial Services of the changes to these forecasts as this is what is
currently populated in the Capital Monitoring spreadsheets completed by Project Managers?
Following consideration of the request for the Project Slippage Report for CHORD_Oban we have
discussed this within the PPMS Team and revised the future years forecasts to take account of the
most up to date information in this return.

Page 20

CAPITAL PROJECT SLIPPAGE OVER £0.500M – YEAR END EXPLANATION REPORT FOR SMT 
Project Name: CHORD - Rothesay Project Manager: Jonathan Miles 
Year 2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Anticipated Spend at start of 2023-24 6.871 1.684 0.226 0.000
Anticipated spend at end of 2023-24 6.170 2.611 0.000 0.000
(Slippage)/Acceleration (0.701) 0.927 (0.226) 0.000 
In 2023-24 there has been £0.701m of slippage compared to the projections for this year at the
beginning of 2023-24. Please identify the reason for this slippage below by ticking (√) the
appropriate box:
Incorrect profiling at start of year  Material delays 
Changes to project plan  Other (explain below) 
Detailed explanation for the above (if there is more than one reason ticked above please give
approximate values applicable to each cause): 
Due in part to delays in works to flat roofs due to discovery risk defects requiring detailed
investigation and repairs. The latest Project Programme estimates that construction works, and
therefore major expenditure, will carry on through to end August 24. 
While it is appreciated figures will not be 100% accurate, are you content that the “Anticipated
Spend at end of 2023-24” noted in the table at the top of the page are a good estimate of what
will be spent in each of the years 2024-25, 2025-26 and 2026-27?
Yes
If not, have you advised Financial Services of the changes to these forecasts as this is what is
currently populated in the Capital Monitoring spreadsheets completed by Project Managers?

Page 21

CAPITAL PROJECT SLIPPAGE OVER £0.500M – YEAR END EXPLANATION REPORT FOR SMT 
Project Name: Dunoon Community STEM Hub Project Manager: I Bremner 
Year 2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Anticipated Spend at start of 2023-24 0.713 1.750 0.00 0.00
Anticipated spend at end of 2023-24 0.036 2.427 0.00 0.00
(Slippage)/Acceleration (0.677) 0.677 0.000 0.000 
In 2023-24 there has been £0.677m of slippage compared to the projections for this year at the
beginning of 2023-24. Please identify the reason for this slippage below by ticking (√) the
appropriate box:
Incorrect profiling at start of year  Material delays 
Changes to project plan √ Other (explain below) 
Detailed explanation for the above (if there is more than one reason ticked above please give
approximate values applicable to each cause): 
Initial tender for construction of Dunoon STEM Hub was terminated after the Internal Rural
Growth Deal Programme Board requested that a new location was sought for the project.
The tender for construction at Hill Street was terminated and as such construction costs
have not started in 2023-24 as originally forecast. 
While it is appreciated figures will not be 100% accurate, are you content that the “Anticipated
Spend at end of 2023-24” noted in the table at the top of the page are a good estimate of what
will be spent in each of the years 2024-25, 2025-26 and 2026-27?
Yes 
If not, have you advised Financial Services of the changes to these forecasts as this is what is
currently populated in the Capital Monitoring spreadsheets completed by Project Managers?

Page 22

CAPITAL PROJECT SLIPPAGE OVER £0.500M – YEAR END EXPLANATION REPORT FOR SMT 
Project Name: Fleet Management Project Manager: J Blake 
Year 2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Anticipated Spend at start of 2023-24 2.512 1.180 0.000 0.000
Anticipated spend at end of 2023-24 1.469 2.382 0.000 0.000
(Slippage)/Acceleration (1.043) 1.202 0.000 0.000
Note additional budget was allocated to this project during the year totalling £0.159m
In 2023-24 there has been £1.043m of slippage compared to the projections for this year at the
beginning of 2023-24. Please identify the reason for this slippage below by ticking (√) the
appropriate box:
Incorrect profiling at start of year  Material delays ✓
Changes to project plan  Other (explain below) 
Detailed explanation for the above (if there is more than one reason ticked above please give
approximate values applicable to each cause): 
Delays in vehicle build and difficulties sourcing vehicles to replace ageing Fleet. 
The slippage was due to the late delivery of 7 x 7.5 tonne roads vehicles, the delay has
been an additional 9 months. 
While it is appreciated figures will not be 100% accurate, are you content that the “Anticipated
Spend at end of 2023-24” noted in the table at the top of the page are a good estimate of what
will be spent in each of the years 2024-25, 2025-26 and 2026-27?
Yes. 
If not, have you advised Financial Services of the changes to these forecasts as this is what is
currently populated in the Capital Monitoring spreadsheets completed by Project Managers?

Page 23

CAPITAL PROJECT SLIPPAGE OVER £0.500M – YEAR END EXPLANATION REPORT FOR SMT 
Project Name: 03 TIF – Halfway House R’bout Project Manager: A Jackson-Stark 
Year 2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Anticipated Spend at start of 2023-24 0.574 0.000 0.000 0.000
Anticipated spend at end of 2023-24 0.000 0.574 0.000 0.000
(Slippage)/Acceleration (0.574) 0.574 0.000 0.000 
In 2023-24 there has been £0.574m of slippage compared to the projections for this year at the
beginning of 2023-24. Please identify the reason for this slippage below by ticking (√) the
appropriate box:
Incorrect profiling at start of year  Material delays 
Changes to project plan  Other (explain below) 
Detailed explanation for the above (if there is more than one reason ticked above please give
approximate values applicable to each cause): 
The project has been delayed for a number of reasons. 
 Our partners LINK Housing Association have been unable to complete the technical
studies required for the submission of planning applications for the wider development
programme within which this project falls.
 The Council is in the process of renegotiating the existing financial elements of the
contract with the Scottish Government – specifically the length of time the project
extends to which affects potential affordability of the project
 Actions are being taken to de-risk the project with revised financial forecasts being
produced and requests made to the Scottish Government to revise the current
agreement. 
While it is appreciated figures will not be 100% accurate, are you content that the “Anticipated
Spend at end of 2023-24” noted in the table at the top of the page are a good estimate of what
will be spent in each of the years 2024-25, 2025-26 and 2026-27?
Yes
If not, have you advised Financial Services of the changes to these forecasts as this is what is
currently populated in the Capital Monitoring spreadsheets completed by Project Managers?

