Projects that are Off Track at Period 7 Appendix 2
Service Project
Approved
Project Life
Cost
Revised
Project Life
Cost
Project Life
Variance
Initial
Completion Date
Revised
Completion
Date
£'000 £'000 £'000
EDUC 3 Schools Estate Improvement Plan - next Phase - Faifley Campus            35,620         36,515 -             895 31/03/2027 31/03/2027
RN 17 Posties Park Sports Hub - New sports hub to include gym & running track             6,252           6,385 -             133 31/03/2022 29/11/2025
RN 28 Balloch Mountain Bike Track                600              450               150 30/11/2023 30/09/2025
Project Name: Schools Estate Improvement Plan - next Phase - Faifley Campus EDUC 3 Project Manager: Michelle Lynn
Initial Completion End Date: 31/03/2027 Revised End Date: 31/03/2027
How was this project initially funded: Council Capital Funding/Prudential Borrowing. Please Detail any additional funding: n/a
Why is the project classified as off track and what has caused the issues identified?
New Completion Date: 31/03/2027
What are the implications on the actions proposed?
Revenue Implications n/a
Virement Implications n/a
Given ongoing volatile market conditions there is an increase in the expected labour and material costs at Faifley Campus. The estimated cost of Faifley Campus has been increased
by £0.895m to £36.515m. At this stage, however, it is anticipated that this it is anticipated that this increase can be accommodated within the overall School Improvement capital
budget which is currently unallocated.
Source of Funding:- Schools Estate ImprovementWhat action will be taken to rectify the position? Virement from Schools Estate Improvement Plan Project EDUC 4.

Page 2

Projects that are Off Track at Period 7 Appendix 2
Project Name: Posties Park RN 17 Project Manager: Gail McFarlane
Initial Completion End Date: 31/03/2022 Revised End Date: 29/11/2025
How was this project initially funded: Council Capital Funding/Prudential Borrowing. Please Detail any additional funding: n/a
Why is the project classified as off track and what has caused the issues identified?
Additional budget required for utility costs incurred as part of the capital build project.
What action will be taken to rectify the position? n/a
New Completion Date: 29/11/2025
What are the implications on the actions proposed?
Revenue Implications
Virement Implications n/a
Project Name: Balloch Mountain Bike Track RN 28 Project Manager: Ian Bain
Initial Completion End Date: 30/11/2023 Revised End Date: 30/09/2025
How was this project initially funded: Council Capital Funding, Prudential Borrowing and Sport Scotland Please Detail any additional funding:- n/a
Why is the project classified as off track and what has caused the issues identified?
Completion amended due to revised project scope.
What action will be taken to rectify the position? n/a
New Completion Date: 30/09/2025
What are the implications on the actions proposed?
Revenue Implications n/a
Virement Implications n/a
Prudential Borrowing of £133k has a revenue implication of £98,533 over 25 years due to the incurred interest on the debt. This equates to  £3,864 per
annum.
Source of Funding:- Prudential Borrowing & Sports Scotland
Source of Funding:- Prudential Borrowing