Democracy Spraffa

Item 11 Housing Revenue Account (HRA) Capital Budgetary Control Report to 31 January 2025 (Period 10)

West Dunbartonshire Council · 26 March 2025
Back to West Dunbartonshire Council — 26 March 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Council – 26 March 2025
___________________________________________________________________
Subject: Housing Revenue Account (HRA) Capital 
Budgetary Control Report to 31 January 25 (Period 10)
1. Purpose
1.1 This report provides an update on the HRA capital programme to 31 January
2025.
2. Recommendations
2.1 Committee is asked to:
i) Note the current position of the 2024/2025 HRA capital budget and the
HRA capital plan.
ii) Note that in year financial performance is monitored against a
2024/2025 capital expenditure budget of £73.664m and a 2024/2025
capital income budget of £10.003m, a one-year borrowing requirement
of £63.661m.
iii) Note that project life performance is monitored against a five-year
project life expenditure budget of £319.740m and a project life income
budget of £54.576m, a five-year borrowing requirement of £265.164m.
iv) Note that there are thirty two projects reporting off track with an
anticipated over / under spend against their 2024/2025 budgets, with a
forecast net underspend of £4.112m in 2024/2025. 
3. Background
3.1 On 6 March 2024 the Council approved the updated Housing Revenue
Account Capital Plan for 2024/2025 to 2028/2029.
3.2 Since then, budget adjustments have taken place to:
 bring forward 2023/24 project under/overspends
 reflect progress delivering the plan and any need for budget
acceleration and budget deceleration from / to future years
 update expenditure and income budgets for Affordable Housing
Supply projects to reflect the 2023/2024 outturn and the most recent
cost and income forecasts.
3.3 The revised capital budget is summarised in Exhibit 1.
ITEM 11

Page 2

Exhibit 1: Revised 2024/2025 – 2028/2029 HRA Capital Budget 
2024/25
BCR10
(£m)
Project
Life
BCR10
(£m)
Project Life
March 24
(£m)
Other Capital Expenditure 7.165 27.129 27.180
Major Component Replacement 19.795 92.604 92.604
Void Capital 4.902 19.212 20.712
Structural & Environmental 2.767 14.175 14.175
Support Costs 2.761 14.367 14.367
Affordable Housing Supply Programme 36.274 152.253 149.053
Total Expenditure 73.664 319.740 318.091
Total Income 10.003 54.576 47.029
Prudential Borrowing 63.661 265.164       271.062
4. Main Issues
4.1 Progress against the 2024/25 capital plan is detailed in:
Appendix 1 – HRA Capital Summary 
Appendix 2 – HRA Capital Detail
4.2 The HRA capital summary report at Appendix 1 reports that planned
expenditure and planned income are both in line with the overall project
budgets. Appendix 1 highlights there are twenty-eight capital projects where
expenditure / income budget is tracked over the multi-year life of the project
and twenty-nine projects that are rolling programme projects / contingency /
fees (programmes of work where an annual budget is set each year that takes
account of demand, cost, and affordability).
4.3 Appendix 2 details all projects and their approved in year and project life
budgets as well as forecast expenditure / income. The appendix highlights a
2024/2025 expenditure budget of £73.664m and a forecast spend of
£68.717m, an underspend of £4.947m. (6.7% of the 2024/2025 budget) The
2024/2025 capital income budget is £10.003m, with a forecast income of
£9.218m.
4.4 2024/2025 expenditure variances greater than £50,000 are summarised in
Exhibit 2.
Exhibit 2: Project Over / Underspends 2024/2025
Project
2024/25
BCR10
Forecast
(£m)
2024/25
BCR10
Budget
(£m)
2024/25
Var
(£m)
Commentary
1 Special Need
Adaptations
0.500 0.655 (0.155) Reduced throughput of
capital adaptations this
year.
Inhouse adaptations
team is fully up to date
with its order book.

Page 3

Project
2024/25
BCR10
Forecast
(£m)
2024/25
BCR10
Budget
(£m)
2024/25
Var
(£m)
Commentary
2 Capitalised
Minor Works
4.100 3.000 1.100 Transfer of Electrical
Installation Condition
Works spend to minor
works budget.
Increase in directing of
minor works requests to
the relevant planned
capital programme.
3 Better Homes
Programme
0.975 0.705 0.270m Initial Project costs
increased due to the
need for isolator switches
to be fitted, which had
been omitted from a
previous legacy work
programme.  The
additional project cost
has been offset  by a
successful application to 
Scottish Power Energy
Networks (SPEN) funding
which awarded the
Council a total of
£355,600. 
4 Housing
CCTV
Installation
Programme
0.000 0.750 (0.750) Excellent progress made
during 24/25, new CCTV
control room completed,
new cabling in majority of
Multi-storey flats
complete, with work in
progress to install new
cameras to network. 
Slight slippage in project
completion date due to
unforeseen technical
issues.  However,
excellent work with CCTV
and BT has ensured any
issues have been quickly
resolved.  Revised
project completion date
anticipated to be before
end of Q1 25/26.
5 Roofing
Works
1.700 2.500 (0.800) Underspend due to
changing mix of the
capital programme with
an increased number of