Page 24

CAPITAL PROJECT SLIPPAGE OVER £0.500M – YEAR END EXPLANATION REPORT FOR SMT 
Project Name: Harbour Investment Programme Project Manager: S Reid 
Year 2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Anticipated Spend at start of 2023-24 9.200 22.000 50.000 2.695
Anticipated spend at end of 2023-24 1.898 25.412 39.000 17.585
(Slippage)/Acceleration (7.302) 3.412 (11.000) 14.890 
In 2023-24 there has been £7.302m of slippage compared to the projections for this year at the
beginning of 2023-24. Please identify the reason for this slippage below by ticking (√) the
appropriate box:
Incorrect profiling at start of year  Material delays 
Changes to project plan  Other (explain below) x     
Detailed explanation for the above (if there is more than one reason ticked above please give
approximate values applicable to each cause): 
Craignure Ground Investigation should have been completed by the end of Summer 2023
though this was held back due to Nature Scotland and Marine Scotland delaying the issue
of licences has delayed this project progressing. 
Iona Breakwater & Fionnphort projects have also seen delays due to the licencing delays
by Nature Scotland and Marine Scotland 
A large cost in progressing the Breakwater project at Iona is the purchase of the stone
used to complete the breakwater. This purchase is too risky to go ahead until licences are
issued due to the value of the materials being purchased. 
While it is appreciated figures will not be 100% accurate, are you content that the “Anticipated
Spend at end of 2023-24” noted in the table at the top of the page are a good estimate of what
will be spent in each of the years 2024-25, 2025-26 and 2026-27?
Yes 
If not, have you advised Financial Services of the changes to these forecasts as this is what is
currently populated in the Capital Monitoring spreadsheets completed by Project Managers?

Page 25

CAPITAL PROJECT SLIPPAGE OVER £0.500M – YEAR END EXPLANATION REPORT FOR SMT 
Project Name: Kilmory Business Park Project Manager: J Gordon 
Year 2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Anticipated Spend at start of 2023-24 1.082 0.000 0.000 0.000
Anticipated spend at end of 2023-24 0.013 1.035 0.034 0.000
(Slippage)/Acceleration (1.069) 1.035 0.034 0.000 
In 2023-24 there has been £1.069m of slippage compared to the projections for this year at the
beginning of 2023-24. Please identify the reason for this slippage below by ticking (√) the
appropriate box:
Incorrect profiling at start of year  Material delays 
Changes to project plan  Other (explain below) X     
Detailed explanation for the above (if there is more than one reason ticked above please give
approximate values applicable to each cause): 
Project expenditure is predicated on the conclusion of the suite of Legal Agreements as between
the Council and M&K MacLeod Ltd for the Phase 2AA Works. These are a complex suite of
documents developed to protect the public and private interests of not only jointly delivering the
Phase 2AA works, but also subsequently enabling each of the parties to develop out their own
land holdings without a requirement to negotiate/agree fundamental principles for each
individual development plot. We are working to close out the Deed of Conditions, which feeds
into the overarching Development Agreement, and which takes account of negotiations with HIE
in respect of access to their land for Phase 2AA construction activities associated with statutory
utility provision, and the subsequent operation and maintenance thereof until such time as these
are formally adopted. It also requires the inclusion of any funding conditions which HIE place upon
the project in support of their funding contribution, the Stage 2 Application for which is nearing
completion. 
Enabling work has commenced on site, so physical works are in progress, however MKML are not
able to invoice to recover these costs against the public sector funding until the legal agreements
are all concluded, expected FQ2 FY24/25. 
While it is appreciated figures will not be 100% accurate, are you content that the “Anticipated
Spend at end of 2023-24” noted in the table at the top of the page are a good estimate of what
will be spent in each of the years 2024-25, 2025-26 and 2026-27?
Yes – on the presumption that legal agreements are concluded in FQ2, then MKML will drawdown
approved funding for works already undertaken as soon as possible thereafter. 
If not, have you advised Financial Services of the changes to these forecasts as this is what is
currently populated in the Capital Monitoring spreadsheets completed by Project Managers?

Page 26

CAPITAL PROJECT SLIPPAGE OVER £0.500M – YEAR END EXPLANATION REPORT FOR SMT 
Project Name: Street Lighting LED Replacement Project Manager: K McIntosh 
Year 2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Anticipated Spend at start of 2023-24 0.674 0.000 0.00 0.00
Anticipated spend at end of 2023-24 0.053 0.621 0.00 0.00
(Slippage)/Acceleration (0.621) 0.621 0.000 0.000 
In 2023-24 there has been £0.621m of slippage compared to the projections for this year at the
beginning of 2023-24. Please identify the reason for this slippage below by ticking (√) the
appropriate box:
Incorrect profiling at start of year  Material delays √
Changes to project plan  Other (explain below) 
Detailed explanation for the above (if there is more than one reason ticked above please give
approximate values applicable to each cause): 
The Column replacement element of the project won’t take place until 2024-25, where 237
columns are to be replaced. Column replacement is planned to be delivered using both in
house and external contractors. 
This has been delayed due to periods of absence within the Street Lighting team. Mixed
method of delivery requires significant planning and coordination where the resources
were not available in 2023-24 due to the absences. 
While it is appreciated figures will not be 100% accurate, are you content that the “Anticipated
Spend at end of 2023-24” noted in the table at the top of the page are a good estimate of what
will be spent in each of the years 2024-25, 2025-26 and 2026-27?
Yes 
If not, have you advised Financial Services of the changes to these forecasts as this is what is
currently populated in the Capital Monitoring spreadsheets completed by Project Managers?

Page 27

CAPITAL PROJECT SLIPPAGE OVER £0.500M – YEAR END EXPLANATION REPORT FOR SMT 
Project Name: Primary Schools Project Manager Rhona Mitchell 
Year 2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Anticipated Spend at start of 2023-24 3.955 1.835 0.000 0.000
Anticipated spend at end of 2023-24 3.195 2.595 1.280 0.000
(Slippage)/Acceleration (0.760) 0.760 0.000 0.000 
In 2023-24 there has been £0.760m of slippage compared to the projections for this year at the
beginning of 2023-24. Please identify the reason for this slippage below by ticking (√) the
appropriate box:
Incorrect profiling at start of year  Material delays Y
Changes to project plan  Other (explain below) 
Detailed explanation for the above (if there is more than one reason ticked above please give
approximate values applicable to each cause): 
Continued issues with availability of materials and suitably skilled labour have resulted in delays to
various sites (John Logie Baird, Garelochhead, Cardross, Parklands and Islay) with works unable to
commence as planned.  In order to mitigate any potential prolongation costs projects have been
reprogrammed to reduce the commercial impact on the programme as a whole, minimise school
disruption and at all times adhere to our rigorous Health & Safety responsibilities and legislative
duties. Advanced preparation works have already been carried out wherever possible to ensure a
smooth delivery through Summer 24 and issues with internal reporting temporarily resolved to
aid accurate periodic reporting. 
While it is appreciated figures will not be 100% accurate, are you content that the “Anticipated
Spend at end of 2023-24” noted in the table at the top of the page are a good estimate of what
will be spent in each of the years 2024-25, 2025-26 and 2026-27?
Yes - Successful completion programmed for Summer 24.   Realistic Capital reporting to take
cognisance of real difficulties in procuring Contractors in remote rural locations.
If not, have you advised Financial Services of the changes to these forecasts as this is what is
currently populated in the Capital Monitoring spreadsheets completed by Project Managers?

