Democracy Spraffa

Item 15 - General Services Capital Budgetary Control Report 2024/25 to Period 5 (31 August 2024)

West Dunbartonshire Council · 30 October 2024
Back to West Dunbartonshire Council — 30 October 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Council 30 October 2024
___________________________________________________________________
Subject: General Services Capital Budgetary Control Report 2024/25 to
Period 5 (31 August 2024)
1. Purpose
1.1 This report provides an update on the General Services capital financial
performance to 31 August 2024.
2. Recommendations
2.1 Committee is asked to:
i) Note the current position of the 2024/25 General Services capital
budget.
ii) Approve £0.231m of additional capital budget for the Posties Park
project.
iii) Approve the revised completion dates detailed in appendix 3.
iv) Note an in-year variance of (£0.644m) due to £1.625m reprofiling and
£0.231m additional budget.
3. Background
3.1 On 6 March 2024 the Council approved the updated General Services Capital
Plan for 2024/2025 to 2032/33.  The three years from 2024/25 to 2026/27
were approved in detail with the remaining years being indicative. The budget
agreed was £76.757m for 2024/25 and £318.357m for the project life budget.
3.2 Since then budget adjustments have taken place which result in a revised
General Services capital budget as set out in Exhibit 1.
Exhibit 1: Revised Capital Budget
2024/25
(£m)
Project Life
(£m)
Capital Budget Agreed 6 March 2024 76.757 318.357
Capital Projects Removed as per P3 Report (0.09) (5.202)
Reprofiling Agreed at P3 (15.786) 0
Reprofiling amendments from P3 to P5 0.168 0
Add Res7 Community Capital Fund 0.150 0.150
ITEM 15

Page 2

Add Res8 Community Sports Success Capital Fund
0.250 0.250
Added RR 13 Clyde Mission Catalyst Fund 1.197 2.000
Developers Contributions for Clydebank Can on the
Canal 0 0.050
New Scottish Government Funding – Nature
Restoration 0.034 0.034
New Scottish Government Funding – Cycling,
Walking and Safer Streets 0.389 0.389
Add RR14 Securing site to make safe AT 3
Castlegate Avenue 0.007 0.007
Reduction in Future Years Funding-  RR 8 Place
Based Investment 0 (0.943)
Add R&N 33 Creation of three new all-weather
pitches at Argyll Park, Post
ies Park and Mountblow playing fields. 0.500 2.250
Revised Capital Budget as at Period 5 63.657 317.342
4. Main Issues
4.1 Progress against the 2024/25 capital plan is detailed in:
Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Off Track Projects
Appendix 3 – Changes to Capital Plan for Noting
Appendix 4 – All Approved Projects
4.2 The overall programme summary report at Appendix 1 shows that planned
expenditure is higher than the budget agreed by £0.231m (0.07% of budget)
due to an anticipated overspend due to Posties Park Project.
4.3 Appendix 2 highlights two projects currently showing as off-track.  One due to
additional budget required (Posties Park) however we will explore the
possibility of recovering the additional costs which, if successful, will remove
or reduce the need for additional prudential borrowing. The other project
(Heritage Fund) is due to revised completion dates.
4.4 Appendix 3 highlights four projects where the project expenditure requires to
be reprofiled but there is no need for additional budget.
4.5 Appendix 4 shows all projects with approved in year and project life budgets
as well as anticipated expenditure. It highlights that the 2024/25 budget is
£63.657m with current forecast spend of £63.013m, a variance of (£0.644m),
of which £1.625m related projects require reprofiling.  The spend as at period
5 is £16.439m (26.09%) of the current forecast spend of £63.013m. 
4.6 Changes to the capital plan already included in the summarised plan in
appendix 4 is:

Page 3

• Faifley Campus Project previous included within Education Services has
moved to Resources.
• Creation of 3 New All-Weather Pitches at Argyll Park and Mountblow playing
fields has been added to the capital plan (R&N33). The project was agreed by
council in March 2024 as a spend to save project.
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital
budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets.
(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full year
costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report.

Page 4

12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the strategic
priorities of the Council’s current Strategic Plan. This report forms part of
the financial governance of the Council.
________________
Laurence Slavin
Chief Officer – Resources
Date:  30 October 2024
Person to Contact: Jackie Thomson
Council Offices, Church Street, Dumbarton
E-mail: jackie.nicolthomson@west-dunbarton.gov.uk
Appendices: Appendix 1 - Project Life Summary
Appendix 2- Off Track Projects
Appendix 3 - Reprofiling and Acceleration of Projects
Appendix 4 - Details of all Projects.
Background Papers: General Services Capital Plan Update - Council 6 March
2024
Capital Monitoring Report – Council 28 August 2024
Wards Affected  All Wards