Erratum Notice for Item 19 (with correct report for 'Housing Revenue Account (HRA) Capital Budgetary Report to 31 August 2025 (Period 5)')

West Dunbartonshire Council · 29 October 2025
Back to West Dunbartonshire Council — 29 October 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Erratum Notice 
West Dunbartonshire Council 
Date:  Wednesday, 29 October 2025
___________________________________________________________________ 
Time:  16:00
___________________________________________________________________ 
Format:      Hybrid meeting 
___________________________________________________________________ 
Contact:    Carol-Ann Burns, Senior Democratic Services Officer  
Email: carol-ann.burns@west-dunbarton.gov.uk   
committee.admin@west-dunbarton.gov.uk 
Dear Member 
ERRATUM – CORRECT REPORT FOR ITEM 19 
I refer to the papers for the above meeting which were issued on 16 October and would
advise that the document pack contained the incorrect report for Item 19, ‘Housing
Revenue Account (HRA) Capital Budgetary Control Report to 31 August 2025 (Period 5)’. 
Please substitute the attached report for the one issued previously. 
I apologise for any inconvenience caused. 
Yours faithfully 
PETER HESSETT 
Chief Executive 
19 HOUSING REVENUE ACCOUNT (HRA) CAPITAL BUDGETARY  291 – 301
CONTROL REPORT TO 31 AUGUST 2025 (PERIOD 5)    
Submit report by the Chief Officer – Resources providing an update on the
HRA capital programme to 31 August 2025.

Page 2

Distribution:- 
Provost Karen Murray Conaghan Councillor June McKay
Councillor James Bollan  Councillor John Millar
Councillor Kevin Crawford Councillor Lawrence O’Neill
Councillor Ian Dickson Councillor Lauren Oxley
Councillor Diane Docherty Councillor Chris Pollock
Councillor Fiona Hennebry Councillor Martin Rooney
Councillor Gurpreet Singh Johal Councillor William Rooney
Councillor Daniel Lennie Councillor Gordon Scanlan
Councillor David McBride Councillor Hazel Sorrell
Councillor Jonathan McColl Councillor Clare Steel
Councillor Michelle McGinty Councillor Sophie Traynor   
Chief Executive
Chief Officers 
Date of issue: 20 October 2025

Page 3

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Council – 29 October 2025
___________________________________________________________________
Subject: Housing Revenue Account (HRA) Capital 
Budgetary Control Report to 31 August 2025 (Period 5)
1. Purpose
1.1 This report provides an update on the HRA capital programme to 31 August
2025.
2. Recommendations
2.1 Council is asked to:
i) Note the position of the 2025/26 HRA capital budget and the HRA capital plan
as 31 August 2025.
ii) Note project life performance is monitored against a £345.311m project life
expenditure estimate, a £80.379m project life income estimate and a
£264.932m five-year borrowing requirement.
iii) Note all projects are currently on track to achieve their planned completion
dates and that eleven projects are forecast to deliver a total underspend of
£6.481m against their five-year project life budgets.
iv) Note in year financial performance is monitored against a 2025/26 capital
expenditure budget of £55.547m, 2025/26 capital income budget of £6.290m
and a one-year borrowing requirement of £49.257m.
v) Note thirty-two projects are reporting as off track in 2025/26 with an
anticipated under spend of £9.812m against their 2025/26 budgets reducing
the forecast one-year borrowing requirement to £39.445m.
3. Background
3.1 The Council approved the HRA Capital Plan for 2025/26 to 2029/30 on 5
March 2025. The HRA capital plan approved £70.590m of capital expenditure
and £15.324m of capital income in 2025/26, creating a borrowing requirement
of £55.266m.
3.2 At its meeting on the 27 August 2025, the Housing and Communities
Committee agreed budget adjustments that revised the 2025/26 capital
expenditure budget to £55.547m and the capital income budget to £6.290m,
an updated one-year borrowing requirement of £49.257m. Committee also
approved a revised project life budget of £264.932m. A summary of the
revised capital budgets is set out in Exhibit 1.
ITEM 19
Page 291