Page 28

CAPITAL PROJECT SLIPPAGE OVER £0.500M – YEAR END EXPLANATION REPORT FOR SMT 
Project Name: Lighting Project Manager: T Murphy 
Year 2023-24
£m
2024-25
£m
2025-26
£m
2026-27
£m
Anticipated Spend at start of 2023-24 0.890 0.150 0.00 0.00
Anticipated spend at end of 2023-24 0.246 0.794 0.00 0.00
(Slippage)/Acceleration (0.644) 0.644 0.000 0.000 
In 2023-24 there has been £0.644m of slippage compared to the projections for this year at the
beginning of 2023-24. Please identify the reason for this slippage below by ticking (√) the
appropriate box:
Incorrect profiling at start of year  Material delays 
Changes to project plan  Other (explain below) 
Detailed explanation for the above (if there is more than one reason ticked above please give
approximate values applicable to each cause): 
The planned lighting schemes were always forecast for completion in 2024-25 however
the finalising of designs for these schemes was delayed later into 2023-24 than
anticipated when setting the budget forecast. This delayed the tendering of these projects
and as such the above slippage has occurred in 2023-24. Schemes are still forecast for
completion in 2024-25. 
While it is appreciated figures will not be 100% accurate, are you content that the “Anticipated
Spend at end of 2023-24” noted in the table at the top of the page are a good estimate of what
will be spent in each of the years 2024-25, 2025-26 and 2026-27?
Yes 
If not, have you advised Financial Services of the changes to these forecasts as this is what is
currently populated in the Capital Monitoring spreadsheets completed by Project Managers?

Page 29

Strategic Change Projects - Cumulative Spend, Start/Finish Dates and Project Risks APPENDIX 5
Strategic Change Projects
Prior Years
Spend
£'000
Current Year
Forecast
£'000
Total Project
Forecast
£'000
Total Project
Budget
£'000
Project Start
Date
Estimated
Completion
Date
Project
Risks
Identified Explanation
Campbeltown Flood Scheme 4,992 8,756 15,925 15,925 01/08/2016 31/03/2025 Amber Contractor's updated programming of work moved Public Utility works from 22/23 to 23/24
CHORD Oban 7,279 47 7,905 7,905 27/10/2016 31/03/2022 Amber Issues with contract close out impacting on timescales.
CHORD Rothesay 15,231 6,170 24,012 24,012 tbc tbc Amber Project recommenced.
Harbour Investment Programme 7,397 1,898 91,335 91,335 01/04/2017 31/03/2028 Amber Budget slipped into future years.
Dunoon Primary 10,635 2 10,869 10,869 18/12/2014 30/04/2020 Amber Physically complete - negotiations with contractor delaying payment of final sums outstanding.
Replacement of Oban High 2,844 0 3,250 3,250 24/04/2014 31/01/2019 Amber Physically complete - negotiations with contractor delaying payment of final sums outstanding.
Clean Energy - NDEEF1 964 145 1,331 1,331 tbc 31/03/2025 Amber
Clean Energy - NDEEF2 0 0 1,140 1,140 tbc 31/03/2027 Amber
Street Lighting LED Replacement 3,226 53 3,900 3,900 01/08/2016 31/12/2025 Green Tender for final package of works still to be awarded.
Helensburgh Waterfront Development 23,415 696 24,392 24,392 01/04/2017 31/03/2025 Green Physically complete, retentions outstanding
TIF - Halfway House Roundabout 66 0 640 640 tbc tbc Green Scope of project still to be determined - budget to be reprofiled.
Kirn Primary School 10,085 0 10,119 10,119 24/04/2014 31/10/2017 Green Physically complete - negotiations with contractor delaying payment of final sums outstanding.
Helensburgh Office Rationalisation 11,538 0 11,838 11,838 25/04/2013 31/12/2022 Green Physically complete - project subject to legal dispute.
CHORD Dunoon 12,495 4 12,522 12,522 03/02/2012 09/03/2018 Green Main contract complete and retentions paid
Kilmory Business Park Phase 2AA 47 13 1,129 1,129 01/02/2022 01/09/2025 Green Development Agreement still to be concluded.
Carbon Management - Non Education 29 0 50 50 01/04/2015 31/12/2025 Green Projects being determined.
Dunoon Pier OBC 2,844 0 2,844 2,844 03/02/2012 26/02/2016 Green Project complete.
Campbeltown Office Rationalisation 595 0 596 596 01/02/2015 31/03/2019 Green Complete.
TIF - Oban Airport Business Park 489 16 590 590 22/01/2015 31/12/2025 Green
Campbeltown Schools Redevelopment 2,092 0 2,130 2,130 16/02/2012 30/11/2018 Green Physically complete - negotiations with contractor delaying payment of financial sums outstanding.
CHORD - Helensburgh 6,529 3 6,557 6,557 29/09/2011 30/04/2015 Green Main contract complete. Art project proposed for 23-24.
TIF - North Pier Extension 214 0 214 214 06/12/2017 06/12/2021 Green Complete.
TIF - Lorn/Kirk Road 2,169 0 2,170 2,170 22/01/2015 31/03/2021 Green Complete.
Carbon Management Fuel Conversions 107 0 107 107 01/02/2014 31/03/2019 Green Complete.
Kilmory Biomass  Carbon Management 956 0 956 956 20/09/2012 31/03/2019 Green Complete.
Net Zero 0 0 366 366 tbc tbc Green
Strategic Change Total 129,739 17,803 240,388 240,388
Project Risk Classifications:
Green - Risks can be managed and are viewed as stable or reducing.
Amber - Risks are increasing but are still manageable.
Red - Risks are increasing or have increased to such an extent they may affect delivery of the project.
Capital Expenditure Dates Risks

