WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Council: 26 March 2025
_________________________________________________________________
Subject: General Services Capital Budgetary Control Report 2024/25 to
31 January 2025 (Period 10).
1. Purpose
1.1 This report provides an update on the General Services capital financial
performance to 31 January 2025.
2. Recommendations
2.1 Members are asked to:
a) Note the current position of the 2024/25 General Services capital budget.
b) Note the project life total is currently on track.
c) Note appendix 2 and 3 which detail the changes between period 7 and 10
including changes agreed at the Council meeting on 5 March 2025.
d) Grant delegated authority to Chief Officer for Roads, Neighbourhood and
Transport, in consultation with the Procurement Manager, to award
contracts in relation to vehicle replacement, using appropriate
procurement routes.
e) Grant delegated authority to Chief Officer Resources, in consultation with
the Procurement Manager, to award any procurement and contract
awards for projects related to Building Upgrades recurring budget using
appropriate procurement routes.
3. Background
3.1 On 6 March 2024 the Council approved the updated General Services Capital
Plan for 2024/2025 to 2032/33. The three years from 2024/25 to 2026/27
were approved in detail with the remaining years being indicative. The budget
agreed was £76.757m for 2024/25 and £318.357m for the project life budget.
4. Main Issues
4.1 Exhibit 1 sets out the revised capital budget at period 7 as reported to Council
on 18 December 2024.
Exhibit 1: Revised Capital Budget as at 18 December 2024.
2024/25
(£m)
Project Life
(£m)
Capital Budget Agreed 6 March 2024 76.757 318.357
Updates reported to Council on 28 August, 30 2.304 1.368
ITEM 9

Page 2

October and 18 December 2024.
Reprofiling reported to Council on 28 August, 30
October and 18 December 2024.
(14.582)
0
Revised Capital Budget at Period 7 64.479 319.725
Updates agreed at Council 18 December 2024. (0.166) (0.166)
Reprofiling reported at period 7 (5.914) 0
Revised Capital Budget as at Period 7 58.399 319.559
4.2 Progress against the 2024/25 capital plan is detailed in:
Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Off Track Projects
Appendix 3 – Changes to Capital Plan for Noting
Appendix 4 – All Approved Projects
4.3 The overall programme summary report at Appendix 1 shows that planned
expenditure against the budget is currently on track.
4.4 Exhibit 2 sets out the revised capital budget at period 10 following approval at
Council on 5 March 2025 as part of the new capital programme.
Exhibit 2: Revised Capital Budget £m £m
2024/2
5 (£m)
Project
Life
(£m)
Revised Capital Budget at 18 December 2024 58.399 319.559
Updates agreed as part of Capital Plan 5 March 2025
(see appendix 2). 2.333 2.950
New Funding – Play Parks. 0 0.508
New Funding – Cycling, Walking and Safer Streets. 0 0.387
New Funding – 20mph speed limits. 0.105 0.105
New Funding – Park and Ride. 0.023 0.023
New Project Agreed Council 5 March 2025 – School
20mph speed limits. 0 0.075
Place Based Investment Programme additional drawn
down. 0 0.100
Additional Budget for Securing Sites 0.059 0.059
Overspends on completed Projects 0.012 0.012
Reprofiling of Projects reported to Council 5 March (2.525) 0
Revised Capital Budget Period 10 58.406 323.778
Underspends on completed Projects (0.035) (0.035)
Revised Proposed Capital Budget Period 10 58.371 323.743
4.5 Appendix 4 shows all projects with approved in year and project life budgets
as well as anticipated expenditure. It highlights that the 2024/25 budget is
£58.371m. The spend as at period 10 is £34.708m (59.43%) of the current
forecast spend of £58.371m.
4.6 The Waste Service have progressed the feasibility and outline design for the
Resource, Recovery Recycling Centre (RRRC) following approval to progress

Page 3

the project to be sited at Poplar Road.  A budget has been allocated for the
project (RN22 – Waste Transfer Station) of £1.9m however following best
value engineering the estimated delivery cost is currently £3.7m. This is due
partly to ground conditions and flood risk implications on the building design
as well as inflationary cost of materials.  Following project inception the
Council has entered into the Cooperation Agreement with Glasgow City
Council which provides a level of resilience and infrastructure that the Council
previously did not have access to. The service recommends the pausing of
this project to allow the monitoring of the implementation of the agreement
and to determine whether there is still a requirement for this infrastructure.
The £1.821m remaining capital budget for this project has been reprofiled into
2028/29 to allow time for a formal decision to be made on the future of the
project. The project budget is £1.980m within the capital budget however the
construction costs are expected to be in the region of £3.7m. To date
£0.159m has been spent on design, site investigation etc with £1.821m
remaining budget. This information is useful should the waste transfer station
be considered as a requirement at a future date or the site be utilised for an
alternative use.
4.7 Appendix 2 highlights that project RN21 (Overburn Allotment Development) is
off track due to a revised completion date as the project design work has been
fully developed with the revised cost estimates indicating that a further
£0.150m will be required to deliver project. This means there is insufficient
budget to deliver the project so it has not been possible to go out to tender. 
Council are not being asked to approve further capital money at the current
time as officers will first explore alternative funding options. If alternative
funding is not identified then Council will be provided with an updated position
and decision will be required on a funding request or on the deliverability of
the project.
4.8 The Council’s Standing Orders have been changed to have contract
authorisation submitted to service committees and delegated authority sought
to appoint the contractor of the returned tender if the contract cost is within the
approved budget and the tender is in line with normal tender parameters. 
4.9 The Fleet Service have undertaken a prioritisation exercise to determine the
corporate fleet requirements to be delivered through the vehicle replacement
budget. To facilitate the purchase of the vehicles approval is sought to
undertake the procurement and contract award of the Vehicle Replacement
Programme 2025/26 by the Chief Officer – Roads and Neighbourhood in
consultation with the Procurement Service and to appoint the contractor of the
returned tender if the contract cost being within the approved budget and the
tender being in line with normal tender parameters. This request for the
authorisation for delegated authority is being made to Council as the project
timelines for the contract award being issued are before the next IRED
committee in May 2025.
4.10 This report also asks Council to approve any procurement and contract award
of projects under the Building Upgrades recurring budget within Corporate
Assets to be made by the Chief Officer Resources, in consultation with the
Procurement Manager provided the contract costs remain within the approved

Page 4

budget and the tenders adhere to standard procurement parameters.  This is
required due to the time constraints required to deliver spend in each financial
year.  There is a risk should this not be approved that projects will not be able
to be carried out in the financial year which will impact on the condition of our
assets.
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets.
(b) As a consequence of current market conditions, inflation is high and
interest rates continue to be volatile. To forecast for the full year costs
budget assumptions have been required. These assumptions continue to
change regularly and therefore it is likely the projected year end
budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
______________
Laurence Slavin
Chief Officer – Resources
Date: 11 March 2025
Person to Contact: Jackie Thomson

Page 5

Council Offices, Church Street, Dumbarton
E-mail: jackie.nicolthomson@west-dunbarton.gov.uk
Appendices:
Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Off Track Projects
Appendix 3 – Changes to Capital Plan for Noting
Appendix 4 – All Approved Projects
Background Papers: 
General Services Capital Plan Update - Council 6 March 2024.
Capital Budgetary Control Report (P3) – Council 28 August 2024
Capital Budgetary Control Report (P5) – Council 30 October 2024
Capital Budgetary Control Report (P7) – Council 18 December 2024
Wards Affected           All Wards