WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Council – 18 December 2024
___________________________________________________________________
Subject: Housing Revenue Account (HRA) Capital 
Budgetary Control Report to 31 October 24 (Period 7)
1. Purpose
1.1 This report provides an update on the HRA capital programme to 31 October
2024.
2. Recommendations
2.1 Committee is asked to:
i) Note the current position of the 2024/2025 HRA capital budget and the
HRA capital plan.
ii) Note that in year financial performance is monitored against a
2024/2025 capital expenditure budget of £73.664m and a 2024/2025
capital income budget of £10.003m, a one-year borrowing requirement
of £63.661m.
iii) Note that project life performance is monitored against a five-year
project life expenditure budget of £319.738m and a project life income
budget of £54.577m, a five-year borrowing requirement of £265.161m.
iv) Note that there are eighteen  projects reporting off track with an
anticipated over / under spend against their 2024/2025 budgets, with a
forecast net underspend of £2.918m in 2024/2025.
v) Note that all projects are currently on track to achieve their planned
completion dates and to deliver within their respective five-year project
life budgets.
3. Background
3.1 On 6 March 2024 the Council approved the updated Housing Revenue
Account Capital Plan for 2024/2025 to 2028/2029.
3.2 Since then budget adjustments have taken place to bring forward in year
project under/over spends during 2023/2024, to reflect up to date information
on progress delivering the plan and any need for budget acceleration and
budget deceleration from / to future years, and to update the expenditure and
income budgets for Affordable Housing Supply projects to reflect the
2023/2024 outturn and to reflect that the most recent cost and income
forecasts  The budget adjustments result in revised capital budgets as set out
in Exhibit 1.  
ITEM 16

Page 2

Exhibit 1: Revised HRA Capital Budget 2024/2025 – 20278/2029
2024/25
BCR07
(£m)
Project Life
BCR07
(£m)
Project Life
March 24
(£m)
Other Capital Expenditure 7.165 27.129 27.180
Major Component Replacement 19.795 92.604 92.604
Void Capital 4.902 19.212 20.712
Structural & Environmental 2.767 14.175 14.175
Support Costs 2.761 14.367 14.367
Affordable Housing Supply Programme 36.274 152.251 149.053
Total Expenditure 73.664 319.738 318.091
Total Income 10.003 54.577 47.029
Prudential Borrowing 63.661 265.161          271.062
4. Main Issues
4.1 Progress against the 2024/25 capital plan is detailed in:
Appendix 1 – HRA Capital Summary BCR07
Appendix 2 – HRA Capital Detail BCR07
4.2 The HRA capital summary report at Appendix 1 reports that planned
expenditure and planned income are both in line with the overall project
budgets. Appendix 1 reports that there are twenty-eight capital projects where
expenditure / income budget is tracked over the multi-year life of the project
and twenty-nine projects classified as rolling programme projects /
contingency / fees, that is programmes of work where an annual budget is set
each year that takes account of demand, cost, and affordability.
4.3 Appendix 2 shows all projects with approved in year and project life budgets
as well as forecast expenditure / income. The appendix highlights a
2024/2025 expenditure budget of £73.664m and a forecast spend of
£70.486m, an underspend of £3.178m (4.3% of the 2024/2025 budget) The
2024/2025 capital income budget is £10.003m, with a forecast income of
£9.743m.
4,4 Commentary on the 2024/2025 expenditure variances are set out in Exhibit 2
below.
Exhibit 2: Project Over / Underspends 2024/2025
Project
2024/2025
BCR07
Forecast
(£m)
2024/2025
BCR07
Budget
(£m)
2024/2025
Variance
(£m)
Commentary
1 Special Need Adaptations 0.506 0.655 (0.149)  Reduced throughput of capital
adaptations this year
 Inhouse adaptations team is
fully up to date with its order
books.
 Improved performance with
average time of 46 days.
 Underspend will be available
for reprofiling in future years.