Page 30

ARGYLL AND BUTE COUNCIL - CAPITAL PLAN MONITORING REPORT - OVERALL COUNCIL Appendix 6
FINANCIAL SUMMARY - NET EXPENDITURE
Budget Forecast
(Over)/Under
Variance Budget Forecast
(Over)/Under
Variance
£000s £000s £000s £000s £000s £000s
EXPENDITURE
Asset Sustainability Projects
Executive Director Douglas Hendry 9,695 8,312 1,383 30,419 30,419 0
Executive Director Kirsty Flanagan 11,658 10,948 710 43,341 43,341 0
Asset Sustainability Total 21,353 19,260 2,093 73,760 73,760 0
Service Development Projects
Executive Director Douglas Hendry 526 333 193 16,438 16,438 0
Executive Director Kirsty Flanagan 4,736 3,267 1,469 39,800 39,800 0
Service Development Total 5,262 3,600 1,662 56,238 56,238 0
Strategic Change Projects
Campbeltown Schools Redevelopment 38 0 38 2,130 2,130 0
Dunoon Primary 234 2 232 10,869 10,869 0
Replacement of Oban High 406 0 406 3,250 3,250 0
Kirn Primary School 34 0 34 10,119 10,119 0
Carbon Management - Non Education 21 0 21 50 50 0
Carbon Management Business Cases 0 0 0 201 201 0
NPDO Schools Solar PV Panel Installations 0 0 0 761 761 0
Non NPDO Schools Solar PV Panel Installations 0 0 0 400 400 0
Carbon Management Fuel Conversions 0 0 0 107 107 0
Carbon Management Capital Property Works 2016/17 0 0 0 19 19 0
Carbon Management - Group Heating Conversion Project 0 0 0 1,938 1,938 0
Kilmory Biomass  Carbon Management 0 0 0 956 956 0
Oil to Gas Heating Conversions 0 0 0 182 182 0
Campbeltown Office Rationalisation 1 0 1 596 596 0
Helensburgh Office Rationalisation 0 0 0 11,838 11,838 0
Clean Energy - NDEEF1 224 145 79 1,331 1,331 0
Clean Energy - NDEEF2 50 0 50 1,140 1,140 0
Net Zero 0 0 0 366 366 0
Campbeltown Flood Scheme 8,625 8,756 (131) 15,925 15,925 0
Street Lighting LED Replacement 61 53 8 3,900 3,900 0
Harbour Investment Programme 1,490 1,898 (408) 91,292 91,292 0
Harbour Investment Programme Non - PB 43 0 43 43 43 0
TIF - Lorn/Kirk Road 1 0 1 2,170 2,170 0
TIF - North Pier Extension 0 0 0 214 214 0
TIF - Oban Airport Business Park 56 16 40 590 590 0
TIF - Halfway House Roundabout 56 0 56 640 640 0
CHORD - Helensburgh 0 3 (3) 6,557 6,557 0
CHORD Dunoon 27 4 23 12,522 12,522 0
CHORD Oban 626 47 579 7,905 7,905 0
CHORD Rothesay 6,744 6,170 574 24,012 24,012 0
Helensburgh Waterfront Development 647 696 (49) 24,392 24,392 0
HWD - FFE (Funded by LA) 34 0 34 350 350 0
Kilmory Business Park Phase 2AA 560 13 547 1,129 1,129 0
Dunoon Pier OBC 0 0 0 2,844 2,844 0
Strategic Change Total 19,978 17,803 2,175 240,738 240,738 0
Total Expenditure 46,593 40,663 5,930 370,736 370,736 0
10,708
INCOME
Asset Sustainability
Executive Director Douglas Hendry (229) (100) (129) (2,370) (2,370) 0
Executive Director Kirsty Flanagan (1,444) (817) (627) (1,635) (1,635) 0
Asset Sustainability Total (1,673) (917) (756) (4,005) (4,005) 0
Service Development Projects
Executive Director Douglas Hendry 0 0 0 (7,771) (7,771) 0
Executive Director Kirsty Flanagan (4,940) (380) (4,560) (24,718) (24,718) 0
Service Development Total (4,940) (380) (4,560) (32,489) (32,489) 0
Strategic Change Projects
Helensburgh Office Rationalisation 0 0 0 (349) (349) 0
Dunoon Primary 0 0 0 (137) (137) 0
Campbeltown Flood 0 0 0 (270) (270) 0
Harbour PB (1,490) (1,490) 0 (91,292) (91,292) 0
01 TIF - Lorn/Kirk Road (16) (16) 0 (2,057) (2,057) 0
H'burgh CHORD Public Realm Imprv 0 0 0 (570) (570) 0
Helensburgh Waterfront Development (2,320) 0 (2,320) (7,979) (7,979) 0
HWD - FFE (Funded by LA) 0 0 0 (350) (350) 0
Rothesay CHORD (2,009) 0 (2,009) (8,854) (8,854) 0
Kilmory Business Park Phase 2AA (829) 0 (829) (829) (829) 0
Kilmory Business Park Phase 2AA - HIE (150) 0 (150) (150) (150) 0
CHORD - Dunoon Waterfront 0 0 0 (10) (10) 0
CHORD - Oban 0 0 0 (1,624) (1,624) 0
Strategic Change Total (6,814) (1,506) (5,308) (114,471) (114,471) 0
Total Income (13,427) (2,803) (10,624) (150,965) (150,965) 0
Net Total 33,166 37,860 (4,694) 219,771 219,771 0
Full Year This Financial Year Total Project Costs
31 March 2024

