Period 3 - 30 June 25 Appendix 1
Summary
HRA Capital Expenditure Project Life
Budget
Project Life
Forecast Spend
Project Life
Variance
Rolling
Programmes
Projects Projects
On Track / Complete
Projects
Off Track
£000 £000 £000
Other Capital Expenditure 26,267                26,267                -                      8                    -                -                              -                             
Major Component Replacement 93,567                93,567                -                      10                  -                -                              -                             
Void Capital 19,873                19,873                -                      1                    -                -                              -                             
Structural & Environmental 17,320                17,320                -                      4                    -                -                              -                             
Support Costs 17,155                17,155                -                      1                    -                -                              -                             
Affordable Housing Supply Programme 171,129              171,129              -                      5                    15                  15                                -                             
Total Expenditure 345,311              345,311              -                      29                  15                  15                                -                             
Total Income (80,378) (80,378) -                      -                              -                             
Total 264,933 264,933              -