Page 4

Exhibit 1: HRA Capital Estimates 2025/26 – 2029/30
Project Life
Budget
(£m)
2025/26
Budget
(£m)
Project Life
Forecast
BCR05
(£m)
2025/26
Forecast
BCR05
(£m)
Other Capital Expenditure 26.267 7.433 26.052 6.738
Component Replacement 93.567 20.881 89.226 14.468
Void Capital 19.873 5.258 19.873 5.700
Structural & Environmental 17.320 3.762 16.653 1.875
Support Costs 17.155 3.100 17.155 3.100
More Homes Programme  171.129 15.113 171.129 17.962
Total Expenditure 345.311 55.547 340.088 49.843
Total Income -80.379 -6.290 -81.636 -10.398
Prudential Borrowing 264.932 49.257 258.452 39.445
4. Main Issues
4.1 Progress against the 2025/26 capital plan is detailed in:
Appendix 1 – HRA Capital Summary BCR05
Appendix 2 – HRA Capital Detail BCR05
4.2 The HRA capital summary report at Appendix 1 reports that:
 project life expenditure is forecast to be less than budget by £5.223m over
the 5-year period of the capital plan.
 one project has forecast project life income of £1.258m more than the
project budget
 consequently, prudential borrowing will be £6.481m less than the approved
project life budget over the 5-year period of the capital plan.
4.3 Appendix 2 reports all projects with their approved in year and project life
estimates as well as their 2025/2026 expenditure and income forecasts. The
appendix reports:
 2025/2026 forecast spend of £49.843m, a £5.704m underspend against
the 2025/2026 budget.
 2025/2026 forecast income of £10.398m, a £4.108m over-recovery against
the 2025/2026 budget
 2025/2026 prudential borrowing will be £39.445m, £9.812m less than the
approved plan for 2025/2026.
4.4 Commentary on the 2025/2026 variances are set out in Exhibit 2 below.
Exhibit 2: Project Over / Underspends 2025/2026 as at BCR05
Project 25/26
Forecast
(£m)
25/26
Budget
(£m)
25/26
Variance
(£m) Commentary
1 Special Need
Adaptations
0.668 0.688 0.020 Small overspend to be re-
profiled across future years.
Page 292

Page 5

Project 25/26
Forecast
(£m)
25/26
Budget
(£m)
25/26
Variance
(£m) Commentary
2 Capitalised
Minor Works
3.500 3.715 -0.215 Reduced contractors spend.
Underspend will reduce
borrowing requirement
3 Environmental
Sensors
1.500 2.000 -0.500 Underspend due to
challenges getting access to
properties.
Underspend will be re-
profiled across future years.
4 Targeted
SHQS /EESSH
compliance
works
5.000 6.628 -1.628 Underspend reflects the
changing mix of the capital
programme with an
increased number of mixed
tenure blocks that require
owner consent before work
can start. This necessary
process delays project start.
Underspend to be re-profiled
across future years.
5 External
Component
Renewal -
Roofs
1.250 2.500 -1.250 Underspend reflects the
changing mix of the capital
programme with an
increased number of mixed
tenure blocks that require
owner consent before work
can start. This necessary
process delays project start.
Underspend will reduce
borrowing requirement.
6 Doors/Windows
Component
Renewals
3.600 4.985 -1.385 Underspend due to
challenges getting access to
properties. Install team to
continue programmed
addresses and revisit no
accesses to use materials
already supplied.
Underspend will reduce
borrowing requirement.
7 External Stores
/ Garages / Bin
Stores
0.000 0.048 -0.048 Works are being funded from
the capitalised minor works
budget.
Underspend will reduce
borrowing requirement
Page 293

Page 6

Project 25/26
Forecast
(£m)
25/26
Budget
(£m)
25/26
Variance
(£m) Commentary
8 Secure entry
component
renewals
0.000 0.100 -0.100 Works are being funded from
the capitalised minor works
budget.
Underspend will reduce
borrowing requirement.
9 Statutory /
Regulatory
Compliance
Works
0.150 0.594 -0.444 Health and safety works are
now being delivered across
two years.
Underspend will be re-
profiled across future years.
10 Energy
Improvements /
Energy
Efficiency
Works
0.000 0.058 -0.058 Works are being funded from
the capitalised minor works
budget.
Underspend will reduce
borrowing requirement.
11 Kitchen
Upgrade
1.600 2.850 -1.250 Underspend projected as
team re-assess and pre-
inspect to ensure a focus on
necessary renewals led by
condition.
Underspend will reduce
borrowing requirement.
12 Bathroom &
Shower
Replacement
0.600 0.800 -0.200 Underspend projected as
team re-assess and pre-
inspect to ensure a focus on
necessary renewals led by
condition.
Underspend will reduce
borrowing requirement.
13 Void House
Strategy
Programme
5.700 5.258 0.442 Contractor voids spend
greater than budgeted.
Overspend will be re-profiled
across future years.
14 Defective
structures
/component
renewals
0.175 0.800 -0.625 Underspend projected as
future blocks are pre-
inspected for condition and
re-prioritisation for
completion if necessary.
Building Services resources
are assisting in the void
house programme of work.
Underspend will reduce
borrowing requirement.
Page 294