Page 31

MONITORING REPORT
Budget Forecast Variance Budget Forecast Variance
£000s £000s £000s £000s £000s £000s
EXPENDITURE
Asset Sustainability
Education 6,150 5,414 736 17,528 17,528 0
Live Argyll 1,253 1,133 120 2,874 2,874 0
Health and Social Care Partnership 903 748 155 5,525 5,525 0
Shared Offices 1,389 1,017 372 4,492 4,492 0
Asset Sustainability Total 9,695 8,312 1,383 30,419 30,419 0
Service Development Projects
Ardrishaig Primary Pre 5 Unit 0 0 0 2 2 0
Bowmore Primary School - Pre 5 Unit 0 0 0 149 149 0
Clyde Cottage - 600 hour provision 0 0 0 556 556 0
Craignish Primary School - Pre 5 Extension 0 0 0 400 400 0
Iona Primary School - Pre 5 Unit 0 0 0 490 490 0
Islay High and Rosneath Primary School Pitches 0 0 0 719 719 0
Lochgoilhead Primary School - Pre 5 Unit 0 0 0 391 391 0
Park Primary Extension/Pre Fives Unit 0 0 0 341 341 0
Sandbank Gaelic Pre Five Unit 0 0 0 491 491 0
Bunessan Primary School - Gaelic Medium Improvements 0 0 0 120 120 0
Early Learning and Childcare 0 0 0 850 850 0
Early Learning and Childcare - 1140 Hours 320 332 (12) 7,774 7,774 0
CO2 Monitoring - Covid Mitigation in Schools 113 0 113 192 192 0
Early Learning and Childcare - 1140 Hours - CFCR 0 0 0 1,379 1,379 0
Bowmore Primary School - Gaelic Medium Grant 38 0 38 38 38 0
Riverside Leisure Centre Refurbishment 1 1 0 1,246 1,246 0
Dunclutha Childrens Home 54 0 54 1,300 1,300 0
Service Development Total 526 333 193 16,438 16,438 0
Strategic Change Projects
Campbeltown Schools Redevelopment 38 0 38 2,130 2,130 0
Dunoon Primary 234 2 232 10,869 10,869 0
Replacement of Oban High 406 0 406 3,250 3,250 0
Kirn Primary School 34 0 34 10,119 10,119 0
Carbon Management - Non Education 21 0 21 50 50 0
Carbon Management Business Cases 0 0 0 201 201 0
NPDO Schools Solar PV Panel Installations 0 0 0 761 761 0
Non NPDO Schools Solar PV Panel Installations 0 0 0 400 400 0
Carbon Management Fuel Conversions 0 0 0 107 107 0
Carbon Management Capital Property Works 2016/17 0 0 0 19 19 0
Carbon Management - Group Heating Conversion Project 0 0 0 1,938 1,938 0
Kilmory Biomass  Carbon Management 0 0 0 956 956 0
Oil to Gas Heating Conversions 0 0 0 182 182 0
Campbeltown Office Rationalisation 1 0 1 596 596 0
Helensburgh Office Rationalisation 0 0 0 11,838 11,838 0
Clean Energy - NDEEF1 224 145 79 1,331 1,331 0
Clean Energy - NDEEF2 50 0 50 1,140 1,140 0
Net Zero 0 0 0 366 366 0
CHORD Oban 626 47 579 7,905 7,905 0
CHORD Rothesay 6,744 6,170 574 24,012 24,012 0
CHORD - Helensburgh 0 3 (3) 6,557 6,557 0
CHORD Dunoon 27 4 23 12,522 12,522 0
Helensburgh Waterfront Deveopment 647 696 (49) 24,392 24,392 0
HWD - FFE (Funded by LA) 34 0 34 350 350 0
Kilmory Business Park Phase 2AA 560 13 547 1,129 1,129 0
Dunoon Pier OBC 0 0 0 2,844 2,844 0
Strategic Change Total 9,646 7,080 2,566 125,964 125,964 0
Total Expenditure 19,867 15,725 4,142 172,821 172,821 0
INCOME
Asset Sustainability
Education (125) 0 (125) (125) (125) 0
Live Argyll (100) (100) 0 (100) (100) 0
Health and Social Care Partnership 0 0 0 (2,141) (2,141) 0
Shared Offices (4) 0 (4) (4) (4) 0
Asset Sustainability Total (229) (100) (129) (2,370) (2,370) 0
Service Development Projects
Sandbank Gaelic Pre Five Unit 0 0 0 (485) (485) 0
Bunessan Primary School - Gaelic Medium Improvements 0 0 0 (30) (30) 0
Early Learning and Childcare 0 0 0 (918) (918) 0
Early Years 1140 Hours 0 0 0 (6,300) (6,300) 0
Bowmore Primary School - Gaelic Medium Grant 0 0 0 (38) (38) 0
Service Development Total 0 0 0 (7,771) (7,771) 0
Strategic Change
Helensburgh Office Rationalisation 0 0 0 (349) (349) 0
Dunoon Primary School 0 0 0 (137) (137) 0
H'burgh CHORD Public Realm Imprv 0 0 0 (570) (570) 0
Helensburgh Waterfront Development (2,320) 0 (2,320) (7,979) (7,979) 0
HWD - FFE (Funded by LA) 0 0 0 (350) (350) 0
Rothesay CHORD (2,009) 0 (2,009) (8,854) (8,854) 0
CHORD - Dunoon Waterfront 0 0 0 (10) (10) 0
CHORD - Oban 0 0 0 (1,624) (1,624) 0
Kilmory Business Park Phase 2AA (829) 0 (829) (829) (829) 0
Kilmory Business Park Phase 2AA - HIE (150) 0 (150) (150) (150) 0
Strategic Change Total (5,308) 0 (5,308) (20,852) (20,852) 0
Total Income (5,537) (100) (5,437) (30,993) (30,993) 0
Net Departmental Total 14,330 15,625 (1,295) 141,828 141,828 0
31 March 2024
Total Project CostsFull Year This Financial Year
Appendix 6
FINANCIAL SUMMARY NET EXPENDITURE - EXECUTIVE DIRECTOR DOUGLAS HENDRY