Page 3

Project
2024/2025
BCR07
Forecast
(£m)
2024/2025
BCR07
Budget
(£m)
2024/2025
Variance
(£m)
Commentary
2 Capitalised Minor Works 4.116 3.000 1.116  Transfer of Electrical
Installation Condition Works
spend to minor works budget.
 Overspend will be re-profiled
over future years.
 Officers are increasingly
directing minor works
requests to the relevant
planned capital programme.
3 Environmental Sensors 1.620 2.000 (0.380)  Excellent progress with this
programme with an
anticipated 2,000 sensors due
to be installed this year.
 Underspend reflects the
mobilization period and
challenges in getting access to
properties.
 Underspend will be available
for reprofiling in future years.
4 Roofing Works 2.201 2.500 (0.299)  Underspend reflects the
changing mix of the capital
programme with an increased
number of mixed tenure
blocks that require owner
consent before work can start.
This necessary process delay
project start
 Underspend will be available
for reprofiling in future years.
5 Void House Works 5.438 4.902 0.536  Transfer of increased void
spend to HRA capital account
following a review.
 Void delivery costs, including
overtime on voids and
contractor spend, have
reduced as void number have
reduced.
 Overspend will be re-profiled
over future years.
6 Environmental Works 0.992 1.068 (0.076)  Reduced throughput of
environmental works this year
because operatives have also
worked across other HRA
service areas.
 Underspend will be available
for reprofiling in future years.
7 Contingency 0.000 0.100 (0.100)  Contingency released to offset
cost pressures across the HRA
capital account.

Page 4

Project
2024/2025
BCR07
Forecast
(£m)
2024/2025
BCR07
Budget
(£m)
2024/2025
Variance
(£m)
Commentary
8 Clydebank East 9.896 9.700 0.196  Good progress with
development and is ahead of
previous projection
 32 homes handed over to date
Pappert
Expenditure
7.446 9.653 (2.207)  Development now on site and
cash flow accurately based on
agreed programme of works
and this is reflected in the
projection
 No impact on overall project
budget or timescales and
development on track.
9
Pappert
Income
(2.803) (3.303) 0.500  Affordable Housing Supply
Programme grant funding
reprofiled.
10 Queen Mary Avenue 0.010 0.120 (0.110)  Revised projection based on
development project plan
Queens Quay Site C
Expenditure
0.000 1.000 (1.000)  Underspend reflects delays
progressing this project within
a financial viability assessment
and the aspiration to acquire
additional neighbouring land.
11
Queens Quay Site C
Income
0.000 (1.000) 1.000  The acquisition grant funding
because of the project not
been taken forward
12 Dennystoun Forge 0.060 0.250 -0.190  Revised projection based on
development project plan
Future New Build &
Related Regeneration
Projects / Professional
Fees
0.500 1.015 -0.515  Ongoing review of the
programme allowed non
committed funds to be
released to offset cost
pressures across the HRA
capital account.
13
Future New Build &
Related Regeneration
Projects
Income
(0.200) 0.000 (0.200)  Ongoing review of the
programme allowed non
committed funds to be
released to offset cost
pressures across the HRA
capital account.
14 Buyback Grant
Income
(2.417) (2.858) 0.441  Revised projection based on
the distribution of Scottish
Government acquisition
funding.
15 7 – 9 Gilmour Avenue
Income
(0.215) (0.195) (0.020)  Revised projection based on
the application of the
Strategic Local Programme
16 Bank Street
Income
(0.518) 0.000 (0.518)  Revised projection based on
the application of the
Strategic Local Programme
17 Bonhill Gap Sites
Income
(0.514) 0.000 (0.514)  Revised projection based on
the application of the
Strategic Local Programme
18 Silverton
Income
(0.429) 0.000 (0.429)  Revised projection based on
the application of the
Strategic Local Programme
(2.918)

Page 5

4.5 Budget assumptions are required to forecast costs / income, especially where
projects span multi-year and project finances have yet to be finalised. It is
therefore likely that the projected year end budgetary position will change
during the year.
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
several variable factors which could arise between now and 31 March
which could affect the year end results for capital budgets.
(b) Because of current market conditions, inflation is at an all-time high and
interest rates continue to be volatile. To forecast for the full year costs
budget assumptions have been required. These assumptions continue to
change regularly and therefore it is likely the projected year end
budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted
during the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
________________

Page 6

Laurence Slavin
Chief Officer – Resources
Date: 18 December 2024
Person to Contact: Jim McCarron
Business Partner, Finance 07772 322055
E-mail: james.mccarron@west-dunbarton.gov.uk
Appendices: Appendix 1 - HRA Capital Summary BCR07
Appendix 2- HRA Capital Details BCR07
Background Papers:
Housing Revenue Account (HRA) Capital Investment Programme, Revenue Budget, and Rent
Levels for 2024/25 - Council 6 March 2024.
Wards Affected           All Wards