West Dunbartonshire Council Appendix 3
General Services Capital 2025/26
Changes to Capital Plan and Implications at P3
Project - RR 2 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Installation of Solar PV at Clydebank Leisure Centre 31/03/2026 31/03/2027 (57) 57                       0 0 0 0 0 0 0 0                            57
Installation of Solar PV at Clydebank Leisure Centre - Revised 0 57 0 0 0 0 0 0 0                            57
Explanation
Project delayed due to planning permission and building control requirements
Project - RR 3 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Leisure Energy projects - air handling units, upgrade lighting, circulating pumps, and draught
proofing 31/03/2026 31/03/2027 (226) 226                     0 0 0 0 0 0 0 0                          226
Leisure Energy projects - air handling units, upgrade lighting, circulating pumps, and
draught proofing - Revised 0 226 0 0 0 0 0 0 0                          226
Explanation
Project delayed  - The Air Handling Units replacement was tendered via a single tender framework via procurement -cost submitted was approx. double the budget approved. Further discussions therefore required about how to progress.
Project - RR 4 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Local Economic Development (1,490) 2,248 2,220 760 500 500 0 0 0 0 6,228
Local Economic Development - Revised 758 2,840 1,300 830 500 0 0 0 0 6,228
Explanation
Project delivery  taking longer than expected.
Project - RR 5 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Regeneration Fund (2,145) 2,145 974 705 0 0 0 0 0 0 3,824
Regeneration Fund  - Revised 0 2,000 1,824 0 0 0 0 0 0 3,824
Explanation
Project - RR 7 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Levelling Up Fund (3,173) 10,249 10,249
Levelling Up Fund - Revised 7,076 3,173 10,249
Explanation
Project delivery  taking longer than expected.
Project - RR 10 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Clyde Mission Catalyst Fund (702) 1,327 0 0 0 0 0 0 1,327
Clyde Mission Catalyst Fund - Revised 625 702 0 0 0 0 0 1,327
Explanation
Project development taking longer than expected, timescales of the external partner outwith our control.
Project - RN 26 Initial End Date  Revised End Date Reprofiling Current Year  2026/27  2027/28  2028/29  2029/30  2030/31  2031/32  2032/33  2033/34  Total Capital Plan
£'000 £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000  £'000
Exxon City Deal 675 19,910 10,970 4,693 0 0 0 0 0 35,573
Exxon City Deal - Revised 20,585 10,970 4,018 0 0 0 0 0 35,573
Explanation
Project development taking longer than expected, timescales of the external partner outwith our control.
Project dependant on timescales of external partners, outwith Council's control