Page 32

MONITORING REPORT
Budget
Year End
Forecast
(Over)/Under
Variance Budget Forecast
(Over)/Under
Variance
£000s £000s £000s £000s £000s £000s
EXPENDITURE
Asset Sustainability Projects
Roads & Infrastructure Services 10,477 9,814 663 39,029 39,029 0
Customer Support Services 1,181 1,134 47 4,312 4,312 0
Asset Sustainability Total 11,658 10,948 710 43,341 43,341 0
Service Development Projects
Preliminary design for  Regional Transport projects 16 0 16 221 221 0
Campbeltown Old Quay 0 0 0 1,381 1,381 0
Fleet Management - Prudential Borrowing 602 0 602 4,861 4,861 0
Fleet Management 1,664 1,469 195 4,697 4,697 0
Public Transport Operation Vehicles 0 0 0 233 233 0
Oban Bus Congestion - Bus Partnership Fund 50 50 0 50 50 0
Lismore Ferry 15 0 15 672 672 0
HITRANS Ferry Fund 0 0 0 0 0 0
Oban Depot Development Project 9 44 (35) 2,189 2,189 0
Lochgilphead Depot Rationalisation 140 125 15 169 169 0
Jackson's Quarry Refurbishment 0 0 0 285 285 0
Witchburn Road Demolition 0 0 0 158 158 0
Safe Streets, Walking and Cycling (CWSS) 370 130 240 3,762 3,762 0
SPT - bus infrastructure 0 0 0 1,430 1,430 0
Cycleways - H&L (FSPT) 300 93 207 3,402 3,402 0
Helensburgh Public Realm - Arts Strategy Fund 0 0 0 53 53 0
Town Centre Funds 546 384 162 4,329 4,329 0
Rural Growth Deal 191 189 2 241 241 0
Dunoon Cycle Bothy 221 224 (3) 563 563 0
Dunoon STEM Hub 56 36 20 2,558 2,558 0
Ardrishaig North Active Travel 83 76 7 880 880 0
Nature Restoration Fund 0 0 0 835 835 0
Gibraltar Street Public Realm Improvements 125 125 0 250 250 0
Hermitage Park 26 0 26 3,388 3,388 0
Applications Projects 322 322 0 3,193 3,193 0
Service Development Total 4,736 3,267 1,469 39,800 39,800 0
Strategic Change Projects
Campbeltown Flood Scheme 8,625 8,756 (131) 15,925 15,925 0
Street Lighting LED Replacement 61 53 8 3,900 3,900 0
Harbour Investment Programme 1,490 1,898 (408) 91,292 91,292 0
Harbour Investment Programme - Non PB 43 0 43 43 43 0
TIF - Lorn/Kirk Road 1 0 1 2,170 2,170 0
TIF - North Pier Extension 0 0 0 214 214 0
TIF - Oban Airport Business Park 56 16 40 590 590 0
TIF - Halfway House Roundabout 56 0 56 640 640 0
Strategic Change Total 10,332 10,723 (391) 114,774 114,774 0
Total Expenditure 26,726 24,938 1,788 197,915 197,915 0
INCOME
Asset Sustainability
Roads & Infrastructure Services (1,444) (817) (627) (1,635) (1,635) 0
Asset Sustainability Total (1,444) (817) (627) (1,635) (1,635) 0
Service Development Projects
Applications Projects (46) (46) 0 (437) (437) 0
Safe Streets, Walking and Cycling (376) 0 (376) (2,988) (2,988) 0
SPfT (25) 0 (25) (1,268) (1,268) 0
Cycleways - H&L (FSPT) (590) (90) (500) (3,502) (3,502) 0
Town Centre Funds (512) 0 (512) (2,124) (2,124) 0
Rural Growth Deal (211) (81) (130) (241) (241) 0
Dunoon STEM Hub (2,050) 0 (2,050) (2,558) (2,558) 0
Ardrishaig North Active Travel 0 0 0 (50) (50) 0
Dunoon Cycle Bothy (394) (96) (298) (563) (563) 0
Gibraltar Street Public Realm Improvements 0 0 0 (250) (250) 0
Hermitage Park 0 0 0 (3,319) (3,319) 0
Fleet Management - PB (602) 0 (602) (4,861) (4,861) 0
Fleet Management (49) (49) 0 (49) (49) 0
Millpark Depot Demolition Insurance 0 0 0 (53) (53) 0
Oban Depot - Mill Park Insurance Claim 0 0 0 (1,681) (1,681) 0
Oban Depot - Revenue Contribution (67) 0 (67) (67) (67) 0
Lismore Ferry 0 0 0 (500) (500) 0
Witchburn Road Demolition 0 0 0 (157) (157) 0
Oban Bus Congestion - Bus Partnership Fund (18) (18) 0 (50) (50) 0
Service Development Total (4,940) (380) (4,560) (24,718) (24,718) 0
Strategic Change Projects
Campbeltown Flood 0 0 0 (270) (270) 0
Harbour PB (1,490) (1,490) 0 (91,292) (91,292) 0
01 TIF - Lorn/Kirk Road (16) (16) 0 (2,057) (2,057) 0
Strategic Change Total (1,506) (1,506) 0 (93,619) (93,619) 0
Total Income (7,890) (2,703) (5,187) (119,972) (119,972) 0
Net Departmental Total 18,836 22,235 (3,399) 77,943 77,943 0
31 March 2024
Full Year This Financial Year Total Project Costs
FINANCIAL SUMMARY NET EXPENDITURE - EXECUTIVE DIRECTOR KIRSTY FLANAGAN
Appendix 6

Page 33

CAPITAL PLAN 2023-24 APPENDIX 7
Overall Summary
Service
Previous Years
£000's
2023-24                                           
£000s
2024-25                 
£000s
2025-26                
£000s
2026-27                 
£000s
2027-28                
£000s Total
Education 39,077 5,719 7,915 3,060 1,988 0 57,759
Shared Offices 17,661 1,162 2,600 2,522 382 0 24,327
ICT 2,529 1,456 1,611 1,221 688 0 7,505
RIS 26,197 22,209 50,782 43,928 21,989 0 165,105
DEG 18,331 1,273 5,676 25 0 0 25,305
HSCP 1,246 777 3,776 1,055 0 0 6,854
Live Argyll 1,274 1,134 1,125 169 468 0 4,170
CHORD 68,156 6,933 4,509 113 0 0 79,711
Overall Total 174,471 40,663 77,994 52,093 25,515 0 370,736

Page 34

CAPITAL PLAN 2023-24 APPENDIX 7
Education
Category Service Project
Previous
Years
£000's
2023-24                     
£000s
2024-25                 
£000s 2025-26                 £000s
2026-27            
£000s
2027-28            
£000s
Total
£000s
Block Allocation - Education 0 0 1,109 520 1,988 0 3,617
Digital Inclusion 20-21 0 0 9 0 0 0 9
Free School Meals 0 213 0 434 0 0 647
Primary Schools 0 3,195 2,595 1,280 0 0 7,070
Primary Schools - CFCR 0 1,257 0 0 0 0 1,257
School Houses - Housing Quality Standard 0 1 0 0 0 0 1
Secondary Schools 0 709 963 226 0 0 1,898
Asset Sustainability Total 0 5,385 7,066 3,060 1,988 0 17,499
Service Development Education Ardrishaig Primar School - Pre Five Extension 2 0 0 0 0 0 2
Bowmore Primary School - Gaelic Medium Grant 0 0 38 0 0 0 38
Bowmore Primary School - Pre Five Unit 149 0 0 0 0 0 149
Bunessan Primary School - Gaelic Medium Improvements 120 0 0 0 0 0 120
Clyde Cottage - 600 hours provision 556 0 0 0 0 0 556
CO2 Monitoring - Covid Mitigation in Schools 79 0 113 0 0 0 192
Craignish Primary School - Pre Five Extension (600 hours funding) 400 0 0 0 0 0 400
Early Learning and Childcare 850 0 0 0 0 0 850
Early Learning and Childcare - 1140 Hours 7,454 332 -12 0 0 0 7,774
Early Learning and Childcare - 1140 Hours - CFCR 1,379 0 0 0 0 0 1,379
Iona Primary School - Pre Five Unit (600 hours funding) 490 0 0 0 0 0 490
Islay High & Rosneath PS Pitches 719 0 0 0 0 0 719
Lochgoilhead Primary School - Pre Five Unit (600 hours funding) 391 0 0 0 0 0 391
Park Primary Extension and Pre Fives Unit 341 0 0 0 0 0 341
Sandbank Gaelic Pre Five Unit 491 0 0 0 0 0 491
Service Development Total 13,421 332 139 0 0 0 13,892
Strategic Change Education Campbeltown Schools Redevelopment 2,092 0 38 0 0 0 2,130
Dunoon Primary School 10,635 2 232 0 0 0 10,869
Kirn Primary School 10,085 0 34 0 0 0 10,119
Replacement of Oban High School 2,844 0 406 0 0 0 3,250
Strategic Change Total 25,656 2 710 0 0 0 26,368
Overall Total 39,077 5,719 7,915 3,060 1,988 0 57,759

