Changes to Capital Plan and Implications at P7 Appendix 3
REGULATORY & REGENERATION
Project - RR 3
Initial End
Date 
Revised
End Date  Reprofiling 
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Installation of Solar PV at Clydebank Leisure Centre 57                 57                     57                    
Installation of Solar PV at Clydebank Leisure Centre Revised 57                57                    
Explanation
Due to staff vacancies within the team, the project will not progress during this financial year.
Project - RR 5
Initial End
Date 
Revised
End Date  Reprofiling 
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Meadow Centre/Vale Swimming Pool - Air Handling Unit Upgrade 226               226                   226                  
Meadow Centre/Vale Swimming Pool - Air Handling Unit Upgrade -
Revised 226              226                  
Explanation
Due to staff vacancies within the team, the project will not progress during this financial year.
Project - RR 6
Initial End
Date 
Revised
End Date  Reprofiling 
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Regeneration/Local Economic Development 725               1,100                1,907           1,855             560          2,500       7,922               
Regeneration/Local Economic Development - Revised 375                   2,232           2,055             760          2,500       7,922               
Explanation
Project development taking longer than anticipated.  Project delayed due to external factors.

Page 2

Changes to Capital Plan and Implications at P7 Appendix 3
Project - RR 8
Initial End
Date 
Revised
End Date  Reprofiling 
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Place Based Investment Programme 307                                   310 310                  
Place Based Investment Programme - Revised 3                       307              310                  
Explanation
Project - RR 9
Initial End
Date 
Revised
End Date  Reprofiling 
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Clydebank Can 717               717                   717                  
Clydebank Can Revised 717              717                  
Explanation
Project - RR 10
Initial End
Date 
Revised
End Date  Reprofiling 
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
LUF 2,826            11,959              2,588           14,547             
LUF-Revised  9,133                5,414           14,547             
Explanation
Project - RR11
Initial End
Date 
Revised
End Date  Reprofiling 
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Levelling Up Capacity                 161                     161  161                  
Levelling Up Capacity Revised                  161  161                  
Explanation
Project is supported by the Clydebank Town Board and its delivery and future maintenance is linked to 3 Year Investment Plan as agreed by the Board and Long Term Plan for Town funding timescales.
Project is supported by the Clydebank Town Board and its delivery and future maintenance is linked to 3 Year Investment Plan as agreed by the Board and Long Term Plan for Town funding timescales.
Project development process and procurement process have taken a considerable amount of time. The construction programme received from the preferred bidder indicates the completion date as end of
October 2025.
The budget is to support development of Levelling Up projects. It has been reprofiled to align with the revised LUF timescales.

Page 3

Changes to Capital Plan and Implications at P7 Appendix 3
ROADS & NEIGHBOURHOOD
Project - RN 2
Initial End
Date 
Revised
End Date  Reprofiling 
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Flood Risk Management 100               500                   500              200                200          915          2,315               
Flood Risk Management - Revised 400                   500              200                200          915          2,215               
Explanation
Limited actions are required under the current management plan.
Project - RN 4
Initial End
Date 
Revised
End Date  Reprofiling 
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Flood Prevention 50                 339                   339                  
Flood Prevention - Revised 289                   289                  
Explanation
Original estimates for surface water management plans were lower than expected, there was also limited uptake on property level protection.
Project - RN 28
Initial End
Date 
Revised
End Date  Reprofiling 
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Balloch Mountain Bike Track 30/09/2024 30/09/2025 500               600                   -               -                 -           -           600                  
Balloch Mountain Bike Track - Revised 100                   350              -                 -           -           450                  
Explanation
Project scope has been reduced which has in turn reduced match funding element.
Project - RN 32
Initial End
Date 
Revised
End Date  Reprofiling 
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Cycling, Walking, Safer Routes Tier 1 (Active Travel) 251               389                   -               -                 -           -           389                  
Cycling, Walking and Safer Routes Tier 1 (Active Travel) 638                   -               -                 -           -           638                  
Explanation
Additional funding from Scottish Government.

Page 4

Changes to Capital Plan and Implications at P7 Appendix 3
Project - RN 34
Initial End
Date 
Revised
End Date  Reprofiling 
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Strathclyde Partnership for Transport - Bus, cycling and walking
infrastructure improvements & Park and Rides 310               -                    -               -                 -           -           -                   
Strathclyde Partnership for Transport - Bus, cycling and walking
infrastructure improvements & Park and Rides - Revised 310                   -               -                 -           -           310.0               
Explanation
Additional Scottish Government funding.
EDUCATION
Project - EDUC 4
Initial End
Date 
Revised
End Date  Reprofiling 
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan
Schools Estate Improvement Plan £'000  £'000  £'000  £'000  £'000  £'000  £'000
Schools Estate Improvement Plan - Revised 895               4,065                -               -                 -           -           4,065               
3,170                -               -                 -           -           3,170               
Explanation
Project - EDUC 5
Initial End
Date 
Revised
End Date  Reprofiling 
Current Year
2024/25  2025/26  2026/27  2027/28 
Future
Years 
Total Capital
Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Free School Meals Expansion 31/03/2025 1,190            -                    -               -                 -           -           -                   
Free School Meals Expansion 1,190                -                 -           -           1,190               
Explanation
OVERALL REPROFILING TOTAL 6,308           
Adjustment required to accommodate Faifley Campus project.
As part of the school meal expansion programme in primary schools the Scottish Government confirmed on 23 September 2024 an additional £1.190m funding has been allocated to the Council to support the
phased expansion of free school meals to those in receipt of Scottish Child Payment in Primary 6 and 7 from February 2025.