Page 7

Project 25/26
Forecast
(£m)
25/26
Budget
(£m)
25/26
Variance
(£m) Commentary
15 Environmental
Renewal -
Paths &
Environment
1.100 1.000 0.100 Overspend due to mix of
work requiring contactors in
addition to in-house team.
Overspend will be re-profiled
across future years.
16 Asbestos
Management
Works
0.200 0.242 -0.042 Demand lower than
anticipated.
Underspend will reduce
borrowing requirement
17 Multi Storey
Flat Strategy
0.400 1.720 -1.320 Revised projection based on
timing of programme.
Underspend will be re-
profiled across future years.
18 Buy Backs 4.000 4.380 -0.380 Revised projection based on
the anticipated programme of
thirty-five acquisitions to be
completed in 25/26.
Underspend will be re-
profiled across future years.
19 Demolition
Programme
0.206 0.140 0.066 Revised projection based on
timing of programme.
In year overspend will be re-
profiled across future years
20 Clydebank East 0.365 0.250 0.115 Revised projection based on
development project plan.
In year overspend will be re-
profiled across future years.
21 Pappert 0.872 0.730 0.142 Revised projection based on
development project plan.
In year overspend will be re-
profiled across future years.
22 Willox Park
Phase1
3.398 2.980 0.418 Revised projection based on
development project plan.
In year overspend will be re-
profiled across future years.
23 Bank Street 0.839 1.500 -0.661 Revised projection based on
development project plan.
In year underspend will be
re-profiled across future
years.
Page 295

Page 8

Project 25/26
Forecast
(£m)
25/26
Budget
(£m)
25/26
Variance
(£m) Commentary
24 Bonhill Gap
Sites
5.145 1.600 3.545 Revised projection based on
development project plan.
Overspend will be re-profiled
across future years.
25 Silverton 0.050 0.100 -0.050 Revised projection based on
development project plan.
In year underspend will be
re-profiled across future
years.
26 Queen Mary
Avenue
1.000 0.800 0.200 Revised projection based on
development project plan.
In year overspend will be re-
profiled across future years.
27 Future New
Build & Related
Regeneration
Projects
0.000 0.550 -0.550 Revised projection based on
development project plan.
In year underspend will be
re-profiled across future
years.
28 Scottish Govt
Buyback Grant
-2.378 -0.550 -1.828 Revised projection based on
the distribution of Scottish
Government acquisition
funding
29 Bank Street -0.839 -1.500 0.661 Revised projection based on
the application of the
Strategic Local Programme
30 Bonhill Gap
Sites
-3.360 -1.600 -1.760 Revised projection based on
the application of the
Strategic Local Programme
31 Clydebank
Health Centre
-0.350 -0.375 0.025 Revised projection based on
the application of the
Strategic Local Programme
32 Other Grant -1.612 -0.406 -1.206 Additional Scottish
Government Net Zero
Funding awarded to fabric
first energy efficiency works
4.5 Budget assumptions are required to forecast costs / income, especially where
projects span multi-year and project finances have yet to be finalised. It is
therefore likely that the projected year end position will change during the
year.
Page 296

Page 9

5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital estimates.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
several variable factors which could arise between now and 31 March
which could affect the year end results for capital budgets.
(b) To forecast for the full year costs budget assumptions have been
required. These assumptions continue to change regularly and therefore
it is likely the projected year end position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital estimates have been consulted
during the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
Page 297

Page 10

________________
Laurence Slavin
Chief Officer – Resources
Date: 29 October 2025
Person to Contact: Jim McCarron
Business Partner, Finance 07772 322055
E-mail: james.mccarron@west-dunbarton.gov.uk
Appendices: Appendix 1 - HRA Capital Summary BCR05
Appendix 2- HRA Capital Details BCR05
Background Papers:
Housing Revenue Account (HRA) Capital Investment Programme, Revenue
Budget, and Rent Levels for 2025/26 - Council 5 March 2025.
Wards Affected           All Wards
Page 298