Page 35

CAPITAL PLAN 2023-24 APPENDIX 7
Shared Office
Category Service Project
Previous
Years
£000's
2023-24     
£000s
2024-25      
£000s
2025-26      
£000s
2026-27        
£000s
2027-28    
£000s
Total
£000s
Asset Sustainability Shared Offices 52 Sinclair Street Flats - CFCR 0 53 0 0 0 0 53
5-7 East Clyde Street - Coastal Communities Fund 0 1 0 0 0 0 1
Block Allocation 0 0 534 427 382 0 1,343
Burnett Building 0 5 107 0 0 0 112
Helensburgh and Lomond Civic Centre - Emergency Heating Pipework 0 217 0 0 0 0 217
Kilmory Castle 0 0 0 1,545 0 0 1,545
Legionella Control Works 0 120 0 0 0 0 120
Our Modern Workspace 0 621 480 0 0 0 1,101
Asset Sustainability Total 0 1,017 1,121 1,972 382 0 4,492
Strategic Change Shared Offices Campbeltown Office Rationalisation 595 0 1 0 0 0 596
Carbon Management - Group Heating Conversion Project (Prudential Borrowing)1,938 0 0 0 0 0 1,938
Carbon Management Business Cases (FPB) 201 0 0 0 0 0 201
Carbon Management Capital Property Works 16/17 19 0 0 0 0 0 19
Carbon Management Fuel Conversions (FPB) 107 0 0 0 0 0 107
Clean Energy - NDEEF1 964 145 222 0 0 0 1,331
Clean Energy - NDEEF2 0 0 590 550 0 0 1,140
Helensburgh Office Rationalisation  (FPB,REC) 11,538 0 300 0 0 0 11,838
Kilmory Biomass Project OBC (FPB,REV) 956 0 0 0 0 0 956
Net Zero 0 0 366 0 0 0 366
Non-NPDO Schools PV Panel Installations 400 0 0 0 0 0 400
NPDO Schools Solar PV Panel Installations 761 0 0 0 0 0 761
Oil to Gas Heating Conversions (FPB) 182 0 0 0 0 0 182
Strategic Change Total 17,661 145 1,479 550 0 0 19,835
Overall Total 17,661 1,162 2,600 2,522 382 0 24,327

Page 36

CAPITAL PLAN 2023-24 APPENDIX 8 APPENDIX 7
Major Projects
Category Service Project
Previous
Years
£000's
2023-24    
£000s
2024-25    
£000s
2025-26     
£000s
2026-27          
£000s
2027-28     
£000s
Total
£000s
Strategic Change CHORD CHORD - Dunoon 12,495 4 23 0 0 0 12,522
CHORD - Helensburgh -Public Realm Imprv 6,529 3 25 0 0 0 6,557
CHORD - Oban 7,279 47 500 79 0 0 7,905
CHORD - Rothesay 15,231 6,170 2,611 0 0 0 24,012
Helensburgh Waterfront Development 23,415 696 281 0 0 0 24,392
HWD - FFE 316 0 34 0 0 0 350
Kilmory Business Park Phase 2AA 47 13 1,035 34 0 0 1,129
OBC for Dunoon Pier 2,844 0 0 0 0 0 2,844
Strategic Change Total 68,156 6,933 4,509 113 0 0 79,711
Overall Total 68,156 6,933 4,509 113 0 0 79,711

Page 37

CAPITAL PLAN 2023-24 APPENDIX 7
ICT
Category Service Project
Previous
Years
£000's
2023-24      
£000s
2024-25      
£000s
2025-26      
£000s
2026-27     
£000s
2027-28       
£000s
Total
£000s
Asset Sustainability ICT Block Allocation - ICT 0 0 132 0 688 0 820
PC Replacement 0 605 561 669 0 0 1,835
Server Sustainability 0 289 488 400 0 0 1,177
Telecomms Network 0 240 88 152 0 0 480
Asset Sustainability Total 0 1,134 1,269 1,221 688 0 4,312
Service Development ICT Applications Projects 2,529 322 342 0 0 0 3,193
Service Development Total 2,529 322 342 0 0 0 3,193
Overall Total 2,529 1,456 1,611 1,221 688 0 7,505

Page 38

CAPITAL PLAN 2023-24 APPENDIX 7
Roads and Infrastructure Services
Category Service Project
Previous
Years
£000's
2023-24     
£000s
2024-25    
£000s
2025-26   
£000s
2026-27    
£000s
2027-28    
£000s
Total
£000s
Asset Sustainability RIS Block Allocation 0 0 0 4,168 3,823 0 7,991
Bridge Strengthening 0 302 1,384 0 0 0 1,686
Bute Sea Wall Repairs 0 47 633 0 0 0 680
Coastal Change Adaptation 0 48 304 0 0 0 352
Coastal Protection 0 3 196 0 0 0 199
Environmental Projects 0 300 721 0 0 0 1,021
EV Quick Chargers 0 10 52 0 0 0 62
Flood Prevention 0 266 847 156 194 0 1,463
Footway Improvements 0 531 219 0 0 0 750
Glengorm - Capping 0 0 0 0 0 0 0
Glengorm - Cell and Transfer Station (PB) 0 90 -1 0 0 0 89
Helensburgh CHORD - Signage etc 0 0 10 0 0 0 10
Helensburgh Flood Mitigation 0 1 427 0 0 0 428
Investment in Active Travel 0 189 200 0 0 0 389
Lighting 0 246 794 0 0 0 1,040
Local Bridge Maintenance Fund 0 213 4,787 203 0 0 5,203
Play Park Renewal 0 0 547 391 0 0 938
Public Convenience Upgrades 0 55 227 0 0 0 282
RIS - Roads Plant and Equipment - CFCR 0 33 0 0 0 0 33
Roads Reconstruction 0 7,259 8,507 0 0 0 15,766
Roads Reconstruction - Helensburgh CHORD 0 0 47 0 0 0 47
Roads Reconstruction - Oban CHORD 0 0 3 0 0 0 3
Tobermory Car Park 0 0 96 0 0 0 96
Asset Sustainability Total 0 9,593 20,000 4,918 4,017 0 38,528
Service Development RIS Campbeltown Old Quay 1,381 0 0 0 0 0 1,381
Fleet Management 3,033 1,469 195 0 0 0 4,697
Fleet Management - Prudential Borrowing 2,674 0 2,187 0 0 0 4,861
Jackson's Quarry Refurbishment 285 0 0 0 0 0 285
Lismore Ferry Replacement 637 0 35 0 0 0 672
Lochgilphead Depot Rationalisation 29 125 15 0 0 0 169
Oban Depot Development 2,180 44 -35 0 0 0 2,189
Preliminary design for  Regional Transport projects (tif) 205 0 16 0 0 0 221
Witchburn Road Demolition 158 0 0 0 0 0 158
Service Development Total 10,582 1,638 2,413 0 0 0 14,633
Strategic Change RIS Campbeltown Flood Scheme 4,992 8,756 1,780 10 387 0 15,925
Harbour Investment Programme PB 7,397 1,898 25,412 39,000 17,585 0 91,292
Street Lighting LED Replacement 3,226 53 621 0 0 0 3,900
Strategic Change Total 15,615 10,707 27,813 39,010 17,972 0 111,117
Overall Total 26,197 21,938 50,226 43,928 21,989 0 164,278