Page 4

Project
2024/25
BCR10
Forecast
(£m)
2024/25
BCR10
Budget
(£m)
2024/25
Var
(£m)
Commentary
mixed tenure blocks that
require owner consent
before work can start.
This necessary process
can delay project start.
6 Statutory
Regulatory
Compliance
Works
0.022 0.294 (0.272) Delay in commencing
works by Building
Services as awaiting
revised technical drawing
designs being received. 
Team have progressed
some works 24/25, with
remaining works planned
for 25/26once technical
drawings available.
7 Heating
Improvement
Works
2.200 1.900 0.300 Demand has been higher
than anticipated due to
referrals of older boilers
needing replaced due to
functionality and
condition.
Budget increased to
£2.268m in 2025/26 to
manage higher demand.
8 Energy
Efficiency /
Energy
Improvement
Works
0.000 0.057 (0.057) Budget for minor energy
efficiency works such as
missing loft insulation
where identified.
9 Kitchen
Upgrade 
3.500 2.652 0.848 Kitchen renewals
progressing well and
higher demand than
anticipated as a
combination of planned
works and repairs service
referrals identifying
additional installations.
Overspend will be
rephased over future
years.
10 Bathroom &
Shower
Replacement
0.600 0.750 (0.150) Lower tenants take up
has led to slightly lower
combined numbers in

Page 5

Project
2024/25
BCR10
Forecast
(£m)
2024/25
BCR10
Budget
(£m)
2024/25
Var
(£m)
Commentary
bathroom/shower
renewals.
11 Void House
Works
5.300 4.902 0.398 Transfer of increased
void spend to HRA
capital account following
a review.
Void delivery costs,
including overtime on
voids and contractor
spend, have reduced as
void number have
reduced.
12 Defective
structures
0.919 0.712 0.207 Higher spend due to
increased construction
costs.
13 Environmental
Renewal -
Paths &
Environment
0.936 1.068 (0.132) Reduced throughput of
environmental works this
year because operatives
have also worked across
other HRA service areas.
14 Asbestos
Management
Works
0.150 0.237 (0.087) This is a demand led
programme. Lower
demand leading to an
underspend.
15 Multi Storey
Flat Strategy
0.100 0.750 (0.650) The enhanced multi
storey strategy was
approved by Housing and
Communities Committee
in May 2023 and involves
positive tenant
engagement.
The strategy
implementation aligns a
number of related
workstreams, of which
survey work was
essential, it was
anticipated that these
surveys would have
commenced earlier which
has resulted in the in-
year underspend as the
identified work will now
be programmed in
2025/26.

Page 6

Project
2024/25
BCR10
Forecast
(£m)
2024/25
BCR10
Budget
(£m)
2024/25
Var
(£m)
Commentary
16 Contingency 0.000 0.100 (0.100) Contingency released to
offset cost pressures
across the HRA capital
account.
17 Clydebank
East
Expenditure
11.235 9.700 1.535 Good progress with
development and is
ahead of previous
projection
18 Pappert
Expenditure
7.566 9.653 (2.087) Development now on site
and cash flow accurately
based on agreed
programme of works now
reflected in projection. No
impact on overall project
budget or timescales and
development on track.
19 Mount
Pleasant
4.311 4.396 (0.085) Revised projection based
on development project
plan.
20 Willox Park
Phase 1
1.463 2.500 (1.037) Revised projection based
on development project
plan.
21 Bank Street 0.106 0.518 (0.412) Revised projection based
on development project
plan.
22 Bonhill Gap
Sites
0.190 0.514 (0.324) Revised projection based
on development project
plan.
23 Silverton –
Smollett /
Dumbuie
0.024 0.429 (0.405) Revised projection based
on development project
plan.
24 Queen Mary
Avenue
0.010 0.120 (0.110) Revised projection based
on development project
plan.
25 Queens Quay
Site C
Expenditure
0.000 1.000 (1.000) Underspend reflects
delays progressing this
project.

Page 7

Project
2024/25
BCR10
Forecast
(£m)
2024/25
BCR10
Budget
(£m)
2024/25
Var
(£m)
Commentary
26 Dennystoun
Forge
0.050 0.250 (0.200) Revised projection based
on development project
plan.
27 Future New
Build &
Related
Regeneration
Projects /
Professional
Fees
0.500 1.015 (0.515) Ongoing review of the
programme allowed non
committed funds to be
released to offset cost
pressures across the
HRA capital account.
28 Fees, Staffing
& Contingency
0.400 0.500 (0.100) Review of programme
identified in year
efficiencies.
29 Buyback Grant
Income
(2.417) (2.858) 0.441 Revised projection based
on distribution of Scottish
Government funding.
30 Bonhill Gap
Sites
Income
(0.189) 0.000 (0.189) Revised projection based
on the application of the
Strategic Local
Programme.
31 Silverton
Income
(0.429) 0.000 (0.429) Revised projection based
on the application of the
Strategic Local
Programme.
32 Queens Quay
Site C
Income
0.000 (1.000) 1.000 Acquisition grant funding
because the project is not
able to be taken forward
at this point as it has
been assessed as
unviable.
4.5 Budget assumptions are required to forecast costs / income, especially where
projects span multi-year and project finances have yet to be finalised. It is
therefore likely that the projected year end budgetary position will change
during the year.
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications

Page 8

6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are:
(a) The reported variances should be viewed in the knowledge that there are
several variable factors which could arise between now and 31 March
which could affect the year end results for capital budgets.
(b) Because of current market conditions, inflation is high and interest rates
continue to be volatile. To forecast for the full year costs budget
assumptions have been required. These assumptions continue to
change regularly and therefore it is likely the projected year end
budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted
during the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
________________
Laurence Slavin
Chief Officer – Resources
Date: 26 March 2025
Person to Contact: Jim McCarron
Business Partner, Finance 07772 322055
E-mail: james.mccarron@west-dunbarton.gov.uk
Appendices: Appendix 1 - HRA Capital Summary BCR10
Appendix 2- HRA Capital Details BCR10
Background Papers:
Housing Revenue Account (HRA) Capital Investment Programme, Revenue Budget, and Rent
Levels for 2024/25 - Council 6 March 2024.

Page 9

Wards Affected           All Wards