Page 11

Period 5 - 31 August 2025 Appendix 1
Summary
HRA Capital Expenditure Project Life
Budget
Project Life
Forecast Spend
Project Life
Variance
Rolling
Programmes
Projects Projects
On Track / Complete
Projects
Off Track
£000 £000 £000
Other Capital Expenditure 26,267                26,052                (215) 8                    -                -                              -                             
Major Component Replacement 93,567                89,226                (4,341) 11                  -                -                              -                             
Void Capital 19,873                19,873                0 1                    -                -                              -                             
Structural & Environmental 17,320                16,653                (667) 4                    -                -                              -                             
Support Costs 17,155                17,155                0 1                    -                -                              -                             
Affordable Housing Supply Programme 171,129              171,129              0 5                    12                  12                                -                             
Total Expenditure 345,311              340,088              (5,223) 30                  12                  12                                -                             
Total Income (80,378) (81,636) (1,258) 4                    12                  12                                -                             
Total 264,933 258,452 (6,481)
Page 299

Page 12

All Approved HRA Capital Projects at Period 05  _  31 August 2025 Appendix 2
Project Category Planned
End Date
Revised
End Date
Project Life
Budget
Expenditure
to 31 /3/25
Expenditure
to Date
Projected
Future Spend
Project Life
Forecast Spend
Project
Variance
Approved
Budget
2025/26
Expenditure
to Date
2025/26
Projected
Spend
2025/26
In Year
Variance
2025/26
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
OCE1 Special Needs Adaptations Rolling 31/03/2026 3,661                    -                             288                       3,373                    3,661                    -                             668                       288                       688                       20                         
OCE2 Capitalised Minor Works Rolling 31/03/2026 12,623                  -                             1,106                    11,302                  12,408                  (215) 3,715                    1,106                    3,500                    (215)
OCE3 Better Homes Priority Budget Rolling 31/03/2026 1,175                    -                             6                            1,169                    1,175                    -                             275                       6                            275                       -                       
OCE4 Environmental Sensors Programme Rolling 31/03/2026 7,897                    -                             444                       7,453                    7,897                    -                             2,000                    444                       1,500                    (500)
OCE5 Housing CCTV Installation Programme Rolling 31/03/2026 750                       -                             287                       463                       750                       -                             750                       287                       750                       -                       
OCE6 QL Development Rolling 31/03/2026 50                          -                             1                            49                          50                          -                             10                          1                            10                          -                       
OCE7 Gypsy Travellers Site Rolling 31/03/2026 15                          -                             5                            10 15                          -                             15                          5                            15                          -                       
OCE8 Airport Noise Rolling 31/03/2026 96                          -                             -                             96                          96                          -                             -                             -                             -                             -                       
Other Capital Expenditure 26,267                  -                        2,137                    23,915                  26,052                  (215) 7,433                    2,137                    6,738                    (695)
MCR1 Targeted SHQS /EESSH compliance works Rolling 31/03/2026 30,163                  -                             1,437                    28,726                  30,163                  0 6,628                    1,437                    5,000                    (1,628)
MCR2 External Component Renewal - Roofs Rolling 31/03/2026 13,204                  -                             574                       11,330                  11,904                  (1,300) 2,550                    574                       1,250                    (1,300)
MCR3 Doors/Windows Component Renewals Rolling 31/03/2026 23,190                  -                             1,806                    19,999                  21,805                  (1,385) 4,985                    1,806                    3,600                    (1,385)
MCR4 External Stores / Garages / Bin Stores Rolling 31/03/2026 247                       -                             -                             199                       199                       (48) 48                          -                             -                             (48)
MCR5 Secure entry component renewals Rolling 31/03/2026 500                       -                             -                             400                       400                       (100) 100                       -                             -                             (100)
MCR6 Statutory / Regulatory Compliance Works Rolling 31/03/2026 1,106                    -                             -                             1,106                    1,106                    -                        594                       -                             150                       (444)
MCR7 Heating Improvement Works Rolling 31/03/2026 11,771                  -                             705                       11,066                  11,771                  -                        2,268                    705                       2,268                    -                       
MCR8 Energy Improvements / Energy Efficiency Works Rolling 31/03/2026 297                       -                             -                             239                       239                       (58) 58                          -                             -                             (58)
MCR9 Kitchen Upgrade Rolling 31/03/2026 10,089                  -                             552                       8,287                    8,839                    (1,250) 2,850                    552                       1,600                    (1,250)
MCR10 Bathroom & Shower Replacement Rolling 31/03/2026 3,000                    -                             247                       2,553                    2,800                    (200) 800                       247                       600                       (200)
Major Component Replacement 93,567                  -                        5,321                    83,905                  89,226                  (4,341) 20,881                  5,321                    14,468                  (6,413)
VOC1 Void House Strategy Programme Rolling 31/03/2026 19,873                  -                             2,265                    17,608                                     19,873                            -   5,258                    2,265                    5,700                    442                      
-                       
Void Capital 19,873                  -                        2,265                    17,608                  19,873                  -                        5,258                    2,265                    5,700                    442                      