Page 39

CAPITAL PLAN 2023-24 APPENDIX 7
Development and Economic Growth
Category Service Project
Previous
Years
£000's
2023-24    
£000s
2024-25   
£000s
2025-26    
£000s
2026-27     
£000s
2027-28     
£000s
Total
£000s
Service Development DEG Ardrishaig North Active Travel 755 76 49 0 0 0 880
Cycleways - H&L (FSPT) 2,812 93 497 0 0 0 3,402
Dunoon Cycle Bothy 259 224 80 0 0 0 563
Dunoon STEM Hub 95 36 2,427 0 0 0 2,558
Gibraltar Street Public Realm Improvements 28 125 97 0 0 0 250
Helensburgh Public Realm - Arts Strategy Fund 3 0 25 25 0 0 53
Hermitage Park 3,362 0 26 0 0 0 3,388
Nature Restoration Fund 0 0 835 0 0 0 835
Rural Growth Deal 50 189 2 0 0 0 241
Safe Streets, Walking and Cycling (CWSS) 3,013 130 619 0 0 0 3,762
SPT - bus infrastructure 1,405 0 25 0 0 0 1,430
Town Centre Funds 3,611 384 334 0 0 0 4,329
Service Development Total 15,393 1,257 5,016 25 0 0 21,691
Strategic Change DEG 01 TIF - Lorn/Kirk Road 2,169 0 1 0 0 0 2,170
05 TIF - North Pier Extension 214 0 0 0 0 0 214
09 TIF - Oban Airport Business Park 489 16 85 0 0 0 590
TIF - Halfway House Roundabout 66 0 574 0 0 0 640
Strategic Change Total 2,938 16 660 0 0 0 3,614
Overall Total 18,331 1,273 5,676 25 0 0 25,305

Page 40

CAPITAL PLAN 2023-24 APPENDIX 7
Health & Social Care Partnership
Category Service Project
Previous
Years
£000's
2023-24   
£000s
2024-25   
£000s
2025-26   
£000s
2026-27    
£000s
2027-28    
£000s
Total
£000s
Asset Sustainability HSCP Ardfenaig 0 27 11 0 0 0 38
Capital Property Works 0 0 92 0 0 0 92
Digitalising telecare 0 100 0 0 0 0 100
Eadar Glinn 0 7 34 0 0 0 41
East King Street Childrens Home 0 50 0 0 0 0 50
Glencruitten Hostel 0 9 280 0 0 0 289
Gortonvogie 0 1 0 0 0 0 1
Greenwood/Woodlands 0 123 1 0 0 0 124
HSCP - 102 East King Street "Jean's Bothy" - Rewire - 23-240 21 4 0 0 0 25
Kintyre Care Home 0 0 150 650 0 0 800
Shellach View 0 144 2 0 0 0 146
Struan Lodge Boiler 0 59 700 0 0 0 759
Thomson Home Rothesay 0 6 270 370 0 0 646
Tigh An Rudha HFE 0 201 2,178 35 0 0 2,414
Tobermory Top Flat 0 29 0 0 0 0 29
Asset Sustainability Total 0 777 3,722 1,055 0 0 5,554
Service Development HSCP Dunclutha Childrens Home 1,246 0 54 0 0 0 1,300
Service Development Total 1,246 0 54 0 0 0 1,300
Overall Total 1,246 777 3,776 1,055 0 0 6,854

Page 41

CAPITAL PLAN 2023-24 APPENDIX 7
Live Argyll
Category Service Project
Previous
Years
£000's
2023-24    
£000s
2024-25    
£000s
2025-26    
£000s
2026-27   
£000s
2027-28 
£000s
Total
£000s
Asset Sustainability Live Argyll Aqualibrium 0 360 63 104 0 0 527
Capital Property Works 0 0 73 0 382 0 455
Corran Halls Gaelic Centre 0 109 19 0 86 0 214
Dunoon Community Education Centre - CFCR 0 77 0 0 0 0 77
Gym Equipment - CFCR 0 191 0 0 0 0 191
Kintyre Community Education Centre - Lift Shaft Refurbishment 0 3 0 0 0 0 3
Lochgilphead Community Ed Centre 0 108 368 0 0 0 476
Lochgilphead Library Relocation 0 1 0 0 0 0 1
Queen's Hall - Legionella Works 0 25 0 0 0 0 25
Riverside Leisure Centre - Health Suite Upgrade 0 86 140 0 0 0 226
Riverside Leisure Centre - Spa Pool Upgrade 0 2 0 0 0 0 2
Rothesay Swimming Pool 0 31 24 65 0 0 120
The Moat Centre 0 85 393 0 0 0 478
Victoria Halls, Helensburgh 0 55 24 0 0 0 79
Asset Sustainability Total 0 1,133 1,104 169 468 0 2,874
Service Development Live Argyll Riverside Leisure Centre Refurbishment 1,245 1 0 0 0 0 1,246
Service Development Total 1,245 1 0 0 0 0 1,246
Strategic Change Live Argyll Carbon Management 29 0 21 0 0 0 50
Strategic Change Total 29 0 21 0 0 0 50
Overall Total 1,274 1,134 1,125 169 468 0 4,170