STE1 Defective structures/component renewals Rolling 31/03/2026 4,389                                                 - 174                       3,590                    3,764                    (625) 800                       174                       175                       (625)
STE2 Environmental Renewal - Paths & Environment Rolling 31/03/2026 5,436                                                 - 479                       4,957                    5,436                    -                        1,000                    479                       1,100                    100                      
STE3 Asbestos Management Works Rolling 31/03/2026 1,239                                                 - 85                          1,112                    1,197                    (42) 242                       85                          200                       (42)
STE4 Multi Storey Flat Strategy Rolling 31/03/2026 6,256                    -                             44                          6,212                    6,256                                               -   1,720                    44                          400                       (1,320)
Structural & Environmental 17,320                  -                             782                       15,871                  16,653                  (667) 3,762                    782                       1,875                    (1,887)
SUP1 Salaries / Central Support / Overhead Rolling 31/03/2026 17,155                  -                             1,292                    15,863                                     17,155                            -   3,100                    1,292                    3,100                    -                       
Support Costs 17,155                  -                        1,292                    15,863                  17,155                  -                        3,100                    1,292                    3,100                    -                            
AHP1 Buy Backs Rolling 31/03/2030 21,387                  -                             1,243                    20,144                                     21,387                            -   4,380                    1,243                    4,000                    (380)
AHP2 Demolition Programme Rolling 31/03/2029 1,140                    -                             207                       933                                            1,140                            -   140                       207                       206                       66                         
AHP3 Contingency Rolling 31/03/2030 530                       -                             -                             530                                               530                            -   102                       -                             102                       -                       
AHP4 Clydebank East Project 30/04/2025 33,643                  32,953                  33,085                  558                                          33,643                            -   250                       132                       365                       115                      
AHP5 Pappert Project 30/06/2025 9,034                    8,169                    9,041                    7-                                                 9,034                            -   730                       872                       872                       142                      
AHP6 Mount Pleasant Project 30/04/2025 5,357                    4,900                    5,282                    75                                               5,357                            -   382                       382                       382                       -                       
AHP7 7-9 Gilmour Avenue Project 30/09/2025 733                       459                       467                       266                                               733                            -   264                       8                            263                       (1)
AHP8 Willox Park Phase1 Project 31/12/2025 5,531                    1,951                    3,313                    2,218                                         5,531                            -   2,980                    1,362                    3,398                    418                      
AHP9 Willox Park Phase2 Project 30/06/2027 5,355                    -                             1                            5,354                                         5,355                            -   100                       1                            100                       -                       
AHP10 Bank Street Project 31/12/2026 5,797                    297                       483                       5,314                                         5,797                            -   1,500                    186                       839                       (661)
AHP11 Bonhill Gap Sites Project 30/09/2026 9,521                    241                       656                       8,865                                         9,521                            -   1,600                    415                       5,145                    3,545                   
AHP12 Clydebank Health Centre Project 31/12/2027 15,642                  1,017                    1,186                    14,456                                     15,642                            -   375                       169                       380                       5                           
AHP13 Silverton Project 31/03/2027 2,889                    29                          29                          2,860                                         2,889                            -   100                       -                             50                          (50)
AHP14 Queen Mary Avenue Project 31/12/2026 4,540                    40                          223                       4,317                                         4,540                            -   800                       183                       1,000                    200                      
AHP15 Queens Quay Site C Project 31/03/2020 7,231                    31                          31                          7,200                                         7,231                            -   -                             -                             -                             -                       
AHP16 Dennystoun Forge – New Build Project 30/09/2027 4,129                    59                          61                          4,068                                         4,129                            -   400                       2                            400                       -                       
AHP17 28 Bridge Street Project 31/03/2027 810                       -                             -                             810                                               810                            -   60                          -                             60                          -                       
AHP18 Ottawa Crescent Project 30/06/2027 6,000                    -                             -                             6,000                                         6,000                            -   250                       -                             250                       -                       
AHP19 Future New Build & Related Regeneration Projects Rolling 31/03/2030 31,030                  -                             31,030                                     31,030                            -   550                       -                             -                             (550)
AHP20 Fees, Staffing Costs, contingency Rolling 31/03/2030 830                       -                             -                             830                                               830                            -   150                       -                             150                       -                       
Affordable Housing Supply Programme 171,129                50,146                  55,308                  115,821                171,129                0 15,113                  5,162                    17,962                  2,849                   
Total Expenditure 345,311                50,146                  67,105                  272,983                340,088                (5,223) 55,547                  16,959                  49,843                  (5,704)
Full Project Life
Page 300

Page 13

All Approved HRA Capital Projects at Period 05  _  31 August 2025 Appendix 2
Full Project Life
Project Category Planned
End Date
Revised
End Date
Project Life
Budget
Income
to 31/3/25
Income
to Date
Projected
Future Income
Project Life
Forecast Income
Project
Variance
Approved
Budget
2025/26
Income
to Date
2025/26
Projected
Income
2025/26
In Year
Variance
2025/26
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
CAPI1 Scottish Govt Buyback Grant Rolling 31/03/2030 (10,550) -                             -                             (10,550) (10,550) -                             (550) -                             (2,378) (1,828)
CAPI2 Clydebank East Project 30/04/2025 (12,605) (12,605) (12,605) -                             (12,605) -                             -                             -                             -                             -                            
CAPI3 Pappert Site Project 30/06/2025 (3,725) (3,475) (3,725) -                             (3,725) -                             (250) (250) (250) -                            
CAPI4 Mount Pleasant Project 30/04/2025 (1,838) (1,838) (1,838) -                             (1,838) -                             -                             -                             -                             -                            
CAPI5 7-9 Gilmour Avenue Project 30/09/2025 (311) (191) (191) (120) (311) -                             (120) -                             (120) -                            
CAPI6 Willox Park Phase1 Project 31/12/2025 (1,644) (1,644) (1,644) -                             (1,644) -                             -                             -                             -                             -                            
CAPI7 Bank Street Project 31/12/2026 (2,220) (258) (258) (1,962) (2,220) -                             (1,500) -                             (839) 661                      
CAPI8 Bonhill Gap Sites Project 30/09/2026 (3,748) (378) (378) (3,370) (3,748) -                             (1,600) -                             (3,360) (1,760)
CAPI9 Clydebank Health Centre Project 31/12/2027 (4,781) (966) (966) (3,815) (4,781) -                             (375) -                             (350) 25                         
CAPI10 Silverton Project 31/03/2027 (1,080) -                             -                             (1,080) (1,080) -                             -                             -                             -                             -                            
CAPI11 Queen Mary Avenue Project 31/12/2026 (2,040) (140) (140) 1,900-                    2,040-                    -                             -                             -                             -                             -                            
CAPI12 Queens Quay Site C Project 31/03/2020 (4,814) (2,086) (2,014) (2,800) (4,814) -                             72 72                          72 -                            
CAPI13 Dennystoun Forge – New Build Project 30/09/2027 (2,400) -                             -                             (2,400) (2,400) -                             -                             -                             -                             -                            
CAPI14 Future new build sites & related regeneration projects Rolling 31/03/2030 (24,711) -                             -                             (24,711) (24,711) -                             (60) -                             (60) -                            
CAPI15 Owners Recoveries Rolling 31/03/2030 (3,500) -                             1,168-                    (2,332) (3,500) -                             (1,500) (1,168) (1,500) -                            
CAPI16 Other Grant Rolling 31/03/2030 (406) -                             (832) (832) (1,664) (1,258) (406) (832) (1,612) (1,206)
CAPI17 HRA Loan Repayments Rolling 31/03/2030 (5) -                             -                             (5) (5) -                             (1) -                             (1) -                            
Total Income (80,378) (23,581) (25,759) (55,877) (81,636) (1,258) (6,290) (2,178) (10,398) (4,108)
Prudential Borrowing Requirement 264,933                26,565                  41,346                  217,106                258,452                (6,481) 49,257                  14,781                  39,445                  (9,812)
Full Project Life In Year
Page 301